SlideShare a Scribd company logo
1 of 1
Download to read offline
PMP® Formula Pocket Guide
Print it - Fold it - Study wherever you go.
Visit www.pmprepcast.com for more PMP resources. Please see disclaimer on the PMP Formula Study Guide.
© 2008 ScopeCreep Project Management Consultants. All rights reserved. Version 1.1
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘no variances’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘atypical’ = AC + BAC - EV
EAC ‘typical’ = AC + ((BAC - EV) / CPI)
ETC = EAC - AC
ETC ‘atypical’ = BAC - EV
ETC ‘typical’ = (BAC - EV) / CPI
ETC ‘flawed’ = new estimate
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
PERT
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6
PERT σ = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Variance all activities = √sum((Pessimistic - Optimistic) / 6)^2
Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1
Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Formula not required. Select biggest number.
ROI = Formula not required. Select biggest number.
IRR = Formula not required. Select biggest number.
Payback Period = Add up the projected cash inflow minus expenses
until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.
Communications
Communication Channels = n * (n-1) / 2
Probability
EMV = Probability * Impact in currency
Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target
Cost
Depreciation
Straight-line Depreciation:
Depr. Expense = Asset Cost / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Mathematical Basics
Average (Mean) = Sum of all members divided by the number of items.
Median = Arrange values from lowest value to highest. Pick the middle
one. If there is an even number of values, calculate the mean of the
two middle values.
Mode = Find the value in a data set that occurs most often.
Values
1 sigma = 68.26%
2 sigma = 95.46%
3 sigma = 99.73%
6 sigma = 99.99%
Control Limits = 3 sigma from mean
Control Specifications = Defined by customer; looser than
the control limits
Order of Magnitude estimate = -25% to +75%
Preliminary estimate = -15% to + 50%
Budget estimate = -10% to +25%
Definitive estimate = -5% to +10%
Final estimate = 0%
Float on the critical path = 0 days
Pareto Diagram = 80/20
Time a PM spends communicating = 90%
Crashing a project = Crash least expensive tasks on critical
path.
JIT inventory = 0% (or very close to 0%.)
Minus 100 = (100) or -100
Acronyms
AC Actual Cost
BAC Budget at Completion
BCR Benefit Cost Ratio
CBR Cost Benefit Ratio
CPI Cost Performance Index
CV Cost Variance
DUR Duration
EAC Estimate at Completion
EF Early Finish
EMV Expected Monetary Value
ES Early Start
ETC Estimate to Complete
EV Earned Value
FV Future Value
IRR Internal Rate of Return
LF Late Finish
LS Late Start
NPV Net Present Value
PERT Program Evaluation and Review Technique
PTA Point of Total Assumption
PV Planned Value
PV Present Value
ROI Return on Investment
SPI Schedule Performance Index
SV Schedule Variance
VAC Variance at Completion
σ Sigma / Standard Deviation
^ “To the power of” (2^3 = 2*2*2 = 8)

More Related Content

What's hot

Blog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisBlog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk Analysis
Asaman Patnaik
 

What's hot (18)

Cost analysis
Cost analysisCost analysis
Cost analysis
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpm
 
FC and VC changes
FC and VC changesFC and VC changes
FC and VC changes
 
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...
 
Cost output relationship
Cost output relationshipCost output relationship
Cost output relationship
 
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Price-Cost Analysis
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Price-Cost AnalysisCOBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Price-Cost Analysis
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Price-Cost Analysis
 
F0dd9 cost
F0dd9 costF0dd9 cost
F0dd9 cost
 
Chapter 8: Cost Analysis
Chapter 8: Cost AnalysisChapter 8: Cost Analysis
Chapter 8: Cost Analysis
 
Interactive Transmission System Computation Unit
Interactive Transmission System Computation UnitInteractive Transmission System Computation Unit
Interactive Transmission System Computation Unit
 
Costs
CostsCosts
Costs
 
Control structures(class 02)
Control structures(class 02)Control structures(class 02)
Control structures(class 02)
 
Amortized complexity
Amortized complexityAmortized complexity
Amortized complexity
 
Blog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisBlog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk Analysis
 
Amortized complexity
Amortized complexityAmortized complexity
Amortized complexity
 
2Bytesprog2 course_2014_c1_sets
2Bytesprog2 course_2014_c1_sets2Bytesprog2 course_2014_c1_sets
2Bytesprog2 course_2014_c1_sets
 
Cost
CostCost
Cost
 
Economics
EconomicsEconomics
Economics
 
Amortized complexity
Amortized complexityAmortized complexity
Amortized complexity
 

Viewers also liked

Presentación1
Presentación1Presentación1
Presentación1
stalin789
 
Tipos de bancos que operan en colombia
Tipos de bancos que operan en colombiaTipos de bancos que operan en colombia
Tipos de bancos que operan en colombia
Mariana Rodriguez
 
34 05-aktuell-zg
34 05-aktuell-zg34 05-aktuell-zg
34 05-aktuell-zg
petrbilek
 
Pérez Vivas asegura que Táchira será bastión en la victoria de …
Pérez Vivas asegura que Táchira será bastión en la victoria de …Pérez Vivas asegura que Táchira será bastión en la victoria de …
Pérez Vivas asegura que Táchira será bastión en la victoria de …
visitatachira
 

Viewers also liked (17)

Presentación1
Presentación1Presentación1
Presentación1
 
June 21.2015 - Sunday Message - TAKING THE INITIATIVE
June 21.2015 - Sunday Message - TAKING THE INITIATIVEJune 21.2015 - Sunday Message - TAKING THE INITIATIVE
June 21.2015 - Sunday Message - TAKING THE INITIATIVE
 
SEO Tips for Beginners
SEO Tips for BeginnersSEO Tips for Beginners
SEO Tips for Beginners
 
GBI Trabajo en equipo y trabajo en grupo
GBI Trabajo en equipo y trabajo en grupo GBI Trabajo en equipo y trabajo en grupo
GBI Trabajo en equipo y trabajo en grupo
 
Tissue engineering9
Tissue engineering9Tissue engineering9
Tissue engineering9
 
12. history of broadcasting
12. history of broadcasting12. history of broadcasting
12. history of broadcasting
 
öğrenci merkezli eğitim- görüş geliştime
öğrenci merkezli eğitim- görüş geliştimeöğrenci merkezli eğitim- görüş geliştime
öğrenci merkezli eğitim- görüş geliştime
 
高専カンファレンス宣言
高専カンファレンス宣言高専カンファレンス宣言
高専カンファレンス宣言
 
Tipos de bancos que operan en colombia
Tipos de bancos que operan en colombiaTipos de bancos que operan en colombia
Tipos de bancos que operan en colombia
 
Military Embedded Systems 2015 Media Kit
Military Embedded Systems 2015 Media KitMilitary Embedded Systems 2015 Media Kit
Military Embedded Systems 2015 Media Kit
 
Factores de riesgo laboral
Factores de riesgo laboralFactores de riesgo laboral
Factores de riesgo laboral
 
Fractura de astragalo
Fractura de astragaloFractura de astragalo
Fractura de astragalo
 
34 05-aktuell-zg
34 05-aktuell-zg34 05-aktuell-zg
34 05-aktuell-zg
 
Pérez Vivas asegura que Táchira será bastión en la victoria de …
Pérez Vivas asegura que Táchira será bastión en la victoria de …Pérez Vivas asegura que Táchira será bastión en la victoria de …
Pérez Vivas asegura que Táchira será bastión en la victoria de …
 
Gladys Mendez, MPH, CRCR, CPXP
Gladys Mendez, MPH, CRCR, CPXPGladys Mendez, MPH, CRCR, CPXP
Gladys Mendez, MPH, CRCR, CPXP
 
013
013013
013
 
Mateo cv
Mateo cvMateo cv
Mateo cv
 

Similar to Formula pocket guide

projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
Nita Cristian
 
PM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula SheetPM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula Sheet
Mohammad Elsheimy
 

Similar to Formula pocket guide (20)

Pmp formulas
Pmp  formulasPmp  formulas
Pmp formulas
 
PMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdfPMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdf
 
cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Important formules for ugc net commerce,management (most important) downl...
Important  formules  for  ugc net commerce,management (most important)  downl...Important  formules  for  ugc net commerce,management (most important)  downl...
Important formules for ugc net commerce,management (most important) downl...
 
fm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdffm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdf
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Chapter 7 cost of production
Chapter 7 cost of productionChapter 7 cost of production
Chapter 7 cost of production
 
Risk Concept And Management 5
Risk Concept And Management 5Risk Concept And Management 5
Risk Concept And Management 5
 
Project : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringProject : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoring
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
PM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula SheetPM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula Sheet
 
Pmp formulas pmbok5
Pmp formulas pmbok5Pmp formulas pmbok5
Pmp formulas pmbok5
 
Financial Management
Financial Management Financial Management
Financial Management
 
Important formules for ugc net commerce,management (most important) downl...
Important  formules  for  ugc net commerce,management (most important)  downl...Important  formules  for  ugc net commerce,management (most important)  downl...
Important formules for ugc net commerce,management (most important) downl...
 
Cost theory
Cost theoryCost theory
Cost theory
 

Recently uploaded

Recently uploaded (20)

Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learning
 
Basic Intentional Injuries Health Education
Basic Intentional Injuries Health EducationBasic Intentional Injuries Health Education
Basic Intentional Injuries Health Education
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Simple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdfSimple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdf
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.ppt
 
latest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answerslatest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answers
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 

Formula pocket guide

  • 1. PMP® Formula Pocket Guide Print it - Fold it - Study wherever you go. Visit www.pmprepcast.com for more PMP resources. Please see disclaimer on the PMP Formula Study Guide. © 2008 ScopeCreep Project Management Consultants. All rights reserved. Version 1.1 Earned Value CV = EV - AC CPI = EV / AC SV = EV - PV SPI = EV / PV EAC ‘no variances’ = BAC / CPI EAC ‘fundamentally flawed’ = AC + ETC EAC ‘atypical’ = AC + BAC - EV EAC ‘typical’ = AC + ((BAC - EV) / CPI) ETC = EAC - AC ETC ‘atypical’ = BAC - EV ETC ‘typical’ = (BAC - EV) / CPI ETC ‘flawed’ = new estimate Percent Complete = EV / BAC * 100 VAC = BAC - EAC EV = % complete * BAC PERT PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6 PERT σ = (Pessimistic - Optimistic) / 6 PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2 PERT Variance all activities = √sum((Pessimistic - Optimistic) / 6)^2 Network Diagram Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1 Total Float = LS - ES or Total Float = LF – EF Free Float = ES of Following - ES of Present - DUR of Present EF = ES + duration - 1 ES = EF of predecessor + 1 LF = LS of successor - 1 LS = LF - duration + 1 Project Selection PV = FV / (1+r)^n FV = PV * (1+r)^n NPV = Formula not required. Select biggest number. ROI = Formula not required. Select biggest number. IRR = Formula not required. Select biggest number. Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment. BCR = Benefit / Cost CBR = Cost / Benefit Opportunity Cost = The value of the project not chosen. Communications Communication Channels = n * (n-1) / 2 Probability EMV = Probability * Impact in currency Procurement PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost Depreciation Straight-line Depreciation: Depr. Expense = Asset Cost / Useful Life Depr. Rate = 100% / Useful Life Double Declining Balance Method: Depr. Rate = 2 * (100% / Useful Life) Depr. Expense = Depreciation Rate * Book Value at Beginning of Year Book Value = Book Value at beginning of year - Depreciation Expense Sum-of-Years' Digits Method: Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th) Mathematical Basics Average (Mean) = Sum of all members divided by the number of items. Median = Arrange values from lowest value to highest. Pick the middle one. If there is an even number of values, calculate the mean of the two middle values. Mode = Find the value in a data set that occurs most often. Values 1 sigma = 68.26% 2 sigma = 95.46% 3 sigma = 99.73% 6 sigma = 99.99% Control Limits = 3 sigma from mean Control Specifications = Defined by customer; looser than the control limits Order of Magnitude estimate = -25% to +75% Preliminary estimate = -15% to + 50% Budget estimate = -10% to +25% Definitive estimate = -5% to +10% Final estimate = 0% Float on the critical path = 0 days Pareto Diagram = 80/20 Time a PM spends communicating = 90% Crashing a project = Crash least expensive tasks on critical path. JIT inventory = 0% (or very close to 0%.) Minus 100 = (100) or -100 Acronyms AC Actual Cost BAC Budget at Completion BCR Benefit Cost Ratio CBR Cost Benefit Ratio CPI Cost Performance Index CV Cost Variance DUR Duration EAC Estimate at Completion EF Early Finish EMV Expected Monetary Value ES Early Start ETC Estimate to Complete EV Earned Value FV Future Value IRR Internal Rate of Return LF Late Finish LS Late Start NPV Net Present Value PERT Program Evaluation and Review Technique PTA Point of Total Assumption PV Planned Value PV Present Value ROI Return on Investment SPI Schedule Performance Index SV Schedule Variance VAC Variance at Completion σ Sigma / Standard Deviation ^ “To the power of” (2^3 = 2*2*2 = 8)