SlideShare a Scribd company logo
1 of 13
1NCR Confidential
CONTROL PLAN
2NCR Confidential
Control Plan
A document that describes how to
control the critical inputs to
continue to meet customer
expectations of the output.
What is It?
Objective or Purpose
• Primary reference source for
minimizing process and product
variation.
• Description of how teams should
react to out-of-control situations.
Since processes are expected to be continuously
updated and improved, the control plan
is a living document!
NOTE
When to Use It
• Implementation of new process
• Following a process change
3NCR Confidential
Process Steps
New/Revised Process
Steps
Project Idea
Fill Out Master
Form
with Initial
Information
Is Hard
Savings > $???
Does the
Project Involve
Only Your
Group?
Does the
Project Involve
>3 Depts.
outside Eng?
Does the
Project Involve
>2 Groups in
Eng?
Do you
have BB/GB to
Assist/Work the
project?
Prefer to work
this project
within your
area?
6 Sigma
Project
Department
or Group
Project
Yes
No
Yes
No
Yes
No
No
No
Yes
Yes
Yes No
Enter Remaining
Information on
Master Form
Master Form Will
Generate
Contract
Finance Approval
and Signature
Other Required
Signatures:
Segment CEO
Champion
Process Owner
BB or GB
6 Sigma Assigns
Project Number
Get WO Assigned
Begin/Work
Project
Follow DMAIC or
DFSS process
Monitor Progress
through Power
Steering and
Monthly
Financial
Reviews
Complete Project
(Has to be fully
Documented
Finance Approval
and Signature
Other Required
Signatures:
Champion: Dir T&E
Process Owner
Project Owner
Dept BB or MBB
Enter Remaining
Information on
Master Form
Master Form Will
Generate
Contract
Finance Approval
and Signature
Other Required
Signatures:
Champion:
Process Owner
Project Owner
Dept GB/BB/MBB
Group Assigns
Project Number
Get DLN
Assigned
Monitor Progress
through Bi-
Weekly Updates
and Monthly
Reviews
Begin/Work
Project
Follow DMAIC or
DFSS process
Complete Project
(Has to be fully
Documented)
Finance Approval
and Signature
Other Required
Signatures:
Champion: Dir T&E
Process Owner
Project Owner
Dept BB or MBB
Complete all
Documentation
including a
(1) Page Close-
out Sheet
Close
Project
Complete all
Documentation
including a
(1) Page Close-
out Sheet
Final Project
Review
Close
Project
Final Project
Review
6 Sigma Project
High Level Process Map
Department/Group Project
High Level Process Map
Process Flowchart
Process Step
Key
Process
Input
Potential
Failure Mode
Potential
Failure Effects
S
E
V
Potential Causes
O
C
C
Current Controls
D
E
T
R
P
N
E
O
C
Actions
Recommended
Resp. Actions
Receive
Payment
Checks Delay internal
mail
AR balance does
not go down
7
Inadequate
staffing in mail
room 7
None
10 490
Investigate mail room
staffing and associated
processes
G. Lee Added anoth
clerk. Adjus
schedule.
Identify
Customer
Wire
Transfer
reference
line
Information not
supplied
AR balance is
past due
10
Customer or bank
did not include
name and/or
account info on
wire transfer
5
Acct identifies problem
when trying to apply
payment
5 250
Poka-Yoke wire transer
process
N. Peart Contacted b
established w
transfer proc
2112)
Identify Invoice Checks Incorrect
invoice
supplied
Invoice shows
outstanding (AR
balance does go
down)
5
Customer error
5
Customer might catch
it when reviewing the
next statement 10 250
Provide payment stub
with statement for each
invoice
A. Lifeson Revised stat
include paym
with each inv
Identify Invoice Checks Invoice number
not supplied
Invoice shows
outstanding (AR
balance does go
down)
5
Customer error
10
Acct identifies problem
when trying to apply
payment 5 250
Provide payment stub
with statement for each
invoice
S. Hagar Revised stat
include paym
with each inv
Process FMEA
Control Plan
Tool Interaction
Control Plan
4NCR Confidential
Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.)
Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.)
Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.)
Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.)
Size Freq.
CONTROL PLAN
Part/Process
Number
Process
Name/Operation
Description
Machine,
Device,
Jig, Tools,
for MFG.
Characteristics
Special
Char.
Class
No. Product Process
Methods
Sample
Product/Process
Specification/
Tolerance
Evaluation
/Measure
ment
Technique
Control
Method
Prototype Pre-Launch Production
Reaction
Plan
NCR’s Control Plan
This is included in the
PPAP Playbook!
5NCR Confidential
Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.)
Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.)
Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.)
Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.)
Size Freq.
CONTROL PLAN
Part/Process
Number
Process
Name/Operation
Description
Machine,
Device,
Jig, Tools,
for MFG.
Characteristics
Special
Char.
Class
No. Product Process
Methods
Sample
Product/Process
Specification/
Tolerance
Evaluation
/Measure
ment
Technique
Control
Method
Prototype Pre-Launch Production
Reaction
Plan
Control Plan
3 Distinct Phases
1. Prototype – a description of the
dimensional measurements and
material and performance tests that
will occur during Prototype build.
3 Distinct Phases
3 Distinct Phases
2. Pre-Launch – a description of the
dimensional measurements and
material and performance tests that
will occur after Prototype and before
full Production.
3 Distinct Phases
3. Production – a comprehensive
documentation of product/process
characteristics, process controls,
tests, and measurement systems that
will occur during mass production
6NCR Confidential
Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.)
Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.)
Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.)
Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.)
Size Freq.
CONTROL PLAN
Part/Process
Number
Process
Name/Operation
Description
Machine,
Device,
Jig, Tools,
for MFG.
Characteristics
Special
Char.
Class
No. Product Process
Methods
Sample
Product/Process
Specification/
Tolerance
Evaluation
/Measure
ment
Technique
Control
Method
Prototype Pre-Launch Production
Reaction
Plan
Control Plan
Administrative Section
Identifies part number and description,
supplier, required approval signatures,
and dates.
Administrative Section
7NCR Confidential
Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.)
Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.)
Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.)
Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.)
Size Freq.
CONTROL PLAN
Part/Process
Number
Process
Name/Operation
Description
Machine,
Device,
Jig, Tools,
for MFG.
Characteristics
Special
Char.
Class
No. Product Process
Methods
Sample
Product/Process
Specification/
Tolerance
Evaluation
/Measure
ment
Technique
Control
Method
Prototype Pre-Launch Production
Reaction
Plan
Control Plan
Part/Process
Use this area to define
part/process number and
description.
Machine/Tools
List the machine, device, jig, or tools
that will be used in the
manufacturing process
Characteristics
Define the characteristics
of the product or process
Process, Machine/Tools, Characteristics
8NCR Confidential
Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.)
Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.)
Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.)
Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.)
Size Freq.
CONTROL PLAN
Part/Process
Number
Process
Name/Operation
Description
Machine,
Device,
Jig, Tools,
for MFG.
Characteristics
Special
Char.
Class
No. Product Process
Methods
Sample
Product/Process
Specification/
Tolerance
Evaluation
/Measure
ment
Technique
Control
Method
Prototype Pre-Launch Production
Reaction
Plan
Control Plan
Specifications/Tolerance
Use this area to define upper/lower
spec limits for each control element.
Measurement Technique
For each line in the control plan, list the
measurement procedure that will be
used (may list R&R Gage Plan or Poka-
Yoke).
Sample Size
What is the size of the
sample you should gather
data from?
Frequency
Define the frequency for
which the measurement
will be taken.
Specifications, Measurement, Sample Size & Frequency
9NCR Confidential
Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.)
Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.)
Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.)
Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.)
Size Freq.
CONTROL PLAN
Part/Process
Number
Process
Name/Operation
Description
Machine,
Device,
Jig, Tools,
for MFG.
Characteristics
Special
Char.
Class
No. Product Process
Methods
Sample
Product/Process
Specification/
Tolerance
Evaluation
/Measure
ment
Technique
Control
Method
Prototype Pre-Launch Production
Reaction
Plan
Control Plan
Control Method
Method that will be used
to control the process
Reaction Plan
Actions to be taken if
controls fail
Control Method, Reaction Plan
10NCR Confidential
Control Plan
Audit Plans
•Audit plans should be included in the control plan as a
separate line.
•Auditing is an important tool for control.
•Process auditing should be a key element of the quality
system of a business.
•Audits generally cover:
Effectiveness of controls
Control plan (say) vs. what is actually done (do)
•Audits should be objective (done by internal or external third
parties if possible).
•Audit frequencies should be based on balancing level of risk
(FMEA) and cost.
11NCR Confidential
Control Plan – Example
Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.)
002 T. Smith / 313-555-5555 11/29/2009 2/20/2010
Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.)
54321231 / D Erin Hope, Alan Burt, Ken Light
Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.)
Electronic Circuit Board
Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.)
ACR Control 439412
Size Freq.
2
Soldering
Connections
Wave
solder
machine
Wave
solder
height 2.0 +/- .25 mc
Sensor
continuity
check 100% Continuous
Automated
inspection
(error
proofing)
Adjust and
retest
Flux
concen -
tration Standard #302B
Test sampling
lab
environment 1 pc 4 hours x-MR chart
Segregate
and retest
Prototype Pre-Launch Production
Reaction
Plan
Sample
Product/Process
Specification/
Tolerance
Evaluation /
Measurement
Technique
Control
Method
CONTROL PLAN
Part /
Process
Number
Process Name
/ Operation
Description
Machine,
Device,
Jig, Tools,
for MFG.
Characteristics
Special
Char.
Class
No. Product Process
Methods
A supplier manufactures a circuit board with electronic components soldered on the
board. Properly soldered connections are the major product characteristics. Two major
process characteristics for the wave solder machine are solder level and flux
concentration. An automated feeder controls the solder level by sensing the level of
solder and feeding in additional solder as the level is reduced. This characteristic is
measured 100% by checking electrically for continuity. The flux must be sampled and
tested for the concentration level.
3 Distinct Phases
Production
Part/Process
Soldering Connections
Machine/Tools
Wave solder machine
Characteristics
Product = Wave solder height
Process = Flux concentration
Specifications/Tolerance
Product = 2.0 +/- 0.25 mc
Process = Standard #302B
Measurement Technique
Product = Sensor continuity check
Process = Test sampling lab environment
Sample Size
Product = 100%
Process = 1 pc
Frequency
Product = Continuous
Process = 4 hours
Control Method
Product = Automated inspection
Process = x-MR chart
Reaction Plan
Product = Adjust and retest
Process = Segregate and retest
12NCR Confidential
Instructions
•Open the PPAP Training Templates.xls file, then select
the Control Plan worksheet.
•Using the completed Star Process Flow Diagram
(process steps 20 and 25) and the completed PFMEA,
complete 2 rows of the Control Plan.
•Document potential problems that might be
encountered and potential solutions with your teams.
Control Plan Exercise
20 Minutes
Use the file PPAP Training Templates.xls
13NCR Confidential
Control Plan
Use process flow diagram and PFMEA to build the control
plan; keep them aligned
Controls must be used to be effective. Keep it simple.
Ensure that the control plan is in the document control
system of the business
Good control plans address:
All testing requirements - dimensional, material, and performance
All product and process characteristics at every step throughout the process
The control method should be based on an effective analysis
of the process
Such as SPC, Error Proofing, Inspection, Sampling Plan
Control plans should reference other documentation
Specifications, tooling, etc.
Reviewer’s Checklist

More Related Content

What's hot (20)

Spc training
Spc training Spc training
Spc training
 
Production part approval process ppt 1
Production part approval process ppt 1Production part approval process ppt 1
Production part approval process ppt 1
 
The Basics 7 QC Tools - ADDVALUE - Nilesh Arora
The Basics 7 QC Tools - ADDVALUE - Nilesh AroraThe Basics 7 QC Tools - ADDVALUE - Nilesh Arora
The Basics 7 QC Tools - ADDVALUE - Nilesh Arora
 
Measurement System Analysis (MSA)
Measurement System Analysis (MSA)Measurement System Analysis (MSA)
Measurement System Analysis (MSA)
 
Control plan overview
Control plan overviewControl plan overview
Control plan overview
 
PFMEA
PFMEAPFMEA
PFMEA
 
8D analysis presentation
8D analysis presentation8D analysis presentation
8D analysis presentation
 
Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01
 
Iatf 16949 training
Iatf 16949 trainingIatf 16949 training
Iatf 16949 training
 
PPT Presentation on IATF 16949 Documentation
PPT Presentation on IATF 16949 DocumentationPPT Presentation on IATF 16949 Documentation
PPT Presentation on IATF 16949 Documentation
 
Training module 4 m change
Training module   4 m changeTraining module   4 m change
Training module 4 m change
 
APQP
APQPAPQP
APQP
 
List of mandatory IATF 16949 documents
List of mandatory IATF 16949 documents List of mandatory IATF 16949 documents
List of mandatory IATF 16949 documents
 
Process fmea
Process fmea Process fmea
Process fmea
 
MSA (GR&R)
MSA (GR&R)MSA (GR&R)
MSA (GR&R)
 
Design fmea
Design fmeaDesign fmea
Design fmea
 
APQP
APQP APQP
APQP
 
Ppap training presentation
Ppap   training presentationPpap   training presentation
Ppap training presentation
 
FMEA training (AIAG VDA Edition 01)
FMEA training (AIAG VDA Edition 01)FMEA training (AIAG VDA Edition 01)
FMEA training (AIAG VDA Edition 01)
 
PFMEA
PFMEA PFMEA
PFMEA
 

Similar to Training ppt for control plan

04 ppap training material
04 ppap training material04 ppap training material
04 ppap training material營松 林
 
Plex Supply Chain Community Conference
Plex Supply Chain Community Conference Plex Supply Chain Community Conference
Plex Supply Chain Community Conference Rev_Group
 
BB Project on AHT .pptx
BB Project on AHT .pptxBB Project on AHT .pptx
BB Project on AHT .pptxPankaj Kumar
 
Six sigma-measure-phase2505
Six sigma-measure-phase2505Six sigma-measure-phase2505
Six sigma-measure-phase2505densongco
 
MARINEW Resume
MARINEW ResumeMARINEW Resume
MARINEW Resumemari muthu
 
Zero Defect Competition @ July 22.pptx
Zero Defect Competition  @ July 22.pptxZero Defect Competition  @ July 22.pptx
Zero Defect Competition @ July 22.pptxsonutyagi20
 
Basics of defining processes
Basics of defining processesBasics of defining processes
Basics of defining processesFaried Sandianto
 
2 1 Determine Measure Vsw Edits(Rev)
2 1 Determine Measure Vsw Edits(Rev)2 1 Determine Measure Vsw Edits(Rev)
2 1 Determine Measure Vsw Edits(Rev)gueste14b0f
 
Control phase lean six sigma tollgate template
Control phase   lean six sigma tollgate templateControl phase   lean six sigma tollgate template
Control phase lean six sigma tollgate templateSteven Bonacorsi
 
Control phase lean six sigma tollgate template
Control phase   lean six sigma tollgate templateControl phase   lean six sigma tollgate template
Control phase lean six sigma tollgate templateSteven Bonacorsi
 
jabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdfjabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdfTraptiSharma28
 
Improve phase lean six sigma tollgate template
Improve phase   lean six sigma tollgate templateImprove phase   lean six sigma tollgate template
Improve phase lean six sigma tollgate templateSteven Bonacorsi
 
Improve phase lean six sigma tollgate template
Improve phase   lean six sigma tollgate templateImprove phase   lean six sigma tollgate template
Improve phase lean six sigma tollgate templateSteven Bonacorsi
 
6 sigma-process-mapping-1233778357447980-3
6 sigma-process-mapping-1233778357447980-36 sigma-process-mapping-1233778357447980-3
6 sigma-process-mapping-1233778357447980-3jseets
 
Control-Plan-Training.pptx for the Automotive standard AIAG
Control-Plan-Training.pptx for the Automotive standard AIAGControl-Plan-Training.pptx for the Automotive standard AIAG
Control-Plan-Training.pptx for the Automotive standard AIAGVikrantPawar37
 
Six_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxSix_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxPhngPhmTrung
 

Similar to Training ppt for control plan (20)

04 ppap training material
04 ppap training material04 ppap training material
04 ppap training material
 
Plex Supply Chain Community Conference
Plex Supply Chain Community Conference Plex Supply Chain Community Conference
Plex Supply Chain Community Conference
 
Six Sigma Process Improvement Foundational Steps
Six Sigma Process Improvement Foundational StepsSix Sigma Process Improvement Foundational Steps
Six Sigma Process Improvement Foundational Steps
 
BB Project on AHT .pptx
BB Project on AHT .pptxBB Project on AHT .pptx
BB Project on AHT .pptx
 
Six sigma-measure-phase2505
Six sigma-measure-phase2505Six sigma-measure-phase2505
Six sigma-measure-phase2505
 
Ppaptr
PpaptrPpaptr
Ppaptr
 
PPAP.ppt
PPAP.pptPPAP.ppt
PPAP.ppt
 
MARINEW Resume
MARINEW ResumeMARINEW Resume
MARINEW Resume
 
Zero Defect Competition @ July 22.pptx
Zero Defect Competition  @ July 22.pptxZero Defect Competition  @ July 22.pptx
Zero Defect Competition @ July 22.pptx
 
Basics of defining processes
Basics of defining processesBasics of defining processes
Basics of defining processes
 
2 1 Determine Measure Vsw Edits(Rev)
2 1 Determine Measure Vsw Edits(Rev)2 1 Determine Measure Vsw Edits(Rev)
2 1 Determine Measure Vsw Edits(Rev)
 
Control phase lean six sigma tollgate template
Control phase   lean six sigma tollgate templateControl phase   lean six sigma tollgate template
Control phase lean six sigma tollgate template
 
Control phase lean six sigma tollgate template
Control phase   lean six sigma tollgate templateControl phase   lean six sigma tollgate template
Control phase lean six sigma tollgate template
 
jabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdfjabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdf
 
Improve phase lean six sigma tollgate template
Improve phase   lean six sigma tollgate templateImprove phase   lean six sigma tollgate template
Improve phase lean six sigma tollgate template
 
Improve phase lean six sigma tollgate template
Improve phase   lean six sigma tollgate templateImprove phase   lean six sigma tollgate template
Improve phase lean six sigma tollgate template
 
Ap test script
Ap test scriptAp test script
Ap test script
 
6 sigma-process-mapping-1233778357447980-3
6 sigma-process-mapping-1233778357447980-36 sigma-process-mapping-1233778357447980-3
6 sigma-process-mapping-1233778357447980-3
 
Control-Plan-Training.pptx for the Automotive standard AIAG
Control-Plan-Training.pptx for the Automotive standard AIAGControl-Plan-Training.pptx for the Automotive standard AIAG
Control-Plan-Training.pptx for the Automotive standard AIAG
 
Six_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxSix_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptx
 

More from Jitesh Gaurav (20)

What i es do iie iab v2
What i es do iie iab v2What i es do iie iab v2
What i es do iie iab v2
 
Weld material
Weld materialWeld material
Weld material
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Spi link
Spi linkSpi link
Spi link
 
6 Sigma - Chapter3
6 Sigma - Chapter36 Sigma - Chapter3
6 Sigma - Chapter3
 
6 Sigma - Chapter2
6 Sigma - Chapter26 Sigma - Chapter2
6 Sigma - Chapter2
 
6 Sigma - Chapter1
6 Sigma - Chapter16 Sigma - Chapter1
6 Sigma - Chapter1
 
6 Sigma - Chapter8
6 Sigma - Chapter86 Sigma - Chapter8
6 Sigma - Chapter8
 
6 Sigma - Chapter7
6 Sigma - Chapter76 Sigma - Chapter7
6 Sigma - Chapter7
 
6 Sigma - Chapter6
6 Sigma - Chapter66 Sigma - Chapter6
6 Sigma - Chapter6
 
6 Sigma - Chapter5
6 Sigma - Chapter56 Sigma - Chapter5
6 Sigma - Chapter5
 
6 Sigma - Chapter4
6 Sigma - Chapter46 Sigma - Chapter4
6 Sigma - Chapter4
 
Pattern production
Pattern productionPattern production
Pattern production
 
smed
smedsmed
smed
 
Methods of kaizen
Methods of kaizenMethods of kaizen
Methods of kaizen
 
Dfmea rating
Dfmea ratingDfmea rating
Dfmea rating
 
Qip
QipQip
Qip
 
Rodebaugh sixsigma[1]
Rodebaugh sixsigma[1]Rodebaugh sixsigma[1]
Rodebaugh sixsigma[1]
 
Tqm
TqmTqm
Tqm
 
Tpm+basics
Tpm+basicsTpm+basics
Tpm+basics
 

Recently uploaded

Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfJNTUA
 
Computer Graphics - Windowing and Clipping
Computer Graphics - Windowing and ClippingComputer Graphics - Windowing and Clipping
Computer Graphics - Windowing and ClippingChandrakantDivate1
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docxrahulmanepalli02
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...archanaece3
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxMustafa Ahmed
 
Danikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfDanikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfthietkevietthinh
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxMustafa Ahmed
 
Circuit Breakers for Engineering Students
Circuit Breakers for Engineering StudentsCircuit Breakers for Engineering Students
Circuit Breakers for Engineering Studentskannan348865
 
Working Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfWorking Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfSkNahidulIslamShrabo
 
Scouring of cotton and wool fabric with effective scouring method
Scouring of cotton and wool fabric with effective scouring methodScouring of cotton and wool fabric with effective scouring method
Scouring of cotton and wool fabric with effective scouring methodvimal412355
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Stationsiddharthteach18
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2ChandrakantDivate1
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxMustafa Ahmed
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelDrAjayKumarYadav4
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 

Recently uploaded (20)

Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
 
Computer Graphics - Windowing and Clipping
Computer Graphics - Windowing and ClippingComputer Graphics - Windowing and Clipping
Computer Graphics - Windowing and Clipping
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Danikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfDanikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdf
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
Circuit Breakers for Engineering Students
Circuit Breakers for Engineering StudentsCircuit Breakers for Engineering Students
Circuit Breakers for Engineering Students
 
Working Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfWorking Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdf
 
Scouring of cotton and wool fabric with effective scouring method
Scouring of cotton and wool fabric with effective scouring methodScouring of cotton and wool fabric with effective scouring method
Scouring of cotton and wool fabric with effective scouring method
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Station
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptx
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 

Training ppt for control plan

  • 2. 2NCR Confidential Control Plan A document that describes how to control the critical inputs to continue to meet customer expectations of the output. What is It? Objective or Purpose • Primary reference source for minimizing process and product variation. • Description of how teams should react to out-of-control situations. Since processes are expected to be continuously updated and improved, the control plan is a living document! NOTE When to Use It • Implementation of new process • Following a process change
  • 3. 3NCR Confidential Process Steps New/Revised Process Steps Project Idea Fill Out Master Form with Initial Information Is Hard Savings > $??? Does the Project Involve Only Your Group? Does the Project Involve >3 Depts. outside Eng? Does the Project Involve >2 Groups in Eng? Do you have BB/GB to Assist/Work the project? Prefer to work this project within your area? 6 Sigma Project Department or Group Project Yes No Yes No Yes No No No Yes Yes Yes No Enter Remaining Information on Master Form Master Form Will Generate Contract Finance Approval and Signature Other Required Signatures: Segment CEO Champion Process Owner BB or GB 6 Sigma Assigns Project Number Get WO Assigned Begin/Work Project Follow DMAIC or DFSS process Monitor Progress through Power Steering and Monthly Financial Reviews Complete Project (Has to be fully Documented Finance Approval and Signature Other Required Signatures: Champion: Dir T&E Process Owner Project Owner Dept BB or MBB Enter Remaining Information on Master Form Master Form Will Generate Contract Finance Approval and Signature Other Required Signatures: Champion: Process Owner Project Owner Dept GB/BB/MBB Group Assigns Project Number Get DLN Assigned Monitor Progress through Bi- Weekly Updates and Monthly Reviews Begin/Work Project Follow DMAIC or DFSS process Complete Project (Has to be fully Documented) Finance Approval and Signature Other Required Signatures: Champion: Dir T&E Process Owner Project Owner Dept BB or MBB Complete all Documentation including a (1) Page Close- out Sheet Close Project Complete all Documentation including a (1) Page Close- out Sheet Final Project Review Close Project Final Project Review 6 Sigma Project High Level Process Map Department/Group Project High Level Process Map Process Flowchart Process Step Key Process Input Potential Failure Mode Potential Failure Effects S E V Potential Causes O C C Current Controls D E T R P N E O C Actions Recommended Resp. Actions Receive Payment Checks Delay internal mail AR balance does not go down 7 Inadequate staffing in mail room 7 None 10 490 Investigate mail room staffing and associated processes G. Lee Added anoth clerk. Adjus schedule. Identify Customer Wire Transfer reference line Information not supplied AR balance is past due 10 Customer or bank did not include name and/or account info on wire transfer 5 Acct identifies problem when trying to apply payment 5 250 Poka-Yoke wire transer process N. Peart Contacted b established w transfer proc 2112) Identify Invoice Checks Incorrect invoice supplied Invoice shows outstanding (AR balance does go down) 5 Customer error 5 Customer might catch it when reviewing the next statement 10 250 Provide payment stub with statement for each invoice A. Lifeson Revised stat include paym with each inv Identify Invoice Checks Invoice number not supplied Invoice shows outstanding (AR balance does go down) 5 Customer error 10 Acct identifies problem when trying to apply payment 5 250 Provide payment stub with statement for each invoice S. Hagar Revised stat include paym with each inv Process FMEA Control Plan Tool Interaction Control Plan
  • 4. 4NCR Confidential Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.) Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.) Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.) Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.) Size Freq. CONTROL PLAN Part/Process Number Process Name/Operation Description Machine, Device, Jig, Tools, for MFG. Characteristics Special Char. Class No. Product Process Methods Sample Product/Process Specification/ Tolerance Evaluation /Measure ment Technique Control Method Prototype Pre-Launch Production Reaction Plan NCR’s Control Plan This is included in the PPAP Playbook!
  • 5. 5NCR Confidential Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.) Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.) Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.) Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.) Size Freq. CONTROL PLAN Part/Process Number Process Name/Operation Description Machine, Device, Jig, Tools, for MFG. Characteristics Special Char. Class No. Product Process Methods Sample Product/Process Specification/ Tolerance Evaluation /Measure ment Technique Control Method Prototype Pre-Launch Production Reaction Plan Control Plan 3 Distinct Phases 1. Prototype – a description of the dimensional measurements and material and performance tests that will occur during Prototype build. 3 Distinct Phases 3 Distinct Phases 2. Pre-Launch – a description of the dimensional measurements and material and performance tests that will occur after Prototype and before full Production. 3 Distinct Phases 3. Production – a comprehensive documentation of product/process characteristics, process controls, tests, and measurement systems that will occur during mass production
  • 6. 6NCR Confidential Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.) Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.) Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.) Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.) Size Freq. CONTROL PLAN Part/Process Number Process Name/Operation Description Machine, Device, Jig, Tools, for MFG. Characteristics Special Char. Class No. Product Process Methods Sample Product/Process Specification/ Tolerance Evaluation /Measure ment Technique Control Method Prototype Pre-Launch Production Reaction Plan Control Plan Administrative Section Identifies part number and description, supplier, required approval signatures, and dates. Administrative Section
  • 7. 7NCR Confidential Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.) Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.) Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.) Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.) Size Freq. CONTROL PLAN Part/Process Number Process Name/Operation Description Machine, Device, Jig, Tools, for MFG. Characteristics Special Char. Class No. Product Process Methods Sample Product/Process Specification/ Tolerance Evaluation /Measure ment Technique Control Method Prototype Pre-Launch Production Reaction Plan Control Plan Part/Process Use this area to define part/process number and description. Machine/Tools List the machine, device, jig, or tools that will be used in the manufacturing process Characteristics Define the characteristics of the product or process Process, Machine/Tools, Characteristics
  • 8. 8NCR Confidential Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.) Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.) Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.) Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.) Size Freq. CONTROL PLAN Part/Process Number Process Name/Operation Description Machine, Device, Jig, Tools, for MFG. Characteristics Special Char. Class No. Product Process Methods Sample Product/Process Specification/ Tolerance Evaluation /Measure ment Technique Control Method Prototype Pre-Launch Production Reaction Plan Control Plan Specifications/Tolerance Use this area to define upper/lower spec limits for each control element. Measurement Technique For each line in the control plan, list the measurement procedure that will be used (may list R&R Gage Plan or Poka- Yoke). Sample Size What is the size of the sample you should gather data from? Frequency Define the frequency for which the measurement will be taken. Specifications, Measurement, Sample Size & Frequency
  • 9. 9NCR Confidential Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.) Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.) Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.) Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.) Size Freq. CONTROL PLAN Part/Process Number Process Name/Operation Description Machine, Device, Jig, Tools, for MFG. Characteristics Special Char. Class No. Product Process Methods Sample Product/Process Specification/ Tolerance Evaluation /Measure ment Technique Control Method Prototype Pre-Launch Production Reaction Plan Control Plan Control Method Method that will be used to control the process Reaction Plan Actions to be taken if controls fail Control Method, Reaction Plan
  • 10. 10NCR Confidential Control Plan Audit Plans •Audit plans should be included in the control plan as a separate line. •Auditing is an important tool for control. •Process auditing should be a key element of the quality system of a business. •Audits generally cover: Effectiveness of controls Control plan (say) vs. what is actually done (do) •Audits should be objective (done by internal or external third parties if possible). •Audit frequencies should be based on balancing level of risk (FMEA) and cost.
  • 11. 11NCR Confidential Control Plan – Example Control Plan Number Key Contact/Phone Date:(Org.) Date (Rev.) 002 T. Smith / 313-555-5555 11/29/2009 2/20/2010 Part Number/Latest Change Level Core Team Customer Engineering Approval/Date (If Req'd.) 54321231 / D Erin Hope, Alan Burt, Ken Light Part Name/Description Supplier/Plant Approval/Date Customer Quality Approval/Date(If Req'd.) Electronic Circuit Board Supplier/Plant Supplier Code Other Approval/Date (If Req'd.) Other Approval/Date (If Req'd.) ACR Control 439412 Size Freq. 2 Soldering Connections Wave solder machine Wave solder height 2.0 +/- .25 mc Sensor continuity check 100% Continuous Automated inspection (error proofing) Adjust and retest Flux concen - tration Standard #302B Test sampling lab environment 1 pc 4 hours x-MR chart Segregate and retest Prototype Pre-Launch Production Reaction Plan Sample Product/Process Specification/ Tolerance Evaluation / Measurement Technique Control Method CONTROL PLAN Part / Process Number Process Name / Operation Description Machine, Device, Jig, Tools, for MFG. Characteristics Special Char. Class No. Product Process Methods A supplier manufactures a circuit board with electronic components soldered on the board. Properly soldered connections are the major product characteristics. Two major process characteristics for the wave solder machine are solder level and flux concentration. An automated feeder controls the solder level by sensing the level of solder and feeding in additional solder as the level is reduced. This characteristic is measured 100% by checking electrically for continuity. The flux must be sampled and tested for the concentration level. 3 Distinct Phases Production Part/Process Soldering Connections Machine/Tools Wave solder machine Characteristics Product = Wave solder height Process = Flux concentration Specifications/Tolerance Product = 2.0 +/- 0.25 mc Process = Standard #302B Measurement Technique Product = Sensor continuity check Process = Test sampling lab environment Sample Size Product = 100% Process = 1 pc Frequency Product = Continuous Process = 4 hours Control Method Product = Automated inspection Process = x-MR chart Reaction Plan Product = Adjust and retest Process = Segregate and retest
  • 12. 12NCR Confidential Instructions •Open the PPAP Training Templates.xls file, then select the Control Plan worksheet. •Using the completed Star Process Flow Diagram (process steps 20 and 25) and the completed PFMEA, complete 2 rows of the Control Plan. •Document potential problems that might be encountered and potential solutions with your teams. Control Plan Exercise 20 Minutes Use the file PPAP Training Templates.xls
  • 13. 13NCR Confidential Control Plan Use process flow diagram and PFMEA to build the control plan; keep them aligned Controls must be used to be effective. Keep it simple. Ensure that the control plan is in the document control system of the business Good control plans address: All testing requirements - dimensional, material, and performance All product and process characteristics at every step throughout the process The control method should be based on an effective analysis of the process Such as SPC, Error Proofing, Inspection, Sampling Plan Control plans should reference other documentation Specifications, tooling, etc. Reviewer’s Checklist