Assessment of Project Monitoring and Control Techniques in Ondo
State Agency for Road Maintenance and Construction (OSARMCO)
Adebayo O. R.1
, Eniowo O. D.2
and Ogunjobi V. O.3
1
Research Student, Department of Project Management Technology, Federal University of Technology, Akure, NIGERIA
2
Lecturer II, Department of Project Management Technology, Federal University of Technology, Akure, NIGERIA
3
Assistant Lecturer, Department of Project Management Technology, Federal University of Technology, Akure, NIGERIA
1
Corresponding Author: ridhwaan_a@yahoo.com
ABSTRACT
Monitoring and control is an essential process in
construction project management and delivery. It is
therefore imperative for construction companies to employ
the usage of the most effective monitoring and control
techniques available to meet project objectives. This study
examined project management techniques employed by
Ondo State Agency for Road Maintenance and
Construction, a construction company in Ondo State,
Nigeria.The research design that was used for this study is
the survey method where copies of a well-structured
questionnaire were distributed to elicit appropriate
information from respondents. The results showed
thatthere is a relationship existing between the type of
project monitoring and control technique used by a
construction company and project delivery/success and that
the use of Program Evaluation and Review Technique
(PERT) for time/schedule control and Earned Value
Management (EVM) (alongside other monitoring and
control techniques) for cost control as used by the company
are very effective in meeting set project objectives.Based on
the findings, a number of recommendations were made.
Among these are, that monitoring and control units should
be established withinconstruction companies and well-
trained workers/professionals should be put in charge of
handling these units and the techniques and tools used
therein.
Keywords-- Construction, Monitoring and Control,
Project, Project Management
I. INTRODUCTION
Projects are one of the most important
components of today‟s organizations. According to PMI
(2000) and Nokes (2007), the term project is a temporary
endeavor designed to produce a unique product, service
or result with a defined beginning and end (usually time-
constrained, and often constrained by funding or
deliverables) undertaken to meet unique goals and
objectives, typically to bring about beneficial change or
added value. A project has a clear time frame (start and
end), and a clear strategy of how to use resources to
produce results. The temporary nature of projects stands
in contrast with business as usual or operations, which
are repetitive, permanent, or semi-permanent functional
activities to produce products or services (Dinsmore,
2005). Projects are also characterized by general
attributes such as the purpose, life cycle, uniqueness,
interdependencies and conflict (Meredith & Mantel,
2000). Projects are designed and implemented to address
developmental needs or problems (Woodhill, 2000).
Project monitoring and control process is done
to make sure everything goes according to plan. In other
words, it identifies discrepancies, handles change
management, and provides feedback to update and
progressively elaborate the plan (Jack, Okeke,
Okechukwu & Akinola, 2016). To put formally, a
project monitoring and control system works to
minimize the deviations from the project plans and
consists of identifying and reporting the status of the
project, comparing it with the plan, analyzing the
deviations, and implementing the appropriate corrective
actions. Hence it includes the set of policies, methods
and tools that would ensure the achievementof the
project targets (Hazir, 2014). The development of a
suitable Project Control system is an important part of
the project management effort (Shtub, Bard &
Globerson, 2005). There have been a number of articles
published to support the importance of control in the
achievement of project objectives, Project performance
can be improved if more attention is given to the issue of
control.(Avison, Baskerville & Myers, 2001). A project
control system is not the development of something
entirely new. It is more the bringing together of many
proven project control techniques. Furthermore, because
the exact combination of control techniques varies
significantly to meet the unique needs of each project, no
single detailed control system is appropriate for every
construction environment. Therefore, every owner,
contractor and engineer should become aware of all
www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962
178 Copyright © 2018. IJEMR. All Rights Reserved.
project control techniques in order to be able to employ
the most appropriate technique to his or her project
(Attalla, 1996).
The construction industry is indeed an integral
component of a nation‟s infrastructure and industrial
growth (Tom & Paul, 2013). The industry is considered
one of the oldest industries organized on a project basis
(Chitkara, 2012; Roberts & Wallace, 2004). The purpose
of construction project management is to plan,
coordinate and control the application of project
objectives in the most effective way according to
stakeholders‟ needs (Harris & McCaffer, 2013).
Therefore, this study aims at assessing various
monitoring and control techniques and their effects on
construction project delivery/success, taking Ondo State
Agency for Road Maintenance and Construction, a
construction company inOndo, Nigeria as a case study.
II. LITERATURE REVIEW
2.1 Concepts of Control
2.1.1 Time Control
A. Critical Path Method (CPM)
According to Guo-li (2010), based on the
original plan (Gantt charts), we can analyze what
activities are on the critical path, what activities have no
free float and what activities have less than a specified
float via the network diagram. Then we can monitor
these activities and take control actions to avoid delay.
Once an activity on the critical path is going to cause
delay, commonly, there are three ways to avoid delay or
even shorten the duration of activities:
a. Increasing resource levels, such as adding
labour.
b. Improving resource efficiency, such as
transferring highly-skilled employees to the
activity, improving efficient tools.
c. And employing means that can shorten critical
path timescales to bring a project back on
target, such as overtime, outsourcing, etc.
B. Optimal Timing
Falco and Macchiaroli (1998) opine that
considering optimal timing of project monitoring and
control points is significant to success. They suggest that
we should determine the optimal frequency of the
monitoring and reviewing to different activities in
different stages. It can help us to efficiently monitor and
correct control so as to reach time and cost target.
C. Crashing
In recent years, network crashing was
developed along with the CPM (Critical Path Method)
for planning and controlling large scale projects. The
purpose of crashing is the minimization of the
pessimistic time estimate in Program Evaluation and
Review Technique (PERT) networks by investing
additional amounts of money in the activities on the
critical path. Sometimes, crashing methods are required
to combine in the monitoring and controlling process
when the duration of the activity has to be completed
within a specified time (Abbasi&Mukattash, 2001).
2.1.2 Cost Control
Guo-li (2010) stated that the main cost of a
project includes staff cost, material cost and delay cost.
To control these costs, managers should first set up a
cost control system to:
a. Allocate responsibilities for administration and
analysis of financial data.
b. Ensure all costs are properly allocated against
project codes.
c. Ensure all costs are genuinely in pursuit of
project activities.
d. Ensure contractors‟ payments are authorized.
e. Check that other projects are not using the
budget.
As a project is dynamic, sometimes the project
managers know the project is going off target by
monitoring, but don‟t know the best action to take. In
this circumstance, net present value (NPV) should be
used as an ongoing monitoring and control mechanism,
because NPV takes account of the time element and
discounts future cash flows, it is the result of the time
effect on cash (Gardiner & Stewart, 2000).
2.1.3 Quality Control
Quality control is considered to be the process
of testing and inspecting material and workmanship for
compliance with the specifications and the applicable
codes. This process is also impacted by the type of
organization, contract format and the project life cycle.
Quality control may be studied in a lump sum contract
environment and within the execution and finish stages
of the project life cycle. Also, quality control is highly
related to both cost and schedule functions. Furthermore,
quality may be considered as a product of cost and
schedule control (Atalla, 1996).
2.1.4 Change Monitor and Control
Voropajev (1998) states that dynamic changes
of project environment will influence the process of
project implementation, the project itself and may cause
heightened risk. When carrying out some activities, the
methods different from that in the original plan must be
used to keep the process moving forward (as experienced
under practice). Therefore, changes are inevitable and
need to be managed during project life-cycle. An
effective change control system should be established to
ensure change procedure is clear and unambiguous and
easy for employee to request a change. And the
following things need to be concerned:
a. Monitoring and forecasting key factors that
generate change to ensure good results
b. Ensuring that change is beneficial
c. Request for change must be checked by suitable
person before being approved
d. Changes should take place once it is approved
and be monitored to check whether it worked as
expected
e. All changes in project should be recorded in the
project documentation (Voropajev, 1998)
www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962
179 Copyright © 2018. IJEMR. All Rights Reserved.
2.2 Theoretical Review
2.2.1 Theory of Control
The theory of control consists of two models:
themostat model and the scientific experimentation
model (Koskela& Howell, 2002).
A. Themostat Model
The themostat model conceptualized that in the
production process, there is a process to control, a unit
for performance measurement, a standard of
performance, and a controlling unit, while the scientific
experimental model of control as advocated by Shewhart
and Deming (1983) cited in Koskela and Howell (2002)
focuses on finding causes of deviations and acting on
those causes, instead of only changing the performance
level for achieving predetermined goals in the case of
deviation.
B. Scientific Experimentation Model
The scientific experimentation model adds the
aspect of learning to control (Koskela & Howell, 2002).
Thus, project control involves gauging performance,
identifying deviation and learning what are the causes of
deviations, their effects and the best means of countering
them. The learning process is an avenue that can be used
by contractors to improve on their project management
potentials.
2.3 Review of Empirical Literature
In a study carried out by Kenley and Harfield
(2015) on “Construction Project Control Methodologies
and Productivity Improvement: EVM, BIM, LBM”. The
main objective of the study was to identify the project
control methods used by organizations to improve
production efficiency. Upon adopting the critical realism
methodology for their explorative research and numeral
analysis for data description, they identified project
control as a contributing factor to project success, and
stated that the project management literature is replete
with models promising control of cost and duration,
process models for more effective project delivery and
software to support their research findings. They also
concluded that controlling external and internal
uncertainty is considered a major part of any
construction project for the implied outcome of
improving overall project productivity.
In another study undertaken by Shanmuganathan
and Baskar (2016) on “Effective Cost and Time
Management Techniques in Construction Industry” to
identify the most successful cost and time management
techniques and software‟s used to control projects in the
construction industry. Data was collected using
questionnaire survey. A 5-point likert scale was used to
understand respondents‟ responses and the Relative
Importance Index (RII) for data analysis, the results of
which revealed that cost management and time
management techniques are important to succeed the
project in the construction industry. It was concluded
that time management software helps to control and
monitor the project whether the project goes in right path
or not. Based upon their research, they established that
cost management techniques like cost flow forecasting
and cost planning control are important for controlling
cost, that time management techniques like critical path
method (CPM) and program evaluation and review
technique (PERT) are the effective time management
techniques in the construction industry.
III. METHODOLOGY
The study area for this study is Ondo State
Agency for Road Maintenance and Construction, a
construction company in Ondo State, Nigeria.The
population of the study consisted of respondents who are
part of the project management team (both lower level
and higher level team members)of Ondo State Agency
for Road Maintenance and Construction (OSARMCO) in
Ondo State amounting to 51 employees. The population
for the study was limited to the project management
team of the construction company to allow for elicitation
of information relevant to title and objectives of the
study.
A sample size of 45 was computed from the
population using the formula for calculating sample size
in research activity as stated in Yamane (1967).
Primary source of data was employed as a
gathering instrument for the survey by means of a
structured questionnaire which was designed in line with
the conceptual framework of the study and was
personally administered by the researcher. Responses
were ranked using a five-pointlikert scale to give an
indication of the degree of the aspect being measured.
The scale was used as it is simple to construct, easy to
read and complete and likely to produce highly reliable
data.
The data pulled together from the field survey
were analysed using descriptive statistics in form of
Percentages and Frequency Tables. Relative Importance
Index (RII), Linear Regression Analysis, ANOVA, and
Pearson Product Moments Correlation Coefficient were
used for the analysis of the research questions. SPSS
(Statistical Package for Social Sciences) version was
used to analyse the data.
IV. RESULTS AND DISCUSSION
4.1 Assessing Time/Schedule Control Technique
Table 1 depicts:
a. the time monitoring and control technique employed
at the study area. 8.9% of respondents selected the
usage of Critical Path Method (CPM) and 91.1%
selected the employment of Program Evaluation and
Review Technique (PERT).
b. the effectiveness of the time/schedule monitoring
and control technique used in the study area in
identifying project activities that are critical. 44.4%
of respondents strongly agreed that it is effective,
51.1% agreed while 4.4% were neutral.
c. the effectiveness of the time/schedule monitoring
and control technique used in the study area in
monitoring planned versus actual progress. 53.3% of
respondents strongly agreed to its effectiveness,
33.3% agreed while 13.3% were undecided.
www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962
180 Copyright © 2018. IJEMR. All Rights Reserved.
d. the effectiveness & reliability of the time/schedule
monitoring and control techniqueused in study area
in meeting set project delivery dates, 44.4% strongly
agreed to its effectiveness& reliability, 37.8%
agreed while 17.8% were neutral.
Table 1: Assessment of Time/Schedule Control Techniques
Frequency Percentage Cumulative
Percentage
Which time/schedule control technique is employed by
OSARMCO?
Critical Path Method (CPM) 4 8.9 8.9
Program Evaluation and Review Technique (PERT) 41 91.1 100.0
Earned Value Management (EVM) 0 0.0 100.0
Others 0 0.0 100.0
Total 45 100.0
Does or do the time/schedule monitoring and control
technique(s) effectively identify project activities that are
critical?
Strongly agree 20 44.4 44.4
Agree 23 51.1 95.6
Neutral 2 4.4 100.0
Disagree 0 0.0 100.0
Strongly disagree 0 0.0 100.0
Total 45 100.0
Is or are the time/schedule monitoring and control
techniques effective in monitoring planned versus actual
progress?
Strongly agree 24 53.3 53.3
Agree 15 33.3 86.7
Neutral 6 13.3 100.0
Disagree 0 0.0 100.0
Strongly disagree 0 0.0 100.0
Total 45 100.0
Would you say that the time/schedule monitoring and
control techniques are effective and reliable in meeting set
project delivery dates?
Strongly agree 20 44.4 44.4
Agree 17 37.8 82.2
Neutral 8 17.8 100.0
Disagree 0 0.0 100.0
Strongly disagree 0 0.0 100.0
Total 45 100.0
Source: Field Survey (2018)
4.2 Assessing Cost Control Technique
Table 2 depicts:
a. the cost control technique employed at the study
area. 95.6% of respondents chose the usage of
Earned Value Management (EVM) while 4.4%
selected the use of other cost control techniques
b. the effectiveness of the cost monitoring and control
techniqueused in the study area in identifying
potential cost overruns. 28.9% of respondents
strongly agreed to its effectiveness, 57.8% agreed
and 13.3% were undecided.
c. the effectiveness of the cost monitoring and control
techniqueused in the study area in mitigating
unfavourable variations in project cost. 57.8% of
respondents strongly agreed to its effectiveness,
40.0% agreed while 2.2% were neutral.
d. the effectiveness & reliability of the cost monitoring
and control techniqueused in study area in
delivering projects within budget.40.0% of
respondents strongly agreedto its effectiveness and
reliability, 55.6% agreed and 4.4% were neutral.
Table 2: Assessment of Cost Control Techniques
Frequency Percentage Cumulative
Percentage
Which cost control technique is employed by
www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962
181 Copyright © 2018. IJEMR. All Rights Reserved.
OSARMCO?
Earned Value Management (EVM) 43 95.6 95.6
Cost Flow Forecasting 0 0.0 95.6
Others 2 4.4 100.0
Total 45 100.0
Does the cost monitoring and control techniques
effectively identify potential cost overruns and
underruns?
Strongly agree 13 28.9 28.9
Agree 26 57.8 86.7
Neutral 6 13.3 100.0
Disagree 0 0.0 100.0
Strongly disagree 0 0.0 100.0
Total 45 100.0
Cost monitoring and control techniques are highly
effective in mitigating unfavorable variations in project
cost
Strongly agree 26 57.8 57.8
Agree 18 40.0 97.8
Neutral 1 2.2 100.0
Disagree 0 0.0 100.0
Strongly disagree 0 0.0 100.0
Total 45 100.0
Would you say that the cost monitoring and control
techniques are effective and reliable in delivering projects
within budget?
Strongly agree 18 40.0 40.0
Agree 25 55.6 95.6
Neutral 2 4.4 100.0
Disagree 0 0.0 100.0
Strongly disagree 0 0.0 100.0
Total 45 100.0
Source: Field Survey (2018)
4.3 Measurement of Project Delivery/Success
Table 3 depicts the satisfaction of clients (which
is also the measurement of project delivery/success) with
projects delivered to them using the monitoring and
control techniquesadopted in the study area. 20% of
respondents strongly agreed that clients are highly
satisfied and the remaining 80% agreed.
Table 3: Clients’ Satisfaction
Frequency Percentage Cumulative
Percentage
Clients are highly satisfied with projects delivered to them
using the aforementioned monitoring and control techniques
Strongly agree 9 20.0 20.0
Agree 36 80.0 100.0
Neutral 0 0.0 100.0
Disagree 0 0.0 100.0
Strongly disagree 0 0.0 100.0
Total 45 100.0
Source: Field Survey (2018)
4.4 Establishing the Value of Project Monitoring and
Control to Project Execution
Table 4 depicts the value of project monitoring
and control to construction projects. 48.9% of
respondents strongly agreed that it is indispensable to
construction project execution and success, and 51.1%
agreed.
www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962
182 Copyright © 2018. IJEMR. All Rights Reserved.
Table 4: Value of project monitoring and control
Frequency Percentage Cumulative
Percentage
Monitoring and control is a major part of any construction
project and plays a vital role in decision making
Strongly agree 22 48.9 48.9
Agree 23 51.1 100.0
Neutral 0 0.0 100.0
Disagree 0 0.0 100.0
Strongly disagree 0 0.0 100.0
Total 45 100.0
Source: Field Survey (2018)
4.5 Test of Hypothesis
The hypothesis tested in this study is to
determine if there is a relationship between type of
project monitoring and control technique used by a
construction company and project delivery/success. This
was tested using regression analysis at a level of
significance p = 0.05 and the result is shown in tables 5–
7.
H0: there is no relationship existing between type of
project monitoring and control technique used by a
construction company and project delivery/success.
H1: there is a relationship existing between type of
project monitoring and control technique used by a
construction company and project delivery/success.
From Table 5, the R value = 0.839 for project
monitoring and control technique represents the simple
correlation which indicates a normal degree of
correlation between project delivery/success and the
types of project monitoring and control techniques used
in the study area. R Square value = 0.703 shows project
delivery/success is affected by 70.3% of the project
monitoring and control techniques used in the study area.
Table 6 shows that p = 0.037 which is less than 0.05.
This implies that the project monitoring and control
techniques regression model predicts project
delivery/success significantly.
Thus, we reject the null hypothesis H0 and
accept the alternate H1 which states that „there is a
relationship existing between type of project monitoring
and control technique used by a construction company
and project delivery/success.‟ and it can be predicted by
the regression formula below from the coefficients in
Table 7.
Y = 5.82 + 2.549X1
Where Y = Project delivery/success and
X1 = Project monitoring and control techniques.
www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962
183 Copyright © 2018. IJEMR. All Rights Reserved.
V. CONCLUSION AND
RECOMMENDATION
This study assessed the project monitoring and
control techniques used by Ondo State Agency for Road
Maintenance and Construction (OSARMCO). The result
of the assessment conducted to identify the monitoring
and control techniques used in the study area and their
effects on project delivery revealed that the major
techniques used are Program Evaluation and Review
Technique (PERT) for time/schedule control and Earned
Value Management (EVM) for cost control, and that
these techniques aid in timely delivery of projects and
mitigate against cost overruns.
Also, the result of the assessment carried out to
establish the value of project monitoring and control to
the project execution of the construction company in the
study area revealed that the project management process
is indeed fundamental and indispensable to project
execution and success.
Finally, the result of the test conducted to assess
the relationship between the type of project monitoring
and control technique used by a construction company
and project delivery/success revealed that there is indeed
a critical relationship existing between type of project
monitoring and control technique used by a construction
company and project delivery/success.
Based on the findings of this study, it is
therefore recommended that construction companies
should have or establish monitoring and control
departments/units within their companies as this is
essential and integral to the successful execution and
delivery of projects and qualified and well-trained
persons/professionals should be put in charge of
handling the project monitoring and control
departments/units of construction companies and the
techniques and tools used therein. In addition, it is
recommended that construction companies should adopt
the use of Program Evaluation and Review Technique
(PERT) and Earned Value Management (EVM) along
with other effective monitoring and control techniques or
tools for monitoring and controlling their projects as they
have been proven effective in this study. Finally, it is
recommended that particular attention and emphasis
should be given to controlling „cost‟ as it is a very
delicate and volatile aspect of every construction project.
REFERENCES
[1] Agwu, M.O. (2014). Perception survey of poor
construction supervision and building failures in six
major cities in Nigeria. British Journal of Education,
Society &Behavioural Science, 4(4), 450-472.
[2] Al-Jibouri, S.H. (2003). Monitoring systems and
their effectiveness for project cost control in
construction. International Journal of Project
Management, 21, 145-154.
[3] Anyanwu, C.I. (2013). Project cost control in the
nigerian construction industry. International Journal of
Engineering Science Invention, 2(12), 65-71.
[4] Atalla, M.M. (1996). Project control techniques
reconstruction of occupied buildings. National Library
of Canada. Available at:
https://uwspace.uwaterloo.ca/bitstream/handle/10012/22/
mq21531.pdf.
[5] Baccarini, D. (1996). The concept of project
complexity − A Review. International Journal of Project
Management, 14(4), 201-204
[6] Badom, L.N. (2016). Project monitoring and
evaluation: A critical factor in budget implementation,
infrastructure development and sustainability. Nigerian
Institute of Quantity Surveyors’ National Workshop with
the Theme: “Budgeting and Capital Project Monitoring
and Evaluation in an Era of Change”. Rivers State
University of Science and Technology, Available at:
http://niqs.org.ng/wp-content/uploads/2016/07/LUCKY-
BADOM-PRESENTATION-FOR-NIQS-WORKSHOP-
IN-MAKURDI.pdf.
[7] Callistus, T. & Clinton, A. (2016). Evaluating
barriers to effective implementation of project
monitoring and evaluation in the Ghanaian construction
industry. Creative Construction Conference, 164, 389-
394. Available at: https://ac.els-
cdn.com/S1877705816339765/1-s2.0-
S1877705816339765-main.pdf?_tid=41ba9852-c9d6-
49cb-8005-
88c5b9ec888b&acdnat=1541312607_56798090b739b40
c5f1878c13afdec86.
[8] Diugwu, I.A., Mohammed, M., & Baba, D.L. (2015).
Towards effective infrastructure development in nigeria:
Theoretical considerations from a project management
perspective. American Journal of Industrial and
Business Management, 5, 172-180.
[9] Gerver, M. (2015). Project monitoring and control.
COST and VALUE, 22-26. Available at:
https://www.dace.nl/download/?id=17691168.
[10] Guo-li, Y. (2010). Project time and budget monitor
and control. Journal of Management Science and
Engineering, 4(1), 56-61.
[10] Hazir, O. (2014). A review of analytical models,
approaches and decision support tools in project
monitoring and control. International Journal of Project
Management, 33(4), 808-815.
[11] Inuwa, I.I. & Kunya, S.U. (2015). Project
management theory exploration for indigenous
contractors‟ project planning in Nigeria. International
Journal of Applied Science and Technology, 5(3), 60-72.
[12] Idoro, I. I. (2012). Influence of the monitoring and
control strategies of indigenous and expatriate Nigerian
contractors on project outcome. Journal of Construction
in Developing Countries, 17(1), 49-67.
[13] Jack, L., Okeke, O.C., Okechukwu, S.I., & Akinola,
A.O. (2016). Project management: A system approach to
planning, implementation, monitoring and evaluation.
International Journal of Advanced Academic Research,
2(11), 65-79.
[14] Kenley, R. & Harfield, T. (2015). Construction
Project Control Methodologies and Productivity
Improvement: EVM, BIM, LBM. Proceedings of the 6th
www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962
184 Copyright © 2018. IJEMR. All Rights Reserved.
International Conference on Engineering, Project and
Production Management, 57-66.
[15] Kostalova, J., Tetrevova, L., & Svedik, J. (2015).
Support of project management methods by project
management information system. 4th International
Conference on Leadership, Technology, Innovation and
Business Management. University of Pardubice,
Pardubice, Czech Republic.
DOI: 10.1016/j.sbspro.2015.11.333
[16] Mackenzie, D.I. (2010). A review of project
controls in the UK & methodologies to improve the
processes. Teesside University's Research Repository.
Available at:
https://core.ac.uk/download/pdf/9440123.pdf.
[17] Marle, F. & Vidal, L. (2016). Managing complex,
high risk projects. London: Springer-Verlag. 53-74.
[18] Memon, Z., Abd. Majid, M.Z., & Mustaffar, M.
(2006). A systematic approach for monitoring and
evaluating the construction project progress. Journal of
the Institution of Engineers, Malaysia, 67(3), 26-32.
[19] Ogunde, A.O., Olaolu, O., Afolabi, A., Owolabi, J.,
& Ojelabi R. (2017). Challenges confronting
construction project management system for sustainable
construction in developing countries: Professionals
perspectives (A case study of Nigeria). Journal of
Building Performance, 8(1), 1-11.
[20] Shanmuganathan, N. & Baskar, G. (2016). Effective
cost and time management techniques in construction
industry. International Journal of Advanced Engineering
Technology, 7(2), 743-747.
[21] Tom, A.F. & Paul, S. (2013). Project monitoring
and control using primavera. International Journal of
Innovative Research in Science, Engineering and
Technology, 2(3), 762-771.

More Related Content

What's hot

IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
Project management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comProject management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comTutors India
 
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET Journal
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Controlcivej
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionIJERA Editor
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET Journal
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
IRJET - A Review Paper on Effective Material Management to Minimize Probl...
IRJET -  	  A Review Paper on Effective Material Management to Minimize Probl...IRJET -  	  A Review Paper on Effective Material Management to Minimize Probl...
IRJET - A Review Paper on Effective Material Management to Minimize Probl...IRJET Journal
 
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
00 safety_quality_construction
00  safety_quality_construction00  safety_quality_construction
00 safety_quality_constructionAdhitomo Wirawan
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...IAEME Publication
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementIAEME Publication
 
Productivity improvement in construction
Productivity  improvement in constructionProductivity  improvement in construction
Productivity improvement in constructionKabilanP1
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Glen Alleman
 

What's hot (20)

IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
Project management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comProject management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.com
 
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building Construction
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
IRJET - A Review Paper on Effective Material Management to Minimize Probl...
IRJET -  	  A Review Paper on Effective Material Management to Minimize Probl...IRJET -  	  A Review Paper on Effective Material Management to Minimize Probl...
IRJET - A Review Paper on Effective Material Management to Minimize Probl...
 
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
00 safety_quality_construction
00  safety_quality_construction00  safety_quality_construction
00 safety_quality_construction
 
S3 p2 lee_kong_hui
S3 p2 lee_kong_huiS3 p2 lee_kong_hui
S3 p2 lee_kong_hui
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
 
Productivity improvement in construction
Productivity  improvement in constructionProductivity  improvement in construction
Productivity improvement in construction
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...
 

Similar to Assessment of Project Monitoring and Control Techniques in Ondo State Agency for Road Maintenance and Construction (OSARMCO)

The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriaNewman Jonathan
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write31
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write4
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...IRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CA...
MANAGING AND CONTROLLING PROJECT  CHANGES IN POST-CONFLICT COUNTRIES: THE  CA...MANAGING AND CONTROLLING PROJECT  CHANGES IN POST-CONFLICT COUNTRIES: THE  CA...
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CA...ijmvsc
 
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CASE...
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CASE...MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CASE...
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CASE...ijmvsc
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on SiteIRJET Journal
 
Management control of projects
Management control of projectsManagement control of projects
Management control of projectsSai Mahesh
 
PERFORMANCE MONITORING USING EVM INDICATOR
PERFORMANCE MONITORING USING EVM INDICATORPERFORMANCE MONITORING USING EVM INDICATOR
PERFORMANCE MONITORING USING EVM INDICATORDr Ezzat Mansour
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Projectijtsrd
 

Similar to Assessment of Project Monitoring and Control Techniques in Ondo State Agency for Road Maintenance and Construction (OSARMCO) (20)

The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
H1303055462
H1303055462H1303055462
H1303055462
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Ijciet 10 01_075
Ijciet 10 01_075Ijciet 10 01_075
Ijciet 10 01_075
 
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CA...
MANAGING AND CONTROLLING PROJECT  CHANGES IN POST-CONFLICT COUNTRIES: THE  CA...MANAGING AND CONTROLLING PROJECT  CHANGES IN POST-CONFLICT COUNTRIES: THE  CA...
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CA...
 
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CASE...
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CASE...MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CASE...
MANAGING AND CONTROLLING PROJECT CHANGES IN POST-CONFLICT COUNTRIES: THE CASE...
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on Site
 
Management control of projects
Management control of projectsManagement control of projects
Management control of projects
 
PERFORMANCE MONITORING USING EVM INDICATOR
PERFORMANCE MONITORING USING EVM INDICATORPERFORMANCE MONITORING USING EVM INDICATOR
PERFORMANCE MONITORING USING EVM INDICATOR
 
EARNED VALUE MANAGEMENT
EARNED VALUE MANAGEMENTEARNED VALUE MANAGEMENT
EARNED VALUE MANAGEMENT
 
Project Management
Project ManagementProject Management
Project Management
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Project
 

More from Dr. Amarjeet Singh

Total Ionization Cross Sections due to Electron Impact of Ammonia from Thresh...
Total Ionization Cross Sections due to Electron Impact of Ammonia from Thresh...Total Ionization Cross Sections due to Electron Impact of Ammonia from Thresh...
Total Ionization Cross Sections due to Electron Impact of Ammonia from Thresh...Dr. Amarjeet Singh
 
A Case Study on Small Town Big Player – Enjay IT Solutions Ltd., Bhilad
A Case Study on Small Town Big Player – Enjay IT Solutions Ltd., BhiladA Case Study on Small Town Big Player – Enjay IT Solutions Ltd., Bhilad
A Case Study on Small Town Big Player – Enjay IT Solutions Ltd., BhiladDr. Amarjeet Singh
 
Effect of Biopesticide from the Stems of Gossypium Arboreum on Pink Bollworm ...
Effect of Biopesticide from the Stems of Gossypium Arboreum on Pink Bollworm ...Effect of Biopesticide from the Stems of Gossypium Arboreum on Pink Bollworm ...
Effect of Biopesticide from the Stems of Gossypium Arboreum on Pink Bollworm ...Dr. Amarjeet Singh
 
Artificial Intelligence Techniques in E-Commerce: The Possibility of Exploiti...
Artificial Intelligence Techniques in E-Commerce: The Possibility of Exploiti...Artificial Intelligence Techniques in E-Commerce: The Possibility of Exploiti...
Artificial Intelligence Techniques in E-Commerce: The Possibility of Exploiti...Dr. Amarjeet Singh
 
Factors Influencing Ownership Pattern and its Impact on Corporate Performance...
Factors Influencing Ownership Pattern and its Impact on Corporate Performance...Factors Influencing Ownership Pattern and its Impact on Corporate Performance...
Factors Influencing Ownership Pattern and its Impact on Corporate Performance...Dr. Amarjeet Singh
 
An Analytical Study on Ratios Influencing Profitability of Selected Indian Au...
An Analytical Study on Ratios Influencing Profitability of Selected Indian Au...An Analytical Study on Ratios Influencing Profitability of Selected Indian Au...
An Analytical Study on Ratios Influencing Profitability of Selected Indian Au...Dr. Amarjeet Singh
 
A Study on Factors Influencing the Financial Performance Analysis Selected Pr...
A Study on Factors Influencing the Financial Performance Analysis Selected Pr...A Study on Factors Influencing the Financial Performance Analysis Selected Pr...
A Study on Factors Influencing the Financial Performance Analysis Selected Pr...Dr. Amarjeet Singh
 
An Empirical Analysis of Financial Performance of Selected Oil Exploration an...
An Empirical Analysis of Financial Performance of Selected Oil Exploration an...An Empirical Analysis of Financial Performance of Selected Oil Exploration an...
An Empirical Analysis of Financial Performance of Selected Oil Exploration an...Dr. Amarjeet Singh
 
A Study on Derivative Market in India
A Study on Derivative Market in IndiaA Study on Derivative Market in India
A Study on Derivative Market in IndiaDr. Amarjeet Singh
 
Theoretical Estimation of CO2 Compression and Transport Costs for an hypothet...
Theoretical Estimation of CO2 Compression and Transport Costs for an hypothet...Theoretical Estimation of CO2 Compression and Transport Costs for an hypothet...
Theoretical Estimation of CO2 Compression and Transport Costs for an hypothet...Dr. Amarjeet Singh
 
Analytical Mechanics of Magnetic Particles Suspended in Magnetorheological Fluid
Analytical Mechanics of Magnetic Particles Suspended in Magnetorheological FluidAnalytical Mechanics of Magnetic Particles Suspended in Magnetorheological Fluid
Analytical Mechanics of Magnetic Particles Suspended in Magnetorheological FluidDr. Amarjeet Singh
 
Techno-Economic Aspects of Solid Food Wastes into Bio-Manure
Techno-Economic Aspects of Solid Food Wastes into Bio-ManureTechno-Economic Aspects of Solid Food Wastes into Bio-Manure
Techno-Economic Aspects of Solid Food Wastes into Bio-ManureDr. Amarjeet Singh
 
Crypto-Currencies: Can Investors Rely on them as Investment Avenue?
Crypto-Currencies: Can Investors Rely on them as Investment Avenue?Crypto-Currencies: Can Investors Rely on them as Investment Avenue?
Crypto-Currencies: Can Investors Rely on them as Investment Avenue?Dr. Amarjeet Singh
 
Awareness of Disaster Risk Reduction (DRR) among Student of the Catanduanes S...
Awareness of Disaster Risk Reduction (DRR) among Student of the Catanduanes S...Awareness of Disaster Risk Reduction (DRR) among Student of the Catanduanes S...
Awareness of Disaster Risk Reduction (DRR) among Student of the Catanduanes S...Dr. Amarjeet Singh
 
Role of Indians in the Battle of 1857
Role of Indians in the Battle of 1857Role of Indians in the Battle of 1857
Role of Indians in the Battle of 1857Dr. Amarjeet Singh
 
Haryana's Honour Killings: A Social and Legal Point of View
Haryana's Honour Killings: A Social and Legal Point of ViewHaryana's Honour Killings: A Social and Legal Point of View
Haryana's Honour Killings: A Social and Legal Point of ViewDr. Amarjeet Singh
 
Optimization of Digital-Based MSME E-Commerce: Challenges and Opportunities i...
Optimization of Digital-Based MSME E-Commerce: Challenges and Opportunities i...Optimization of Digital-Based MSME E-Commerce: Challenges and Opportunities i...
Optimization of Digital-Based MSME E-Commerce: Challenges and Opportunities i...Dr. Amarjeet Singh
 
Modal Space Controller for Hydraulically Driven Six Degree of Freedom Paralle...
Modal Space Controller for Hydraulically Driven Six Degree of Freedom Paralle...Modal Space Controller for Hydraulically Driven Six Degree of Freedom Paralle...
Modal Space Controller for Hydraulically Driven Six Degree of Freedom Paralle...Dr. Amarjeet Singh
 
Capacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryCapacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryDr. Amarjeet Singh
 
Metamorphosing Indian Blockchain Ecosystem
Metamorphosing Indian Blockchain EcosystemMetamorphosing Indian Blockchain Ecosystem
Metamorphosing Indian Blockchain EcosystemDr. Amarjeet Singh
 

More from Dr. Amarjeet Singh (20)

Total Ionization Cross Sections due to Electron Impact of Ammonia from Thresh...
Total Ionization Cross Sections due to Electron Impact of Ammonia from Thresh...Total Ionization Cross Sections due to Electron Impact of Ammonia from Thresh...
Total Ionization Cross Sections due to Electron Impact of Ammonia from Thresh...
 
A Case Study on Small Town Big Player – Enjay IT Solutions Ltd., Bhilad
A Case Study on Small Town Big Player – Enjay IT Solutions Ltd., BhiladA Case Study on Small Town Big Player – Enjay IT Solutions Ltd., Bhilad
A Case Study on Small Town Big Player – Enjay IT Solutions Ltd., Bhilad
 
Effect of Biopesticide from the Stems of Gossypium Arboreum on Pink Bollworm ...
Effect of Biopesticide from the Stems of Gossypium Arboreum on Pink Bollworm ...Effect of Biopesticide from the Stems of Gossypium Arboreum on Pink Bollworm ...
Effect of Biopesticide from the Stems of Gossypium Arboreum on Pink Bollworm ...
 
Artificial Intelligence Techniques in E-Commerce: The Possibility of Exploiti...
Artificial Intelligence Techniques in E-Commerce: The Possibility of Exploiti...Artificial Intelligence Techniques in E-Commerce: The Possibility of Exploiti...
Artificial Intelligence Techniques in E-Commerce: The Possibility of Exploiti...
 
Factors Influencing Ownership Pattern and its Impact on Corporate Performance...
Factors Influencing Ownership Pattern and its Impact on Corporate Performance...Factors Influencing Ownership Pattern and its Impact on Corporate Performance...
Factors Influencing Ownership Pattern and its Impact on Corporate Performance...
 
An Analytical Study on Ratios Influencing Profitability of Selected Indian Au...
An Analytical Study on Ratios Influencing Profitability of Selected Indian Au...An Analytical Study on Ratios Influencing Profitability of Selected Indian Au...
An Analytical Study on Ratios Influencing Profitability of Selected Indian Au...
 
A Study on Factors Influencing the Financial Performance Analysis Selected Pr...
A Study on Factors Influencing the Financial Performance Analysis Selected Pr...A Study on Factors Influencing the Financial Performance Analysis Selected Pr...
A Study on Factors Influencing the Financial Performance Analysis Selected Pr...
 
An Empirical Analysis of Financial Performance of Selected Oil Exploration an...
An Empirical Analysis of Financial Performance of Selected Oil Exploration an...An Empirical Analysis of Financial Performance of Selected Oil Exploration an...
An Empirical Analysis of Financial Performance of Selected Oil Exploration an...
 
A Study on Derivative Market in India
A Study on Derivative Market in IndiaA Study on Derivative Market in India
A Study on Derivative Market in India
 
Theoretical Estimation of CO2 Compression and Transport Costs for an hypothet...
Theoretical Estimation of CO2 Compression and Transport Costs for an hypothet...Theoretical Estimation of CO2 Compression and Transport Costs for an hypothet...
Theoretical Estimation of CO2 Compression and Transport Costs for an hypothet...
 
Analytical Mechanics of Magnetic Particles Suspended in Magnetorheological Fluid
Analytical Mechanics of Magnetic Particles Suspended in Magnetorheological FluidAnalytical Mechanics of Magnetic Particles Suspended in Magnetorheological Fluid
Analytical Mechanics of Magnetic Particles Suspended in Magnetorheological Fluid
 
Techno-Economic Aspects of Solid Food Wastes into Bio-Manure
Techno-Economic Aspects of Solid Food Wastes into Bio-ManureTechno-Economic Aspects of Solid Food Wastes into Bio-Manure
Techno-Economic Aspects of Solid Food Wastes into Bio-Manure
 
Crypto-Currencies: Can Investors Rely on them as Investment Avenue?
Crypto-Currencies: Can Investors Rely on them as Investment Avenue?Crypto-Currencies: Can Investors Rely on them as Investment Avenue?
Crypto-Currencies: Can Investors Rely on them as Investment Avenue?
 
Awareness of Disaster Risk Reduction (DRR) among Student of the Catanduanes S...
Awareness of Disaster Risk Reduction (DRR) among Student of the Catanduanes S...Awareness of Disaster Risk Reduction (DRR) among Student of the Catanduanes S...
Awareness of Disaster Risk Reduction (DRR) among Student of the Catanduanes S...
 
Role of Indians in the Battle of 1857
Role of Indians in the Battle of 1857Role of Indians in the Battle of 1857
Role of Indians in the Battle of 1857
 
Haryana's Honour Killings: A Social and Legal Point of View
Haryana's Honour Killings: A Social and Legal Point of ViewHaryana's Honour Killings: A Social and Legal Point of View
Haryana's Honour Killings: A Social and Legal Point of View
 
Optimization of Digital-Based MSME E-Commerce: Challenges and Opportunities i...
Optimization of Digital-Based MSME E-Commerce: Challenges and Opportunities i...Optimization of Digital-Based MSME E-Commerce: Challenges and Opportunities i...
Optimization of Digital-Based MSME E-Commerce: Challenges and Opportunities i...
 
Modal Space Controller for Hydraulically Driven Six Degree of Freedom Paralle...
Modal Space Controller for Hydraulically Driven Six Degree of Freedom Paralle...Modal Space Controller for Hydraulically Driven Six Degree of Freedom Paralle...
Modal Space Controller for Hydraulically Driven Six Degree of Freedom Paralle...
 
Capacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryCapacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel Industry
 
Metamorphosing Indian Blockchain Ecosystem
Metamorphosing Indian Blockchain EcosystemMetamorphosing Indian Blockchain Ecosystem
Metamorphosing Indian Blockchain Ecosystem
 

Recently uploaded

Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 

Recently uploaded (20)

Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 

Assessment of Project Monitoring and Control Techniques in Ondo State Agency for Road Maintenance and Construction (OSARMCO)

  • 1. www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962 177 Copyright © 2018. IJEMR. All Rights Reserved. Volume-8, Issue-5, October 2018 International Journal of Engineering and Management Research Page Number: 177-184 DOI: doi.org/10.31033/ijemr.8.5.21 Assessment of Project Monitoring and Control Techniques in Ondo State Agency for Road Maintenance and Construction (OSARMCO) Adebayo O. R.1 , Eniowo O. D.2 and Ogunjobi V. O.3 1 Research Student, Department of Project Management Technology, Federal University of Technology, Akure, NIGERIA 2 Lecturer II, Department of Project Management Technology, Federal University of Technology, Akure, NIGERIA 3 Assistant Lecturer, Department of Project Management Technology, Federal University of Technology, Akure, NIGERIA 1 Corresponding Author: ridhwaan_a@yahoo.com ABSTRACT Monitoring and control is an essential process in construction project management and delivery. It is therefore imperative for construction companies to employ the usage of the most effective monitoring and control techniques available to meet project objectives. This study examined project management techniques employed by Ondo State Agency for Road Maintenance and Construction, a construction company in Ondo State, Nigeria.The research design that was used for this study is the survey method where copies of a well-structured questionnaire were distributed to elicit appropriate information from respondents. The results showed thatthere is a relationship existing between the type of project monitoring and control technique used by a construction company and project delivery/success and that the use of Program Evaluation and Review Technique (PERT) for time/schedule control and Earned Value Management (EVM) (alongside other monitoring and control techniques) for cost control as used by the company are very effective in meeting set project objectives.Based on the findings, a number of recommendations were made. Among these are, that monitoring and control units should be established withinconstruction companies and well- trained workers/professionals should be put in charge of handling these units and the techniques and tools used therein. Keywords-- Construction, Monitoring and Control, Project, Project Management I. INTRODUCTION Projects are one of the most important components of today‟s organizations. According to PMI (2000) and Nokes (2007), the term project is a temporary endeavor designed to produce a unique product, service or result with a defined beginning and end (usually time- constrained, and often constrained by funding or deliverables) undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value. A project has a clear time frame (start and end), and a clear strategy of how to use resources to produce results. The temporary nature of projects stands in contrast with business as usual or operations, which are repetitive, permanent, or semi-permanent functional activities to produce products or services (Dinsmore, 2005). Projects are also characterized by general attributes such as the purpose, life cycle, uniqueness, interdependencies and conflict (Meredith & Mantel, 2000). Projects are designed and implemented to address developmental needs or problems (Woodhill, 2000). Project monitoring and control process is done to make sure everything goes according to plan. In other words, it identifies discrepancies, handles change management, and provides feedback to update and progressively elaborate the plan (Jack, Okeke, Okechukwu & Akinola, 2016). To put formally, a project monitoring and control system works to minimize the deviations from the project plans and consists of identifying and reporting the status of the project, comparing it with the plan, analyzing the deviations, and implementing the appropriate corrective actions. Hence it includes the set of policies, methods and tools that would ensure the achievementof the project targets (Hazir, 2014). The development of a suitable Project Control system is an important part of the project management effort (Shtub, Bard & Globerson, 2005). There have been a number of articles published to support the importance of control in the achievement of project objectives, Project performance can be improved if more attention is given to the issue of control.(Avison, Baskerville & Myers, 2001). A project control system is not the development of something entirely new. It is more the bringing together of many proven project control techniques. Furthermore, because the exact combination of control techniques varies significantly to meet the unique needs of each project, no single detailed control system is appropriate for every construction environment. Therefore, every owner, contractor and engineer should become aware of all
  • 2. www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962 178 Copyright © 2018. IJEMR. All Rights Reserved. project control techniques in order to be able to employ the most appropriate technique to his or her project (Attalla, 1996). The construction industry is indeed an integral component of a nation‟s infrastructure and industrial growth (Tom & Paul, 2013). The industry is considered one of the oldest industries organized on a project basis (Chitkara, 2012; Roberts & Wallace, 2004). The purpose of construction project management is to plan, coordinate and control the application of project objectives in the most effective way according to stakeholders‟ needs (Harris & McCaffer, 2013). Therefore, this study aims at assessing various monitoring and control techniques and their effects on construction project delivery/success, taking Ondo State Agency for Road Maintenance and Construction, a construction company inOndo, Nigeria as a case study. II. LITERATURE REVIEW 2.1 Concepts of Control 2.1.1 Time Control A. Critical Path Method (CPM) According to Guo-li (2010), based on the original plan (Gantt charts), we can analyze what activities are on the critical path, what activities have no free float and what activities have less than a specified float via the network diagram. Then we can monitor these activities and take control actions to avoid delay. Once an activity on the critical path is going to cause delay, commonly, there are three ways to avoid delay or even shorten the duration of activities: a. Increasing resource levels, such as adding labour. b. Improving resource efficiency, such as transferring highly-skilled employees to the activity, improving efficient tools. c. And employing means that can shorten critical path timescales to bring a project back on target, such as overtime, outsourcing, etc. B. Optimal Timing Falco and Macchiaroli (1998) opine that considering optimal timing of project monitoring and control points is significant to success. They suggest that we should determine the optimal frequency of the monitoring and reviewing to different activities in different stages. It can help us to efficiently monitor and correct control so as to reach time and cost target. C. Crashing In recent years, network crashing was developed along with the CPM (Critical Path Method) for planning and controlling large scale projects. The purpose of crashing is the minimization of the pessimistic time estimate in Program Evaluation and Review Technique (PERT) networks by investing additional amounts of money in the activities on the critical path. Sometimes, crashing methods are required to combine in the monitoring and controlling process when the duration of the activity has to be completed within a specified time (Abbasi&Mukattash, 2001). 2.1.2 Cost Control Guo-li (2010) stated that the main cost of a project includes staff cost, material cost and delay cost. To control these costs, managers should first set up a cost control system to: a. Allocate responsibilities for administration and analysis of financial data. b. Ensure all costs are properly allocated against project codes. c. Ensure all costs are genuinely in pursuit of project activities. d. Ensure contractors‟ payments are authorized. e. Check that other projects are not using the budget. As a project is dynamic, sometimes the project managers know the project is going off target by monitoring, but don‟t know the best action to take. In this circumstance, net present value (NPV) should be used as an ongoing monitoring and control mechanism, because NPV takes account of the time element and discounts future cash flows, it is the result of the time effect on cash (Gardiner & Stewart, 2000). 2.1.3 Quality Control Quality control is considered to be the process of testing and inspecting material and workmanship for compliance with the specifications and the applicable codes. This process is also impacted by the type of organization, contract format and the project life cycle. Quality control may be studied in a lump sum contract environment and within the execution and finish stages of the project life cycle. Also, quality control is highly related to both cost and schedule functions. Furthermore, quality may be considered as a product of cost and schedule control (Atalla, 1996). 2.1.4 Change Monitor and Control Voropajev (1998) states that dynamic changes of project environment will influence the process of project implementation, the project itself and may cause heightened risk. When carrying out some activities, the methods different from that in the original plan must be used to keep the process moving forward (as experienced under practice). Therefore, changes are inevitable and need to be managed during project life-cycle. An effective change control system should be established to ensure change procedure is clear and unambiguous and easy for employee to request a change. And the following things need to be concerned: a. Monitoring and forecasting key factors that generate change to ensure good results b. Ensuring that change is beneficial c. Request for change must be checked by suitable person before being approved d. Changes should take place once it is approved and be monitored to check whether it worked as expected e. All changes in project should be recorded in the project documentation (Voropajev, 1998)
  • 3. www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962 179 Copyright © 2018. IJEMR. All Rights Reserved. 2.2 Theoretical Review 2.2.1 Theory of Control The theory of control consists of two models: themostat model and the scientific experimentation model (Koskela& Howell, 2002). A. Themostat Model The themostat model conceptualized that in the production process, there is a process to control, a unit for performance measurement, a standard of performance, and a controlling unit, while the scientific experimental model of control as advocated by Shewhart and Deming (1983) cited in Koskela and Howell (2002) focuses on finding causes of deviations and acting on those causes, instead of only changing the performance level for achieving predetermined goals in the case of deviation. B. Scientific Experimentation Model The scientific experimentation model adds the aspect of learning to control (Koskela & Howell, 2002). Thus, project control involves gauging performance, identifying deviation and learning what are the causes of deviations, their effects and the best means of countering them. The learning process is an avenue that can be used by contractors to improve on their project management potentials. 2.3 Review of Empirical Literature In a study carried out by Kenley and Harfield (2015) on “Construction Project Control Methodologies and Productivity Improvement: EVM, BIM, LBM”. The main objective of the study was to identify the project control methods used by organizations to improve production efficiency. Upon adopting the critical realism methodology for their explorative research and numeral analysis for data description, they identified project control as a contributing factor to project success, and stated that the project management literature is replete with models promising control of cost and duration, process models for more effective project delivery and software to support their research findings. They also concluded that controlling external and internal uncertainty is considered a major part of any construction project for the implied outcome of improving overall project productivity. In another study undertaken by Shanmuganathan and Baskar (2016) on “Effective Cost and Time Management Techniques in Construction Industry” to identify the most successful cost and time management techniques and software‟s used to control projects in the construction industry. Data was collected using questionnaire survey. A 5-point likert scale was used to understand respondents‟ responses and the Relative Importance Index (RII) for data analysis, the results of which revealed that cost management and time management techniques are important to succeed the project in the construction industry. It was concluded that time management software helps to control and monitor the project whether the project goes in right path or not. Based upon their research, they established that cost management techniques like cost flow forecasting and cost planning control are important for controlling cost, that time management techniques like critical path method (CPM) and program evaluation and review technique (PERT) are the effective time management techniques in the construction industry. III. METHODOLOGY The study area for this study is Ondo State Agency for Road Maintenance and Construction, a construction company in Ondo State, Nigeria.The population of the study consisted of respondents who are part of the project management team (both lower level and higher level team members)of Ondo State Agency for Road Maintenance and Construction (OSARMCO) in Ondo State amounting to 51 employees. The population for the study was limited to the project management team of the construction company to allow for elicitation of information relevant to title and objectives of the study. A sample size of 45 was computed from the population using the formula for calculating sample size in research activity as stated in Yamane (1967). Primary source of data was employed as a gathering instrument for the survey by means of a structured questionnaire which was designed in line with the conceptual framework of the study and was personally administered by the researcher. Responses were ranked using a five-pointlikert scale to give an indication of the degree of the aspect being measured. The scale was used as it is simple to construct, easy to read and complete and likely to produce highly reliable data. The data pulled together from the field survey were analysed using descriptive statistics in form of Percentages and Frequency Tables. Relative Importance Index (RII), Linear Regression Analysis, ANOVA, and Pearson Product Moments Correlation Coefficient were used for the analysis of the research questions. SPSS (Statistical Package for Social Sciences) version was used to analyse the data. IV. RESULTS AND DISCUSSION 4.1 Assessing Time/Schedule Control Technique Table 1 depicts: a. the time monitoring and control technique employed at the study area. 8.9% of respondents selected the usage of Critical Path Method (CPM) and 91.1% selected the employment of Program Evaluation and Review Technique (PERT). b. the effectiveness of the time/schedule monitoring and control technique used in the study area in identifying project activities that are critical. 44.4% of respondents strongly agreed that it is effective, 51.1% agreed while 4.4% were neutral. c. the effectiveness of the time/schedule monitoring and control technique used in the study area in monitoring planned versus actual progress. 53.3% of respondents strongly agreed to its effectiveness, 33.3% agreed while 13.3% were undecided.
  • 4. www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962 180 Copyright © 2018. IJEMR. All Rights Reserved. d. the effectiveness & reliability of the time/schedule monitoring and control techniqueused in study area in meeting set project delivery dates, 44.4% strongly agreed to its effectiveness& reliability, 37.8% agreed while 17.8% were neutral. Table 1: Assessment of Time/Schedule Control Techniques Frequency Percentage Cumulative Percentage Which time/schedule control technique is employed by OSARMCO? Critical Path Method (CPM) 4 8.9 8.9 Program Evaluation and Review Technique (PERT) 41 91.1 100.0 Earned Value Management (EVM) 0 0.0 100.0 Others 0 0.0 100.0 Total 45 100.0 Does or do the time/schedule monitoring and control technique(s) effectively identify project activities that are critical? Strongly agree 20 44.4 44.4 Agree 23 51.1 95.6 Neutral 2 4.4 100.0 Disagree 0 0.0 100.0 Strongly disagree 0 0.0 100.0 Total 45 100.0 Is or are the time/schedule monitoring and control techniques effective in monitoring planned versus actual progress? Strongly agree 24 53.3 53.3 Agree 15 33.3 86.7 Neutral 6 13.3 100.0 Disagree 0 0.0 100.0 Strongly disagree 0 0.0 100.0 Total 45 100.0 Would you say that the time/schedule monitoring and control techniques are effective and reliable in meeting set project delivery dates? Strongly agree 20 44.4 44.4 Agree 17 37.8 82.2 Neutral 8 17.8 100.0 Disagree 0 0.0 100.0 Strongly disagree 0 0.0 100.0 Total 45 100.0 Source: Field Survey (2018) 4.2 Assessing Cost Control Technique Table 2 depicts: a. the cost control technique employed at the study area. 95.6% of respondents chose the usage of Earned Value Management (EVM) while 4.4% selected the use of other cost control techniques b. the effectiveness of the cost monitoring and control techniqueused in the study area in identifying potential cost overruns. 28.9% of respondents strongly agreed to its effectiveness, 57.8% agreed and 13.3% were undecided. c. the effectiveness of the cost monitoring and control techniqueused in the study area in mitigating unfavourable variations in project cost. 57.8% of respondents strongly agreed to its effectiveness, 40.0% agreed while 2.2% were neutral. d. the effectiveness & reliability of the cost monitoring and control techniqueused in study area in delivering projects within budget.40.0% of respondents strongly agreedto its effectiveness and reliability, 55.6% agreed and 4.4% were neutral. Table 2: Assessment of Cost Control Techniques Frequency Percentage Cumulative Percentage Which cost control technique is employed by
  • 5. www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962 181 Copyright © 2018. IJEMR. All Rights Reserved. OSARMCO? Earned Value Management (EVM) 43 95.6 95.6 Cost Flow Forecasting 0 0.0 95.6 Others 2 4.4 100.0 Total 45 100.0 Does the cost monitoring and control techniques effectively identify potential cost overruns and underruns? Strongly agree 13 28.9 28.9 Agree 26 57.8 86.7 Neutral 6 13.3 100.0 Disagree 0 0.0 100.0 Strongly disagree 0 0.0 100.0 Total 45 100.0 Cost monitoring and control techniques are highly effective in mitigating unfavorable variations in project cost Strongly agree 26 57.8 57.8 Agree 18 40.0 97.8 Neutral 1 2.2 100.0 Disagree 0 0.0 100.0 Strongly disagree 0 0.0 100.0 Total 45 100.0 Would you say that the cost monitoring and control techniques are effective and reliable in delivering projects within budget? Strongly agree 18 40.0 40.0 Agree 25 55.6 95.6 Neutral 2 4.4 100.0 Disagree 0 0.0 100.0 Strongly disagree 0 0.0 100.0 Total 45 100.0 Source: Field Survey (2018) 4.3 Measurement of Project Delivery/Success Table 3 depicts the satisfaction of clients (which is also the measurement of project delivery/success) with projects delivered to them using the monitoring and control techniquesadopted in the study area. 20% of respondents strongly agreed that clients are highly satisfied and the remaining 80% agreed. Table 3: Clients’ Satisfaction Frequency Percentage Cumulative Percentage Clients are highly satisfied with projects delivered to them using the aforementioned monitoring and control techniques Strongly agree 9 20.0 20.0 Agree 36 80.0 100.0 Neutral 0 0.0 100.0 Disagree 0 0.0 100.0 Strongly disagree 0 0.0 100.0 Total 45 100.0 Source: Field Survey (2018) 4.4 Establishing the Value of Project Monitoring and Control to Project Execution Table 4 depicts the value of project monitoring and control to construction projects. 48.9% of respondents strongly agreed that it is indispensable to construction project execution and success, and 51.1% agreed.
  • 6. www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962 182 Copyright © 2018. IJEMR. All Rights Reserved. Table 4: Value of project monitoring and control Frequency Percentage Cumulative Percentage Monitoring and control is a major part of any construction project and plays a vital role in decision making Strongly agree 22 48.9 48.9 Agree 23 51.1 100.0 Neutral 0 0.0 100.0 Disagree 0 0.0 100.0 Strongly disagree 0 0.0 100.0 Total 45 100.0 Source: Field Survey (2018) 4.5 Test of Hypothesis The hypothesis tested in this study is to determine if there is a relationship between type of project monitoring and control technique used by a construction company and project delivery/success. This was tested using regression analysis at a level of significance p = 0.05 and the result is shown in tables 5– 7. H0: there is no relationship existing between type of project monitoring and control technique used by a construction company and project delivery/success. H1: there is a relationship existing between type of project monitoring and control technique used by a construction company and project delivery/success. From Table 5, the R value = 0.839 for project monitoring and control technique represents the simple correlation which indicates a normal degree of correlation between project delivery/success and the types of project monitoring and control techniques used in the study area. R Square value = 0.703 shows project delivery/success is affected by 70.3% of the project monitoring and control techniques used in the study area. Table 6 shows that p = 0.037 which is less than 0.05. This implies that the project monitoring and control techniques regression model predicts project delivery/success significantly. Thus, we reject the null hypothesis H0 and accept the alternate H1 which states that „there is a relationship existing between type of project monitoring and control technique used by a construction company and project delivery/success.‟ and it can be predicted by the regression formula below from the coefficients in Table 7. Y = 5.82 + 2.549X1 Where Y = Project delivery/success and X1 = Project monitoring and control techniques.
  • 7. www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962 183 Copyright © 2018. IJEMR. All Rights Reserved. V. CONCLUSION AND RECOMMENDATION This study assessed the project monitoring and control techniques used by Ondo State Agency for Road Maintenance and Construction (OSARMCO). The result of the assessment conducted to identify the monitoring and control techniques used in the study area and their effects on project delivery revealed that the major techniques used are Program Evaluation and Review Technique (PERT) for time/schedule control and Earned Value Management (EVM) for cost control, and that these techniques aid in timely delivery of projects and mitigate against cost overruns. Also, the result of the assessment carried out to establish the value of project monitoring and control to the project execution of the construction company in the study area revealed that the project management process is indeed fundamental and indispensable to project execution and success. Finally, the result of the test conducted to assess the relationship between the type of project monitoring and control technique used by a construction company and project delivery/success revealed that there is indeed a critical relationship existing between type of project monitoring and control technique used by a construction company and project delivery/success. Based on the findings of this study, it is therefore recommended that construction companies should have or establish monitoring and control departments/units within their companies as this is essential and integral to the successful execution and delivery of projects and qualified and well-trained persons/professionals should be put in charge of handling the project monitoring and control departments/units of construction companies and the techniques and tools used therein. In addition, it is recommended that construction companies should adopt the use of Program Evaluation and Review Technique (PERT) and Earned Value Management (EVM) along with other effective monitoring and control techniques or tools for monitoring and controlling their projects as they have been proven effective in this study. Finally, it is recommended that particular attention and emphasis should be given to controlling „cost‟ as it is a very delicate and volatile aspect of every construction project. REFERENCES [1] Agwu, M.O. (2014). Perception survey of poor construction supervision and building failures in six major cities in Nigeria. British Journal of Education, Society &Behavioural Science, 4(4), 450-472. [2] Al-Jibouri, S.H. (2003). Monitoring systems and their effectiveness for project cost control in construction. International Journal of Project Management, 21, 145-154. [3] Anyanwu, C.I. (2013). Project cost control in the nigerian construction industry. International Journal of Engineering Science Invention, 2(12), 65-71. [4] Atalla, M.M. (1996). Project control techniques reconstruction of occupied buildings. National Library of Canada. Available at: https://uwspace.uwaterloo.ca/bitstream/handle/10012/22/ mq21531.pdf. [5] Baccarini, D. (1996). The concept of project complexity − A Review. International Journal of Project Management, 14(4), 201-204 [6] Badom, L.N. (2016). Project monitoring and evaluation: A critical factor in budget implementation, infrastructure development and sustainability. Nigerian Institute of Quantity Surveyors’ National Workshop with the Theme: “Budgeting and Capital Project Monitoring and Evaluation in an Era of Change”. Rivers State University of Science and Technology, Available at: http://niqs.org.ng/wp-content/uploads/2016/07/LUCKY- BADOM-PRESENTATION-FOR-NIQS-WORKSHOP- IN-MAKURDI.pdf. [7] Callistus, T. & Clinton, A. (2016). Evaluating barriers to effective implementation of project monitoring and evaluation in the Ghanaian construction industry. Creative Construction Conference, 164, 389- 394. Available at: https://ac.els- cdn.com/S1877705816339765/1-s2.0- S1877705816339765-main.pdf?_tid=41ba9852-c9d6- 49cb-8005- 88c5b9ec888b&acdnat=1541312607_56798090b739b40 c5f1878c13afdec86. [8] Diugwu, I.A., Mohammed, M., & Baba, D.L. (2015). Towards effective infrastructure development in nigeria: Theoretical considerations from a project management perspective. American Journal of Industrial and Business Management, 5, 172-180. [9] Gerver, M. (2015). Project monitoring and control. COST and VALUE, 22-26. Available at: https://www.dace.nl/download/?id=17691168. [10] Guo-li, Y. (2010). Project time and budget monitor and control. Journal of Management Science and Engineering, 4(1), 56-61. [10] Hazir, O. (2014). A review of analytical models, approaches and decision support tools in project monitoring and control. International Journal of Project Management, 33(4), 808-815. [11] Inuwa, I.I. & Kunya, S.U. (2015). Project management theory exploration for indigenous contractors‟ project planning in Nigeria. International Journal of Applied Science and Technology, 5(3), 60-72. [12] Idoro, I. I. (2012). Influence of the monitoring and control strategies of indigenous and expatriate Nigerian contractors on project outcome. Journal of Construction in Developing Countries, 17(1), 49-67. [13] Jack, L., Okeke, O.C., Okechukwu, S.I., & Akinola, A.O. (2016). Project management: A system approach to planning, implementation, monitoring and evaluation. International Journal of Advanced Academic Research, 2(11), 65-79. [14] Kenley, R. & Harfield, T. (2015). Construction Project Control Methodologies and Productivity Improvement: EVM, BIM, LBM. Proceedings of the 6th
  • 8. www.ijemr.net ISSN (ONLINE): 2250-0758, ISSN (PRINT): 2394-6962 184 Copyright © 2018. IJEMR. All Rights Reserved. International Conference on Engineering, Project and Production Management, 57-66. [15] Kostalova, J., Tetrevova, L., & Svedik, J. (2015). Support of project management methods by project management information system. 4th International Conference on Leadership, Technology, Innovation and Business Management. University of Pardubice, Pardubice, Czech Republic. DOI: 10.1016/j.sbspro.2015.11.333 [16] Mackenzie, D.I. (2010). A review of project controls in the UK & methodologies to improve the processes. Teesside University's Research Repository. Available at: https://core.ac.uk/download/pdf/9440123.pdf. [17] Marle, F. & Vidal, L. (2016). Managing complex, high risk projects. London: Springer-Verlag. 53-74. [18] Memon, Z., Abd. Majid, M.Z., & Mustaffar, M. (2006). A systematic approach for monitoring and evaluating the construction project progress. Journal of the Institution of Engineers, Malaysia, 67(3), 26-32. [19] Ogunde, A.O., Olaolu, O., Afolabi, A., Owolabi, J., & Ojelabi R. (2017). Challenges confronting construction project management system for sustainable construction in developing countries: Professionals perspectives (A case study of Nigeria). Journal of Building Performance, 8(1), 1-11. [20] Shanmuganathan, N. & Baskar, G. (2016). Effective cost and time management techniques in construction industry. International Journal of Advanced Engineering Technology, 7(2), 743-747. [21] Tom, A.F. & Paul, S. (2013). Project monitoring and control using primavera. International Journal of Innovative Research in Science, Engineering and Technology, 2(3), 762-771.