SlideShare a Scribd company logo
VARIABLE COST OF UP & UTTARAKHAND
SL NO. Station Paisa/ Unit Station Paisa/ Unit
1 SALAL HPS 48.00 CHIBRO (YAMUNA) 27.00
2 URI HEP 81.00 KHATIMA HPS 30.00
3 CHAMERA HEP 107.00 KULHAL HPS 31.00
4 TANAKPUR HEP 115.00 CHILLA HPS 34.00
5 SASAN 128.50 KHODRI HPS 34.00
6 SINGARAULI STPS 131.00 DHAKRANI HPS 36.00
7 SIGARAULI STAGE III 136.60 RAMGANGA HPS 37.00
8 VISHUNUPRAYAG 140.00 DHALIPUR HPS 40.00
9 RIHAND STAGE II 143.70 SALAL HPS 102.00
10 DHAULI GANGA HEP 145.00 SINGARAULI STPS 131.00
11 NATHPA JHAKRI (SJVNT) 146.00 MANERI BHALI-II 134.00
12 CHAMERA -II HEP 169.90 RIHAND STAGE -III 136.60
13 URI-II HEP 169.90 RIHAND STAGE -II 143.70
14 SEWA HEP 170.00 URI HEP 169.00
15 OBRA B 171.50 CHAMERA HEP 169.90
16 ANPARA B 181.50 RIHAND 184.60
17 OBRA A 184.30 KAHALGAON-II 249.50
18 RIHAND-I 184.60 UNCHAHAR-III TPS 252.10
19 ANPARA A 213.00 UNCHAHAR-II TPS 252.20
20 CHAMERA-III 220.00 UNCHAHAR-I TPS 257.20
21 KOTESHWAR HEP 220.00 NARORA APS 259.00
22 KAHALGAON-II 249.50 TANAKPUR HEP 260.00
23 UNCHAHAR-III TPS 252.10 NAPTHA JHAKRI (SJVNL) 283.00
24 UNCHAHAR-II TPS 252.20 CHAMERA -II HEP 294.00
25 UNCHAHAR-I TPS 257.20 DHAULI GANGA HEP 306.00
26 KAHALGAON 257.40 ANTA G 314.00
27 ANPARA-C (Lanco) 258.00 URI-II HEP 326.00
28 TEHRI HYDRO 260.00 DADRI STAGE -II 327.00
29 FARAKKA 261.40 DADRI G 327.30
30 NARORA APS 277.40 RAPP © 340.40
31 TANDA 278.60 KOTESHWAR HEP 342.00
32 HARDUAGANJ Ext 295.30 JHAJJAR 361.80
33 DILHASTI HEP 306.40 CHAMERA-III HEP 373.00
34 RAPP (B) 306.40 AURAIYA G 373.30
35 NATA G 314.00 RAPP (B) 373.90
36 DADRI STAGE - II 327.20 SEWA HEP 453.00
37 DADRI G 327.30 TEHRI HYDRO 538.00
38 DADRI NCTPS 348.90 DULHASTI HEP 560.00
39 PARICCHA Ext 361.30 DADRI L 706.20
40 JHAJJAR 361.80 ANTA L 808.20
NTPC TANDA OUTAGE
PROFITABILITY
A CHALLENGE
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
UNIT#1 OUT FOR 94 DAYS, UNIT#2 OUT FOR 90 DAYS-NTPC MAUDA
349.438 MUS LOST DUE TO BACKING DOWN/RESERVE SHUT DOWN-NTPC TANDA
32.983 % OF TOTAL LOSS DUE TO BACKING DOWN/RESERVE SHUT DOWN-NTPC DADRI
17.66% OF TOTAL LOSS DUE TO BACKING DOWN/RESERVE SHUT DOWN-NTPC UNCHAHAR
FROM 01ST APRIL 2015 TO 30TH MARCH 2016
PC SHARP
UNDER THE GUIDANCE OF
SHRI RAKESH BAJAJ (AGM MM)
TEAM
T RAMCHANDRAN (SR MGR-FQA)
AMIT KR NAYAK (MGR-TMD)
PRAVEEN PRAJAPATI (DY MGR-BMD)
RAVI PAL SINGH (DY MGR-OPN)
KNOWLEDGE SHARING BY SHARP
SL. NO TIME THEME/TOPIC SPEAKER EVENT
1
SEPTEMBER, 2015 ENERGY EFFICIENT CARTRIDGE AMIT NAYAK तकनिकी गोष्ठी
2
APRIL, 2015 THERMO DYNAMICS AND THERMAL ENGINEERING RAVI PAL SINGH KNOWLEDEG SHARING
3
FRBRUARY, 2015 BREAKDOWN IN ROTARY PART PRAVEEN PRAJAPATI BOILER KT MEET
4 NOVEMBER, 2015 UT AND DPT TECHNOLOGY T RAMCHANDRAN KNOWLEDGE SHARING
5 FEBRUARY, 2016 STUDY OF 03 MW BACK PRESSURE TURBINE ALL 04 MEMBERS BABHNAN CHINI MILL
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
ACCOLADES OF SHARP
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
FOUNDED IN JANUARY, 2011.
FIRST POSITION IN NOCET-2011, STATION LEVEL.
FIRST RUNNER UP IN NOCET-2011, REGIONAL LEVEL.
FIRST POSITION IN PC-2012, STATION LEVEL.
FIRST RUNNER UP IN PC-2012, REGIONAL LEVEL.
FIRST POSITION IN Q4E-2013, STATION LEVEL.
FIRST POSITION IN Q4E-2013, REGIONAL LEVEL.
SECOND RUNNER UP IN Q4E-2013, COMPANY LEVEL.
FIRST POSITION IN Q4E-2014, STATION LEVEL.
FIRST RUNNER UP IN Q4E-2014, REGIONAL LEVEL.
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
THE SOLUTION
MAKE THE PLANT AS ENERGY
EFFICIENT AS POSSIBLE,
PREFERABLY USING
EXISTING RESOURCES
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
PRESSURE REDUCING VALVES
THE PRESSURE ENERGY (POTENTIAL ENERGY) IS
CONVERTED TO USELESS TURBULENCE & NOISE IN THE
PRV.
POTENTIAL OF ABOUT 3000 MW IN INDIA ITSELF,
WHICH IS 1.2 % OF THE TOTAL INSTALLED CAPACITY
BY BUREAU OF ENERGY EFFICIENCY
ENERGY CONSERVATION TURBINE
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
ENERGY
CONSERVATION TURBINE
LOSS
KW
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
ENERGY
CONSERVATION TURBINE
• ECT IS A SMALL COGENERATION SYSTEM CATERING
TO STEAM FLOW RATES FROM 1.5 T/HR AND
UPWARDS.
• BACK PRESSURE STEAM TURBINE USED IN PARALLEL
TO AN EXISTING PRESSURE REDUCING VALVE (PRV).
• STEAM IS EXPANDED IN THE ECT, THUS CONVERTING
HEAT ENERGY (OF STEAM ) TO ELECTRICAL POWER.
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
ENERGY
CONSERVATION TURBINE
ANTI
VIBRATION
MOUNTS
GENERATOR
LUBE OIL FILTER
TURBINE
LUBE OIL COOLER
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
ENERGY
CONSERVATION TURBINE
• ALLOW THE STEAM FLOW VARIATION WHILE
KEEPING THE PROCESS PRESSURE CONSTANT.
• INDUCTION GENERATORS CONTINUE TO
OPERATE IN SPITE OF LARGE FLUCTUATIONS IN
INLET PRESSURE.
• GREATER THAN 80% TURBINE EFFICIENCY.
• COMPACT POWER PACKAGE
• FITS IN CONGESTED EQUIPMENT ROOMS.
NTPC TANDA POTENTIAL
HP BY PASS VALVE
LP BY PASS VALVE
APRDS CONTROL VALVE
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
HP BY PASS VALVE
INLET PRESSURE : 90 KG/CM2, 500 DEG C
OUTLET PRESSURE : 6 KG/CM2, 300 DEG C
STEAM FLOW : 130 T/H
POWER POTENTIAL
11.76 MW
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
LP BY PASS VALVE
INLET PRESSURE : 6 KG/CM2, 300 DEG C
OUTLET PRESSURE : 0.08KG/CM2, 40 DEG C,
90% DF
STEAM FLOW : 150 T/HR
POWER POTENTIAL
21.25 MW
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
APRDS CONTROL VALVE
INLET PRESSURE : 150 KG/CM2, 500 DEG C
OUTLET PRESSURE : 13 KG/CM2, 350 DEG C
STEAM FLOW : 60 T/HR
POWER POTENTIAL
2.7 MW
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
VALVE
HP BYPASS
VALVE
LP BYPASS
VALVE
APRDS CONTROL
VALVE
POWER IN MW 11.76 21.25 2.70
DURATION IN
MINUTES
10 10 60 X24X365
(5 TPH TO SJAE)
FEASABILITY
CASE STUDY
ECT AT APRDS CHARGED FROM MS-LINE
WHAT IF CHARGED FROM CRH-LINE ??
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
CAPACITY OF APRDS
MP STARTUP STEAM FLOW 35 T/HR
F.O AUTOMISATION STEAM FLOW 25 T/HR
HP GLAND SEALING 2 T/HR
TO STEAM JET AIR EJECTOR 5 T/HR
TO D/A PEGGING FROM 6 ATA 21 T/HR
SCAPH 5 T/HR
APH SOOT BLOWING 1.25 T/HR
L.P SEALING 2 T/HR
AT MCR 5 TPH OF PERENNIAL ENTHALPY FLOW IN APRDS
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
ECT~
APRDS MS LINE
TO APRDS 11 ATA HDR
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
APRDS MS LINE
STEAM FLOW : 5 TPH
INLET PRESSURE : 150 KG/CM2, 500 DEG C
OUTLET PRESSURE : 13 KG/CM2, 350 DEG C
STEAM FLOW : 5 T/HR
ECT EFFICEINCY : 95%
310 KW
@RS. 4/KWH RS. 1.08 CRORE PER ANNUM SAVINGS
HEAT RATE REDUCED BY 7.71 KCAL/KWH
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
APRDS MS LINE-SPECS OF ECT
•DIMENSIONS : 6.5X4X3 (IN METERS)
•NO. OF STAGES : 2
•POWER PACK SET WEIGHT (KG) 4500 KG.
•TURBINE SPEED (RPM): 12000 – 14400
•OUTPUT (RPM) : 1500 / 1800
•PRECISION ROLLING ELEMENT BEARING.
•PRESSURIZED OIL CIRCULATION SYSTEM.
•FLEXIBLE COUPLING OF TURBINE AND GENERATOR.
•MOUNTING SKID WITH ANTI-VIBRATION MOUNTS.
•NO FOUNDATION REQUIRED.
BY TURBOTECH PRECISION ENGINEERING PRIVATE LIMITED BANGLORE
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
APRDS MS LINE-PROJECT COST
BY TURBOTECH PRECISION ENGINEERING PRIVATE LIMITED
BANGLORE
DESCRIPTION (RS.IN LAKHS)
TURBINE GENERATOR 94
C.S.T(4%) 1.81
E.D(16.32%) 6.36
SUPERVISION OF ERECTION 8
FREIGHT 0.2
EXPANSION BELLOWS 0.6
TURBINE ERECTION 1
ELECTRIC CABLING 1
STEAM PIPING ETC. 2
CIVIL WORK 0.5
MISCELLANEOUS 1
LESS MODVAT 6.36
INVESTMENT 1.20 CRORE
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
APRDS CRH LINE
TO APRDS 11 ATA HDR
ECT~
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
APRDS CRH LINE
STEAM FLOW : 5 T/HR
INLET PRESSURE : 35 KG/CM2, 380 DEG C
OUTLET PRESSURE : 13 KG/CM2, 350 DEG C
STEAM FLOW : 5 T/HR
ECT EFFICEINCY : 95%
100 KW
@RS. 4/KWH RS. 35.04 LAKH PER ANNUM SAVINGS
HEAT RATE REDUCED BY 11.78 KCAL/KWH
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
APRDS CRH LINE-SPECS OF ECT
• SINGLE STAGE IMPULSE TYPE
• DIMENSIONS : 5X4X4(IN METERS)
• HIGH SPEED FLEXIBLE COUPLING
• FREQUENCY: 50 HZ
• VOLTAGE: 380V / 415V
• INDUCTION GENERATOR WITH GRID EXCITATION SYSTEM
• CONFIGURATION: BACK PRESSURE
• POWER SET WEIGHT : 2000 KG
BY KESSELS TURBINE NEW DELHI
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
APRDS CRH LINE-PROJECT COST
BY KESSELS TURBINE NEW DELHI
DESCRIPTION (RS.IN LAKHS)
TURBINE GENERATOR 43.5
PANEL, SWITCH & CABLING 2.5
ERECTION , MODIFICATION 2.5
INVESTMENT 48.5
V ECT IN INDIA
• 300KW AT AMRUT DISTILLARIES LTD, KUMBALGOLD, BANGLORE
BY TURBOTECH PRECISION ENGINEERING.
• 340 KW AT UNITED SPIRITS, POONAMALLEE, CHENNAI BY
TURBOTECH PRECISION ENGINEERING.
• 1600 KW AT PHARMACEUTICAL INDUSTRY, HIMANCHAL BY
SIEMENS.
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
V COMPARISON
• @ RS 2 CRORE, BFP ENERGY EFFICIENT
CARTRIDGE, SAVINGS 300 KW PER BFP.
• @2.5 CRORE TG ROOF TOP SOLAR 450
KW FOR ONLY ~04 HRS PER DAY
@ RS 48 LAKH, 100 KW
USING ECT AT APRDS
ECT AT APRDS
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
V
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
LIMITATIONS
OBLIVIOUS TO INSIGNIFICANT YET
PERINNIAL LOSS IN PRVS.
FINANCIALLY NOT VIABLE FOR ALL
PRVS.
APREHENSION TOWARDS RELIABILITY
OF UNCHARTED INNOVATION.
V CONCLUSION
INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
•GROWING DEMAND AND RISING PRICES
MAKE INVESTMENT IN SMALL-SCALE
TURBINES ECONOMICALLY VIABLE.
•USE PROVEN AND ESTABLISHED
TECHNOLOGY AND CONSISTS OF
CONTINUOUS TECHNICAL
IMPROVEMENTS.
•RELIABLE SMALL-SCALE TURBINE WILL BE
A PROFITABLE AND LASTING DECISION.
BABHNAN SUGAR MILLS LTD
GONDA
3MW BACKPRESSURE TURBINE
FLOW :30 TPH
30 KG, 350 DEG C TO 2 KG 165 DEG C
Thank You
Transforming lives
“Our most basic common link is that we all inhabit this small planet. We all breathe the same air.
We all cherish our children's future. And we are all mortal.” John F. Kennedy

More Related Content

What's hot

Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
Nitin Patel
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
Ashvani Shukla
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
Vaibhav Paydelwar
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
SHIVAJI CHOUDHURY
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & Working
Tahoor Alam Khan
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
SAI SHARATH GAMPA
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
Jaypee power ventures limited
 
Air heater
Air heaterAir heater
Air heater
Akhilesh Kushwaha
 
Steam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticSteam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnostic
Pichai Chaibamrung
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Manohar Tatwawadi
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance Indices
Manohar Tatwawadi
 
Final Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptxFinal Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptx
BhimarajuKanireddy
 
Steam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptSteam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance ppt
Biswajit Mohanty
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGSURAJ KUMAR
 
Heat rate of thermal power plant
Heat rate of thermal power plantHeat rate of thermal power plant
Heat rate of thermal power plant
Manohar Tatwawadi
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
Ashvani Shukla
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
Susovan Sensharma
 
Steam generator part 2
Steam generator part 2Steam generator part 2
Steam generator part 2
Mohammad Shoeb Siddiqui
 
The Coal mill performance monitoring
The Coal mill performance monitoringThe Coal mill performance monitoring
The Coal mill performance monitoring
Manohar Tatwawadi
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsSHIVAJI CHOUDHURY
 

What's hot (20)

Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & Working
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
Air heater
Air heaterAir heater
Air heater
 
Steam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticSteam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnostic
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance Indices
 
Final Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptxFinal Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptx
 
Steam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptSteam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance ppt
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 
Heat rate of thermal power plant
Heat rate of thermal power plantHeat rate of thermal power plant
Heat rate of thermal power plant
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
 
Steam generator part 2
Steam generator part 2Steam generator part 2
Steam generator part 2
 
The Coal mill performance monitoring
The Coal mill performance monitoringThe Coal mill performance monitoring
The Coal mill performance monitoring
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plants
 

Viewers also liked

Thermal Analysis of Steam Turbine Power Plants
Thermal Analysis of Steam Turbine Power PlantsThermal Analysis of Steam Turbine Power Plants
Thermal Analysis of Steam Turbine Power Plants
IOSR Journals
 
Steam turbine ntpc seepat bilaspur chhattisgarh
Steam turbine ntpc seepat bilaspur chhattisgarhSteam turbine ntpc seepat bilaspur chhattisgarh
Steam turbine ntpc seepat bilaspur chhattisgarh
pratikguptateddy
 
1.1 power plant module1 batch3
1.1 power plant module1 batch31.1 power plant module1 batch3
1.1 power plant module1 batch3daisydhei
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its types
Sanila Khalid
 
STEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGSSTEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGS
Akhil Krishnan G
 
Steam Turbines
Steam TurbinesSteam Turbines
Steam Turbines
Hrishikesh Devan
 
STEAM TURBINE BASIC
STEAM TURBINE BASIC STEAM TURBINE BASIC
STEAM TURBINE BASIC
Nguyen Phuong Dong
 
Steam turbine Working
Steam turbine WorkingSteam turbine Working
Steam turbine Working
Chaudhry Hassan Ali
 
Steam Turbines Basics
Steam Turbines BasicsSteam Turbines Basics
Steam Turbines Basics
Prasad Vejendla
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
Gaurav Kaushik
 
[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam Turbine
Sumit Sharma
 
Steam turbine
Steam turbineSteam turbine
steam turbine casing manufacture
steam turbine casing manufacturesteam turbine casing manufacture
steam turbine casing manufacture
omkar manav
 
Bhel steam turbine manufacturing
Bhel steam turbine manufacturingBhel steam turbine manufacturing
Bhel steam turbine manufacturing
Home
 

Viewers also liked (14)

Thermal Analysis of Steam Turbine Power Plants
Thermal Analysis of Steam Turbine Power PlantsThermal Analysis of Steam Turbine Power Plants
Thermal Analysis of Steam Turbine Power Plants
 
Steam turbine ntpc seepat bilaspur chhattisgarh
Steam turbine ntpc seepat bilaspur chhattisgarhSteam turbine ntpc seepat bilaspur chhattisgarh
Steam turbine ntpc seepat bilaspur chhattisgarh
 
1.1 power plant module1 batch3
1.1 power plant module1 batch31.1 power plant module1 batch3
1.1 power plant module1 batch3
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its types
 
STEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGSSTEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGS
 
Steam Turbines
Steam TurbinesSteam Turbines
Steam Turbines
 
STEAM TURBINE BASIC
STEAM TURBINE BASIC STEAM TURBINE BASIC
STEAM TURBINE BASIC
 
Steam turbine Working
Steam turbine WorkingSteam turbine Working
Steam turbine Working
 
Steam Turbines Basics
Steam Turbines BasicsSteam Turbines Basics
Steam Turbines Basics
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam Turbine
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
steam turbine casing manufacture
steam turbine casing manufacturesteam turbine casing manufacture
steam turbine casing manufacture
 
Bhel steam turbine manufacturing
Bhel steam turbine manufacturingBhel steam turbine manufacturing
Bhel steam turbine manufacturing
 

Similar to ENERGY CONSERVATION BACK PRESSURE TURBINE

electrical.ppt
electrical.pptelectrical.ppt
electrical.ppt
AdityanshuBehera
 
Protection of power
Protection of powerProtection of power
Protection of power
BHAGWAN PRASAD
 
Ggel power distribution
Ggel power distributionGgel power distribution
Ggel power distribution
Banwari Lal
 
Short description about GGEL
Short description about GGELShort description about GGEL
Short description about GGEL
Banwari Lal
 
MANOJ KUMAWAT -Textiles RFT regarding project
MANOJ KUMAWAT -Textiles RFT regarding project MANOJ KUMAWAT -Textiles RFT regarding project
MANOJ KUMAWAT -Textiles RFT regarding project
RJManojKumawat
 
Electro Static Precipitator for Spent Wash Application.
Electro Static Precipitator for Spent Wash Application.Electro Static Precipitator for Spent Wash Application.
Electro Static Precipitator for Spent Wash Application.
IJERA Editor
 
Ntpc report
Ntpc  report Ntpc  report
Ntpc report
vipinchaudhary45
 
Datasheet
DatasheetDatasheet
Datasheet
olvit
 
Study Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power PlantStudy Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power Plant
SUDHEER KUMAR KALYANAM
 
NTPC KAHALGAON Main page
 NTPC KAHALGAON Main page NTPC KAHALGAON Main page
NTPC KAHALGAON Main page
Ranjan kumar
 
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
Tejasvi Anant
 
Training NTPC
Training NTPCTraining NTPC
Training NTPC
Anil Jadon
 
RTM 2014 ECONOMICS OF POWER AND STEAM
RTM 2014 ECONOMICS OF POWER AND STEAMRTM 2014 ECONOMICS OF POWER AND STEAM
RTM 2014 ECONOMICS OF POWER AND STEAMKarthick Ramalingam
 
Long Term Performance Prediction of a Borehole and Determination of Optimal T...
Long Term Performance Prediction of a Borehole and Determination of Optimal T...Long Term Performance Prediction of a Borehole and Determination of Optimal T...
Long Term Performance Prediction of a Borehole and Determination of Optimal T...lynxcem
 
INTERFACING.ppt
INTERFACING.pptINTERFACING.ppt
INTERFACING.ppt
DundiKumarBevara
 
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
IJMTST Journal
 
SPIN ECHO SEQUENCES MRI PPT
SPIN ECHO SEQUENCES MRI PPTSPIN ECHO SEQUENCES MRI PPT
SPIN ECHO SEQUENCES MRI PPT
SEHRISH97
 
summer training report of Iocl,haldia
summer training report of Iocl,haldiasummer training report of Iocl,haldia
summer training report of Iocl,haldia
sumanscience
 

Similar to ENERGY CONSERVATION BACK PRESSURE TURBINE (20)

DC Component of Fault Current
DC Component of Fault CurrentDC Component of Fault Current
DC Component of Fault Current
 
electrical.ppt
electrical.pptelectrical.ppt
electrical.ppt
 
Protection of power
Protection of powerProtection of power
Protection of power
 
Ggel power distribution
Ggel power distributionGgel power distribution
Ggel power distribution
 
Short description about GGEL
Short description about GGELShort description about GGEL
Short description about GGEL
 
NASA 2004 PP
NASA 2004 PPNASA 2004 PP
NASA 2004 PP
 
MANOJ KUMAWAT -Textiles RFT regarding project
MANOJ KUMAWAT -Textiles RFT regarding project MANOJ KUMAWAT -Textiles RFT regarding project
MANOJ KUMAWAT -Textiles RFT regarding project
 
Electro Static Precipitator for Spent Wash Application.
Electro Static Precipitator for Spent Wash Application.Electro Static Precipitator for Spent Wash Application.
Electro Static Precipitator for Spent Wash Application.
 
Ntpc report
Ntpc  report Ntpc  report
Ntpc report
 
Datasheet
DatasheetDatasheet
Datasheet
 
Study Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power PlantStudy Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power Plant
 
NTPC KAHALGAON Main page
 NTPC KAHALGAON Main page NTPC KAHALGAON Main page
NTPC KAHALGAON Main page
 
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
 
Training NTPC
Training NTPCTraining NTPC
Training NTPC
 
RTM 2014 ECONOMICS OF POWER AND STEAM
RTM 2014 ECONOMICS OF POWER AND STEAMRTM 2014 ECONOMICS OF POWER AND STEAM
RTM 2014 ECONOMICS OF POWER AND STEAM
 
Long Term Performance Prediction of a Borehole and Determination of Optimal T...
Long Term Performance Prediction of a Borehole and Determination of Optimal T...Long Term Performance Prediction of a Borehole and Determination of Optimal T...
Long Term Performance Prediction of a Borehole and Determination of Optimal T...
 
INTERFACING.ppt
INTERFACING.pptINTERFACING.ppt
INTERFACING.ppt
 
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
 
SPIN ECHO SEQUENCES MRI PPT
SPIN ECHO SEQUENCES MRI PPTSPIN ECHO SEQUENCES MRI PPT
SPIN ECHO SEQUENCES MRI PPT
 
summer training report of Iocl,haldia
summer training report of Iocl,haldiasummer training report of Iocl,haldia
summer training report of Iocl,haldia
 

More from RAVI PAL SINGH

HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam Turbine
RAVI PAL SINGH
 
QC CASE STUDY: PREVENT OR REDUCE CHOCKING OF RC FEEDER#G AND MILL#G CENTRE PIPE
QC CASE STUDY: PREVENT OR REDUCE CHOCKING OF RC FEEDER#G AND MILL#G CENTRE PIPEQC CASE STUDY: PREVENT OR REDUCE CHOCKING OF RC FEEDER#G AND MILL#G CENTRE PIPE
QC CASE STUDY: PREVENT OR REDUCE CHOCKING OF RC FEEDER#G AND MILL#G CENTRE PIPE
RAVI PAL SINGH
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGRAVI PAL SINGH
 
CSR and sustainable development innovative possibilities
CSR and sustainable development innovative possibilitiesCSR and sustainable development innovative possibilities
CSR and sustainable development innovative possibilities
RAVI PAL SINGH
 
Air cooled condensers
Air cooled condensersAir cooled condensers
Air cooled condensers
RAVI PAL SINGH
 
Condensate system
Condensate systemCondensate system
Condensate system
RAVI PAL SINGH
 
DC failiure at NTPC Tanda
DC failiure at NTPC TandaDC failiure at NTPC Tanda
DC failiure at NTPC Tanda
RAVI PAL SINGH
 

More from RAVI PAL SINGH (8)

HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam Turbine
 
QC CASE STUDY: PREVENT OR REDUCE CHOCKING OF RC FEEDER#G AND MILL#G CENTRE PIPE
QC CASE STUDY: PREVENT OR REDUCE CHOCKING OF RC FEEDER#G AND MILL#G CENTRE PIPEQC CASE STUDY: PREVENT OR REDUCE CHOCKING OF RC FEEDER#G AND MILL#G CENTRE PIPE
QC CASE STUDY: PREVENT OR REDUCE CHOCKING OF RC FEEDER#G AND MILL#G CENTRE PIPE
 
VALUE ETHICS MORALS
VALUE ETHICS MORALSVALUE ETHICS MORALS
VALUE ETHICS MORALS
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDING
 
CSR and sustainable development innovative possibilities
CSR and sustainable development innovative possibilitiesCSR and sustainable development innovative possibilities
CSR and sustainable development innovative possibilities
 
Air cooled condensers
Air cooled condensersAir cooled condensers
Air cooled condensers
 
Condensate system
Condensate systemCondensate system
Condensate system
 
DC failiure at NTPC Tanda
DC failiure at NTPC TandaDC failiure at NTPC Tanda
DC failiure at NTPC Tanda
 

ENERGY CONSERVATION BACK PRESSURE TURBINE

  • 1.
  • 2. VARIABLE COST OF UP & UTTARAKHAND SL NO. Station Paisa/ Unit Station Paisa/ Unit 1 SALAL HPS 48.00 CHIBRO (YAMUNA) 27.00 2 URI HEP 81.00 KHATIMA HPS 30.00 3 CHAMERA HEP 107.00 KULHAL HPS 31.00 4 TANAKPUR HEP 115.00 CHILLA HPS 34.00 5 SASAN 128.50 KHODRI HPS 34.00 6 SINGARAULI STPS 131.00 DHAKRANI HPS 36.00 7 SIGARAULI STAGE III 136.60 RAMGANGA HPS 37.00 8 VISHUNUPRAYAG 140.00 DHALIPUR HPS 40.00 9 RIHAND STAGE II 143.70 SALAL HPS 102.00 10 DHAULI GANGA HEP 145.00 SINGARAULI STPS 131.00 11 NATHPA JHAKRI (SJVNT) 146.00 MANERI BHALI-II 134.00 12 CHAMERA -II HEP 169.90 RIHAND STAGE -III 136.60 13 URI-II HEP 169.90 RIHAND STAGE -II 143.70 14 SEWA HEP 170.00 URI HEP 169.00 15 OBRA B 171.50 CHAMERA HEP 169.90 16 ANPARA B 181.50 RIHAND 184.60 17 OBRA A 184.30 KAHALGAON-II 249.50 18 RIHAND-I 184.60 UNCHAHAR-III TPS 252.10 19 ANPARA A 213.00 UNCHAHAR-II TPS 252.20 20 CHAMERA-III 220.00 UNCHAHAR-I TPS 257.20 21 KOTESHWAR HEP 220.00 NARORA APS 259.00 22 KAHALGAON-II 249.50 TANAKPUR HEP 260.00 23 UNCHAHAR-III TPS 252.10 NAPTHA JHAKRI (SJVNL) 283.00 24 UNCHAHAR-II TPS 252.20 CHAMERA -II HEP 294.00 25 UNCHAHAR-I TPS 257.20 DHAULI GANGA HEP 306.00 26 KAHALGAON 257.40 ANTA G 314.00 27 ANPARA-C (Lanco) 258.00 URI-II HEP 326.00 28 TEHRI HYDRO 260.00 DADRI STAGE -II 327.00 29 FARAKKA 261.40 DADRI G 327.30 30 NARORA APS 277.40 RAPP © 340.40 31 TANDA 278.60 KOTESHWAR HEP 342.00 32 HARDUAGANJ Ext 295.30 JHAJJAR 361.80 33 DILHASTI HEP 306.40 CHAMERA-III HEP 373.00 34 RAPP (B) 306.40 AURAIYA G 373.30 35 NATA G 314.00 RAPP (B) 373.90 36 DADRI STAGE - II 327.20 SEWA HEP 453.00 37 DADRI G 327.30 TEHRI HYDRO 538.00 38 DADRI NCTPS 348.90 DULHASTI HEP 560.00 39 PARICCHA Ext 361.30 DADRI L 706.20 40 JHAJJAR 361.80 ANTA L 808.20
  • 3. NTPC TANDA OUTAGE PROFITABILITY A CHALLENGE INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION UNIT#1 OUT FOR 94 DAYS, UNIT#2 OUT FOR 90 DAYS-NTPC MAUDA 349.438 MUS LOST DUE TO BACKING DOWN/RESERVE SHUT DOWN-NTPC TANDA 32.983 % OF TOTAL LOSS DUE TO BACKING DOWN/RESERVE SHUT DOWN-NTPC DADRI 17.66% OF TOTAL LOSS DUE TO BACKING DOWN/RESERVE SHUT DOWN-NTPC UNCHAHAR FROM 01ST APRIL 2015 TO 30TH MARCH 2016
  • 4. PC SHARP UNDER THE GUIDANCE OF SHRI RAKESH BAJAJ (AGM MM) TEAM T RAMCHANDRAN (SR MGR-FQA) AMIT KR NAYAK (MGR-TMD) PRAVEEN PRAJAPATI (DY MGR-BMD) RAVI PAL SINGH (DY MGR-OPN)
  • 5. KNOWLEDGE SHARING BY SHARP SL. NO TIME THEME/TOPIC SPEAKER EVENT 1 SEPTEMBER, 2015 ENERGY EFFICIENT CARTRIDGE AMIT NAYAK तकनिकी गोष्ठी 2 APRIL, 2015 THERMO DYNAMICS AND THERMAL ENGINEERING RAVI PAL SINGH KNOWLEDEG SHARING 3 FRBRUARY, 2015 BREAKDOWN IN ROTARY PART PRAVEEN PRAJAPATI BOILER KT MEET 4 NOVEMBER, 2015 UT AND DPT TECHNOLOGY T RAMCHANDRAN KNOWLEDGE SHARING 5 FEBRUARY, 2016 STUDY OF 03 MW BACK PRESSURE TURBINE ALL 04 MEMBERS BABHNAN CHINI MILL INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
  • 6. ACCOLADES OF SHARP INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION FOUNDED IN JANUARY, 2011. FIRST POSITION IN NOCET-2011, STATION LEVEL. FIRST RUNNER UP IN NOCET-2011, REGIONAL LEVEL. FIRST POSITION IN PC-2012, STATION LEVEL. FIRST RUNNER UP IN PC-2012, REGIONAL LEVEL. FIRST POSITION IN Q4E-2013, STATION LEVEL. FIRST POSITION IN Q4E-2013, REGIONAL LEVEL. SECOND RUNNER UP IN Q4E-2013, COMPANY LEVEL. FIRST POSITION IN Q4E-2014, STATION LEVEL. FIRST RUNNER UP IN Q4E-2014, REGIONAL LEVEL.
  • 7. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION THE SOLUTION MAKE THE PLANT AS ENERGY EFFICIENT AS POSSIBLE, PREFERABLY USING EXISTING RESOURCES
  • 8. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION PRESSURE REDUCING VALVES THE PRESSURE ENERGY (POTENTIAL ENERGY) IS CONVERTED TO USELESS TURBULENCE & NOISE IN THE PRV. POTENTIAL OF ABOUT 3000 MW IN INDIA ITSELF, WHICH IS 1.2 % OF THE TOTAL INSTALLED CAPACITY BY BUREAU OF ENERGY EFFICIENCY
  • 10. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION ENERGY CONSERVATION TURBINE LOSS KW
  • 11. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION ENERGY CONSERVATION TURBINE • ECT IS A SMALL COGENERATION SYSTEM CATERING TO STEAM FLOW RATES FROM 1.5 T/HR AND UPWARDS. • BACK PRESSURE STEAM TURBINE USED IN PARALLEL TO AN EXISTING PRESSURE REDUCING VALVE (PRV). • STEAM IS EXPANDED IN THE ECT, THUS CONVERTING HEAT ENERGY (OF STEAM ) TO ELECTRICAL POWER.
  • 12. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION ENERGY CONSERVATION TURBINE ANTI VIBRATION MOUNTS GENERATOR LUBE OIL FILTER TURBINE LUBE OIL COOLER
  • 13. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION ENERGY CONSERVATION TURBINE • ALLOW THE STEAM FLOW VARIATION WHILE KEEPING THE PROCESS PRESSURE CONSTANT. • INDUCTION GENERATORS CONTINUE TO OPERATE IN SPITE OF LARGE FLUCTUATIONS IN INLET PRESSURE. • GREATER THAN 80% TURBINE EFFICIENCY. • COMPACT POWER PACKAGE • FITS IN CONGESTED EQUIPMENT ROOMS.
  • 14. NTPC TANDA POTENTIAL HP BY PASS VALVE LP BY PASS VALVE APRDS CONTROL VALVE
  • 15. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION HP BY PASS VALVE INLET PRESSURE : 90 KG/CM2, 500 DEG C OUTLET PRESSURE : 6 KG/CM2, 300 DEG C STEAM FLOW : 130 T/H POWER POTENTIAL 11.76 MW
  • 16. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION LP BY PASS VALVE INLET PRESSURE : 6 KG/CM2, 300 DEG C OUTLET PRESSURE : 0.08KG/CM2, 40 DEG C, 90% DF STEAM FLOW : 150 T/HR POWER POTENTIAL 21.25 MW
  • 17. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION APRDS CONTROL VALVE INLET PRESSURE : 150 KG/CM2, 500 DEG C OUTLET PRESSURE : 13 KG/CM2, 350 DEG C STEAM FLOW : 60 T/HR POWER POTENTIAL 2.7 MW
  • 18. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION VALVE HP BYPASS VALVE LP BYPASS VALVE APRDS CONTROL VALVE POWER IN MW 11.76 21.25 2.70 DURATION IN MINUTES 10 10 60 X24X365 (5 TPH TO SJAE) FEASABILITY
  • 19. CASE STUDY ECT AT APRDS CHARGED FROM MS-LINE WHAT IF CHARGED FROM CRH-LINE ??
  • 20. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION CAPACITY OF APRDS MP STARTUP STEAM FLOW 35 T/HR F.O AUTOMISATION STEAM FLOW 25 T/HR HP GLAND SEALING 2 T/HR TO STEAM JET AIR EJECTOR 5 T/HR TO D/A PEGGING FROM 6 ATA 21 T/HR SCAPH 5 T/HR APH SOOT BLOWING 1.25 T/HR L.P SEALING 2 T/HR AT MCR 5 TPH OF PERENNIAL ENTHALPY FLOW IN APRDS
  • 21. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION ECT~ APRDS MS LINE TO APRDS 11 ATA HDR
  • 22. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION APRDS MS LINE STEAM FLOW : 5 TPH INLET PRESSURE : 150 KG/CM2, 500 DEG C OUTLET PRESSURE : 13 KG/CM2, 350 DEG C STEAM FLOW : 5 T/HR ECT EFFICEINCY : 95% 310 KW @RS. 4/KWH RS. 1.08 CRORE PER ANNUM SAVINGS HEAT RATE REDUCED BY 7.71 KCAL/KWH
  • 23. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION APRDS MS LINE-SPECS OF ECT •DIMENSIONS : 6.5X4X3 (IN METERS) •NO. OF STAGES : 2 •POWER PACK SET WEIGHT (KG) 4500 KG. •TURBINE SPEED (RPM): 12000 – 14400 •OUTPUT (RPM) : 1500 / 1800 •PRECISION ROLLING ELEMENT BEARING. •PRESSURIZED OIL CIRCULATION SYSTEM. •FLEXIBLE COUPLING OF TURBINE AND GENERATOR. •MOUNTING SKID WITH ANTI-VIBRATION MOUNTS. •NO FOUNDATION REQUIRED. BY TURBOTECH PRECISION ENGINEERING PRIVATE LIMITED BANGLORE
  • 24. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION APRDS MS LINE-PROJECT COST BY TURBOTECH PRECISION ENGINEERING PRIVATE LIMITED BANGLORE DESCRIPTION (RS.IN LAKHS) TURBINE GENERATOR 94 C.S.T(4%) 1.81 E.D(16.32%) 6.36 SUPERVISION OF ERECTION 8 FREIGHT 0.2 EXPANSION BELLOWS 0.6 TURBINE ERECTION 1 ELECTRIC CABLING 1 STEAM PIPING ETC. 2 CIVIL WORK 0.5 MISCELLANEOUS 1 LESS MODVAT 6.36 INVESTMENT 1.20 CRORE
  • 25. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION APRDS CRH LINE TO APRDS 11 ATA HDR ECT~
  • 26. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION APRDS CRH LINE STEAM FLOW : 5 T/HR INLET PRESSURE : 35 KG/CM2, 380 DEG C OUTLET PRESSURE : 13 KG/CM2, 350 DEG C STEAM FLOW : 5 T/HR ECT EFFICEINCY : 95% 100 KW @RS. 4/KWH RS. 35.04 LAKH PER ANNUM SAVINGS HEAT RATE REDUCED BY 11.78 KCAL/KWH
  • 27. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION APRDS CRH LINE-SPECS OF ECT • SINGLE STAGE IMPULSE TYPE • DIMENSIONS : 5X4X4(IN METERS) • HIGH SPEED FLEXIBLE COUPLING • FREQUENCY: 50 HZ • VOLTAGE: 380V / 415V • INDUCTION GENERATOR WITH GRID EXCITATION SYSTEM • CONFIGURATION: BACK PRESSURE • POWER SET WEIGHT : 2000 KG BY KESSELS TURBINE NEW DELHI
  • 28. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION APRDS CRH LINE-PROJECT COST BY KESSELS TURBINE NEW DELHI DESCRIPTION (RS.IN LAKHS) TURBINE GENERATOR 43.5 PANEL, SWITCH & CABLING 2.5 ERECTION , MODIFICATION 2.5 INVESTMENT 48.5
  • 29. V ECT IN INDIA • 300KW AT AMRUT DISTILLARIES LTD, KUMBALGOLD, BANGLORE BY TURBOTECH PRECISION ENGINEERING. • 340 KW AT UNITED SPIRITS, POONAMALLEE, CHENNAI BY TURBOTECH PRECISION ENGINEERING. • 1600 KW AT PHARMACEUTICAL INDUSTRY, HIMANCHAL BY SIEMENS. INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
  • 30. V COMPARISON • @ RS 2 CRORE, BFP ENERGY EFFICIENT CARTRIDGE, SAVINGS 300 KW PER BFP. • @2.5 CRORE TG ROOF TOP SOLAR 450 KW FOR ONLY ~04 HRS PER DAY @ RS 48 LAKH, 100 KW USING ECT AT APRDS ECT AT APRDS INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION
  • 31. V INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION LIMITATIONS OBLIVIOUS TO INSIGNIFICANT YET PERINNIAL LOSS IN PRVS. FINANCIALLY NOT VIABLE FOR ALL PRVS. APREHENSION TOWARDS RELIABILITY OF UNCHARTED INNOVATION.
  • 32. V CONCLUSION INTRODUCTION ECT DESCRIPTION TANDA POTENTIAL PRDS CASE STUDY LIMITATIONS CONCLUSION •GROWING DEMAND AND RISING PRICES MAKE INVESTMENT IN SMALL-SCALE TURBINES ECONOMICALLY VIABLE. •USE PROVEN AND ESTABLISHED TECHNOLOGY AND CONSISTS OF CONTINUOUS TECHNICAL IMPROVEMENTS. •RELIABLE SMALL-SCALE TURBINE WILL BE A PROFITABLE AND LASTING DECISION.
  • 33. BABHNAN SUGAR MILLS LTD GONDA 3MW BACKPRESSURE TURBINE FLOW :30 TPH 30 KG, 350 DEG C TO 2 KG 165 DEG C
  • 34.
  • 35.
  • 36.
  • 37.
  • 38. Thank You Transforming lives “Our most basic common link is that we all inhabit this small planet. We all breathe the same air. We all cherish our children's future. And we are all mortal.” John F. Kennedy