SlideShare a Scribd company logo
Failure Analysis & Prevention
Failure analysis
- FA is a systematic approach of investigation to establish the important causes
of the failure.
Therefore, it is worth to familiarize with
– fundamental causes of failure of mechanical
components,
– general approach to be used for the failure
analysis and prevention.
2
When to consider a failure
• In general, an engineering component or assembly is considered to have
failed under the following three conditions when the component
is
–Inoperable,
– Operates but doesn’t perform the intended
function
– Operates but safety and reliability is very poor
3
Failure of mechanical components
» Failure of a mechanical component can occur in many ways
» – elastic deformation is beyond acceptable limit,
» – excessive and unacceptable level of plastic deformation,
» – complete fracture and
» – loss of dimension due to variety of reasons
» Elastic deformation
» Plastic deformation
» Creep
» Fracture
» wear
4
Fundamental causes of failure
» The failure of an engineering component in actual working conditions can
occur due to very large of factors related with
» – Design,
» – Materials,
» – Manufacturing,
» – Service conditions.
5
Need to know causes of failure
» To have systematic understanding on various factors that can
lead to failure of mechanical components :
» – Improper design
» – Improper selection of materials
» – Defects and discontinuities in metal itself
» – Improper processing of materials
» – Poor service conditions
» – Poor assembling
» – Poor maintenance
6
Engineering disasters
» A disaster is referred to as an engineering disaster when it’s
caused by an engineering failure:
» – design flaws or
» – materials failures
» – insufficient knowledge,
» – different underestimations,
» – even carelessness or negligence.
7
Titanic Ship, 1912
» RMS Titanic was a British passenger ship that
sank after hitting an iceberg on her maiden
voyage from Southampton (UK) to New York
City, in April 1912. The tragedy claimed the
lives of over 1,500 people.
» Several rivets of the 3 million rivets that held
the Titanic together were recently recovered
and tested, and found to be made of low
quality iron, which on impact caused them to
fall apart.
» Another engineering fault was that the 16
watertight compartments that kept the boat
afloat, were not individually sealed, but rather
connected near the ceiling. This enabled the
water to spill from one compartment to
another and sink the boat.
8
St. Francis Dam flooding (1928)
» The St. Francis Dam was a concrete dam built between
the years 1924 and 1926, to create a water reservoir for
Los Angeles.
» The dam was located in a canyon around 40 miles (64
km) from the city.
» On March 12, 1928, just hours after being inspected by
the Chief Engineer William Mulholland, the dam failed,
sending a massive water wave 120 ft tall, and killing as
many as 600 people in one of the worst American civil
engineering disaster
9
Tacoma Narrows Bridge collapse (1940)
» The first Tacoma Narrows Bridge was a suspension
bridge in Washington state that opened in 1940 and
collapsed at the same year. At the time of its
construction, the bridge was the world’s third longest
suspension bridge, by main span length.
» The bridge was known to move vertically in windy
conditions, and in November 7, 1940, under 40 mph
(64 km/h) winds it collapsed. The collapse was
caught on video and made an impact on science and
engineering, especially bridge designing till today
» . The cause of failure was aero elastic flutter – a
dynamic instability of an elastic structure.
10
Kadalundi Train Disaster
» There was a structural failure. The railway bridge was around
140 years old and it definitely needed repair.
» What happened was one of the pier had settled down causing
internal stresses to grow in rails.
» As soon as a train came near it, the track snapped and the train
derailed which eventually landed into river.
» So lesson one, never ever use a structure of high importance
without testing it. Always, keep an eye on it and test it
11
The Bhopal Disaster: Union Carbide
12
Rafiganj rail bridge
» Blamed to poor design and construction as well as low
maintenance.
» It is said that the plate girder deteriorated over time and was
losing its strength in fatigue due to vibrations from trains.
» Nobody paid attention to it. Also the bridge was rusty to a
great extent.
» When the train was passing by, the plate girder gave up
leading to this fatal crash.
» Lesson two, make sure your design is checked against
fatigue and steel is coated with anti-corrosion paints.
13
Industrial Engineering Tools for FA: Failure Mode &
Effect Analysis
» What Is A Failure Mode?
» A Failure Mode is:
» The way in which the component, subassembly, product, input,
or process can fail to perform its intended function
» Things that can go wrong
14
Benefits of FMEA
» Methodology that facilitates process improvement
» Identifies and eliminates concerns early in the development of a process
or design
» Focuses on prevention
15
Approach of FMEA
A structured approach for :
– Identifying the ways in which a product or process can fail
– Estimating risk associated with specific causes
– Prioritizing the actions that should be taken to reduce risk
– Evaluating design validation plan (design FMEA) or current control plan (process FMEA)
When to Conduct an FMEA
» Investigation for the process improvement investigation
» Design of new systems, products, and processes
» Modification of existing designs or processes
» Existing designs for new applications
16
FMEA: A Team Tool
» A team approach is necessary.
» Team should be led by the Process Owner who is the responsible manufacturing
engineer or technical person, or other similar individual familiar with FMEA.
» The following should be considered for team members:
» – Design Engineers
» – Operators
» – Process Engineers
» – Reliability
» – Materials Suppliers
» – Suppliers
» – Customers
17
FMEA Procedure
» For each process input (start with high value inputs), determine the ways in
which the input can go wrong (failure mode)
» For each failure mode, determine effects – Select a severity level for each effect
» Identify potential causes of each failure mode – Select an occurrence level for
each cause
» List current controls for each cause – Select a detection level for each cause
» Calculate the Risk Priority Number (RPN)
» Develop recommended actions, assign responsible persons, and take actions –
-Give priority to high RPNs – MUST look at severities rated a 10
» Assign the predicted severity, occurrence, and detection levels and compare
RPNs
18
Severity, Occurrence, and Detection
» Severity – Importance of the effect on requirements
» Occurrence – Frequency with which a given cause occurs and
creates failure modes (obtain from past data if possible)
» Detection – The ability of the current control scheme to detect
(then prevent) a given cause (may be difficult to estimate early
in process operations).
19
Rating Scales & RPN
» There are a wide variety of scoring “anchors”, both quantitative or
qualitative
» Two types of scales are 1-5 or 1-10 • The 1-5 scale makes it easier for the
teams to decide on scores
» The 1-10 scale may allow for better precision in estimates and a wide
variation in scores (most common)
» Severity – 1 = Not Severe, 10 = Very Severe
» Occurrence – 1 = Not Likely, 10 = Very Likely
» Detection – 1 = Easy to Detect, 10 = Not easy to Detect
» RPN is the product of the severity, occurrence, and detection scores.
20
21
The FMEA Form
THANKS!
STAY HOME & STAY SAFE
22

More Related Content

What's hot

PPT Presentation on IATF 16949 Documentation
PPT Presentation on IATF 16949 DocumentationPPT Presentation on IATF 16949 Documentation
PPT Presentation on IATF 16949 Documentation
Global Manager Group
 
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPTPROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
Inter Alliance Werardt
 
Training ppt for control plan
Training ppt for control plan   Training ppt for control plan
Training ppt for control plan
Jitesh Gaurav
 
Apqp ppt
Apqp pptApqp ppt
Apqp ppt
sbtharan
 
Failure Mode Effective Analysis in TQM
Failure Mode Effective Analysis in TQMFailure Mode Effective Analysis in TQM
Failure Mode Effective Analysis in TQM
Palanivel rajan
 
Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01
BhimKunwar2
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentation
PRASHANT KSHIRSAGAR
 
Sequence and interaction of qms processes
Sequence and interaction of qms processesSequence and interaction of qms processes
Sequence and interaction of qms processes
Jorge Torres
 
Production part approval process ppt 1
Production part approval process ppt 1Production part approval process ppt 1
Production part approval process ppt 1
Inder Pal Dua
 
SMED Kaizen Event
SMED Kaizen EventSMED Kaizen Event
SMED Kaizen Event
Brandon Garrett
 
FMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysisFMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysis
Soumyajit Bhuin
 
PPAP 101: What You Should Know About PPAP
PPAP 101: What You Should Know About PPAPPPAP 101: What You Should Know About PPAP
PPAP 101: What You Should Know About PPAP
Rapid Global Business Solutions, Inc.
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
SedhuSiddarth
 
Total Productive Maintenance
Total Productive MaintenanceTotal Productive Maintenance
Total Productive Maintenance
Anand Subramaniam
 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect Analysis
ECC International
 
Failure Mode & Effects Analysis (FMEA)
Failure Mode & Effects Analysis (FMEA)Failure Mode & Effects Analysis (FMEA)
Failure Mode & Effects Analysis (FMEA)
Operational Excellence Consulting
 
Failure mode and effect analysis
Failure mode and effect analysisFailure mode and effect analysis
Failure mode and effect analysis
Shailendra Veerarajapura
 
Flexible manufacturing system ppt
Flexible manufacturing system pptFlexible manufacturing system ppt
Flexible manufacturing system ppt
Irshad Ansari
 
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
Inter Alliance Werardt
 
Basic quality concepts(3)
Basic quality concepts(3)Basic quality concepts(3)
Basic quality concepts(3)
ngiyari
 

What's hot (20)

PPT Presentation on IATF 16949 Documentation
PPT Presentation on IATF 16949 DocumentationPPT Presentation on IATF 16949 Documentation
PPT Presentation on IATF 16949 Documentation
 
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPTPROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
 
Training ppt for control plan
Training ppt for control plan   Training ppt for control plan
Training ppt for control plan
 
Apqp ppt
Apqp pptApqp ppt
Apqp ppt
 
Failure Mode Effective Analysis in TQM
Failure Mode Effective Analysis in TQMFailure Mode Effective Analysis in TQM
Failure Mode Effective Analysis in TQM
 
Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentation
 
Sequence and interaction of qms processes
Sequence and interaction of qms processesSequence and interaction of qms processes
Sequence and interaction of qms processes
 
Production part approval process ppt 1
Production part approval process ppt 1Production part approval process ppt 1
Production part approval process ppt 1
 
SMED Kaizen Event
SMED Kaizen EventSMED Kaizen Event
SMED Kaizen Event
 
FMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysisFMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysis
 
PPAP 101: What You Should Know About PPAP
PPAP 101: What You Should Know About PPAPPPAP 101: What You Should Know About PPAP
PPAP 101: What You Should Know About PPAP
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
 
Total Productive Maintenance
Total Productive MaintenanceTotal Productive Maintenance
Total Productive Maintenance
 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect Analysis
 
Failure Mode & Effects Analysis (FMEA)
Failure Mode & Effects Analysis (FMEA)Failure Mode & Effects Analysis (FMEA)
Failure Mode & Effects Analysis (FMEA)
 
Failure mode and effect analysis
Failure mode and effect analysisFailure mode and effect analysis
Failure mode and effect analysis
 
Flexible manufacturing system ppt
Flexible manufacturing system pptFlexible manufacturing system ppt
Flexible manufacturing system ppt
 
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
 
Basic quality concepts(3)
Basic quality concepts(3)Basic quality concepts(3)
Basic quality concepts(3)
 

Similar to Fmea

FTA.pptx
FTA.pptxFTA.pptx
FTA.pptx
BigbearBigbear
 
REPAIR METHODS FOR BASIC MACHINE ELEMENTS
REPAIR METHODS FOR BASIC MACHINE ELEMENTSREPAIR METHODS FOR BASIC MACHINE ELEMENTS
REPAIR METHODS FOR BASIC MACHINE ELEMENTS
laxtwinsme
 
Unit v11 proactive maintenance analysis
Unit v11 proactive maintenance analysisUnit v11 proactive maintenance analysis
Unit v11 proactive maintenance analysis
Charlton Inao
 
Testing safety critical systems: Practice and Theory (14-05-2013, VU Amsterdam)
Testing safety critical systems: Practice and Theory (14-05-2013, VU Amsterdam)Testing safety critical systems: Practice and Theory (14-05-2013, VU Amsterdam)
Testing safety critical systems: Practice and Theory (14-05-2013, VU Amsterdam)
Jaap van Ekris
 
Mike Taylor: Lessons from history - Case studies that might help spot where t...
Mike Taylor: Lessons from history - Case studies that might help spot where t...Mike Taylor: Lessons from history - Case studies that might help spot where t...
Mike Taylor: Lessons from history - Case studies that might help spot where t...
NSW Environment and Planning
 
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
IJRES Journal
 
Khatibi lecture cov.uni
Khatibi lecture cov.uniKhatibi lecture cov.uni
Khatibi lecture cov.uni
Rahman Khatibi
 
A content analysis of human factors in the design of marine systems ICSOT 2010
A content analysis of human factors in the design of marine systems ICSOT 2010A content analysis of human factors in the design of marine systems ICSOT 2010
A content analysis of human factors in the design of marine systems ICSOT 2010
Vincentius Rumawas
 
SUBROGATING THE SLIP AND FALL
SUBROGATING THE SLIP AND FALLSUBROGATING THE SLIP AND FALL
SUBROGATING THE SLIP AND FALL
Bob Horn
 
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Vecoin
 
FMEA-Intro.ppt
FMEA-Intro.pptFMEA-Intro.ppt
FMEA-Intro.ppt
YashKarkhanis1
 
Forensic Engineering
Forensic EngineeringForensic Engineering
Forensic Engineering
Dr. ABEER KHALID MANSOUR
 
Compact Spring Supports Webinar
Compact Spring Supports WebinarCompact Spring Supports Webinar
Compact Spring Supports Webinar
Piping Technology & Products, Inc.
 
860686
860686860686
FINAL The Owens Lake Turnout Facility End Cap Study
FINAL The Owens Lake Turnout Facility End Cap StudyFINAL The Owens Lake Turnout Facility End Cap Study
FINAL The Owens Lake Turnout Facility End Cap Study
Kook Dean
 
2017 03-10 - vu amsterdam - testing safety critical systems
2017 03-10 - vu amsterdam - testing safety critical systems2017 03-10 - vu amsterdam - testing safety critical systems
2017 03-10 - vu amsterdam - testing safety critical systems
Jaap van Ekris
 
Unit 9 implementing the reliability strategy
Unit 9  implementing the reliability strategyUnit 9  implementing the reliability strategy
Unit 9 implementing the reliability strategy
Charlton Inao
 
comparison of FACTOR OF SAFETY using LIMIT EQUILIBRIUM(OASYS) and NUMERICAL M...
comparison of FACTOR OF SAFETY using LIMIT EQUILIBRIUM(OASYS) and NUMERICAL M...comparison of FACTOR OF SAFETY using LIMIT EQUILIBRIUM(OASYS) and NUMERICAL M...
comparison of FACTOR OF SAFETY using LIMIT EQUILIBRIUM(OASYS) and NUMERICAL M...
SHIBASOUMYA GHOSH
 
Product assurance
Product assurance Product assurance
Product assurance
PriyankaKg4
 
Targeted assessment program update Greg Connolly
Targeted assessment program update Greg ConnollyTargeted assessment program update Greg Connolly
Targeted assessment program update Greg Connolly
NSW Environment and Planning
 

Similar to Fmea (20)

FTA.pptx
FTA.pptxFTA.pptx
FTA.pptx
 
REPAIR METHODS FOR BASIC MACHINE ELEMENTS
REPAIR METHODS FOR BASIC MACHINE ELEMENTSREPAIR METHODS FOR BASIC MACHINE ELEMENTS
REPAIR METHODS FOR BASIC MACHINE ELEMENTS
 
Unit v11 proactive maintenance analysis
Unit v11 proactive maintenance analysisUnit v11 proactive maintenance analysis
Unit v11 proactive maintenance analysis
 
Testing safety critical systems: Practice and Theory (14-05-2013, VU Amsterdam)
Testing safety critical systems: Practice and Theory (14-05-2013, VU Amsterdam)Testing safety critical systems: Practice and Theory (14-05-2013, VU Amsterdam)
Testing safety critical systems: Practice and Theory (14-05-2013, VU Amsterdam)
 
Mike Taylor: Lessons from history - Case studies that might help spot where t...
Mike Taylor: Lessons from history - Case studies that might help spot where t...Mike Taylor: Lessons from history - Case studies that might help spot where t...
Mike Taylor: Lessons from history - Case studies that might help spot where t...
 
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
 
Khatibi lecture cov.uni
Khatibi lecture cov.uniKhatibi lecture cov.uni
Khatibi lecture cov.uni
 
A content analysis of human factors in the design of marine systems ICSOT 2010
A content analysis of human factors in the design of marine systems ICSOT 2010A content analysis of human factors in the design of marine systems ICSOT 2010
A content analysis of human factors in the design of marine systems ICSOT 2010
 
SUBROGATING THE SLIP AND FALL
SUBROGATING THE SLIP AND FALLSUBROGATING THE SLIP AND FALL
SUBROGATING THE SLIP AND FALL
 
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
 
FMEA-Intro.ppt
FMEA-Intro.pptFMEA-Intro.ppt
FMEA-Intro.ppt
 
Forensic Engineering
Forensic EngineeringForensic Engineering
Forensic Engineering
 
Compact Spring Supports Webinar
Compact Spring Supports WebinarCompact Spring Supports Webinar
Compact Spring Supports Webinar
 
860686
860686860686
860686
 
FINAL The Owens Lake Turnout Facility End Cap Study
FINAL The Owens Lake Turnout Facility End Cap StudyFINAL The Owens Lake Turnout Facility End Cap Study
FINAL The Owens Lake Turnout Facility End Cap Study
 
2017 03-10 - vu amsterdam - testing safety critical systems
2017 03-10 - vu amsterdam - testing safety critical systems2017 03-10 - vu amsterdam - testing safety critical systems
2017 03-10 - vu amsterdam - testing safety critical systems
 
Unit 9 implementing the reliability strategy
Unit 9  implementing the reliability strategyUnit 9  implementing the reliability strategy
Unit 9 implementing the reliability strategy
 
comparison of FACTOR OF SAFETY using LIMIT EQUILIBRIUM(OASYS) and NUMERICAL M...
comparison of FACTOR OF SAFETY using LIMIT EQUILIBRIUM(OASYS) and NUMERICAL M...comparison of FACTOR OF SAFETY using LIMIT EQUILIBRIUM(OASYS) and NUMERICAL M...
comparison of FACTOR OF SAFETY using LIMIT EQUILIBRIUM(OASYS) and NUMERICAL M...
 
Product assurance
Product assurance Product assurance
Product assurance
 
Targeted assessment program update Greg Connolly
Targeted assessment program update Greg ConnollyTargeted assessment program update Greg Connolly
Targeted assessment program update Greg Connolly
 

More from dinesh babu

Metrology Measurements and All units PPT
Metrology Measurements and  All units PPTMetrology Measurements and  All units PPT
Metrology Measurements and All units PPT
dinesh babu
 
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptxUnit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
dinesh babu
 
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptxUnit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
dinesh babu
 
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptxUnit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
dinesh babu
 
UNIT 2-Geometric Modeling.pptx
UNIT 2-Geometric Modeling.pptxUNIT 2-Geometric Modeling.pptx
UNIT 2-Geometric Modeling.pptx
dinesh babu
 
UNIT 1-INTRODUCTION.pptx
UNIT 1-INTRODUCTION.pptxUNIT 1-INTRODUCTION.pptx
UNIT 1-INTRODUCTION.pptx
dinesh babu
 
UNIT-5FIRE SAFETY AND INSTALLATION.pptx
UNIT-5FIRE SAFETY AND INSTALLATION.pptxUNIT-5FIRE SAFETY AND INSTALLATION.pptx
UNIT-5FIRE SAFETY AND INSTALLATION.pptx
dinesh babu
 
UNIT-4-REFIGERATION PRINCIPLES.pptx
UNIT-4-REFIGERATION PRINCIPLES.pptxUNIT-4-REFIGERATION PRINCIPLES.pptx
UNIT-4-REFIGERATION PRINCIPLES.pptx
dinesh babu
 
UNIT-3-Principles of illumination.pptx
UNIT-3-Principles of illumination.pptxUNIT-3-Principles of illumination.pptx
UNIT-3-Principles of illumination.pptx
dinesh babu
 
UNIT-2-Electrical Systems.pptx
UNIT-2-Electrical Systems.pptxUNIT-2-Electrical Systems.pptx
UNIT-2-Electrical Systems.pptx
dinesh babu
 
UNIT-1-MACHINERIES.pptx
UNIT-1-MACHINERIES.pptxUNIT-1-MACHINERIES.pptx
UNIT-1-MACHINERIES.pptx
dinesh babu
 
UNIT- 2&3 based on gear life.pdf
UNIT- 2&3 based on gear life.pdfUNIT- 2&3 based on gear life.pdf
UNIT- 2&3 based on gear life.pdf
dinesh babu
 
ELEMENTS OF TECHNOLOGY.pdf
ELEMENTS OF TECHNOLOGY.pdfELEMENTS OF TECHNOLOGY.pdf
ELEMENTS OF TECHNOLOGY.pdf
dinesh babu
 
belt_drive.ppt
belt_drive.pptbelt_drive.ppt
belt_drive.ppt
dinesh babu
 
Unit iii
Unit iiiUnit iii
Unit iii
dinesh babu
 
Unit ii engine auxiliary systems
Unit ii engine auxiliary systemsUnit ii engine auxiliary systems
Unit ii engine auxiliary systems
dinesh babu
 
Unit i
Unit iUnit i
Unit i
dinesh babu
 
Unitv
Unitv   Unitv
Unitv
dinesh babu
 
Unit iv
Unit ivUnit iv
Unit iv
dinesh babu
 
Mm -unit iii
Mm -unit iii Mm -unit iii
Mm -unit iii
dinesh babu
 

More from dinesh babu (20)

Metrology Measurements and All units PPT
Metrology Measurements and  All units PPTMetrology Measurements and  All units PPT
Metrology Measurements and All units PPT
 
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptxUnit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
 
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptxUnit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
 
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptxUnit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
 
UNIT 2-Geometric Modeling.pptx
UNIT 2-Geometric Modeling.pptxUNIT 2-Geometric Modeling.pptx
UNIT 2-Geometric Modeling.pptx
 
UNIT 1-INTRODUCTION.pptx
UNIT 1-INTRODUCTION.pptxUNIT 1-INTRODUCTION.pptx
UNIT 1-INTRODUCTION.pptx
 
UNIT-5FIRE SAFETY AND INSTALLATION.pptx
UNIT-5FIRE SAFETY AND INSTALLATION.pptxUNIT-5FIRE SAFETY AND INSTALLATION.pptx
UNIT-5FIRE SAFETY AND INSTALLATION.pptx
 
UNIT-4-REFIGERATION PRINCIPLES.pptx
UNIT-4-REFIGERATION PRINCIPLES.pptxUNIT-4-REFIGERATION PRINCIPLES.pptx
UNIT-4-REFIGERATION PRINCIPLES.pptx
 
UNIT-3-Principles of illumination.pptx
UNIT-3-Principles of illumination.pptxUNIT-3-Principles of illumination.pptx
UNIT-3-Principles of illumination.pptx
 
UNIT-2-Electrical Systems.pptx
UNIT-2-Electrical Systems.pptxUNIT-2-Electrical Systems.pptx
UNIT-2-Electrical Systems.pptx
 
UNIT-1-MACHINERIES.pptx
UNIT-1-MACHINERIES.pptxUNIT-1-MACHINERIES.pptx
UNIT-1-MACHINERIES.pptx
 
UNIT- 2&3 based on gear life.pdf
UNIT- 2&3 based on gear life.pdfUNIT- 2&3 based on gear life.pdf
UNIT- 2&3 based on gear life.pdf
 
ELEMENTS OF TECHNOLOGY.pdf
ELEMENTS OF TECHNOLOGY.pdfELEMENTS OF TECHNOLOGY.pdf
ELEMENTS OF TECHNOLOGY.pdf
 
belt_drive.ppt
belt_drive.pptbelt_drive.ppt
belt_drive.ppt
 
Unit iii
Unit iiiUnit iii
Unit iii
 
Unit ii engine auxiliary systems
Unit ii engine auxiliary systemsUnit ii engine auxiliary systems
Unit ii engine auxiliary systems
 
Unit i
Unit iUnit i
Unit i
 
Unitv
Unitv   Unitv
Unitv
 
Unit iv
Unit ivUnit iv
Unit iv
 
Mm -unit iii
Mm -unit iii Mm -unit iii
Mm -unit iii
 

Recently uploaded

ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 

Recently uploaded (20)

ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 

Fmea

  • 1. Failure Analysis & Prevention
  • 2. Failure analysis - FA is a systematic approach of investigation to establish the important causes of the failure. Therefore, it is worth to familiarize with – fundamental causes of failure of mechanical components, – general approach to be used for the failure analysis and prevention. 2
  • 3. When to consider a failure • In general, an engineering component or assembly is considered to have failed under the following three conditions when the component is –Inoperable, – Operates but doesn’t perform the intended function – Operates but safety and reliability is very poor 3
  • 4. Failure of mechanical components » Failure of a mechanical component can occur in many ways » – elastic deformation is beyond acceptable limit, » – excessive and unacceptable level of plastic deformation, » – complete fracture and » – loss of dimension due to variety of reasons » Elastic deformation » Plastic deformation » Creep » Fracture » wear 4
  • 5. Fundamental causes of failure » The failure of an engineering component in actual working conditions can occur due to very large of factors related with » – Design, » – Materials, » – Manufacturing, » – Service conditions. 5
  • 6. Need to know causes of failure » To have systematic understanding on various factors that can lead to failure of mechanical components : » – Improper design » – Improper selection of materials » – Defects and discontinuities in metal itself » – Improper processing of materials » – Poor service conditions » – Poor assembling » – Poor maintenance 6
  • 7. Engineering disasters » A disaster is referred to as an engineering disaster when it’s caused by an engineering failure: » – design flaws or » – materials failures » – insufficient knowledge, » – different underestimations, » – even carelessness or negligence. 7
  • 8. Titanic Ship, 1912 » RMS Titanic was a British passenger ship that sank after hitting an iceberg on her maiden voyage from Southampton (UK) to New York City, in April 1912. The tragedy claimed the lives of over 1,500 people. » Several rivets of the 3 million rivets that held the Titanic together were recently recovered and tested, and found to be made of low quality iron, which on impact caused them to fall apart. » Another engineering fault was that the 16 watertight compartments that kept the boat afloat, were not individually sealed, but rather connected near the ceiling. This enabled the water to spill from one compartment to another and sink the boat. 8
  • 9. St. Francis Dam flooding (1928) » The St. Francis Dam was a concrete dam built between the years 1924 and 1926, to create a water reservoir for Los Angeles. » The dam was located in a canyon around 40 miles (64 km) from the city. » On March 12, 1928, just hours after being inspected by the Chief Engineer William Mulholland, the dam failed, sending a massive water wave 120 ft tall, and killing as many as 600 people in one of the worst American civil engineering disaster 9
  • 10. Tacoma Narrows Bridge collapse (1940) » The first Tacoma Narrows Bridge was a suspension bridge in Washington state that opened in 1940 and collapsed at the same year. At the time of its construction, the bridge was the world’s third longest suspension bridge, by main span length. » The bridge was known to move vertically in windy conditions, and in November 7, 1940, under 40 mph (64 km/h) winds it collapsed. The collapse was caught on video and made an impact on science and engineering, especially bridge designing till today » . The cause of failure was aero elastic flutter – a dynamic instability of an elastic structure. 10
  • 11. Kadalundi Train Disaster » There was a structural failure. The railway bridge was around 140 years old and it definitely needed repair. » What happened was one of the pier had settled down causing internal stresses to grow in rails. » As soon as a train came near it, the track snapped and the train derailed which eventually landed into river. » So lesson one, never ever use a structure of high importance without testing it. Always, keep an eye on it and test it 11
  • 12. The Bhopal Disaster: Union Carbide 12
  • 13. Rafiganj rail bridge » Blamed to poor design and construction as well as low maintenance. » It is said that the plate girder deteriorated over time and was losing its strength in fatigue due to vibrations from trains. » Nobody paid attention to it. Also the bridge was rusty to a great extent. » When the train was passing by, the plate girder gave up leading to this fatal crash. » Lesson two, make sure your design is checked against fatigue and steel is coated with anti-corrosion paints. 13
  • 14. Industrial Engineering Tools for FA: Failure Mode & Effect Analysis » What Is A Failure Mode? » A Failure Mode is: » The way in which the component, subassembly, product, input, or process can fail to perform its intended function » Things that can go wrong 14
  • 15. Benefits of FMEA » Methodology that facilitates process improvement » Identifies and eliminates concerns early in the development of a process or design » Focuses on prevention 15 Approach of FMEA A structured approach for : – Identifying the ways in which a product or process can fail – Estimating risk associated with specific causes – Prioritizing the actions that should be taken to reduce risk – Evaluating design validation plan (design FMEA) or current control plan (process FMEA)
  • 16. When to Conduct an FMEA » Investigation for the process improvement investigation » Design of new systems, products, and processes » Modification of existing designs or processes » Existing designs for new applications 16
  • 17. FMEA: A Team Tool » A team approach is necessary. » Team should be led by the Process Owner who is the responsible manufacturing engineer or technical person, or other similar individual familiar with FMEA. » The following should be considered for team members: » – Design Engineers » – Operators » – Process Engineers » – Reliability » – Materials Suppliers » – Suppliers » – Customers 17
  • 18. FMEA Procedure » For each process input (start with high value inputs), determine the ways in which the input can go wrong (failure mode) » For each failure mode, determine effects – Select a severity level for each effect » Identify potential causes of each failure mode – Select an occurrence level for each cause » List current controls for each cause – Select a detection level for each cause » Calculate the Risk Priority Number (RPN) » Develop recommended actions, assign responsible persons, and take actions – -Give priority to high RPNs – MUST look at severities rated a 10 » Assign the predicted severity, occurrence, and detection levels and compare RPNs 18
  • 19. Severity, Occurrence, and Detection » Severity – Importance of the effect on requirements » Occurrence – Frequency with which a given cause occurs and creates failure modes (obtain from past data if possible) » Detection – The ability of the current control scheme to detect (then prevent) a given cause (may be difficult to estimate early in process operations). 19
  • 20. Rating Scales & RPN » There are a wide variety of scoring “anchors”, both quantitative or qualitative » Two types of scales are 1-5 or 1-10 • The 1-5 scale makes it easier for the teams to decide on scores » The 1-10 scale may allow for better precision in estimates and a wide variation in scores (most common) » Severity – 1 = Not Severe, 10 = Very Severe » Occurrence – 1 = Not Likely, 10 = Very Likely » Detection – 1 = Easy to Detect, 10 = Not easy to Detect » RPN is the product of the severity, occurrence, and detection scores. 20
  • 22. THANKS! STAY HOME & STAY SAFE 22