SlideShare a Scribd company logo
1 of 45
Download to read offline
FORECASTING COST AND
SCHEDULE PERFORMANCE
IN THE PRESENCE OF
UNCERTAINTY
Probabilistic forecasting of program performance
1
Complexity, Risk,
and Uncertainty
drive all projects
2
Our project management
methods must deal with this
uncertainty
Top Level Theme
3
 Earned Value metrics are lagging and linear
representations of project performance
 SPI/CPI are Cumm to date with this underlying
variances washed out
 Current period is a one period extension of a
linearized accumulation
 No information about the dynamics of the past is
available
 Forecasts of the future are linear projects from the
current base point measurement
 No statistical inference or probabilistic projects are
provided
Top Level Theme (Continued)
4
 “All models are wrong, some are useful”
 Time series analysis: Forecasting and
Control, George E. P. Box and Gwilym
M. Jenkins, Holden-Day, 1976
 Box actually said …
Top Level Themes (Concluded)
5
 For credible decisions to be made, we need
confidence intervals on all the numbers we use to
make decisions.
 These confidence intervals come from the underlying
statistics and the related probabilities.
 Statistical forecasting, using time series analysis of
past performance, is mandatory for any credible
discussion of project performance in the future.
|
6
Uncertainties are
things we can not
be certain about.
Uncertainty is
created by
Incomplete
knowledge; not
Ignorance
Risk
All Program Activities have Naturally
Occurring Uncertainty
7
 Naturally occurring uncertainty
and its resulting risk, impacts the
probability of a successful
outcome
What is the probability of making
a desired completion date or cost
target?
 The statistical behavior of these activities, their
arrangement in a network of activities, and correlation
between their behaviors creates risk
 Adding margin protects the outcome from the impact of
this naturally occurring uncertainty
Risk
8
Raw Material For Forecasting
Cost And Schedule
Earned Value Numbers
9
 CPI / SPI
 That’s it, that’s all we got
 Cumulative to date
 Current period
 Cumulative values wipe out the underlying variance
 Current period performance not adjusted for past
variance
 Both cumulative and current period not adjusted for
risk
Technical Performance Numbers
10
 Technical Performance Measures
 Measures of Performance
 Measures of Effectiveness
 Key Performance Parameters
 JROC
 Program specific
11
Our goal in forecasting the future is to …
… Produce a forecast with a range of
confidence intervals
12 Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013
Forecasts Produce Patterns Of Possible
Future Outcomes
13
Some Principles
 Reliable forecasting is a critical component of
project planning, controlling, and risk management.
 At-Completion forecast made before the project
starts is the basis of credible project management
 Execution phase forecasting serves as a leading
indicator of project success
14
Some Important Terms
 The term confidence interval is applied to interval
estimates for fixed but unknown parameters
 The term prediction interval is an interval estimate
for an (unknown) future value.
 A prediction interval consists of an upper and a lower
limit at a prescribed probability, which are referred to
as prediction bounds
15
A core limitation of the current
approach to performance forecasting
 Standard EVM technique for forecasting the final
cost at completion is not applicable to forecasting
the project duration at completion†
 This leads to inconsistent assumptions about the
relationships between past performance and future
performance
 Using CPI creates a future forecast will be the same as
past performance
† Short 1993, Vandevoorde and Vanhoucke 2006, Leach 2005, and Lipke 2003.
16
Forecasting Methods
 Probabilistic Forecasting – explicit uncertainties in
project performance and errors in measurement
provide prediction bounds on the predicted values
 Integrative Forecasting Methodologies – collect all
relevant information from different sources in a
mathematically correct manner
 Consistent Forecasting Methodologies – methods
that can be applied to both cost and schedule
performance forecasts
17
Elements of a good forecast
 Timely
 Reliable
 Accurate
 Meaningful
 Easy to use
 Actionable
18
Three types of forecasts
 Judgmental – Subjective analysis of subjective
inputs
 The Management EAC is a judgmental forecast
 Associative Models – Analyzes historical data to
reveal relationships between (easily or in advance)
observable quantities and forecast quantities. Uses
this relationship to make predictions.
 Time Series – Objective analysis historical data
assuming the future will be like the past
19
Forecasting Techniques
 Moving average – taking the
value of a chosen number of
previous periods to use as an
estimate for the next period
 Weighted average – same as
moving average except giving
greater weight to more recent
periods
 Linear regression – a
mathematical algorithm is using
past data to create a line
showing the direction. The line
can then be carried forward to
create a forecast
 Exponential smoothing –
combines most recent actual
figure with the previous period’s
forecast in order forecast an
upcoming period
 Regression analysis – equations
that are used to analyze the
relationship between a
dependent variable and one or
more independent variables.
 Time series – uses recent history
is a good predictor of the near
future
 Trend analysis – finds trends in
historic data that can be used to
make forecasts.
20
21
Capturing and processing data requires work.
Making forecasts are essentially Free
22
 We’ve got the start of the data capture process
 UN/CEFACT is a place not the name of an XML
protocol
 Cost and schedule information available at the
Control Account level on a monthly basis
 In order to build the Control Account data stream,
the Work Package are used
 Use the Work Package information as well
23
An Example of Additional Insight Gained By Comparing
Schedules Against Planned Program Deliverables
24
FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13
1
25
20
15
10
5
MilestoneCount
3/05 Plan (Rev. A)
Preliminary Rev. H
5/07 Plan (Rev. E)
0
0
6
1
1
9
2
6
4
2
8
6
9
7
0
5
3
0
6
0
0
(actual from
5/07 plan)
(1 actual from
5/07 plan)
3/05 Plan
12/08 Prel. Rev H
5/07 Plan
0
0
6
1
1
15
3
7
19
5
15
25
14
22
0
19
25
0
25
0
0M/S Count
Cum
3/05 Plan
12/08 Prel. Rev H
5/07 Plan
M/S Count
Rate
Actual Plans of
the James Web
Space
Telescope
(JWST)
JWST Schedules and Deliverables by
Subsystems
25
Spacecraft
Sunshield
PDR
CDR
Test Compl
I&T Compl
FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12
OTE
3/05 Plan (Rev. A)
Preliminary Rev. H
5/07 Plan (Rev. E)
3/05 Plan
5/07 Plan
0
0
6
1
1
9
2
6
4
2
8
6
9
7
0
5
3
0
6
0
0
(actual from
5/07 plan)
(1 actual from
5/07 plan)
ISIM
0
0
6
1
1
15
3
7
19
5
15
25
14
22
0
19
25
0
25
0
0
M/S Count
Rate
M/S Count
Cum
STR - PDR
STR - CDR
ETU - NIRSpec
ETU - MIRI
ETU - NIRCam
ETU - FGS
ETU - I&T
FM - NIRCam
FM - FGS
FM - I&T
FM - MIRI
FM - NIRSpec
OTE PDR
Start Polish
OTE CDR
1st Mirror Delivery
Final Mirror Delivery
PDR
CDR
Struct Compl
Prop I&T
3/05 Plan
Prel. Rev H
5/07 Plan
Prel. Rev H
Exhibit 30: Deliverables Planned vs Actuals
Probabilities of Success Results
26
Case 2: Baseline with Uncertainty, Discrete Risks @ 25 probability
34.8%
50.8%
57.4%
30 Sept2022
Probability of meeting both
cost and schedule targets
Probability of meeting
targeted schedule
Probability of
meeting targeted cost
Exhibit 31: Probability of Meeting Cost and Schedule Targets
Current Execution Index (CEI)
• CEI is a forecast schedule
execution metric for a specific near
term window
• The goal of this metric is to
determine or measure how well
the near term schedule represents
what actually takes place through
execution
• The calculation is made through
capturing a forward-looking
snapshot of what is forecasted to
finish in the near term window.
Then a comparison is made to the
original snapshot after that window
has been executed
• CEI is NOT an actual to baseline
comparison. CEI is an actual to
forecast comparison.
27
Baseline Execution (BE) Chart
• Incomplete tasks, as well as
tasks completed late, instill risk to
executing program milestones and
events
• Used with CEI and VI measures,
these indicators can help the team
determine the level of confidence
in Prime’s ability to build a
realistic/ executable schedule
28
Heat Matrix
COST
TAB
%Complete
%Spent
BCWR
ETC(LRE)
VAC%
Cum.CV%
Cum.CPI
TCPI(LRE)
BEStarts
BEFinishes
DurG
Cum.SPI
CEIFinishes
VolatilityFinish
1.1.1 Airframe 218,237 86.22% 86.15% 30,075 47,943 -8.12% 0.08% 1.001 0.627 0.863 0.841 1.182 0.977 0.390 0.680
1.1.2 Propulsion 15,708 87.37% 79.84% 1,983 5,058 -12.03% 8.63% 1.094 0.392 0.981 0.961 0.977 0.955 0.650 0.350
1.1.3 Communications/ 109,508 69.23% 69.77% 33,691 35,708 -2.38% -0.78% 0.992 0.943 0.887 0.873 1.204 0.998 0.420 0.680
1.1.4 Guidance NAV & 186,665 56.77% 68.32% 80,703 92,740 -18.01% -20.36% 0.831 0.870 0.828 0.806 1.279 0.943 0.170 0.870
1.1.7 AV Application 209,584 47.59% 48.76% 109,849 110,629 -1.54% -2.46% 0.976 0.993 0.817 0.775 0.968 0.824 0.220 0.930
1.1.9 AV Integ., Assy 630,622 57.98% 66.93% 264,986 334,479 -19.97% -15.44% 0.866 0.792 0.923 0.907 1.283 0.950 0.400 0.740
1.11.1 Sys Assy Instal 5,982 54.16% 52.23% 2,742 2,858 0.00% 3.56% 1.037 0.960 0.932 0.919 1.129 0.995 0.490 0.590
1.13.1 Spares 25,603 46.49% 45.25% 13,700 13,933 0.33% 2.68% 1.027 0.983 0.963 0.962 1.092 0.994 0.620 0.380
1.13.2 Spares Inventor 6,399 0.00% 0.00% 6,399 6,399 Future Future Future Future Future Future Future Future Future Future
1.13.3 Spares Distribu 5,435 23.44% 23.76% 4,161 4,143 0.00% -1.39% 0.986 1.004 0.973 0.972 1.002 0.982 0.090 1.310
1.2.1 Reconnaissance 97,545 57.32% 54.52% 41,628 44,529 -0.17% 4.89% 1.051 0.935 0.955 0.954 1.055 0.998 0.510 0.620
1.2.3 Electronic Supp 17,251 62.97% 57.07% 6,388 7,405 0.00% 9.36% 1.103 0.863 0.000 0.000 0.000 1.000 0.000 0.000
1.2.6 Payload Applica 347,372 52.68% 54.10% 164,389 173,543 -4.06% -2.70% 0.974 0.947 0.914 0.884 1.149 0.969 0.780 0.410
1.3.5 Misson Control 210,520 63.89% 71.75% 76,024 84,565 -11.92% -12.31% 0.890 0.899 0.918
1.3.6 MCS System SW 16,829 8.83% 8.70% 15,343 16,063 -4.15% 1.43% 1.014 0.955 0.891 0.899 1.195 1.000 0.150 0.880
1.3.7 MCS IAT & C/O 107,163 59.55% 69.65% 43,347 69,151 -34.18% -16.96% 0.855 0.627 0.929 0.925 1.278 0.974 0.440 0.780
SCHEDULEWork RemainingTAB
• Provides a singular integrated view of multiple measures for
performance
• Organizes critical program performance data to drive corrective
action and risk mitigation
• Teams should focus on ‘Red’ and ‘Yellow’ areas
29
Navy PoPS
30
KPP Current Status Indicators
31
Margin Management
32
Late Finish by Status Date
33
Late Finish Aging Metrics
34
Late Start Aging Metrics
35
Schedule Margin Analysis
36
Total Program Starts
0
50
100
150
200
250
300
TotalWeeklyStarts
0
500
1000
1500
2000
2500
3000
3500
4000
CUMStarts
Planned 0 0 0 0 0 111 103 140 140 82 128 82 176 59 87 76 180 107 78 59
Actual 0 0 0 0 0 56 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Forecast 0 0 0 0 0 56 276 154 194 119 138 123 195 83 138 102 232 107 81 86
CUM Planned 1554 1554 1554 1554 1554 1665 1768 1908 2048 2130 2258 2340 2516 2575 2662 2738 2918 3025 3103 3162
CUM Actual 1473 1473 1473 1473 1473 1529
CUM Forecast 1473 1473 1473 1473 1473 1529 1805 1959 2153 2272 2410 2533 2728 2811 2949 3051 3283 3390 3471 3557
6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22
37
Schedule Starts
Total Program Finishes
0
50
100
150
200
250
TotalWeeklyFinishes
0
500
1000
1500
2000
2500
3000
3500
CUMFinishes
Planned 0 0 0 0 0 129 154 194 128 120 126 151 151 83 95 151 195 92 106 87
Actual 0 0 0 0 0 96 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Forecast 0 0 0 0 0 106 223 206 155 166 123 191 175 101 142 144 206 90 92 120
CUM Planned 943 943 943 943 943 1072 1226 1420 1548 1668 1794 1945 2096 2179 2274 2425 2620 2712 2818 2905
CUM Actual 793 793 793 793 793 889
CUM Forecast 793 793 793 793 793 899 1122 1328 1483 1649 1772 1963 2138 2239 2381 2525 2731 2821 2913 3033
6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8
10/1
5
10/2
2
38
Schedule Finishes
39
Program Start Metrics Bow-Wave
Trend
40
Program Finish Metrics Bow-Wave
Trend
 Each status period counts the number of finishes moved to
forward periods and adds them to the planned finishes
 This increase is the debt of work added to that period
41
Late Finish derived directly from the
IMS
Leading Indicators come from
integrating EVM and SE†
42
† Systems Engineering Applied Leading Indicators: Enabling Assessment of Acquisition Technical Performance, 24 September 2010, Paul
Montgomery and Ron Carlson, Graduate School of Engineering & Applied Sciences Naval Postgraduate School, NPS-AM-10-175
Leading Indicators must also connect
MoE, MoP, and TPMs
43
In the end, leading indicators
must tell us how to take
corrective actions before we
end up in the ditch
44
45 Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013

More Related Content

What's hot

Wbs, estimation and scheduling
Wbs, estimation and schedulingWbs, estimation and scheduling
Wbs, estimation and schedulingSulman Ahmed
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/FailurePeter Salmon
 
Risk management process
Risk management processRisk management process
Risk management processeduCBA
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk ManagementHayat Denzi
 
Chapter 7 managing risk
Chapter 7   managing riskChapter 7   managing risk
Chapter 7 managing riskHammad Hashmi
 
Project Cost Estimation Methods PowerPoint Presentation Slides
Project Cost Estimation Methods PowerPoint Presentation Slides Project Cost Estimation Methods PowerPoint Presentation Slides
Project Cost Estimation Methods PowerPoint Presentation Slides SlideTeam
 
Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project ManagementInam Khosa
 
Risk Assessments Best Practice and Practical Approaches Webinar
Risk Assessments Best Practice and Practical Approaches WebinarRisk Assessments Best Practice and Practical Approaches Webinar
Risk Assessments Best Practice and Practical Approaches WebinarAviva Spectrum™
 
Project time management
Project time managementProject time management
Project time managementImran Jamil
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio ManagementAnand Subramaniam
 
Risk Analysis
Risk AnalysisRisk Analysis
Risk AnalysisCIToolkit
 
Introduction to ict project management
Introduction to ict project managementIntroduction to ict project management
Introduction to ict project managementmanproy
 

What's hot (20)

Wbs, estimation and scheduling
Wbs, estimation and schedulingWbs, estimation and scheduling
Wbs, estimation and scheduling
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/Failure
 
Risk management process
Risk management processRisk management process
Risk management process
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
 
Chapter 7 managing risk
Chapter 7   managing riskChapter 7   managing risk
Chapter 7 managing risk
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
Audit Evidence Presentation
Audit Evidence PresentationAudit Evidence Presentation
Audit Evidence Presentation
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Project Cost Estimation Methods PowerPoint Presentation Slides
Project Cost Estimation Methods PowerPoint Presentation Slides Project Cost Estimation Methods PowerPoint Presentation Slides
Project Cost Estimation Methods PowerPoint Presentation Slides
 
Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project Management
 
Risk Assessments Best Practice and Practical Approaches Webinar
Risk Assessments Best Practice and Practical Approaches WebinarRisk Assessments Best Practice and Practical Approaches Webinar
Risk Assessments Best Practice and Practical Approaches Webinar
 
Project time management
Project time managementProject time management
Project time management
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio Management
 
Risk Analysis
Risk AnalysisRisk Analysis
Risk Analysis
 
Project Estimating
Project EstimatingProject Estimating
Project Estimating
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Introduction to ict project management
Introduction to ict project managementIntroduction to ict project management
Introduction to ict project management
 

Viewers also liked

Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Glen Alleman
 
Earned schedule v. Earned Value
Earned schedule v. Earned ValueEarned schedule v. Earned Value
Earned schedule v. Earned ValueGlen Alleman
 
Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)Glen Alleman
 
Basis of Estimate Processes
Basis of Estimate ProcessesBasis of Estimate Processes
Basis of Estimate ProcessesGlen Alleman
 
Denver PMI Symposium 2009
Denver PMI Symposium 2009Denver PMI Symposium 2009
Denver PMI Symposium 2009Glen Alleman
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy piecesGlen Alleman
 
A time study in numerical methods programming
A time study in numerical methods programmingA time study in numerical methods programming
A time study in numerical methods programmingGlen Alleman
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management successGlen Alleman
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indicesGlen Alleman
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 
Flawless Execution
Flawless ExecutionFlawless Execution
Flawless ExecutionGlen Alleman
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 

Viewers also liked (20)

Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)
 
Earned schedule v. Earned Value
Earned schedule v. Earned ValueEarned schedule v. Earned Value
Earned schedule v. Earned Value
 
Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)
 
Basis of Estimate Processes
Basis of Estimate ProcessesBasis of Estimate Processes
Basis of Estimate Processes
 
Denver PMI Symposium 2009
Denver PMI Symposium 2009Denver PMI Symposium 2009
Denver PMI Symposium 2009
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
A time study in numerical methods programming
A time study in numerical methods programmingA time study in numerical methods programming
A time study in numerical methods programming
 
Comment mesurer l'avancement physique ?
Comment mesurer l'avancement physique ?Comment mesurer l'avancement physique ?
Comment mesurer l'avancement physique ?
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management success
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Flawless Execution
Flawless ExecutionFlawless Execution
Flawless Execution
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Control systems
Control systemsControl systems
Control systems
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 

Similar to Probabilistic Forecasting of Program Cost and Schedule Performance

The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Mihai Buta
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysistheijes
 
Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPIGlen Alleman
 
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvhdcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvhWrushabhShirsat3
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasaNASAPMC
 
8 project planning
8 project planning8 project planning
8 project planningrandhirlpu
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performanceGlen Alleman
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big DataGlen Alleman
 

Similar to Probabilistic Forecasting of Program Cost and Schedule Performance (20)

The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
 
formation.docx
formation.docxformation.docx
formation.docx
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPI
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Planning.ppt
Planning.pptPlanning.ppt
Planning.ppt
 
5-ProjPlanning.ppt
5-ProjPlanning.ppt5-ProjPlanning.ppt
5-ProjPlanning.ppt
 
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvhdcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
 
Rsc 04
Rsc 04Rsc 04
Rsc 04
 
Costing
CostingCosting
Costing
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasa
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
4-ProjectPlanning.ppt
4-ProjectPlanning.ppt4-ProjectPlanning.ppt
4-ProjectPlanning.ppt
 
T24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning PresentationT24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning Presentation
 
8 project planning
8 project planning8 project planning
8 project planning
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performance
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big Data
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Probabilistic Forecasting of Program Cost and Schedule Performance

  • 1. FORECASTING COST AND SCHEDULE PERFORMANCE IN THE PRESENCE OF UNCERTAINTY Probabilistic forecasting of program performance 1
  • 2. Complexity, Risk, and Uncertainty drive all projects 2 Our project management methods must deal with this uncertainty
  • 3. Top Level Theme 3  Earned Value metrics are lagging and linear representations of project performance  SPI/CPI are Cumm to date with this underlying variances washed out  Current period is a one period extension of a linearized accumulation  No information about the dynamics of the past is available  Forecasts of the future are linear projects from the current base point measurement  No statistical inference or probabilistic projects are provided
  • 4. Top Level Theme (Continued) 4  “All models are wrong, some are useful”  Time series analysis: Forecasting and Control, George E. P. Box and Gwilym M. Jenkins, Holden-Day, 1976  Box actually said …
  • 5. Top Level Themes (Concluded) 5  For credible decisions to be made, we need confidence intervals on all the numbers we use to make decisions.  These confidence intervals come from the underlying statistics and the related probabilities.  Statistical forecasting, using time series analysis of past performance, is mandatory for any credible discussion of project performance in the future.
  • 6. | 6 Uncertainties are things we can not be certain about. Uncertainty is created by Incomplete knowledge; not Ignorance Risk
  • 7. All Program Activities have Naturally Occurring Uncertainty 7  Naturally occurring uncertainty and its resulting risk, impacts the probability of a successful outcome What is the probability of making a desired completion date or cost target?  The statistical behavior of these activities, their arrangement in a network of activities, and correlation between their behaviors creates risk  Adding margin protects the outcome from the impact of this naturally occurring uncertainty Risk
  • 8. 8 Raw Material For Forecasting Cost And Schedule
  • 9. Earned Value Numbers 9  CPI / SPI  That’s it, that’s all we got  Cumulative to date  Current period  Cumulative values wipe out the underlying variance  Current period performance not adjusted for past variance  Both cumulative and current period not adjusted for risk
  • 10. Technical Performance Numbers 10  Technical Performance Measures  Measures of Performance  Measures of Effectiveness  Key Performance Parameters  JROC  Program specific
  • 11. 11 Our goal in forecasting the future is to … … Produce a forecast with a range of confidence intervals
  • 12. 12 Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013
  • 13. Forecasts Produce Patterns Of Possible Future Outcomes 13
  • 14. Some Principles  Reliable forecasting is a critical component of project planning, controlling, and risk management.  At-Completion forecast made before the project starts is the basis of credible project management  Execution phase forecasting serves as a leading indicator of project success 14
  • 15. Some Important Terms  The term confidence interval is applied to interval estimates for fixed but unknown parameters  The term prediction interval is an interval estimate for an (unknown) future value.  A prediction interval consists of an upper and a lower limit at a prescribed probability, which are referred to as prediction bounds 15
  • 16. A core limitation of the current approach to performance forecasting  Standard EVM technique for forecasting the final cost at completion is not applicable to forecasting the project duration at completion†  This leads to inconsistent assumptions about the relationships between past performance and future performance  Using CPI creates a future forecast will be the same as past performance † Short 1993, Vandevoorde and Vanhoucke 2006, Leach 2005, and Lipke 2003. 16
  • 17. Forecasting Methods  Probabilistic Forecasting – explicit uncertainties in project performance and errors in measurement provide prediction bounds on the predicted values  Integrative Forecasting Methodologies – collect all relevant information from different sources in a mathematically correct manner  Consistent Forecasting Methodologies – methods that can be applied to both cost and schedule performance forecasts 17
  • 18. Elements of a good forecast  Timely  Reliable  Accurate  Meaningful  Easy to use  Actionable 18
  • 19. Three types of forecasts  Judgmental – Subjective analysis of subjective inputs  The Management EAC is a judgmental forecast  Associative Models – Analyzes historical data to reveal relationships between (easily or in advance) observable quantities and forecast quantities. Uses this relationship to make predictions.  Time Series – Objective analysis historical data assuming the future will be like the past 19
  • 20. Forecasting Techniques  Moving average – taking the value of a chosen number of previous periods to use as an estimate for the next period  Weighted average – same as moving average except giving greater weight to more recent periods  Linear regression – a mathematical algorithm is using past data to create a line showing the direction. The line can then be carried forward to create a forecast  Exponential smoothing – combines most recent actual figure with the previous period’s forecast in order forecast an upcoming period  Regression analysis – equations that are used to analyze the relationship between a dependent variable and one or more independent variables.  Time series – uses recent history is a good predictor of the near future  Trend analysis – finds trends in historic data that can be used to make forecasts. 20
  • 21. 21 Capturing and processing data requires work. Making forecasts are essentially Free
  • 22. 22  We’ve got the start of the data capture process  UN/CEFACT is a place not the name of an XML protocol  Cost and schedule information available at the Control Account level on a monthly basis  In order to build the Control Account data stream, the Work Package are used  Use the Work Package information as well
  • 23. 23
  • 24. An Example of Additional Insight Gained By Comparing Schedules Against Planned Program Deliverables 24 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 1 25 20 15 10 5 MilestoneCount 3/05 Plan (Rev. A) Preliminary Rev. H 5/07 Plan (Rev. E) 0 0 6 1 1 9 2 6 4 2 8 6 9 7 0 5 3 0 6 0 0 (actual from 5/07 plan) (1 actual from 5/07 plan) 3/05 Plan 12/08 Prel. Rev H 5/07 Plan 0 0 6 1 1 15 3 7 19 5 15 25 14 22 0 19 25 0 25 0 0M/S Count Cum 3/05 Plan 12/08 Prel. Rev H 5/07 Plan M/S Count Rate Actual Plans of the James Web Space Telescope (JWST)
  • 25. JWST Schedules and Deliverables by Subsystems 25 Spacecraft Sunshield PDR CDR Test Compl I&T Compl FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 OTE 3/05 Plan (Rev. A) Preliminary Rev. H 5/07 Plan (Rev. E) 3/05 Plan 5/07 Plan 0 0 6 1 1 9 2 6 4 2 8 6 9 7 0 5 3 0 6 0 0 (actual from 5/07 plan) (1 actual from 5/07 plan) ISIM 0 0 6 1 1 15 3 7 19 5 15 25 14 22 0 19 25 0 25 0 0 M/S Count Rate M/S Count Cum STR - PDR STR - CDR ETU - NIRSpec ETU - MIRI ETU - NIRCam ETU - FGS ETU - I&T FM - NIRCam FM - FGS FM - I&T FM - MIRI FM - NIRSpec OTE PDR Start Polish OTE CDR 1st Mirror Delivery Final Mirror Delivery PDR CDR Struct Compl Prop I&T 3/05 Plan Prel. Rev H 5/07 Plan Prel. Rev H Exhibit 30: Deliverables Planned vs Actuals
  • 26. Probabilities of Success Results 26 Case 2: Baseline with Uncertainty, Discrete Risks @ 25 probability 34.8% 50.8% 57.4% 30 Sept2022 Probability of meeting both cost and schedule targets Probability of meeting targeted schedule Probability of meeting targeted cost Exhibit 31: Probability of Meeting Cost and Schedule Targets
  • 27. Current Execution Index (CEI) • CEI is a forecast schedule execution metric for a specific near term window • The goal of this metric is to determine or measure how well the near term schedule represents what actually takes place through execution • The calculation is made through capturing a forward-looking snapshot of what is forecasted to finish in the near term window. Then a comparison is made to the original snapshot after that window has been executed • CEI is NOT an actual to baseline comparison. CEI is an actual to forecast comparison. 27
  • 28. Baseline Execution (BE) Chart • Incomplete tasks, as well as tasks completed late, instill risk to executing program milestones and events • Used with CEI and VI measures, these indicators can help the team determine the level of confidence in Prime’s ability to build a realistic/ executable schedule 28
  • 29. Heat Matrix COST TAB %Complete %Spent BCWR ETC(LRE) VAC% Cum.CV% Cum.CPI TCPI(LRE) BEStarts BEFinishes DurG Cum.SPI CEIFinishes VolatilityFinish 1.1.1 Airframe 218,237 86.22% 86.15% 30,075 47,943 -8.12% 0.08% 1.001 0.627 0.863 0.841 1.182 0.977 0.390 0.680 1.1.2 Propulsion 15,708 87.37% 79.84% 1,983 5,058 -12.03% 8.63% 1.094 0.392 0.981 0.961 0.977 0.955 0.650 0.350 1.1.3 Communications/ 109,508 69.23% 69.77% 33,691 35,708 -2.38% -0.78% 0.992 0.943 0.887 0.873 1.204 0.998 0.420 0.680 1.1.4 Guidance NAV & 186,665 56.77% 68.32% 80,703 92,740 -18.01% -20.36% 0.831 0.870 0.828 0.806 1.279 0.943 0.170 0.870 1.1.7 AV Application 209,584 47.59% 48.76% 109,849 110,629 -1.54% -2.46% 0.976 0.993 0.817 0.775 0.968 0.824 0.220 0.930 1.1.9 AV Integ., Assy 630,622 57.98% 66.93% 264,986 334,479 -19.97% -15.44% 0.866 0.792 0.923 0.907 1.283 0.950 0.400 0.740 1.11.1 Sys Assy Instal 5,982 54.16% 52.23% 2,742 2,858 0.00% 3.56% 1.037 0.960 0.932 0.919 1.129 0.995 0.490 0.590 1.13.1 Spares 25,603 46.49% 45.25% 13,700 13,933 0.33% 2.68% 1.027 0.983 0.963 0.962 1.092 0.994 0.620 0.380 1.13.2 Spares Inventor 6,399 0.00% 0.00% 6,399 6,399 Future Future Future Future Future Future Future Future Future Future 1.13.3 Spares Distribu 5,435 23.44% 23.76% 4,161 4,143 0.00% -1.39% 0.986 1.004 0.973 0.972 1.002 0.982 0.090 1.310 1.2.1 Reconnaissance 97,545 57.32% 54.52% 41,628 44,529 -0.17% 4.89% 1.051 0.935 0.955 0.954 1.055 0.998 0.510 0.620 1.2.3 Electronic Supp 17,251 62.97% 57.07% 6,388 7,405 0.00% 9.36% 1.103 0.863 0.000 0.000 0.000 1.000 0.000 0.000 1.2.6 Payload Applica 347,372 52.68% 54.10% 164,389 173,543 -4.06% -2.70% 0.974 0.947 0.914 0.884 1.149 0.969 0.780 0.410 1.3.5 Misson Control 210,520 63.89% 71.75% 76,024 84,565 -11.92% -12.31% 0.890 0.899 0.918 1.3.6 MCS System SW 16,829 8.83% 8.70% 15,343 16,063 -4.15% 1.43% 1.014 0.955 0.891 0.899 1.195 1.000 0.150 0.880 1.3.7 MCS IAT & C/O 107,163 59.55% 69.65% 43,347 69,151 -34.18% -16.96% 0.855 0.627 0.929 0.925 1.278 0.974 0.440 0.780 SCHEDULEWork RemainingTAB • Provides a singular integrated view of multiple measures for performance • Organizes critical program performance data to drive corrective action and risk mitigation • Teams should focus on ‘Red’ and ‘Yellow’ areas 29
  • 31. KPP Current Status Indicators 31
  • 33. Late Finish by Status Date 33
  • 34. Late Finish Aging Metrics 34
  • 35. Late Start Aging Metrics 35
  • 37. Total Program Starts 0 50 100 150 200 250 300 TotalWeeklyStarts 0 500 1000 1500 2000 2500 3000 3500 4000 CUMStarts Planned 0 0 0 0 0 111 103 140 140 82 128 82 176 59 87 76 180 107 78 59 Actual 0 0 0 0 0 56 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Forecast 0 0 0 0 0 56 276 154 194 119 138 123 195 83 138 102 232 107 81 86 CUM Planned 1554 1554 1554 1554 1554 1665 1768 1908 2048 2130 2258 2340 2516 2575 2662 2738 2918 3025 3103 3162 CUM Actual 1473 1473 1473 1473 1473 1529 CUM Forecast 1473 1473 1473 1473 1473 1529 1805 1959 2153 2272 2410 2533 2728 2811 2949 3051 3283 3390 3471 3557 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 37 Schedule Starts
  • 38. Total Program Finishes 0 50 100 150 200 250 TotalWeeklyFinishes 0 500 1000 1500 2000 2500 3000 3500 CUMFinishes Planned 0 0 0 0 0 129 154 194 128 120 126 151 151 83 95 151 195 92 106 87 Actual 0 0 0 0 0 96 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Forecast 0 0 0 0 0 106 223 206 155 166 123 191 175 101 142 144 206 90 92 120 CUM Planned 943 943 943 943 943 1072 1226 1420 1548 1668 1794 1945 2096 2179 2274 2425 2620 2712 2818 2905 CUM Actual 793 793 793 793 793 889 CUM Forecast 793 793 793 793 793 899 1122 1328 1483 1649 1772 1963 2138 2239 2381 2525 2731 2821 2913 3033 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/1 5 10/2 2 38 Schedule Finishes
  • 39. 39 Program Start Metrics Bow-Wave Trend
  • 40. 40 Program Finish Metrics Bow-Wave Trend
  • 41.  Each status period counts the number of finishes moved to forward periods and adds them to the planned finishes  This increase is the debt of work added to that period 41 Late Finish derived directly from the IMS
  • 42. Leading Indicators come from integrating EVM and SE† 42 † Systems Engineering Applied Leading Indicators: Enabling Assessment of Acquisition Technical Performance, 24 September 2010, Paul Montgomery and Ron Carlson, Graduate School of Engineering & Applied Sciences Naval Postgraduate School, NPS-AM-10-175
  • 43. Leading Indicators must also connect MoE, MoP, and TPMs 43
  • 44. In the end, leading indicators must tell us how to take corrective actions before we end up in the ditch 44
  • 45. 45 Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013