SlideShare a Scribd company logo
Eng. Kishor K. Ade
A DISSERTATION ON
Effect of Underground Tunnelling by (TBM) on
Foundations of Existing Structures
By
Kishor K. Ade
M.E. (Structures)
(5057)
Under guidance of
Dr. Prof. Mrs. B. S. Karkare
&
Mrs. G. R. Chillal
Vishwakarma Institute Of Information Technology,
Pune
Eng. Kishor K. Ade
CONTENTS
 Introduction
 Literature Review
 Need of Project
 Aim and Objectives
 Methodology
 Parametric Study
 Results and Discussion
 Conclusion
 Publications
 References
Eng. Kishor K. Ade
INTRODUCTION
 Underground Tunnelling is an artificial underground
passage to by pass obstacles
 Underground tunnel construction has been rapidly
increasing worldwide
 Most of the projects are located in urban areas
 A few projects have been completed and some are under
construction
 The use of tunnelling for utility, such as water supply,
sewage disposal and metro rail
Eng. Kishor K. Ade
CLASSIFICATION OF TUNNELLING
Flowchart-1 Classification of Tunnelling
Eng. Kishor K. Ade
UNDERGROUND TUNNELLING METHODS
Flowchart-2 Underground tunnelling method
Fig-1 Main Parts of TBM
Eng. Kishor K. Ade
TUNNEL BORING MACHINE
• Tunnel boring machine (TBM) is a machine used to excavate
tunnels with a circular cross section through a variety of soil
and rock strata
• It can bore through anything from hard rock to sand
• TBM has the advantages of limiting the disturbance to the
surrounding ground and producing a smooth tunnel wall.
 EARTH PRESSURE BALANCE METHOD
(EPB)
• Earth balance pressure (EPB) tunnel shields are used in
excavating and advancing tunnels through any type of soft
ground or soil condition
Eng. Kishor K. Ade
 the design and analysis of
structures
Different Component Parts of Underground Tunnelling
Fig-2 Component parts of tunnel
Eng. Kishor K. Ade
HOW IT WORKS
Eng. Kishor K. Ade
LITERATURE REVIEW
Sr no Author Study Description
1 M. Abdel-Meguid
(2003)
3D Effects of Surface
Construction Over Existing
Subway Tunnels
Three-dimensional elasto-plastic finite element
method was used to simulate the construction
of an existing part of Toronto subway tunnels
and the response of the lining to the
construction of Phase III of York-Mills Centre
over the tunnels. The analysis allowed the
calculation of the tunnels deformation, the
lining distortion, and stresses in both
transverse and longitudinal directions.
2 L.Q. Zhang 2005 A displacement-based back-
analysis method for rock mass
modulus and horizontal in situ
stress in tunneling
The DBBA method presented in this paper has
been developed to back-analyze the elastic
modulus of rock mass and the horizontal in
situ stress perpendicular to the axis of an
underground opening, by using immediate
displacements induced by the excavation of
the tunneling face. This indirect method can be
used as a supplement to the present field test
methods.
The back-analysis technique is ideally suitable
for good rock mass conditions.
.
Eng. Kishor K. Ade
CONT…….
Sr no Author Study Description
3 Hsiung, B.C.B
(2010)
Analysis and Construction of
Cross Passage of Delhi Metro
Project Background The contract was located at
south end of Qutab Minar Line of Delhi metro
project comprises 5260 m of tunnel, with 4 cut-
and-cover stations. The inner and outer diameter
of the running tunnel is 5.6 and 6.35m
respectively. Lining of the tunnel was erected by
7- pieces 2750mm reinforcement concrete
segment. Four earth- pressure- balance (EPB)
tunnel boring machines (TBM) were used to
construct these tunnels. The diameter and length
of the shield varies from 6.52m to 6.54m and
from 7.7m to 8.8m.
4 Giovanni Barla
(2013)
Time-Dependent Modeling of
Tunnels in Squeezing
Conditions
The numerical analysis of tunnels in rock masses,
which exhibit a squeezing behavior, is
considered, with reference to the use of two
elastovisc oplastic constitutive laws implemented
in finite-difference and finite-element codes.
Because of the fact that in the most severe
squeezing conditions time dependence is
observed during excavation and may last for a
long time, both the reinforcement of the tunnel
face and the support of the tunnel section are to
be considered at the design and construction
stages.
.
Eng. Kishor K. Ade
NEED OF PROJECT
 The growth of many cities has resulted in the need for
increased infrastructure. As urban space become more
limited.
 The subsurface structures such as tunnels are becoming
more efficient in providing the required infrastructure.
 The cities like Mumbai, Delhi are facing the problem of
land. They already have constructed lots of roads, bridges
and building So that there is no availability of land for
the further infrastructure
Eng. Kishor K. Ade
CONT…….
 Recently Delhi government has made the rule of even and
odd combination for the vehicles just because of the
problem of traffic and pollution.
 To avoid for all this problem the underground tunnel is
best solution.
Eng. Kishor K. Ade
AIM AND OBJECTIVES
 Aim:-
To study the Unaffected depth of underground tunneling on existing
foundations.
 Objectives:-
To find the unaffected depth of tunnelling in different soil strata for
different type of foundations.
To Study the displacement of existing foundations due to tunnelling.
.
Eng. Kishor K. Ade
Software Information
 Midas GTS NX software is based on finite element analysis
 It can handle the entire range of geotechnical design application
Fig-3 Software information
Eng. Kishor K. Ade
FOUNDATION SETTLEMENT
 Problem 9 - A Square footing 1.2 X 1.2 m rests on a saturated
clay layer 4m deep. wL =30% , unit weight saturated =17.8
KN/m3, W = 28% and G = 2.68, Determine the settlement if
footing carries a load of 300 KN.
Where,
σo = Initial Overburden pressure at the
middle of clay layer
SC = Consolidation Settlement
µ = Poisson’s Ratio
H = Thickness of clay layer
W = Water Content
G = Specific gravity of soil solids
CC = Compression Index.
WL = Liquid limit in%
FOUNDATION SETTLEMENT
Dr. S. K. Prasad
Professor of Civil Engineering
S. J. College of Engineering, Mysore
Pg. No. 18
Eng. Kishor K. Ade
Software Results
43.86mm
Displacement
Eng. Kishor K. Ade
Comparison
 Book Results = 48.50mm
 Software Results = 43.86mm
 Difference between book and software results are = 4.64mm
Eng. Kishor K. Ade
METHODOLOGY
Data
collection
Create model
Placing of
foundations
Pressure load on
foundations
Self weight of
soil
To give the Boundary
conditions
Analyse the model for 15m
depth from bottom of the
foundations to the tunnel crown
Similarly Repeat the
analysis for the 20m and
25m depth of tunnel crown.
Check
Results
Model is
Safe
Start
Change the
material properties
Stop
YES
NO
Flowchart-3 Methodology
Eng. Kishor K. Ade
Comparison
 Book Results = 48.50mm
 Software Results = 43.86mm
 Difference between book and software results are = 4.64mm
Eng. Kishor K. Ade
Comparison
Reference- SBC of different Soil Strata as per IS 1904-1978
Eng. Kishor K. Ade
Material Properties
Table No.1
Material Properties of Ground Medium
Depth
(M) Strata
Dry Unit
Wt.
(kN/m3
)
Sat. unit
wt
(kN/m3
)
Poisons
Ratio
(μ)
Elastic
Modulus
E (kN/m2
)
Angle of
Friction
Ø
Cohesion
C
(kN/m2
)
15
20
25
Hard
Murrum
19 20 0.2 150000 39 0
15
20
25
Soft
murrum
18 20 0.4 52000 27 0
15
20
25
Shadu 16 20 0.49 9000 0 38
Reference: Material Properties - Some Useful Numbers on the Engineering Properties of Materials
)Geologic and Otherwise) GEOL 615
Eng. Kishor K. Ade
CONT…….
Table No.2
Material Properties of Structural Medium
Sr. No. Material Type Elastic Modulus
E (kN/m2
)
Unit Weight (kN/m3
)
1 Segment 21 X 106
24
2 Steel 20 X 108
78
3 Grout 10 X 106
22.5
4 Concrete )M20) 22.36 X 106
25
Structural Properties- Midas References
Eng. Kishor K. Ade
Type of shallow foundations
Fig-4 Shallow Foundation Fig-5 Raft Foundation
Eng. Kishor K. Ade
Comparison
 Total Load on Shallow Foundation is 5995.78 T
(B + G + 11 Stories)
 Total Load on Raft Foundation is 5397.50 T.
(B + G + 4 Stories)
 Load is converted in pressure and it applied on individual
foundations on models.
Eng. Kishor K. Ade
Size of model
Fig- 6 Shallow Foundation- (50m X 30m X40m(
(B X D X L(
Fig-7 Raft Foundation-
(30X 50 X 50(
Tunnel Dimension
External Diameter of Tunnel = 7.4 m
Internal Diameter of Tunnel = 6.8 m
Shield Thickness = 0.3m
Reference- All Standard dimensions are taken w.r.t. Delhi metro train tunnel.
Eng. Kishor K. Ade
Flowchart for Analysis
Flowchart No.2 For Analysis
Eng. Kishor K. Ade
Different depth of tunnel crown
A- It shows 15m depth of bottom of the foundation to the depth of top
of the tunnel crown
B- It shows 20m depth of bottom of the foundation to the depth of top
of the tunnel crown
C- It shows 25m depth of bottom of the foundation to the depth of top
of the tunnel crown
Fig-8 Depth of underground tunnel
Eng. Kishor K. Ade
Hard Murrum
 Displacement for Shallow foundation at 15m depth of tunnel
crown
 Displacement at construction stage eleven
Note- Different colour shows displacement at particular portion
Eng. Kishor K. Ade
CONT…….
 Displacement for Shallow foundation at 20m depth of tunnel
crown
 Displacement at construction stage eleven
Eng. Kishor K. Ade
CONT…….
 Displacement for Shallow foundation at 25m depth of tunnel
crown
 Displacement at construction stage eleven
Eng. Kishor K. Ade
Hard Murrum
 Displacement for Raft foundation at 15m depth of tunnel
crown
 Displacement at construction stage five
Note- Different colour shows displacement at particular portion
Eng. Kishor K. Ade
CONT…….
 Displacement for Raft foundation at 20m depth of tunnel
crown
 Displacement at construction stage five
Eng. Kishor K. Ade
CONT…….
 Displacement for Raft foundation at 25m depth of tunnel
crown
 Displacement at construction stage five
Eng. Kishor K. Ade
RESULTS FOR RAFT FOUNDATION
Fig.4 Fig.5
Fig.6
Eng. Kishor K. Ade
IS Code 1904-1986
Eng. Kishor K. Ade
RESULTS AND DISCUSSION
 For Shallow Foundation
 The displacement of existing Shallow foundation due to
underground tunnelling on hard murrum is 61.91mm at
15m depth of tunnel crown. Displacement of foundation
should not exceed 70mm as per IS Code 1904-1986. Hence it is
not suitable to construct the underground tunneling, because
it is nearest to the existing foundation and foundation may be
disturbed.
 Similarly displacement of existing Raft foundation at 20m and
25m depth of tunnel crown is 59.14mm and 58.01mm
respectively.
Eng. Kishor K. Ade
CONT…….
 The displacement of existing Shallow foundation due to
underground tunnelling on soft murrum is 61.91mm at 15m
depth of tunnel crown. Displacement of foundation should
not exceed 70mm as per IS Code 1904-1986. Hence it is not
suitable to construct the underground tunneling, because it is
nearest to the existing foundation and foundation may be
disturbed.
 Similarly displacement of existing Raft foundation at 20m and
25m depth of tunnel crown is 59.14mm and 58.01mm
respectively.
Eng. Kishor K. Ade
CONT…….
 The displacement of existing Shallow foundation due to
underground tunnelling on Shadu strata is 61.91mm at 15m
depth of tunnel crown. Displacement of foundation should
not exceed 70mm as per IS Code 1904-1986. Hence it is not
suitable to construct the underground tunneling, because it is
nearest to the existing foundation and foundation may be
disturbed.
 Similarly displacement of existing Raft foundation at 20m
and 25m depth of tunnel crown is 59.14mm and 58.01mm
respectively.
Eng. Kishor K. Ade
CONT…….
 For Raft Foundation
 The displacement of existing Raft foundation due to
underground tunnelling on hard murrum is 61.91mm at
15m depth of tunnel crown. Displacement of foundation
should not exceed 70mm as per IS Code 1904-1986. Hence it is
not suitable to construct the underground tunneling, because
it is nearest to the existing foundation and foundation may be
disturbed.
 Similarly displacement of existing Raft foundation at 20m
and 25m depth of tunnel crown is 59.14mm and 58.01mm
respectively
Eng. Kishor K. Ade
CONT…….
 The displacement of existing Raft foundation due to
underground tunnelling on soft murrum is 61.91mm at 15m
depth of tunnel crown. Displacement of foundation should
not exceed 70mm as per IS Code 1904-1986. Hence it is not
suitable to construct the underground tunneling, because it is
nearest to the existing foundation and foundation may be
disturbed.
 Similarly displacement of existing Raft foundation at 20m
and 25m depth of tunnel crown is 59.14mm and 58.01mm
respectively.
Eng. Kishor K. Ade
CONT…….
 The displacement of existing Raft foundation due to
underground tunnelling on Shadu strata is 61.91mm at 15m
depth of tunnel crown. Displacement of foundation should
not exceed 70mm as per IS Code 1904-1986. Hence it is not
suitable to construct the underground tunneling, because it is
nearest to the existing foundation and foundation may be
disturbed.
 Similarly displacement of existing Raft foundation at 20m
and 25m depth of tunnel crown is 59.14mm and 58.01mm
respectively.
Eng. Kishor K. Ade
CONCLUSION
 The underground tunnel construction is suitable for Raft
Foundation on hard Murrum and Soft Murrum up to
20m to 25m depth of the bottom of foundation to the
depth of top of the tunnel Crown.
 The underground tunnel construction is suitable for Shallow
Foundation on hard Murrum and Soft Murrum up to 20m to
25m depth of the bottom of the tunnel Crown. Displacement
of foundation is not exceed 50mm as per IS Code 1904-1986.
 The underground tunnel construction is not suitable for
Shallow and Raft Foundations on shadu strata up to 15m,
20m and 25m.
Eng. Kishor K. Ade
PUBLICATIONS
 Kishor K. Ade, B. S. Karkare, G. R. Chillal, “Effect of
Underground Tunnelling by (TBM) on existing
Structures”, Civil engineering post graduation
conference- PGCON 2015, MAEER’s MIT Pune.
 2. Kishor K. Ade, B. S. Karkare, G. R. Chillal, “Effect
of Underground Tunnelling by (TBM) on Raft
foundation”, Smarter cities – India 2015 : Smarter
solution for a better tomorrow (SCI 2015)
Eng. Kishor K. Ade
REFERENCE
 M. Abdel-Meguid, R. K. Rowe, and K. Y. Lo (2003), “3D Effects
of Surface Construction Over Existing Subway Tunnels.”
ASCE, the International Journal of Geomechanics Volume 2,
Number 4, 447–469 (2002).
 L.Q. Zhang, Z.Q. Yue, Z.F. Yang, J.X. Qi, F.C. Liu, (2005)“A
displacement-based back-analysis method for rock mass
modulus and horizontal in situ stress in tunneling – Illustrated
with a case study. Science direct, Tunnelling and Underground
Space Technology 21 (2006) 636–649
 Hsiung, B.C.B. Tsai, Y.Y. Tsai, C.C. (2010) “Analysis and
Construction of Cross Passage of Delhi Metro” Indian
Geotechnical Conference – 2010, GEO trendz December 16–18,
2010 IGS Mumbai Chapter & IIT Bombay.
Eng. Kishor K. Ade
CONT…….
 Gordon T. K. Lee and Charles W. W. Ng, M.ASCE, “Effects of
Advancing Open Face Tunneling on an Existing Loaded Pile”
ASCE, Journal of Geotechnical and Geoenvironmental
Engineering, Vol. 131, No. 2
 K. H. Park (2003), “Elastic Solution for Tunneling-Induced
Ground Movements in Clays” ASCE, International Journal of
Geomechanics, Vol. 4, No. 4, December 1, 2004.
 Guilhem Mollon; Daniel Dias; and Abdul-Hamid Soubra (2010),
“Face Stability Analysis of Circular Tunnels Driven by a
Pressurized Shield” ASCE journal of Geotechnical and
Geoenvironmental Engineering, Vol. 136, No. 1
Eng. Kishor K. Ade
CONT…….
 R.C.K. Wong and P. K. Kaiser (1991) “ Performance Assessment
of tunnels in Cohesions less” ASCE, Journal of Geotechnical
Engineering, Vol. 117, No 12.
 Sang-baik Woo, Jong-ho Park, Hong-Sung Lee, Yong-Ki Choi,
“Recovery Execution in Collapsed Face of Soil-Tunnel Entrance
When One-Way Driving” Midas Journals
 A. Pourtaghi , M.A. Lotfollahi-Yaghin (2011) “Wavenet ability
assessment in comparison to ANN for predicting the maximum
surface settlement caused by tunneling” Tunnelling and
Underground Space Technology
 G. Girmscheid and Cliff Schexnayder, F.ASCE (2003), “Tunnel
Boring Machines” ASCE Practice Periodica
Eng. Kishor K. Ade
Thank You…

More Related Content

What's hot

Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnels
partha sharma
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
jamali husain
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
jagadish chintu
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
1971995
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnel
Abhishek Kansara
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
akjain_mkt
 
Tunnels concepts
Tunnels conceptsTunnels concepts
Tunnels concepts
Sathish Kumar
 
Tunneling & Drilling Equipments
Tunneling & Drilling EquipmentsTunneling & Drilling Equipments
Tunneling & Drilling Equipments
Rajarshi Patty
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
dinesh sharma
 
Board & Pillar
Board & PillarBoard & Pillar
Board & Pillar
Chittranjan Vaishnav
 
Tunnel engineering
Tunnel engineeringTunnel engineering
Tunnel engineering
Vinod Shikhare
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
Rajesh Prasad
 
Cofferdam
CofferdamCofferdam
Cofferdam
sauravsaxena3
 
multi swing bridges
multi swing bridgesmulti swing bridges
multi swing bridges
Gaurav Shukla
 
Micropiles
Micropiles Micropiles
Micropiles
Sumit Rawat
 
seepage through earthen dam
seepage through earthen damseepage through earthen dam
seepage through earthen dam
Nathanimahar
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
luisaam
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
vikasravekar
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 

What's hot (20)

Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnels
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Tunnel construction
Tunnel constructionTunnel construction
Tunnel construction
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnel
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Tunnels concepts
Tunnels conceptsTunnels concepts
Tunnels concepts
 
Tunneling & Drilling Equipments
Tunneling & Drilling EquipmentsTunneling & Drilling Equipments
Tunneling & Drilling Equipments
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Board & Pillar
Board & PillarBoard & Pillar
Board & Pillar
 
Tunnel engineering
Tunnel engineeringTunnel engineering
Tunnel engineering
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
multi swing bridges
multi swing bridgesmulti swing bridges
multi swing bridges
 
Micropiles
Micropiles Micropiles
Micropiles
 
seepage through earthen dam
seepage through earthen damseepage through earthen dam
seepage through earthen dam
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 

Similar to Effect of underground tunnelling by (TBM) on foundations of existing structures

PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
IRJET Journal
 
The Experimental Failure behaviour of a Prestressed Concrete Electricity Tran...
The Experimental Failure behaviour of a Prestressed Concrete Electricity Tran...The Experimental Failure behaviour of a Prestressed Concrete Electricity Tran...
The Experimental Failure behaviour of a Prestressed Concrete Electricity Tran...
Samirsinh Parmar
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
ijceronline
 
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
ijiert bestjournal
 
Cutterhead & Cutting Tools Configuration in Course Grain Soils
Cutterhead & Cutting Tools Configuration in Course Grain SoilsCutterhead & Cutting Tools Configuration in Course Grain Soils
Cutterhead & Cutting Tools Configuration in Course Grain Soils
rab13
 
Numerical analysis of influence of deep excavation on nearby existing tunnel
Numerical analysis of influence of deep excavation on nearby existing tunnelNumerical analysis of influence of deep excavation on nearby existing tunnel
Numerical analysis of influence of deep excavation on nearby existing tunnel
eSAT Publishing House
 
Optimization of 3 d geometrical soil model for
Optimization of 3 d geometrical soil model forOptimization of 3 d geometrical soil model for
Optimization of 3 d geometrical soil model for
eSAT Publishing House
 
Optimization of 3 d geometrical soil model for multiple footing resting on sand
Optimization of 3 d geometrical soil model for multiple footing resting on sandOptimization of 3 d geometrical soil model for multiple footing resting on sand
Optimization of 3 d geometrical soil model for multiple footing resting on sand
eSAT Journals
 
Analytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interactionAnalytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interaction
eSAT Publishing House
 
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
CrimsonPublishersAMMS
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete Structure
IJERA Editor
 
Analysis of Soil-Structure Interaction Mechanisms on Integral Abutment Bridge
Analysis of Soil-Structure Interaction Mechanisms on Integral Abutment BridgeAnalysis of Soil-Structure Interaction Mechanisms on Integral Abutment Bridge
Analysis of Soil-Structure Interaction Mechanisms on Integral Abutment Bridge
IRJET Journal
 
Estimating the shear modulus of soils based on
Estimating the shear modulus of soils based onEstimating the shear modulus of soils based on
Estimating the shear modulus of soils based on
eSAT Publishing House
 
Analytical Study of Steel Fibre Reinforced Rigid Pavements Under Moving Loads
Analytical Study of Steel Fibre Reinforced Rigid Pavements Under Moving LoadsAnalytical Study of Steel Fibre Reinforced Rigid Pavements Under Moving Loads
Analytical Study of Steel Fibre Reinforced Rigid Pavements Under Moving Loads
ijsrd.com
 
Effect of vertical cross sectional shape of foundation and soil reinforcement
Effect of vertical cross sectional shape of foundation and soil reinforcementEffect of vertical cross sectional shape of foundation and soil reinforcement
Effect of vertical cross sectional shape of foundation and soil reinforcementIAEME Publication
 
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGEMECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
EditorIJAERD
 
cut-off wall
cut-off wallcut-off wall
cut-off wall
ManishSharma1965
 
Analysis and Design of PSC post te girder
Analysis and Design of PSC post te girderAnalysis and Design of PSC post te girder
Analysis and Design of PSC post te girder
JesikaLalwani
 

Similar to Effect of underground tunnelling by (TBM) on foundations of existing structures (20)

PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
 
The Experimental Failure behaviour of a Prestressed Concrete Electricity Tran...
The Experimental Failure behaviour of a Prestressed Concrete Electricity Tran...The Experimental Failure behaviour of a Prestressed Concrete Electricity Tran...
The Experimental Failure behaviour of a Prestressed Concrete Electricity Tran...
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
 
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
 
Cutterhead & Cutting Tools Configuration in Course Grain Soils
Cutterhead & Cutting Tools Configuration in Course Grain SoilsCutterhead & Cutting Tools Configuration in Course Grain Soils
Cutterhead & Cutting Tools Configuration in Course Grain Soils
 
Numerical analysis of influence of deep excavation on nearby existing tunnel
Numerical analysis of influence of deep excavation on nearby existing tunnelNumerical analysis of influence of deep excavation on nearby existing tunnel
Numerical analysis of influence of deep excavation on nearby existing tunnel
 
Optimization of 3 d geometrical soil model for
Optimization of 3 d geometrical soil model forOptimization of 3 d geometrical soil model for
Optimization of 3 d geometrical soil model for
 
Optimization of 3 d geometrical soil model for multiple footing resting on sand
Optimization of 3 d geometrical soil model for multiple footing resting on sandOptimization of 3 d geometrical soil model for multiple footing resting on sand
Optimization of 3 d geometrical soil model for multiple footing resting on sand
 
Analytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interactionAnalytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interaction
 
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete Structure
 
Analysis of Soil-Structure Interaction Mechanisms on Integral Abutment Bridge
Analysis of Soil-Structure Interaction Mechanisms on Integral Abutment BridgeAnalysis of Soil-Structure Interaction Mechanisms on Integral Abutment Bridge
Analysis of Soil-Structure Interaction Mechanisms on Integral Abutment Bridge
 
Estimating the shear modulus of soils based on
Estimating the shear modulus of soils based onEstimating the shear modulus of soils based on
Estimating the shear modulus of soils based on
 
Analytical Study of Steel Fibre Reinforced Rigid Pavements Under Moving Loads
Analytical Study of Steel Fibre Reinforced Rigid Pavements Under Moving LoadsAnalytical Study of Steel Fibre Reinforced Rigid Pavements Under Moving Loads
Analytical Study of Steel Fibre Reinforced Rigid Pavements Under Moving Loads
 
Effect of vertical cross sectional shape of foundation and soil reinforcement
Effect of vertical cross sectional shape of foundation and soil reinforcementEffect of vertical cross sectional shape of foundation and soil reinforcement
Effect of vertical cross sectional shape of foundation and soil reinforcement
 
Civil ques
Civil quesCivil ques
Civil ques
 
Cv15 nalisis method
Cv15 nalisis methodCv15 nalisis method
Cv15 nalisis method
 
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGEMECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
 
cut-off wall
cut-off wallcut-off wall
cut-off wall
 
Analysis and Design of PSC post te girder
Analysis and Design of PSC post te girderAnalysis and Design of PSC post te girder
Analysis and Design of PSC post te girder
 

More from Kishor Ade

Motivation
MotivationMotivation
Motivation
Kishor Ade
 
Contouring
ContouringContouring
Contouring
Kishor Ade
 
Balbharati aani kumarbhartitalya marathi kavita
Balbharati aani kumarbhartitalya marathi kavitaBalbharati aani kumarbhartitalya marathi kavita
Balbharati aani kumarbhartitalya marathi kavita
Kishor Ade
 
THEORY OF STRUCTURES-I [B. ARCH.]
THEORY OF STRUCTURES-I [B. ARCH.]THEORY OF STRUCTURES-I [B. ARCH.]
THEORY OF STRUCTURES-I [B. ARCH.]
Kishor Ade
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
Kishor Ade
 
First lecture on First year at Trinity Architecture college Pune
First lecture on First year at Trinity Architecture college PuneFirst lecture on First year at Trinity Architecture college Pune
First lecture on First year at Trinity Architecture college Pune
Kishor Ade
 
Demolition work of existing building
Demolition work of existing buildingDemolition work of existing building
Demolition work of existing building
Kishor Ade
 
Levelling
LevellingLevelling
Levelling
Kishor Ade
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
Kishor Ade
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
Kishor Ade
 
Plane Table Survey
Plane Table SurveyPlane Table Survey
Plane Table Survey
Kishor Ade
 
Compass surveying
Compass surveying Compass surveying
Compass surveying
Kishor Ade
 
Natural Beauty of India...............!
Natural Beauty of India...............!Natural Beauty of India...............!
Natural Beauty of India...............!
Kishor Ade
 
Life will be never ending..........!
Life will be never ending..........!Life will be never ending..........!
Life will be never ending..........!
Kishor Ade
 
Structures-V
Structures-VStructures-V
Structures-V
Kishor Ade
 
Specification Writing-I
Specification Writing-I Specification Writing-I
Specification Writing-I
Kishor Ade
 
Research Methodology Module-08
Research Methodology Module-08Research Methodology Module-08
Research Methodology Module-08
Kishor Ade
 
Research Methodology Module-07
Research Methodology Module-07Research Methodology Module-07
Research Methodology Module-07
Kishor Ade
 
Research Methodology Module-06
Research Methodology Module-06Research Methodology Module-06
Research Methodology Module-06
Kishor Ade
 
Research Methodology Module-05
Research Methodology Module-05Research Methodology Module-05
Research Methodology Module-05
Kishor Ade
 

More from Kishor Ade (20)

Motivation
MotivationMotivation
Motivation
 
Contouring
ContouringContouring
Contouring
 
Balbharati aani kumarbhartitalya marathi kavita
Balbharati aani kumarbhartitalya marathi kavitaBalbharati aani kumarbhartitalya marathi kavita
Balbharati aani kumarbhartitalya marathi kavita
 
THEORY OF STRUCTURES-I [B. ARCH.]
THEORY OF STRUCTURES-I [B. ARCH.]THEORY OF STRUCTURES-I [B. ARCH.]
THEORY OF STRUCTURES-I [B. ARCH.]
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
First lecture on First year at Trinity Architecture college Pune
First lecture on First year at Trinity Architecture college PuneFirst lecture on First year at Trinity Architecture college Pune
First lecture on First year at Trinity Architecture college Pune
 
Demolition work of existing building
Demolition work of existing buildingDemolition work of existing building
Demolition work of existing building
 
Levelling
LevellingLevelling
Levelling
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
 
Plane Table Survey
Plane Table SurveyPlane Table Survey
Plane Table Survey
 
Compass surveying
Compass surveying Compass surveying
Compass surveying
 
Natural Beauty of India...............!
Natural Beauty of India...............!Natural Beauty of India...............!
Natural Beauty of India...............!
 
Life will be never ending..........!
Life will be never ending..........!Life will be never ending..........!
Life will be never ending..........!
 
Structures-V
Structures-VStructures-V
Structures-V
 
Specification Writing-I
Specification Writing-I Specification Writing-I
Specification Writing-I
 
Research Methodology Module-08
Research Methodology Module-08Research Methodology Module-08
Research Methodology Module-08
 
Research Methodology Module-07
Research Methodology Module-07Research Methodology Module-07
Research Methodology Module-07
 
Research Methodology Module-06
Research Methodology Module-06Research Methodology Module-06
Research Methodology Module-06
 
Research Methodology Module-05
Research Methodology Module-05Research Methodology Module-05
Research Methodology Module-05
 

Recently uploaded

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 

Recently uploaded (20)

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 

Effect of underground tunnelling by (TBM) on foundations of existing structures

  • 1. Eng. Kishor K. Ade A DISSERTATION ON Effect of Underground Tunnelling by (TBM) on Foundations of Existing Structures By Kishor K. Ade M.E. (Structures) (5057) Under guidance of Dr. Prof. Mrs. B. S. Karkare & Mrs. G. R. Chillal Vishwakarma Institute Of Information Technology, Pune
  • 2. Eng. Kishor K. Ade CONTENTS  Introduction  Literature Review  Need of Project  Aim and Objectives  Methodology  Parametric Study  Results and Discussion  Conclusion  Publications  References
  • 3. Eng. Kishor K. Ade INTRODUCTION  Underground Tunnelling is an artificial underground passage to by pass obstacles  Underground tunnel construction has been rapidly increasing worldwide  Most of the projects are located in urban areas  A few projects have been completed and some are under construction  The use of tunnelling for utility, such as water supply, sewage disposal and metro rail
  • 4. Eng. Kishor K. Ade CLASSIFICATION OF TUNNELLING Flowchart-1 Classification of Tunnelling
  • 5. Eng. Kishor K. Ade UNDERGROUND TUNNELLING METHODS Flowchart-2 Underground tunnelling method Fig-1 Main Parts of TBM
  • 6. Eng. Kishor K. Ade TUNNEL BORING MACHINE • Tunnel boring machine (TBM) is a machine used to excavate tunnels with a circular cross section through a variety of soil and rock strata • It can bore through anything from hard rock to sand • TBM has the advantages of limiting the disturbance to the surrounding ground and producing a smooth tunnel wall.  EARTH PRESSURE BALANCE METHOD (EPB) • Earth balance pressure (EPB) tunnel shields are used in excavating and advancing tunnels through any type of soft ground or soil condition
  • 7. Eng. Kishor K. Ade  the design and analysis of structures Different Component Parts of Underground Tunnelling Fig-2 Component parts of tunnel
  • 8. Eng. Kishor K. Ade HOW IT WORKS
  • 9. Eng. Kishor K. Ade LITERATURE REVIEW Sr no Author Study Description 1 M. Abdel-Meguid (2003) 3D Effects of Surface Construction Over Existing Subway Tunnels Three-dimensional elasto-plastic finite element method was used to simulate the construction of an existing part of Toronto subway tunnels and the response of the lining to the construction of Phase III of York-Mills Centre over the tunnels. The analysis allowed the calculation of the tunnels deformation, the lining distortion, and stresses in both transverse and longitudinal directions. 2 L.Q. Zhang 2005 A displacement-based back- analysis method for rock mass modulus and horizontal in situ stress in tunneling The DBBA method presented in this paper has been developed to back-analyze the elastic modulus of rock mass and the horizontal in situ stress perpendicular to the axis of an underground opening, by using immediate displacements induced by the excavation of the tunneling face. This indirect method can be used as a supplement to the present field test methods. The back-analysis technique is ideally suitable for good rock mass conditions. .
  • 10. Eng. Kishor K. Ade CONT……. Sr no Author Study Description 3 Hsiung, B.C.B (2010) Analysis and Construction of Cross Passage of Delhi Metro Project Background The contract was located at south end of Qutab Minar Line of Delhi metro project comprises 5260 m of tunnel, with 4 cut- and-cover stations. The inner and outer diameter of the running tunnel is 5.6 and 6.35m respectively. Lining of the tunnel was erected by 7- pieces 2750mm reinforcement concrete segment. Four earth- pressure- balance (EPB) tunnel boring machines (TBM) were used to construct these tunnels. The diameter and length of the shield varies from 6.52m to 6.54m and from 7.7m to 8.8m. 4 Giovanni Barla (2013) Time-Dependent Modeling of Tunnels in Squeezing Conditions The numerical analysis of tunnels in rock masses, which exhibit a squeezing behavior, is considered, with reference to the use of two elastovisc oplastic constitutive laws implemented in finite-difference and finite-element codes. Because of the fact that in the most severe squeezing conditions time dependence is observed during excavation and may last for a long time, both the reinforcement of the tunnel face and the support of the tunnel section are to be considered at the design and construction stages. .
  • 11. Eng. Kishor K. Ade NEED OF PROJECT  The growth of many cities has resulted in the need for increased infrastructure. As urban space become more limited.  The subsurface structures such as tunnels are becoming more efficient in providing the required infrastructure.  The cities like Mumbai, Delhi are facing the problem of land. They already have constructed lots of roads, bridges and building So that there is no availability of land for the further infrastructure
  • 12. Eng. Kishor K. Ade CONT…….  Recently Delhi government has made the rule of even and odd combination for the vehicles just because of the problem of traffic and pollution.  To avoid for all this problem the underground tunnel is best solution.
  • 13. Eng. Kishor K. Ade AIM AND OBJECTIVES  Aim:- To study the Unaffected depth of underground tunneling on existing foundations.  Objectives:- To find the unaffected depth of tunnelling in different soil strata for different type of foundations. To Study the displacement of existing foundations due to tunnelling. .
  • 14. Eng. Kishor K. Ade Software Information  Midas GTS NX software is based on finite element analysis  It can handle the entire range of geotechnical design application Fig-3 Software information
  • 15. Eng. Kishor K. Ade FOUNDATION SETTLEMENT  Problem 9 - A Square footing 1.2 X 1.2 m rests on a saturated clay layer 4m deep. wL =30% , unit weight saturated =17.8 KN/m3, W = 28% and G = 2.68, Determine the settlement if footing carries a load of 300 KN. Where, σo = Initial Overburden pressure at the middle of clay layer SC = Consolidation Settlement µ = Poisson’s Ratio H = Thickness of clay layer W = Water Content G = Specific gravity of soil solids CC = Compression Index. WL = Liquid limit in% FOUNDATION SETTLEMENT Dr. S. K. Prasad Professor of Civil Engineering S. J. College of Engineering, Mysore Pg. No. 18
  • 16. Eng. Kishor K. Ade Software Results 43.86mm Displacement
  • 17. Eng. Kishor K. Ade Comparison  Book Results = 48.50mm  Software Results = 43.86mm  Difference between book and software results are = 4.64mm
  • 18. Eng. Kishor K. Ade METHODOLOGY Data collection Create model Placing of foundations Pressure load on foundations Self weight of soil To give the Boundary conditions Analyse the model for 15m depth from bottom of the foundations to the tunnel crown Similarly Repeat the analysis for the 20m and 25m depth of tunnel crown. Check Results Model is Safe Start Change the material properties Stop YES NO Flowchart-3 Methodology
  • 19. Eng. Kishor K. Ade Comparison  Book Results = 48.50mm  Software Results = 43.86mm  Difference between book and software results are = 4.64mm
  • 20. Eng. Kishor K. Ade Comparison Reference- SBC of different Soil Strata as per IS 1904-1978
  • 21. Eng. Kishor K. Ade Material Properties Table No.1 Material Properties of Ground Medium Depth (M) Strata Dry Unit Wt. (kN/m3 ) Sat. unit wt (kN/m3 ) Poisons Ratio (μ) Elastic Modulus E (kN/m2 ) Angle of Friction Ø Cohesion C (kN/m2 ) 15 20 25 Hard Murrum 19 20 0.2 150000 39 0 15 20 25 Soft murrum 18 20 0.4 52000 27 0 15 20 25 Shadu 16 20 0.49 9000 0 38 Reference: Material Properties - Some Useful Numbers on the Engineering Properties of Materials )Geologic and Otherwise) GEOL 615
  • 22. Eng. Kishor K. Ade CONT……. Table No.2 Material Properties of Structural Medium Sr. No. Material Type Elastic Modulus E (kN/m2 ) Unit Weight (kN/m3 ) 1 Segment 21 X 106 24 2 Steel 20 X 108 78 3 Grout 10 X 106 22.5 4 Concrete )M20) 22.36 X 106 25 Structural Properties- Midas References
  • 23. Eng. Kishor K. Ade Type of shallow foundations Fig-4 Shallow Foundation Fig-5 Raft Foundation
  • 24. Eng. Kishor K. Ade Comparison  Total Load on Shallow Foundation is 5995.78 T (B + G + 11 Stories)  Total Load on Raft Foundation is 5397.50 T. (B + G + 4 Stories)  Load is converted in pressure and it applied on individual foundations on models.
  • 25. Eng. Kishor K. Ade Size of model Fig- 6 Shallow Foundation- (50m X 30m X40m( (B X D X L( Fig-7 Raft Foundation- (30X 50 X 50( Tunnel Dimension External Diameter of Tunnel = 7.4 m Internal Diameter of Tunnel = 6.8 m Shield Thickness = 0.3m Reference- All Standard dimensions are taken w.r.t. Delhi metro train tunnel.
  • 26. Eng. Kishor K. Ade Flowchart for Analysis Flowchart No.2 For Analysis
  • 27. Eng. Kishor K. Ade Different depth of tunnel crown A- It shows 15m depth of bottom of the foundation to the depth of top of the tunnel crown B- It shows 20m depth of bottom of the foundation to the depth of top of the tunnel crown C- It shows 25m depth of bottom of the foundation to the depth of top of the tunnel crown Fig-8 Depth of underground tunnel
  • 28. Eng. Kishor K. Ade Hard Murrum  Displacement for Shallow foundation at 15m depth of tunnel crown  Displacement at construction stage eleven Note- Different colour shows displacement at particular portion
  • 29. Eng. Kishor K. Ade CONT…….  Displacement for Shallow foundation at 20m depth of tunnel crown  Displacement at construction stage eleven
  • 30. Eng. Kishor K. Ade CONT…….  Displacement for Shallow foundation at 25m depth of tunnel crown  Displacement at construction stage eleven
  • 31. Eng. Kishor K. Ade Hard Murrum  Displacement for Raft foundation at 15m depth of tunnel crown  Displacement at construction stage five Note- Different colour shows displacement at particular portion
  • 32. Eng. Kishor K. Ade CONT…….  Displacement for Raft foundation at 20m depth of tunnel crown  Displacement at construction stage five
  • 33. Eng. Kishor K. Ade CONT…….  Displacement for Raft foundation at 25m depth of tunnel crown  Displacement at construction stage five
  • 34. Eng. Kishor K. Ade RESULTS FOR RAFT FOUNDATION Fig.4 Fig.5 Fig.6
  • 35. Eng. Kishor K. Ade IS Code 1904-1986
  • 36. Eng. Kishor K. Ade RESULTS AND DISCUSSION  For Shallow Foundation  The displacement of existing Shallow foundation due to underground tunnelling on hard murrum is 61.91mm at 15m depth of tunnel crown. Displacement of foundation should not exceed 70mm as per IS Code 1904-1986. Hence it is not suitable to construct the underground tunneling, because it is nearest to the existing foundation and foundation may be disturbed.  Similarly displacement of existing Raft foundation at 20m and 25m depth of tunnel crown is 59.14mm and 58.01mm respectively.
  • 37. Eng. Kishor K. Ade CONT…….  The displacement of existing Shallow foundation due to underground tunnelling on soft murrum is 61.91mm at 15m depth of tunnel crown. Displacement of foundation should not exceed 70mm as per IS Code 1904-1986. Hence it is not suitable to construct the underground tunneling, because it is nearest to the existing foundation and foundation may be disturbed.  Similarly displacement of existing Raft foundation at 20m and 25m depth of tunnel crown is 59.14mm and 58.01mm respectively.
  • 38. Eng. Kishor K. Ade CONT…….  The displacement of existing Shallow foundation due to underground tunnelling on Shadu strata is 61.91mm at 15m depth of tunnel crown. Displacement of foundation should not exceed 70mm as per IS Code 1904-1986. Hence it is not suitable to construct the underground tunneling, because it is nearest to the existing foundation and foundation may be disturbed.  Similarly displacement of existing Raft foundation at 20m and 25m depth of tunnel crown is 59.14mm and 58.01mm respectively.
  • 39. Eng. Kishor K. Ade CONT…….  For Raft Foundation  The displacement of existing Raft foundation due to underground tunnelling on hard murrum is 61.91mm at 15m depth of tunnel crown. Displacement of foundation should not exceed 70mm as per IS Code 1904-1986. Hence it is not suitable to construct the underground tunneling, because it is nearest to the existing foundation and foundation may be disturbed.  Similarly displacement of existing Raft foundation at 20m and 25m depth of tunnel crown is 59.14mm and 58.01mm respectively
  • 40. Eng. Kishor K. Ade CONT…….  The displacement of existing Raft foundation due to underground tunnelling on soft murrum is 61.91mm at 15m depth of tunnel crown. Displacement of foundation should not exceed 70mm as per IS Code 1904-1986. Hence it is not suitable to construct the underground tunneling, because it is nearest to the existing foundation and foundation may be disturbed.  Similarly displacement of existing Raft foundation at 20m and 25m depth of tunnel crown is 59.14mm and 58.01mm respectively.
  • 41. Eng. Kishor K. Ade CONT…….  The displacement of existing Raft foundation due to underground tunnelling on Shadu strata is 61.91mm at 15m depth of tunnel crown. Displacement of foundation should not exceed 70mm as per IS Code 1904-1986. Hence it is not suitable to construct the underground tunneling, because it is nearest to the existing foundation and foundation may be disturbed.  Similarly displacement of existing Raft foundation at 20m and 25m depth of tunnel crown is 59.14mm and 58.01mm respectively.
  • 42. Eng. Kishor K. Ade CONCLUSION  The underground tunnel construction is suitable for Raft Foundation on hard Murrum and Soft Murrum up to 20m to 25m depth of the bottom of foundation to the depth of top of the tunnel Crown.  The underground tunnel construction is suitable for Shallow Foundation on hard Murrum and Soft Murrum up to 20m to 25m depth of the bottom of the tunnel Crown. Displacement of foundation is not exceed 50mm as per IS Code 1904-1986.  The underground tunnel construction is not suitable for Shallow and Raft Foundations on shadu strata up to 15m, 20m and 25m.
  • 43. Eng. Kishor K. Ade PUBLICATIONS  Kishor K. Ade, B. S. Karkare, G. R. Chillal, “Effect of Underground Tunnelling by (TBM) on existing Structures”, Civil engineering post graduation conference- PGCON 2015, MAEER’s MIT Pune.  2. Kishor K. Ade, B. S. Karkare, G. R. Chillal, “Effect of Underground Tunnelling by (TBM) on Raft foundation”, Smarter cities – India 2015 : Smarter solution for a better tomorrow (SCI 2015)
  • 44. Eng. Kishor K. Ade REFERENCE  M. Abdel-Meguid, R. K. Rowe, and K. Y. Lo (2003), “3D Effects of Surface Construction Over Existing Subway Tunnels.” ASCE, the International Journal of Geomechanics Volume 2, Number 4, 447–469 (2002).  L.Q. Zhang, Z.Q. Yue, Z.F. Yang, J.X. Qi, F.C. Liu, (2005)“A displacement-based back-analysis method for rock mass modulus and horizontal in situ stress in tunneling – Illustrated with a case study. Science direct, Tunnelling and Underground Space Technology 21 (2006) 636–649  Hsiung, B.C.B. Tsai, Y.Y. Tsai, C.C. (2010) “Analysis and Construction of Cross Passage of Delhi Metro” Indian Geotechnical Conference – 2010, GEO trendz December 16–18, 2010 IGS Mumbai Chapter & IIT Bombay.
  • 45. Eng. Kishor K. Ade CONT…….  Gordon T. K. Lee and Charles W. W. Ng, M.ASCE, “Effects of Advancing Open Face Tunneling on an Existing Loaded Pile” ASCE, Journal of Geotechnical and Geoenvironmental Engineering, Vol. 131, No. 2  K. H. Park (2003), “Elastic Solution for Tunneling-Induced Ground Movements in Clays” ASCE, International Journal of Geomechanics, Vol. 4, No. 4, December 1, 2004.  Guilhem Mollon; Daniel Dias; and Abdul-Hamid Soubra (2010), “Face Stability Analysis of Circular Tunnels Driven by a Pressurized Shield” ASCE journal of Geotechnical and Geoenvironmental Engineering, Vol. 136, No. 1
  • 46. Eng. Kishor K. Ade CONT…….  R.C.K. Wong and P. K. Kaiser (1991) “ Performance Assessment of tunnels in Cohesions less” ASCE, Journal of Geotechnical Engineering, Vol. 117, No 12.  Sang-baik Woo, Jong-ho Park, Hong-Sung Lee, Yong-Ki Choi, “Recovery Execution in Collapsed Face of Soil-Tunnel Entrance When One-Way Driving” Midas Journals  A. Pourtaghi , M.A. Lotfollahi-Yaghin (2011) “Wavenet ability assessment in comparison to ANN for predicting the maximum surface settlement caused by tunneling” Tunnelling and Underground Space Technology  G. Girmscheid and Cliff Schexnayder, F.ASCE (2003), “Tunnel Boring Machines” ASCE Practice Periodica
  • 47. Eng. Kishor K. Ade Thank You…