Development of Materials
Requirements Planning (MRP)
in Microsoft Excel
SUPERVISED BY
Md. Saiful Islam
Assistant Professor
Department of Industrial
Engineering and Management
SUBMITTED BY
MD. AKIBUL ISLAM
Roll: 1411018
MD. MANOARUL AMIN HAWLIDER
Roll: 1411031
Khulna University of Engineering & Technology
Why MRP?
• To guarantee material availability
• Optimizing service level
• Minimizing cost
Block Diagram of MRP System
Master Production
Schedule (MPS)
Bill of Material
(BOM)
Inventory Data
Purchase Order
Materials Plan
Works Order
Input OutputProcessing
MRP Processing
Gross Requirements
Schedule Receipts
Projected On Hand
Net Requirements
Planned-Order Receipts
Planned-Order Releases
Ordering Technique of MRP
Two types of ordering techniques that
we have developed in the MRP system.
• Lot – for – lot ordering
• Lot-size ordering
Presentation on the MRP system that we
have developed
The whole system has been
developed in Microsoft Excel
by using VBA.
1. The maximum number of delivery week is 100.
2. The program is done for wooden shops only. Though the
other products MRP can be planned by following this program.
3. Only two types of lot sizing is used on that system.
4. Calculation of program for MRP uses a few times.
5. In master production schedule, One data can be given at a
time.
Limitations
An inventory management system becomes
costly for the computer functioning calculation.
The Microsoft excel is very common one that is
used in the normal days. As the program is
completely done in excel, this can be used in
every official or non-official production farms in
the world. The most tempted part is using and
unmistakable data giving that makes the program
more user friendly. With a simple knowledge in
excel, anyone can operate the system on their own
hands.
Conclusion
Development of MRP in Microsoft Excel

Development of MRP in Microsoft Excel

  • 1.
    Development of Materials RequirementsPlanning (MRP) in Microsoft Excel SUPERVISED BY Md. Saiful Islam Assistant Professor Department of Industrial Engineering and Management SUBMITTED BY MD. AKIBUL ISLAM Roll: 1411018 MD. MANOARUL AMIN HAWLIDER Roll: 1411031 Khulna University of Engineering & Technology
  • 2.
    Why MRP? • Toguarantee material availability • Optimizing service level • Minimizing cost
  • 3.
    Block Diagram ofMRP System Master Production Schedule (MPS) Bill of Material (BOM) Inventory Data Purchase Order Materials Plan Works Order Input OutputProcessing
  • 4.
    MRP Processing Gross Requirements ScheduleReceipts Projected On Hand Net Requirements Planned-Order Receipts Planned-Order Releases
  • 5.
    Ordering Technique ofMRP Two types of ordering techniques that we have developed in the MRP system. • Lot – for – lot ordering • Lot-size ordering
  • 6.
    Presentation on theMRP system that we have developed
  • 7.
    The whole systemhas been developed in Microsoft Excel by using VBA.
  • 15.
    1. The maximumnumber of delivery week is 100. 2. The program is done for wooden shops only. Though the other products MRP can be planned by following this program. 3. Only two types of lot sizing is used on that system. 4. Calculation of program for MRP uses a few times. 5. In master production schedule, One data can be given at a time. Limitations
  • 16.
    An inventory managementsystem becomes costly for the computer functioning calculation. The Microsoft excel is very common one that is used in the normal days. As the program is completely done in excel, this can be used in every official or non-official production farms in the world. The most tempted part is using and unmistakable data giving that makes the program more user friendly. With a simple knowledge in excel, anyone can operate the system on their own hands. Conclusion