SlideShare a Scribd company logo
1 of 69
Download to read offline
presented by:
MOHD HAZREEN HASHIM
OUTLINE
 INTRODUCTION/SYSTEM OVERVIEW
 OBJECTIVE
 DESIGN BASIS & PHILOSOPHY
 FIRE AREA ZONING
 POSSIBLE MAJOR FIRE SCENARIOS
 FIREWATER DEMAND CALCULATIONS
 PRELIMINARY FIREWATER LINES SIZING
 FIREWATER PUMP SIZING
FIREWATER SYSTEM
 FW systems are one of the systems which used to reduce
the risk of fire and explosion – Active Fire Protection
(AFP).
 Intended to mitigate the consequences of fire/explosion
event by extinguishing or limiting the spread of fire.
OBJECTIVES
 To find maximum firewater demand required for a single
major fire scenario which will dictate the firewater pump
capacity
 To determine required FW pump discharge pressure (to
meet the most hydraulically remote fire fighting
equipment)
 To preliminarily size the FW ringmain and other pipeworks
DESIGN OBJECTIVE
 The purposes of providing FW systems on offshore
facilities including followings:
To protect personnel
Minimise fire damage and thus enable the facility
return to operation ASAP after fire
Minimise escalation which could lead to major damage
and environmental pollution.
DESIGN OBJECTIVE cont’d
 Water can reduce the potential risk resulting from fire by:
Cool high flashpointliquidsor combustiblesolid material
Suffocatesthe firewhen wateris converted to steam
Blanketspool fireswhen appliedwith foam
Cool the environment( air, hot gas, flame, smokeetc) to limit
the spreadof fire by convection
Cool adjacent facilitiesor structuresto prevent firespread by
radiationeffects
Forming heatabsorbing barrierbetween fireand facilities
DESIGN PHILOSOPHY
 In general, the whole facilities will be treated as single fire
area. However, if the FW demand for such area cannot be
satisfied, additional physical separation can be employed
 Zoning segregation is deemed effective enough that only
single fire scenario is assumed to occur at any given time
 Design FW demand is dictated be the largest FW demand
of a single fire event
Requirement for personnel protection during escape
and evacuation / manual fire-fighting by personnel
The FW demand which will be initiated upon fire
detection
DESIGN PHILOSOPHY cont’d
 Operating pressures of fire-fighting equipments such as
monitors, hosereels n light water station are rated at 7.0
barg (100 psig)
 FW pump shall be sized to provide either 100% of the
calculated design fire water demand or an appropriate
fraction of adopted sparing philosophy
 FW ringmain and other piping within the Wet system will
constantly pressurized by jockey pump(s)
DESIGN PHILOSOPHY cont’d
 As per NFPA 20 requirements, the FW pump shall have
maximum capacity not less than 150% of rated capacity
with differential head not less than 65% of differential
head at rated capacity.
CASE STUDY
 FW system on TBCP-A facilities is taken as case study.
FIRE AREA ZONING
 In order to minimize design (largest) FW demand, the
facilities (one large fire area) will be divided into several
smaller fire area as reasonably practicable
 This can be achieved either by employing physical
separation or by forming heat absorbing barrier between
fire and facilities upon fire event
 Physical separation is achieved by installing/providing
firewall, plated deck etc
 Heat absorbing barrier is formed when the adjacent/
neighbouring fire area is spray with water
FIRE AREA ZONING cont’d
 Each fire area is provided with automatic deluge valve
(ADV) or alternatively actuated isolation valve with RO at
the inlet from FW ringmain
 Upon detection of fire, the affected ADV(s) will be
activated (open) to discharge FW to the affected
equipments/area.
 In addition, the adjacent/neighbouring fire zone which
exposed to radiation will be deluged as well.
FIRE AREA ZONING cont’d
Plated Deck
Firewall
FIRE AREA ZONING cont’d
Plated Deck
Firewall
FIRE AREA ZONING cont’d
 From the equipment layout, it is possible to segregate
the facilities into 11 independent fire zones which
require 11 nos of ADV.
POSSIBLE MAJOR FIRE
SCENARIOS
 List of possible major fire scenarios:
No. Scenarios No. Firewater Demand
1 Fire in module 1 Level 2 (North Side) 14 Fire in module 4 Level 3 or Level 2 (South Side)
2 Fire in module 1 Level 2 (South Side) 15 Fire in module 4 Level 1 (North Side)
3 Fire in module 1 Level 1 or Cellar Deck (North Side) 16 Fire in module 4 Level 1 (South Side)
4 Fire in module 1 Level 1 or Cellar Deck (South Side) 17 Fire in module 4 Cellar Deck (North Side)
5 Fire in module 2 Level 2 (North Side) 18 Fire in module 4 Cellar Deck (South Side)
6 Fire in module 2 Level 2 (South Side) 19 Fire in module 5 Level 3 or Level 2 (North Side)
7 Fire in module 2 Level 1 or Cellar Deck (North Side) 20 Fire in module 5 Level 3 or Level 2 (South Side)
8 Fire in module 2 Level 1 or Cellar Deck (South Side) 21 Fire in module 5 Level 1 (North Side)
9 Fire in module 3 Level 3 or Level 2 (North Side) 22 Fire in module 5 Level 1 (South Side)
10 Fire in module 3 Level 3 or Level 2 (South Side) 23 Fire in module 5 Cellar Deck (North Side)
11 Fire in Module 3 Level 1 or Cellar Deck(North Side) 24 Fire in module 5 Cellar Deck (South Side)
12 Fire in Module 3 Level 1 or Cellar Deck(South Side) 25 Fire in Helideck Area
13 Fire in module 4 Level 3 or Level 2 (North Side)
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
MAJOR FIRE SCENARIOS cont’d
Plated Deck
Firewall
DELUGE SYSTEM
 The FW demand is contributed by:
The FW demand which will be initiated upon fire
detection – deluge consumption
Requirement for personnel protection during escape
and evacuation / manual fire-fighting by personnel
 Deluge systems are arrays of open head nozzles which are
fed from a common valve. The nozzles discharge
simultaneously upon opening of the valve.
DELUGE SYSTEM cont’d
 Specific objective of deluge system are:
To providean optimallydesigneddistributionsystemwhich
deliverswaterat design rateto spray nozzles
To providea uniformdistributionof waterat that rate such
that the wholearea requiring protection is adequately
covered.
DELUGE SYSTEM cont’d
 Deluge system may be used effectively for the following
applications:
Extinguishment– by cooling surfacehence reducingvapour
emission rate,suppressfirethroughgenerationof steam
which displaceair, dilutionof water-solubleflammable
liquids,emulsificationat the surfaceof flammableliquidsto
preventreleaseof vapourand making the flameunstablethus
discontinuethe combustion.
Controlof burning – by reducingthe flame temperaturesand
evaporationrate forpool fires
Exposureprotection– by limiting the heat transferred to
personnel,equipmentsand structures
DELUGE SYSTEM cont’d
 Deluge water application rates are varies between types of
protection, generally range from 6.1 lit/min/m2 to 20.4
lit/min/m2 (NFPA 15).
DELUGE SYSTEM cont’d
 Table below shows typical deluge application rate for various type of
equipment/protectionas per PTS 80.47.10.12
DELUGE CONSUMPTION
MODULE 2: BOOSTER COMPRESSOR MODULE
DELUGE VALVE: ADV-5378
COVERAGE AREA: CELLAR DECK & LEVEL 1
As per NFPA 15/
PTS 80.47.10.12
ProjectionArea = Width x Length
Total surface area for a vessel with 2 heads
= ( π x D ) L + [ 2 (1.09 x D2 ) ]
Consumption = Total area x Water rate required
DELUGE CONSUMPTION cont’d
MODULE 2: BOOSTER COMPRESSOR MODULE
DELUGE VALVE: ADV-5378
COVERAGE AREA: CELLAR DECK & LEVEL 1
DELUGE CONSUMPTION cont’d
 Summary of deluge consumptions are tabulated below:
No. Area to be Deluged / Spray ADV Tag No Deluge Consumption
1 Module 1 Level 2 ADV-5370 2186.44 lit/min
2 Module 1 Level 1 and Cellar Deck ADV-5373 3137.70 lit/min
3 Module 2 Level 2 ADV-5375 2186.44 lit/min
4 Module 2 Level 1 and Cellar Deck ADV-5378 1952.78 lit/min
5 Module 3 Level 2 and Level 3 ADV-5380 1489.78 lit/min
6 Module 3 Level 1 and Cellar Deck and
Module 4 Cellar Deck North Side
ADV-5383 4155.69 lit/min
7 Module 4 Level 2 and Level 3 ADV-5385 4674.55 lit/min
8 Module 4 Level 1 ADV-5388 4918.37 lit/min
9 Module 5 Level 3 and Level 2 ADV-5390 7189.23 lit/min
10 Module 5 Level 1 ADV-5393 3756.50 lit/min
11 Module 5 Cellar Deck and Module 4 Cellar
Deck South Side
ADV-5398 837.57 lit/min
FW DEMAND
CALCULATIONS
 FW demand by deluge system for each major fire scenario.
No. Scenarios Area to be Deluged / Spray Firewater Demand
1 Fire in module 1 Level 2 (North Side) 1. Module 1 Level 2 2186.44 lit/min
Sub-Total 2186.44 lit/min = 131.19 m3
/hr
2 Fire in module 1 Level 2 (South Side) 1. Module 1 Level 2 2186.44 lit/min
2. Module 2 Level 2 2186.44 lit/min
Sub-Total 4372.44 lit/min = 262.38 m3/hr
3 Fire in module 1 Level 1 or Cellar Deck
(North Side)
1. Module 1 Level 1 and Cellar Deck 3137.70 lit/min
Sub-Total 3137.70 lit/min = 188.26 m3/hr
4 Fire in module 1 Level 1 or Cellar Deck
(South Side)
1. Module 1 Level 1 and Cellar Deck 3137.70 lit/min
2. Module 2 Level 1 and Cellar Deck 1952.78 lit/min
Sub-Total 5090.48 lit/min = 305.43 m3/hr
5 Fire in module 2 Level 2 (North Side) 1. Module 1 Level 2 2186.44 lit/min
2. Module 2 Level 2 2186.44 lit/min
Sub-Total 4372.44 lit/min = 262.38 m3/hr
6 Fire in module 2 Level 2 (South Side) 1. Module 2 Level 2 2186.44 lit/min
2. Module 3 Level 2 and Level 3 1489.78 lit/min
Sub-Total 3676.22 lit/min = 220.57 m3/hr
FW DEMAND
CALCULATIONS cont’d
 Major fire scenario table continued.
No. Scenarios Area to be Deluged / Spray Firewater Demand
7 Fire in module 2 Level 1 or Cellar Deck
(North Side)
1. Module 2 Level 1 and Cellar Deck 1952.78 lit/min
2. Module 1 Level 1 and Cellar Deck 3137.70 lit/min
Sub-Total 5090.48 lit/min = 305.43 m3
/hr
8 Fire in module 2 Level 1 or Cellar Deck
(South Side)
1. Module 2 Level 1 and Cellar Deck 1952.78 lit/min
2. Module 3 Level 1 and Cellar Deck and
Module 4 Cellar Deck North Side
4155.69 lit/min
Sub-Total 6108.47 lit/min = 366.51 m3/hr
9 Fire in module 3 Level 3 or Level 2 (North
Side)
1. Module 3 Level 2 and Level 3 1489.78 lit/min
2. Module 2 Level 2 2186.44 lit/min
Sub-Total 3676.22 lit/min = 220.57 m3/hr
10 Fire in module 3 Level 3 or Level 2 (South
Side)
1. Module 3 Level 2 and Level 3 1489.78 lit/min
2. Module 4 Level 2 and Level 3 4674.55 lit/min
Sub-Total 6164.33 lit/min = 369.86 m3/hr
11 Fire in Module 3 Level 1 or Cellar Deck
(North Side)
1. Module 3 Level 1 and Cellar Deck and
Module 4 Cellar Deck North Side
4155.69 lit/min
2. Module 2 Level 1 and Cellar Deck 1952.78 lit/min
Sub-Total 6108.47 lit/min = 366.51 m3/hr
FW DEMAND
CALCULATIONS cont’d
 Major fire scenario table continued.
No. Scenarios Area to be Deluged / Spray Firewater Demand
12 Fire in Module 3 Level 1 or Cellar Deck
(South Side)
1. Module 3 Level 1 and Cellar Deck and
Module 4 Cellar Deck North Side
4155.69 lit/min
2. Module 4 Level 1 4918.37 lit/min
Sub-Total 9074.06 lit/min = 544.44 m3/hr
13 Fire in module 4 Level 3 or Level 2 (North
Side)
1. Module 4 Level 2 and Level 3 4674.55 lit/min
2. Module 3 Level 2 and Level 3 1489.78 lit/min
Sub-Total 6164.33lit/min = 369.86 m3/hr
14 Fire in module 4 Level 3 or Level 2 (South
Side)
1. Module 4 Level 2 and Level 3 4674.55 lit/min
2. Module 5 Level 2 and Level 3 7189.23 lit/min
Sub-Total 11863.78 lit/min = 711.83 m3/hr
15 Fire in module 4 Level 1 (North Side) 1. Module 4 Level 1 4918.37 lit/min
2. Module 3 Level 1 and Cellar Deck and
Module 4 Cellar Deck North Side
4155.69 lit/min
Sub-Total 9074.06 lit/min = 544.44 m3/hr
16 Fire in module 4 Level 1 (South Side) 1. Module 4 Level 1 4918.37 lit/min
2. Module 5 Level 1 3756.50 lit/min
Sub-Total 8674.87 lit/min = 520.49 m3/hr
FW DEMAND
CALCULATIONS cont’d
 Major fire scenario table continued.
No. Scenarios Area to be Deluged / Spray Firewater Demand
17 Fire in module 4 Cellar Deck (North Side) 1. Module 3 Level 1 and Cellar Deck and
Module 4 Cellar Deck North Side
4155.67 lit/min
2. Module 5 Cellar Deck and Module 4
Cellar Deck South Side
837.57 lit/min
Sub-Total 4993.24 lit/min = 299.59 m3
/hr
18 Fire in module 4 Cellar Deck (South Side) 1. Module 5 Cellar Deck and Module 4
Cellar Deck South Side
837.57 lit/min
2. Module 3 Level 1 and Cellar Deck and
Module 4 Cellar Deck North Side
4155.67 lit/min
Sub-Total 4993.24 lit/min = 299.59 m3/hr
19 Fire in module 5 Level 3 or Level 2 (North
Side)
1. Module 5 Level 3 and Level 2 7189.23 lit/min
2. Module 4 Level 2 and Level 3 4674.55 lit/min
Sub-Total 11863.78 lit/min = 711.83 m3/hr
20 Fire in module 5 Level 3 or Level 2 (South
Side)
1. Module 5 Level 3 and Level 2 7189.23 lit/min
Sub-Total 7189.23 lit/min = 431.35 m3/hr
21 Fire in module 5 Level 1 (North Side) 1. Module 5 Level 1 3756.50 lit/min
2. Module 4 Level 1 4918.37 lit/min
Sub-Total 8674.87 lit/min = 520.49 m3/hr
FW DEMAND
CALCULATIONS cont’d
 Major fire scenario table continued.
No. Scenarios Area to be Deluged / Spray Firewater Demand
22 Fire in module 5 Level 1 (South Side) 1. Module 5 Level 1 3756.50lit/min
Sub-Total 3756.50 lit/min = 225.39 m3/hr
23 Fire in module 5 Cellar Deck (North Side) 1. Module 5 Cellar Deck and Module 4
Cellar Deck South Side
837.57 lit/min
Sub-Total 837.57 lit/min = 50.25 m3
/hr
24 Fire in module 5 Cellar Deck (South Side) 1. Module 5 Cellar Deck and Module 4
Cellar Deck South Side
837.57 lit/min
Sub-Total 837.57 lit/min = 50.25 m3/hr
25 Fire in Helideck Area 1. 2 Foam monitors 460.00 m3/hr
Sub-Total 460.00 m3
/hr
26 Fire at TBDR-A 1. Wellhead Area (21 Slots) 8400.00 lit/min
2. TBDR-A Slug Catcher 2717.16 lit/min
Sub-Total 11117.16 lit/min = 667.03 m3/hr
FW DEMAND
CALCULATIONS cont’d
 Maximum FW demand for deluge system are 711.83 m3/hr
 2 FW monitors considered to be used for personnel
protection during evacuation
 Rated capacity for each monitor of 120 m3/hr @ 7.o barg
(100 psig) is specified for this case. This is as per PTS
80.47.10.12:
FW DEMAND
CALCULATIONS cont’d
From the table, the max. anticipated firewaterdemand forsingle major
fire scenariooccurduring scenario 14 and 19.
➢ Maximum demand for deluge = 711.83 m3/hr
➢ 15% marginadded for
hydraulic balance = 711.83 x 1.15 m3/hr
= 818.60 m3/hr
➢ 2 monitors used for
personnel protection = 2 x 120 m3/hr
= 240 m3/hr
➢ Hence,total firewaterdemand = 818.60 + 240 m3/hr
= 1058.60 m3/hr
➢ FW pump rated capacity ≈ 1100 m3/hr
PRELIMINARY PIPE SIZING
 Objectives: To provide preliminary line size estimation for
main pipeworks in FW system e.g. FW pump discharge,
ringmain, risers and deluge pipings.
 The preliminary line sizing is established using Preliminary
Line Sizing Chart provided in P.T.S 31.38.01.11-Appendix A.
 These line sizes will be verified using software during
hydraulic analysis
PRELIMINARY PIPE SIZING
cont’d
 Prelim. line sizing for water extracted from P.T.S 31.38.01.11
PRELIMINARY PIPE SIZING
cont’d
 If more than one selection is possible, smaller size should
be for lines up to 100m length; while larger lines size for
length over 100m.
 Sample of results are tabulated below:
Line Segment Flowrate (m3/hr) Pipe Size (mm)
Pump discharge line 1650 DN350
Ringmain 1650 DN350
M1, East side riser 240 DN200
M1, West side riser 147 DN150
M2, East side riser 240 DN200
M2, West side riser 147 DN150
FW PUMP SIZING
 Objective :
i. To determinethe requiredFW pumpdischargepressure.
 Basis :
i. FW pumpdischargehead characteristicshall be sufficient
to meetall firewatersystempressuredemandspluslosses
withindistributionsystem – to meet 100 psig at the most
hydraulicallyremoteFW monitor/otherfirefighting
equipment.
ii. Pressuredropis calculated using Hazen-Williams formula.
iii. 50% additional marginof pipe length is included tothe
calculatedstraightlengthof the pipe to cater for fittings
and bends.
iv. Maximumpressuredropacross helideck foamskid is taken
as 1 bar.
FW PUMP SIZING cont’d
 FW pump discharge
 The Hazen-Williams formula is expressed as:
•7 Barg
•230 m3/hr
Max. flowrate = 230 m3/hr
Flow in the ringmain = 1100 m3/hr
Max. ∆P across Helideck Foam Skid = 1.0 bar
FW PUMP SIZING cont’d
FW PUMP SIZING cont’d
 FW pumpdischargepressure:
 Each FW pump shall have capabilityto deliverreliableFW
supplyof 1100 m3/hr rated flowrate@ flangedischargepressureof
11.0 barg.
 In addition,as per NFPA 20, each FW pumpshall have maximum
capacity of not lessthan 150% rated capacity @ dischargehead of
not lessthan 65% of dischargeat rated capacity.
Pressure Loss = 0.11 barg
Vertical Head = 2.23 barg
Pressure Loss = 0.11 barg
Vertical Head = 0.52 barg
Min P at remote monitor = 7 barg
Max. ∆PHelideck Foam Skid = 1.0 bar
FW PUMP SIZING cont’d

More Related Content

What's hot

Fire and Gas Detection System : Part 1_The Field Devices and Its Panels
Fire and Gas Detection System : Part 1_The Field Devices and Its PanelsFire and Gas Detection System : Part 1_The Field Devices and Its Panels
Fire and Gas Detection System : Part 1_The Field Devices and Its PanelsGan Chun Chet
 
Introductory training on fire water pumping system
Introductory training  on fire water pumping systemIntroductory training  on fire water pumping system
Introductory training on fire water pumping systemSabrul Jamil
 
Introduction to fires and explosions
Introduction to fires and explosionsIntroduction to fires and explosions
Introduction to fires and explosionsSheetal Yadav
 
Coal Dust Explosion and its Safety at Thermal Power Plant
Coal Dust Explosion and its Safety at Thermal Power PlantCoal Dust Explosion and its Safety at Thermal Power Plant
Coal Dust Explosion and its Safety at Thermal Power PlantSyed Aqeel Ahmed
 
Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureVarun Patel
 
Carbon dioxide fire suppression
Carbon dioxide fire suppressionCarbon dioxide fire suppression
Carbon dioxide fire suppressiontasander
 
Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"EzazulHaqueSiddique
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classificationguest81e1c7
 
Storage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh RajputStorage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh RajputGaurav Singh Rajput
 
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS Gerard B. Hawkins
 
Clean Agent & Inert Gas Fire Suppression
Clean Agent & Inert Gas Fire SuppressionClean Agent & Inert Gas Fire Suppression
Clean Agent & Inert Gas Fire SuppressionBen Adams
 
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.pptBASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.pptRajeshKannan579711
 
Fire and Gas Detection System : Part 2_Block Diagram_Philosophy, Signal Types...
Fire and Gas Detection System : Part 2_Block Diagram_Philosophy, Signal Types...Fire and Gas Detection System : Part 2_Block Diagram_Philosophy, Signal Types...
Fire and Gas Detection System : Part 2_Block Diagram_Philosophy, Signal Types...Gan Chun Chet
 
Pressure Relief Devices_Presenation
Pressure Relief Devices_PresenationPressure Relief Devices_Presenation
Pressure Relief Devices_Presenationsumit handa
 
psv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.pptpsv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.pptssuser73bb74
 

What's hot (20)

Fire and Gas Detection System : Part 1_The Field Devices and Its Panels
Fire and Gas Detection System : Part 1_The Field Devices and Its PanelsFire and Gas Detection System : Part 1_The Field Devices and Its Panels
Fire and Gas Detection System : Part 1_The Field Devices and Its Panels
 
Introductory training on fire water pumping system
Introductory training  on fire water pumping systemIntroductory training  on fire water pumping system
Introductory training on fire water pumping system
 
Introduction to fires and explosions
Introduction to fires and explosionsIntroduction to fires and explosions
Introduction to fires and explosions
 
343312365 mt-ppt
343312365 mt-ppt343312365 mt-ppt
343312365 mt-ppt
 
Coal Dust Explosion and its Safety at Thermal Power Plant
Coal Dust Explosion and its Safety at Thermal Power PlantCoal Dust Explosion and its Safety at Thermal Power Plant
Coal Dust Explosion and its Safety at Thermal Power Plant
 
Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressure
 
Carbon dioxide fire suppression
Carbon dioxide fire suppressionCarbon dioxide fire suppression
Carbon dioxide fire suppression
 
flare system design.pdf
flare system design.pdfflare system design.pdf
flare system design.pdf
 
Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"
 
API STD 521
API STD 521API STD 521
API STD 521
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
 
PSV Sizing.pdf
PSV Sizing.pdfPSV Sizing.pdf
PSV Sizing.pdf
 
Storage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh RajputStorage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh Rajput
 
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
 
36512435-Fired-Heater-Design.ppt
36512435-Fired-Heater-Design.ppt36512435-Fired-Heater-Design.ppt
36512435-Fired-Heater-Design.ppt
 
Clean Agent & Inert Gas Fire Suppression
Clean Agent & Inert Gas Fire SuppressionClean Agent & Inert Gas Fire Suppression
Clean Agent & Inert Gas Fire Suppression
 
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.pptBASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
BASICS OF FIRE PROTECTION SYSTEM, HYDRANT SYSTEM.ppt
 
Fire and Gas Detection System : Part 2_Block Diagram_Philosophy, Signal Types...
Fire and Gas Detection System : Part 2_Block Diagram_Philosophy, Signal Types...Fire and Gas Detection System : Part 2_Block Diagram_Philosophy, Signal Types...
Fire and Gas Detection System : Part 2_Block Diagram_Philosophy, Signal Types...
 
Pressure Relief Devices_Presenation
Pressure Relief Devices_PresenationPressure Relief Devices_Presenation
Pressure Relief Devices_Presenation
 
psv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.pptpsv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.ppt
 

Similar to FIRE WATER DEMAND CALCULATION.pdf

Blueproof Update to FEU May 2014
Blueproof Update to FEU May 2014 Blueproof Update to FEU May 2014
Blueproof Update to FEU May 2014 Dave Atkinson
 
Hazardous area classification and Elecrtical, Instrument and Process Engineer...
Hazardous area classification and Elecrtical, Instrument and Process Engineer...Hazardous area classification and Elecrtical, Instrument and Process Engineer...
Hazardous area classification and Elecrtical, Instrument and Process Engineer...Kathiresan Nadar
 
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...gurkanarifyalcinkaya
 
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPTFIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPTMEP ENGINEER'S SERVICES
 
Safetypassport hydrostatics
Safetypassport hydrostaticsSafetypassport hydrostatics
Safetypassport hydrostaticsfiretraining
 
fire-fighting-design-brief-report.pptx
fire-fighting-design-brief-report.pptxfire-fighting-design-brief-report.pptx
fire-fighting-design-brief-report.pptxRanu Agarwal
 
Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
 Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi... Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...BREEZE Software
 
160621 Experience of Shipboard firefighting with Cutting Extinguishers (v 1.0)
160621 Experience of Shipboard firefighting with Cutting Extinguishers (v 1.0)160621 Experience of Shipboard firefighting with Cutting Extinguishers (v 1.0)
160621 Experience of Shipboard firefighting with Cutting Extinguishers (v 1.0)Anders Trewe
 
20_BPFireonBoard_000.pdf
20_BPFireonBoard_000.pdf20_BPFireonBoard_000.pdf
20_BPFireonBoard_000.pdfSridharIyer37
 
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT.pptxFIRE PREVENTION & FIRE FIGHTING EQUIPMENT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT.pptx8006467070
 
fire fighting and fire extinguishing systems .pptx
fire fighting and fire extinguishing systems .pptxfire fighting and fire extinguishing systems .pptx
fire fighting and fire extinguishing systems .pptxdevmarineacademy
 
Vds 2815en web
Vds 2815en webVds 2815en web
Vds 2815en webprodrigd
 
DMUG 2016 - Bethan Tuckett-Jones, WSP Parsons Brinkerhoff
DMUG 2016 - Bethan Tuckett-Jones, WSP Parsons BrinkerhoffDMUG 2016 - Bethan Tuckett-Jones, WSP Parsons Brinkerhoff
DMUG 2016 - Bethan Tuckett-Jones, WSP Parsons BrinkerhoffIES / IAQM
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classificationdebuddit
 
IRJET- Automatic Fire Extinguisher System
IRJET- Automatic Fire Extinguisher SystemIRJET- Automatic Fire Extinguisher System
IRJET- Automatic Fire Extinguisher SystemIRJET Journal
 

Similar to FIRE WATER DEMAND CALCULATION.pdf (20)

Blueproof Update to FEU May 2014
Blueproof Update to FEU May 2014 Blueproof Update to FEU May 2014
Blueproof Update to FEU May 2014
 
Hazardous area classification and Elecrtical, Instrument and Process Engineer...
Hazardous area classification and Elecrtical, Instrument and Process Engineer...Hazardous area classification and Elecrtical, Instrument and Process Engineer...
Hazardous area classification and Elecrtical, Instrument and Process Engineer...
 
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
 
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPTFIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
 
FIRE HYDRALICS AND FIRE LOSS CONTROL
FIRE HYDRALICS AND FIRE LOSS CONTROLFIRE HYDRALICS AND FIRE LOSS CONTROL
FIRE HYDRALICS AND FIRE LOSS CONTROL
 
Safetypassport hydrostatics
Safetypassport hydrostaticsSafetypassport hydrostatics
Safetypassport hydrostatics
 
fire-fighting-design-brief-report.pptx
fire-fighting-design-brief-report.pptxfire-fighting-design-brief-report.pptx
fire-fighting-design-brief-report.pptx
 
Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
 Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi... Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
 
160621 Experience of Shipboard firefighting with Cutting Extinguishers (v 1.0)
160621 Experience of Shipboard firefighting with Cutting Extinguishers (v 1.0)160621 Experience of Shipboard firefighting with Cutting Extinguishers (v 1.0)
160621 Experience of Shipboard firefighting with Cutting Extinguishers (v 1.0)
 
20_BPFireonBoard_000.pdf
20_BPFireonBoard_000.pdf20_BPFireonBoard_000.pdf
20_BPFireonBoard_000.pdf
 
Fire fighting -2 By Er. Ezaz
Fire fighting -2 By Er. EzazFire fighting -2 By Er. Ezaz
Fire fighting -2 By Er. Ezaz
 
Fire smokedampers
Fire smokedampersFire smokedampers
Fire smokedampers
 
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT.pptxFIRE PREVENTION & FIRE FIGHTING EQUIPMENT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT.pptx
 
Best practice catalogue_en
Best practice catalogue_enBest practice catalogue_en
Best practice catalogue_en
 
fire fighting and fire extinguishing systems .pptx
fire fighting and fire extinguishing systems .pptxfire fighting and fire extinguishing systems .pptx
fire fighting and fire extinguishing systems .pptx
 
Vds 2815en web
Vds 2815en webVds 2815en web
Vds 2815en web
 
DMUG 2016 - Bethan Tuckett-Jones, WSP Parsons Brinkerhoff
DMUG 2016 - Bethan Tuckett-Jones, WSP Parsons BrinkerhoffDMUG 2016 - Bethan Tuckett-Jones, WSP Parsons Brinkerhoff
DMUG 2016 - Bethan Tuckett-Jones, WSP Parsons Brinkerhoff
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
 
Guards manual
Guards manualGuards manual
Guards manual
 
IRJET- Automatic Fire Extinguisher System
IRJET- Automatic Fire Extinguisher SystemIRJET- Automatic Fire Extinguisher System
IRJET- Automatic Fire Extinguisher System
 

More from rhamset

Bahaya_Listrik_dan_Sistem_Pengamanannya.pptx
Bahaya_Listrik_dan_Sistem_Pengamanannya.pptxBahaya_Listrik_dan_Sistem_Pengamanannya.pptx
Bahaya_Listrik_dan_Sistem_Pengamanannya.pptxrhamset
 
pembinaan materi training Boom-truck-ppt.ppt
pembinaan materi training Boom-truck-ppt.pptpembinaan materi training Boom-truck-ppt.ppt
pembinaan materi training Boom-truck-ppt.pptrhamset
 
Work_Permit_ijin kerja berbahaya PPT.pptx
Work_Permit_ijin kerja berbahaya PPT.pptxWork_Permit_ijin kerja berbahaya PPT.pptx
Work_Permit_ijin kerja berbahaya PPT.pptxrhamset
 
Training pembinaa Alat berat TRAKTOR.pptx
Training pembinaa Alat berat TRAKTOR.pptxTraining pembinaa Alat berat TRAKTOR.pptx
Training pembinaa Alat berat TRAKTOR.pptxrhamset
 
Materi-Training Audit internal ISO-19011-2018.pptx
Materi-Training Audit internal ISO-19011-2018.pptxMateri-Training Audit internal ISO-19011-2018.pptx
Materi-Training Audit internal ISO-19011-2018.pptxrhamset
 
Basic Keselamatan kesehatan kerja dan APD.pdf
Basic Keselamatan kesehatan kerja dan APD.pdfBasic Keselamatan kesehatan kerja dan APD.pdf
Basic Keselamatan kesehatan kerja dan APD.pdfrhamset
 
Pengoperasian aman Forklift di tempat kerja
Pengoperasian aman Forklift di tempat kerjaPengoperasian aman Forklift di tempat kerja
Pengoperasian aman Forklift di tempat kerjarhamset
 
4-manajemen keselamatan kebakaran gedung-20170927015521.pptx
4-manajemen keselamatan kebakaran gedung-20170927015521.pptx4-manajemen keselamatan kebakaran gedung-20170927015521.pptx
4-manajemen keselamatan kebakaran gedung-20170927015521.pptxrhamset
 
Training Corporate social responsbility hijau
Training Corporate social responsbility hijauTraining Corporate social responsbility hijau
Training Corporate social responsbility hijaurhamset
 
silabus Tumpahan B3.pptx
silabus Tumpahan B3.pptxsilabus Tumpahan B3.pptx
silabus Tumpahan B3.pptxrhamset
 
Limbah B3.pptx
Limbah B3.pptxLimbah B3.pptx
Limbah B3.pptxrhamset
 
materi training IATF 16949.pptx
materi training IATF 16949.pptxmateri training IATF 16949.pptx
materi training IATF 16949.pptxrhamset
 
SMK3 KONTRUKSI.pptx
SMK3 KONTRUKSI.pptxSMK3 KONTRUKSI.pptx
SMK3 KONTRUKSI.pptxrhamset
 
PROSES KOMUNIKASI.ppt
PROSES KOMUNIKASI.pptPROSES KOMUNIKASI.ppt
PROSES KOMUNIKASI.pptrhamset
 
pertolongan-pertama-p3k.pptx
pertolongan-pertama-p3k.pptxpertolongan-pertama-p3k.pptx
pertolongan-pertama-p3k.pptxrhamset
 
Fire Hydrant System.ppt
Fire Hydrant System.pptFire Hydrant System.ppt
Fire Hydrant System.pptrhamset
 
APAR.ppt
APAR.pptAPAR.ppt
APAR.pptrhamset
 
Turbin uap.pptx
Turbin uap.pptxTurbin uap.pptx
Turbin uap.pptxrhamset
 
PROPER.ppt
PROPER.pptPROPER.ppt
PROPER.pptrhamset
 
ISO 14001-2015.pptx
ISO 14001-2015.pptxISO 14001-2015.pptx
ISO 14001-2015.pptxrhamset
 

More from rhamset (20)

Bahaya_Listrik_dan_Sistem_Pengamanannya.pptx
Bahaya_Listrik_dan_Sistem_Pengamanannya.pptxBahaya_Listrik_dan_Sistem_Pengamanannya.pptx
Bahaya_Listrik_dan_Sistem_Pengamanannya.pptx
 
pembinaan materi training Boom-truck-ppt.ppt
pembinaan materi training Boom-truck-ppt.pptpembinaan materi training Boom-truck-ppt.ppt
pembinaan materi training Boom-truck-ppt.ppt
 
Work_Permit_ijin kerja berbahaya PPT.pptx
Work_Permit_ijin kerja berbahaya PPT.pptxWork_Permit_ijin kerja berbahaya PPT.pptx
Work_Permit_ijin kerja berbahaya PPT.pptx
 
Training pembinaa Alat berat TRAKTOR.pptx
Training pembinaa Alat berat TRAKTOR.pptxTraining pembinaa Alat berat TRAKTOR.pptx
Training pembinaa Alat berat TRAKTOR.pptx
 
Materi-Training Audit internal ISO-19011-2018.pptx
Materi-Training Audit internal ISO-19011-2018.pptxMateri-Training Audit internal ISO-19011-2018.pptx
Materi-Training Audit internal ISO-19011-2018.pptx
 
Basic Keselamatan kesehatan kerja dan APD.pdf
Basic Keselamatan kesehatan kerja dan APD.pdfBasic Keselamatan kesehatan kerja dan APD.pdf
Basic Keselamatan kesehatan kerja dan APD.pdf
 
Pengoperasian aman Forklift di tempat kerja
Pengoperasian aman Forklift di tempat kerjaPengoperasian aman Forklift di tempat kerja
Pengoperasian aman Forklift di tempat kerja
 
4-manajemen keselamatan kebakaran gedung-20170927015521.pptx
4-manajemen keselamatan kebakaran gedung-20170927015521.pptx4-manajemen keselamatan kebakaran gedung-20170927015521.pptx
4-manajemen keselamatan kebakaran gedung-20170927015521.pptx
 
Training Corporate social responsbility hijau
Training Corporate social responsbility hijauTraining Corporate social responsbility hijau
Training Corporate social responsbility hijau
 
silabus Tumpahan B3.pptx
silabus Tumpahan B3.pptxsilabus Tumpahan B3.pptx
silabus Tumpahan B3.pptx
 
Limbah B3.pptx
Limbah B3.pptxLimbah B3.pptx
Limbah B3.pptx
 
materi training IATF 16949.pptx
materi training IATF 16949.pptxmateri training IATF 16949.pptx
materi training IATF 16949.pptx
 
SMK3 KONTRUKSI.pptx
SMK3 KONTRUKSI.pptxSMK3 KONTRUKSI.pptx
SMK3 KONTRUKSI.pptx
 
PROSES KOMUNIKASI.ppt
PROSES KOMUNIKASI.pptPROSES KOMUNIKASI.ppt
PROSES KOMUNIKASI.ppt
 
pertolongan-pertama-p3k.pptx
pertolongan-pertama-p3k.pptxpertolongan-pertama-p3k.pptx
pertolongan-pertama-p3k.pptx
 
Fire Hydrant System.ppt
Fire Hydrant System.pptFire Hydrant System.ppt
Fire Hydrant System.ppt
 
APAR.ppt
APAR.pptAPAR.ppt
APAR.ppt
 
Turbin uap.pptx
Turbin uap.pptxTurbin uap.pptx
Turbin uap.pptx
 
PROPER.ppt
PROPER.pptPROPER.ppt
PROPER.ppt
 
ISO 14001-2015.pptx
ISO 14001-2015.pptxISO 14001-2015.pptx
ISO 14001-2015.pptx
 

Recently uploaded

Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Recently uploaded (20)

Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 

FIRE WATER DEMAND CALCULATION.pdf

  • 2. OUTLINE  INTRODUCTION/SYSTEM OVERVIEW  OBJECTIVE  DESIGN BASIS & PHILOSOPHY  FIRE AREA ZONING  POSSIBLE MAJOR FIRE SCENARIOS  FIREWATER DEMAND CALCULATIONS  PRELIMINARY FIREWATER LINES SIZING  FIREWATER PUMP SIZING
  • 3.
  • 4. FIREWATER SYSTEM  FW systems are one of the systems which used to reduce the risk of fire and explosion – Active Fire Protection (AFP).  Intended to mitigate the consequences of fire/explosion event by extinguishing or limiting the spread of fire.
  • 5.
  • 6. OBJECTIVES  To find maximum firewater demand required for a single major fire scenario which will dictate the firewater pump capacity  To determine required FW pump discharge pressure (to meet the most hydraulically remote fire fighting equipment)  To preliminarily size the FW ringmain and other pipeworks
  • 7.
  • 8. DESIGN OBJECTIVE  The purposes of providing FW systems on offshore facilities including followings: To protect personnel Minimise fire damage and thus enable the facility return to operation ASAP after fire Minimise escalation which could lead to major damage and environmental pollution.
  • 9. DESIGN OBJECTIVE cont’d  Water can reduce the potential risk resulting from fire by: Cool high flashpointliquidsor combustiblesolid material Suffocatesthe firewhen wateris converted to steam Blanketspool fireswhen appliedwith foam Cool the environment( air, hot gas, flame, smokeetc) to limit the spreadof fire by convection Cool adjacent facilitiesor structuresto prevent firespread by radiationeffects Forming heatabsorbing barrierbetween fireand facilities
  • 10. DESIGN PHILOSOPHY  In general, the whole facilities will be treated as single fire area. However, if the FW demand for such area cannot be satisfied, additional physical separation can be employed  Zoning segregation is deemed effective enough that only single fire scenario is assumed to occur at any given time  Design FW demand is dictated be the largest FW demand of a single fire event Requirement for personnel protection during escape and evacuation / manual fire-fighting by personnel The FW demand which will be initiated upon fire detection
  • 11. DESIGN PHILOSOPHY cont’d  Operating pressures of fire-fighting equipments such as monitors, hosereels n light water station are rated at 7.0 barg (100 psig)  FW pump shall be sized to provide either 100% of the calculated design fire water demand or an appropriate fraction of adopted sparing philosophy  FW ringmain and other piping within the Wet system will constantly pressurized by jockey pump(s)
  • 12. DESIGN PHILOSOPHY cont’d  As per NFPA 20 requirements, the FW pump shall have maximum capacity not less than 150% of rated capacity with differential head not less than 65% of differential head at rated capacity.
  • 13. CASE STUDY  FW system on TBCP-A facilities is taken as case study.
  • 14.
  • 15. FIRE AREA ZONING  In order to minimize design (largest) FW demand, the facilities (one large fire area) will be divided into several smaller fire area as reasonably practicable  This can be achieved either by employing physical separation or by forming heat absorbing barrier between fire and facilities upon fire event  Physical separation is achieved by installing/providing firewall, plated deck etc  Heat absorbing barrier is formed when the adjacent/ neighbouring fire area is spray with water
  • 16. FIRE AREA ZONING cont’d  Each fire area is provided with automatic deluge valve (ADV) or alternatively actuated isolation valve with RO at the inlet from FW ringmain  Upon detection of fire, the affected ADV(s) will be activated (open) to discharge FW to the affected equipments/area.  In addition, the adjacent/neighbouring fire zone which exposed to radiation will be deluged as well.
  • 17. FIRE AREA ZONING cont’d Plated Deck Firewall
  • 18. FIRE AREA ZONING cont’d Plated Deck Firewall
  • 19. FIRE AREA ZONING cont’d  From the equipment layout, it is possible to segregate the facilities into 11 independent fire zones which require 11 nos of ADV.
  • 20.
  • 21. POSSIBLE MAJOR FIRE SCENARIOS  List of possible major fire scenarios: No. Scenarios No. Firewater Demand 1 Fire in module 1 Level 2 (North Side) 14 Fire in module 4 Level 3 or Level 2 (South Side) 2 Fire in module 1 Level 2 (South Side) 15 Fire in module 4 Level 1 (North Side) 3 Fire in module 1 Level 1 or Cellar Deck (North Side) 16 Fire in module 4 Level 1 (South Side) 4 Fire in module 1 Level 1 or Cellar Deck (South Side) 17 Fire in module 4 Cellar Deck (North Side) 5 Fire in module 2 Level 2 (North Side) 18 Fire in module 4 Cellar Deck (South Side) 6 Fire in module 2 Level 2 (South Side) 19 Fire in module 5 Level 3 or Level 2 (North Side) 7 Fire in module 2 Level 1 or Cellar Deck (North Side) 20 Fire in module 5 Level 3 or Level 2 (South Side) 8 Fire in module 2 Level 1 or Cellar Deck (South Side) 21 Fire in module 5 Level 1 (North Side) 9 Fire in module 3 Level 3 or Level 2 (North Side) 22 Fire in module 5 Level 1 (South Side) 10 Fire in module 3 Level 3 or Level 2 (South Side) 23 Fire in module 5 Cellar Deck (North Side) 11 Fire in Module 3 Level 1 or Cellar Deck(North Side) 24 Fire in module 5 Cellar Deck (South Side) 12 Fire in Module 3 Level 1 or Cellar Deck(South Side) 25 Fire in Helideck Area 13 Fire in module 4 Level 3 or Level 2 (North Side)
  • 22. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 23. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 24. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 25. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 26. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 27. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 28. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 29. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 30. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 31. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 32. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 33. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 34. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 35. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 36. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 37. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 38. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 39. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 40. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 41. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 42. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 43. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 44. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 45. MAJOR FIRE SCENARIOS cont’d Plated Deck Firewall
  • 46.
  • 47. DELUGE SYSTEM  The FW demand is contributed by: The FW demand which will be initiated upon fire detection – deluge consumption Requirement for personnel protection during escape and evacuation / manual fire-fighting by personnel  Deluge systems are arrays of open head nozzles which are fed from a common valve. The nozzles discharge simultaneously upon opening of the valve.
  • 48. DELUGE SYSTEM cont’d  Specific objective of deluge system are: To providean optimallydesigneddistributionsystemwhich deliverswaterat design rateto spray nozzles To providea uniformdistributionof waterat that rate such that the wholearea requiring protection is adequately covered.
  • 49. DELUGE SYSTEM cont’d  Deluge system may be used effectively for the following applications: Extinguishment– by cooling surfacehence reducingvapour emission rate,suppressfirethroughgenerationof steam which displaceair, dilutionof water-solubleflammable liquids,emulsificationat the surfaceof flammableliquidsto preventreleaseof vapourand making the flameunstablethus discontinuethe combustion. Controlof burning – by reducingthe flame temperaturesand evaporationrate forpool fires Exposureprotection– by limiting the heat transferred to personnel,equipmentsand structures
  • 50. DELUGE SYSTEM cont’d  Deluge water application rates are varies between types of protection, generally range from 6.1 lit/min/m2 to 20.4 lit/min/m2 (NFPA 15).
  • 51. DELUGE SYSTEM cont’d  Table below shows typical deluge application rate for various type of equipment/protectionas per PTS 80.47.10.12
  • 52. DELUGE CONSUMPTION MODULE 2: BOOSTER COMPRESSOR MODULE DELUGE VALVE: ADV-5378 COVERAGE AREA: CELLAR DECK & LEVEL 1 As per NFPA 15/ PTS 80.47.10.12 ProjectionArea = Width x Length Total surface area for a vessel with 2 heads = ( π x D ) L + [ 2 (1.09 x D2 ) ] Consumption = Total area x Water rate required
  • 53. DELUGE CONSUMPTION cont’d MODULE 2: BOOSTER COMPRESSOR MODULE DELUGE VALVE: ADV-5378 COVERAGE AREA: CELLAR DECK & LEVEL 1
  • 54. DELUGE CONSUMPTION cont’d  Summary of deluge consumptions are tabulated below: No. Area to be Deluged / Spray ADV Tag No Deluge Consumption 1 Module 1 Level 2 ADV-5370 2186.44 lit/min 2 Module 1 Level 1 and Cellar Deck ADV-5373 3137.70 lit/min 3 Module 2 Level 2 ADV-5375 2186.44 lit/min 4 Module 2 Level 1 and Cellar Deck ADV-5378 1952.78 lit/min 5 Module 3 Level 2 and Level 3 ADV-5380 1489.78 lit/min 6 Module 3 Level 1 and Cellar Deck and Module 4 Cellar Deck North Side ADV-5383 4155.69 lit/min 7 Module 4 Level 2 and Level 3 ADV-5385 4674.55 lit/min 8 Module 4 Level 1 ADV-5388 4918.37 lit/min 9 Module 5 Level 3 and Level 2 ADV-5390 7189.23 lit/min 10 Module 5 Level 1 ADV-5393 3756.50 lit/min 11 Module 5 Cellar Deck and Module 4 Cellar Deck South Side ADV-5398 837.57 lit/min
  • 55. FW DEMAND CALCULATIONS  FW demand by deluge system for each major fire scenario. No. Scenarios Area to be Deluged / Spray Firewater Demand 1 Fire in module 1 Level 2 (North Side) 1. Module 1 Level 2 2186.44 lit/min Sub-Total 2186.44 lit/min = 131.19 m3 /hr 2 Fire in module 1 Level 2 (South Side) 1. Module 1 Level 2 2186.44 lit/min 2. Module 2 Level 2 2186.44 lit/min Sub-Total 4372.44 lit/min = 262.38 m3/hr 3 Fire in module 1 Level 1 or Cellar Deck (North Side) 1. Module 1 Level 1 and Cellar Deck 3137.70 lit/min Sub-Total 3137.70 lit/min = 188.26 m3/hr 4 Fire in module 1 Level 1 or Cellar Deck (South Side) 1. Module 1 Level 1 and Cellar Deck 3137.70 lit/min 2. Module 2 Level 1 and Cellar Deck 1952.78 lit/min Sub-Total 5090.48 lit/min = 305.43 m3/hr 5 Fire in module 2 Level 2 (North Side) 1. Module 1 Level 2 2186.44 lit/min 2. Module 2 Level 2 2186.44 lit/min Sub-Total 4372.44 lit/min = 262.38 m3/hr 6 Fire in module 2 Level 2 (South Side) 1. Module 2 Level 2 2186.44 lit/min 2. Module 3 Level 2 and Level 3 1489.78 lit/min Sub-Total 3676.22 lit/min = 220.57 m3/hr
  • 56. FW DEMAND CALCULATIONS cont’d  Major fire scenario table continued. No. Scenarios Area to be Deluged / Spray Firewater Demand 7 Fire in module 2 Level 1 or Cellar Deck (North Side) 1. Module 2 Level 1 and Cellar Deck 1952.78 lit/min 2. Module 1 Level 1 and Cellar Deck 3137.70 lit/min Sub-Total 5090.48 lit/min = 305.43 m3 /hr 8 Fire in module 2 Level 1 or Cellar Deck (South Side) 1. Module 2 Level 1 and Cellar Deck 1952.78 lit/min 2. Module 3 Level 1 and Cellar Deck and Module 4 Cellar Deck North Side 4155.69 lit/min Sub-Total 6108.47 lit/min = 366.51 m3/hr 9 Fire in module 3 Level 3 or Level 2 (North Side) 1. Module 3 Level 2 and Level 3 1489.78 lit/min 2. Module 2 Level 2 2186.44 lit/min Sub-Total 3676.22 lit/min = 220.57 m3/hr 10 Fire in module 3 Level 3 or Level 2 (South Side) 1. Module 3 Level 2 and Level 3 1489.78 lit/min 2. Module 4 Level 2 and Level 3 4674.55 lit/min Sub-Total 6164.33 lit/min = 369.86 m3/hr 11 Fire in Module 3 Level 1 or Cellar Deck (North Side) 1. Module 3 Level 1 and Cellar Deck and Module 4 Cellar Deck North Side 4155.69 lit/min 2. Module 2 Level 1 and Cellar Deck 1952.78 lit/min Sub-Total 6108.47 lit/min = 366.51 m3/hr
  • 57. FW DEMAND CALCULATIONS cont’d  Major fire scenario table continued. No. Scenarios Area to be Deluged / Spray Firewater Demand 12 Fire in Module 3 Level 1 or Cellar Deck (South Side) 1. Module 3 Level 1 and Cellar Deck and Module 4 Cellar Deck North Side 4155.69 lit/min 2. Module 4 Level 1 4918.37 lit/min Sub-Total 9074.06 lit/min = 544.44 m3/hr 13 Fire in module 4 Level 3 or Level 2 (North Side) 1. Module 4 Level 2 and Level 3 4674.55 lit/min 2. Module 3 Level 2 and Level 3 1489.78 lit/min Sub-Total 6164.33lit/min = 369.86 m3/hr 14 Fire in module 4 Level 3 or Level 2 (South Side) 1. Module 4 Level 2 and Level 3 4674.55 lit/min 2. Module 5 Level 2 and Level 3 7189.23 lit/min Sub-Total 11863.78 lit/min = 711.83 m3/hr 15 Fire in module 4 Level 1 (North Side) 1. Module 4 Level 1 4918.37 lit/min 2. Module 3 Level 1 and Cellar Deck and Module 4 Cellar Deck North Side 4155.69 lit/min Sub-Total 9074.06 lit/min = 544.44 m3/hr 16 Fire in module 4 Level 1 (South Side) 1. Module 4 Level 1 4918.37 lit/min 2. Module 5 Level 1 3756.50 lit/min Sub-Total 8674.87 lit/min = 520.49 m3/hr
  • 58. FW DEMAND CALCULATIONS cont’d  Major fire scenario table continued. No. Scenarios Area to be Deluged / Spray Firewater Demand 17 Fire in module 4 Cellar Deck (North Side) 1. Module 3 Level 1 and Cellar Deck and Module 4 Cellar Deck North Side 4155.67 lit/min 2. Module 5 Cellar Deck and Module 4 Cellar Deck South Side 837.57 lit/min Sub-Total 4993.24 lit/min = 299.59 m3 /hr 18 Fire in module 4 Cellar Deck (South Side) 1. Module 5 Cellar Deck and Module 4 Cellar Deck South Side 837.57 lit/min 2. Module 3 Level 1 and Cellar Deck and Module 4 Cellar Deck North Side 4155.67 lit/min Sub-Total 4993.24 lit/min = 299.59 m3/hr 19 Fire in module 5 Level 3 or Level 2 (North Side) 1. Module 5 Level 3 and Level 2 7189.23 lit/min 2. Module 4 Level 2 and Level 3 4674.55 lit/min Sub-Total 11863.78 lit/min = 711.83 m3/hr 20 Fire in module 5 Level 3 or Level 2 (South Side) 1. Module 5 Level 3 and Level 2 7189.23 lit/min Sub-Total 7189.23 lit/min = 431.35 m3/hr 21 Fire in module 5 Level 1 (North Side) 1. Module 5 Level 1 3756.50 lit/min 2. Module 4 Level 1 4918.37 lit/min Sub-Total 8674.87 lit/min = 520.49 m3/hr
  • 59. FW DEMAND CALCULATIONS cont’d  Major fire scenario table continued. No. Scenarios Area to be Deluged / Spray Firewater Demand 22 Fire in module 5 Level 1 (South Side) 1. Module 5 Level 1 3756.50lit/min Sub-Total 3756.50 lit/min = 225.39 m3/hr 23 Fire in module 5 Cellar Deck (North Side) 1. Module 5 Cellar Deck and Module 4 Cellar Deck South Side 837.57 lit/min Sub-Total 837.57 lit/min = 50.25 m3 /hr 24 Fire in module 5 Cellar Deck (South Side) 1. Module 5 Cellar Deck and Module 4 Cellar Deck South Side 837.57 lit/min Sub-Total 837.57 lit/min = 50.25 m3/hr 25 Fire in Helideck Area 1. 2 Foam monitors 460.00 m3/hr Sub-Total 460.00 m3 /hr 26 Fire at TBDR-A 1. Wellhead Area (21 Slots) 8400.00 lit/min 2. TBDR-A Slug Catcher 2717.16 lit/min Sub-Total 11117.16 lit/min = 667.03 m3/hr
  • 60. FW DEMAND CALCULATIONS cont’d  Maximum FW demand for deluge system are 711.83 m3/hr  2 FW monitors considered to be used for personnel protection during evacuation  Rated capacity for each monitor of 120 m3/hr @ 7.o barg (100 psig) is specified for this case. This is as per PTS 80.47.10.12:
  • 61. FW DEMAND CALCULATIONS cont’d From the table, the max. anticipated firewaterdemand forsingle major fire scenariooccurduring scenario 14 and 19. ➢ Maximum demand for deluge = 711.83 m3/hr ➢ 15% marginadded for hydraulic balance = 711.83 x 1.15 m3/hr = 818.60 m3/hr ➢ 2 monitors used for personnel protection = 2 x 120 m3/hr = 240 m3/hr ➢ Hence,total firewaterdemand = 818.60 + 240 m3/hr = 1058.60 m3/hr ➢ FW pump rated capacity ≈ 1100 m3/hr
  • 62. PRELIMINARY PIPE SIZING  Objectives: To provide preliminary line size estimation for main pipeworks in FW system e.g. FW pump discharge, ringmain, risers and deluge pipings.  The preliminary line sizing is established using Preliminary Line Sizing Chart provided in P.T.S 31.38.01.11-Appendix A.  These line sizes will be verified using software during hydraulic analysis
  • 63. PRELIMINARY PIPE SIZING cont’d  Prelim. line sizing for water extracted from P.T.S 31.38.01.11
  • 64. PRELIMINARY PIPE SIZING cont’d  If more than one selection is possible, smaller size should be for lines up to 100m length; while larger lines size for length over 100m.  Sample of results are tabulated below: Line Segment Flowrate (m3/hr) Pipe Size (mm) Pump discharge line 1650 DN350 Ringmain 1650 DN350 M1, East side riser 240 DN200 M1, West side riser 147 DN150 M2, East side riser 240 DN200 M2, West side riser 147 DN150
  • 65. FW PUMP SIZING  Objective : i. To determinethe requiredFW pumpdischargepressure.  Basis : i. FW pumpdischargehead characteristicshall be sufficient to meetall firewatersystempressuredemandspluslosses withindistributionsystem – to meet 100 psig at the most hydraulicallyremoteFW monitor/otherfirefighting equipment. ii. Pressuredropis calculated using Hazen-Williams formula. iii. 50% additional marginof pipe length is included tothe calculatedstraightlengthof the pipe to cater for fittings and bends. iv. Maximumpressuredropacross helideck foamskid is taken as 1 bar.
  • 66. FW PUMP SIZING cont’d  FW pump discharge  The Hazen-Williams formula is expressed as:
  • 67. •7 Barg •230 m3/hr Max. flowrate = 230 m3/hr Flow in the ringmain = 1100 m3/hr Max. ∆P across Helideck Foam Skid = 1.0 bar FW PUMP SIZING cont’d
  • 68. FW PUMP SIZING cont’d  FW pumpdischargepressure:  Each FW pump shall have capabilityto deliverreliableFW supplyof 1100 m3/hr rated flowrate@ flangedischargepressureof 11.0 barg.  In addition,as per NFPA 20, each FW pumpshall have maximum capacity of not lessthan 150% rated capacity @ dischargehead of not lessthan 65% of dischargeat rated capacity.
  • 69. Pressure Loss = 0.11 barg Vertical Head = 2.23 barg Pressure Loss = 0.11 barg Vertical Head = 0.52 barg Min P at remote monitor = 7 barg Max. ∆PHelideck Foam Skid = 1.0 bar FW PUMP SIZING cont’d