SlideShare a Scribd company logo
DETERMINING COSTS OF
CONSTRUCTION ERRORS, BASED ON
FUZZY LOGIC SYSTEMS
Presentation Date : 16/11/2018
Authors:
M.Sc. Civil Eng. M. Lemar ZALMAI
Assist. Prof. Dr. Cemil AKÇAY
Prof. Dr. Ekrem MANİSALI
1
Contents
 Introduction
 Research Question
 Construction Project Life Cycle
 Fuzzy Expert Systems
 Case Study
 Discussion and Conclusion
2
M. L. Zalmai, C. Akçay, E. Manisalı
Introduction
3
In construction projects, construction errors affect negatively to the
production, that influences the overall of the project in both time and budget.
Generally, construction companies could not estimate this kind of errors
during the bidding process. In this case, these companies did not consider
important issues on the budget of the contract, and in the contracting period,
project participants assumed that the project would be executed as it
scheduled and designed. During the project, different construction processes’
costs are higher than estimated values due to construction errors.
M. L. Zalmai, C. Akçay, E. Manisalı
4
The errors that were recognized during the construction process cause
time and financial losses, on the other hand, the errors that were
noticed after the project’s termination cause repair and correction costs.
Moreover, the company may gain a bad reputation in the sector.
The key points of this study are to analyze project costs by considering
construction errors and re-construction costs due to labor errors by
using fuzzy interpretation mechanism. This methodology is applied to a
residential construction project. With using of this methodology,
forthcoming extra costs related to construction errors can be
estimated. And some precautions can be taken for further legal
conflicts between parties.
M. L. Zalmai, C. Akçay, E. Manisalı
Construction projects' life cycle
5Figure 1: Representative construction project life cycle (PBOK Guide, 2004)
Construction projects' life cycle
6
The Construction projects' life cycle is shown in the figure as above; this
process starts with the feasibility and will be continuing with designing
and planning. For the construction firms, most of the errors are
happened in the production process and the main construction's contract
affected in both time and financial issues.
The intent of this study is to remove the error from the estimated budget
and finding the most important factors to achieve the project in expected
duration as well as control the technical staff during the project activities.
M. L. Zalmai, C. Akçay, E. Manisalı
Fuzzy Expert Systems
7
A fuzzy expert system is comprised of fuzzy membership functions
and rules. It contains four main parts: fuzzification, inference,
composition, and defuzzification
Figure 2: Architecture of a fuzzy expert system
M. L. Zalmai, C. Akçay, E. Manisalı
Fuzzy Expert Systems
8
The fuzzification process transforms the crisp input into a fuzzy input
set. The inference process uses the fuzzy input set to determine the
fuzzy output set using rules formulated in the knowledge base and the
membership functions.
The composition process aggregates all output fuzzy sets into a single
fuzzy set. Finally, the defuzzification process calculates a crisp output
using the fuzzy set produced by the composition process.
M. L. Zalmai, C. Akçay, E. Manisalı
Case Study
9
1. Fuzzification
a. Project Duration
The average standard duration of the residential construction projects is 18 months.
The completion of the project period less than 10 months and more than 28 months
will be out of assessment, it will be related to the abnormal condition. Among this
interval, duration has obscured and defined in the table below:
M. L. Zalmai, C. Akçay, E. Manisalı
10
b. Technical Staff Ratio:
The numbers of manufacturing controller staff should be converted to a
common control ratio because the numbers of manufacturing controller staff
are different according to the project's size. The Controller staff per
construction m2 will be a correct approach. In a housing project with a
total construction area of 50,000 m2, 20 technical staff is considered within
normal standards. With this approach, the manufacturing controller technical
staffs per construction m2 data are illustrating as follows:
11
c. Error Cost Ratio:
The error cost ratio is the construction direct cost or the construction
incorrect cost. This ratio is reflected according to the company's
experiences as follows;
M. L. Zalmai, C. Akçay, E. Manisalı
12
2. Rule Case
The base on experiences of previous projects, tow rules were created
in the following manners:
a. If the project duration is short and technical staff ratio is low, then
the error cost is high.
b. If the project duration is short and technical staff ratio is normal,
then the error cost is normal.
M. L. Zalmai, C. Akçay, E. Manisalı
13
3. Fuzzy Interpretation
In this study, under the rules described above, the fuzzy interpretation
of a project with a project duration of 17 months and a technical staff
ratio of 3.6x10-4 will be done.
Integration process according to Mamdani interpretation;
14
4. Defuzzification
There are different types of defuzzifiers. The two popular techniques used for
defuzzification process are called Mamdani inference method and Center of
Gravity method modeling. (Yeng, 2000). In this study, the Center of Gravity
method modeling has been used.
The final step in this study, the defuzzification process of results which was
obtained according to the fuzzy rule base that created before. the following
method was preferred due to the symmetrical output values. With this method
has been found as follows;
15
These results found the indicates that the error costs rate of a project
which the construction company wants to show the realization in the 17
months with 3.6x10-4 technical staff ratio, the project direct cost will be
0.75 percent. According to the past data and defined the rules, for a
project with a direct cost of 100.000.000 TL. the error cost will be
750.000 TL.
Results:
M. L. Zalmai, C. Akçay, E. Manisalı
Conclusions
In this study, a fuzzy rule-based model was established based on a
construction company's experience and the company’s previous project
data including error cost rates, project durations and technical staff
ratio over total employee number in each project. The error cost of the
as-planned project is calculated by using the Mamdani Fuzzy
interpretation mechanism with this rule base and data.
16
M. L. Zalmai, C. Akçay, E. Manisalı
Conclusions
Also, besides the possibility of estimating error costs by using technical
staff rates before the project, contractors can organize their technical
staff number to adjust error cost rates and project durations.
In this study, a generic methodology is proposed that different kind of
risk factors such as occupational health safety, accident rates, and
budget variance rates can be estimated by using previous data and
expert opinion.
17
M. L. Zalmai, C. Akçay, E. Manisalı
References
 A. Schwartz, H. Do. (2013). A fuzzy expert system for cost-effective regression testing strategies.
Proceedings of the 29th IEEE International Conference on Sofware Maintenance (ICSM), September, pp. 1-10.
 E. H. Mamdani, S. Assilian. (1975). An experiment in linguistic synthesis with a fuzzy logic controller,
Int. J. Man-Mach. Stud. 1-13.
 Idri, A. and Abran, A. (2001). Towards a fuzzy logic based measures for software projects similarity. 7th
International Symposium on Software Metrics, pp. 85-96, England, UK.
 Simon, D. (2003). Introduction to fuzzy control. Courtesy of Embedded Systems Programming.
http://www.embedded.com/showArticle.jhtml?articleID=10700619.
 Sivanandam, S., Sumathi, S. and Deepa, S. (2007). Introduction to Fuzzy Logic using MATLAB.
Springer-Verlag Berlin Heidelberg.
 Ying, h, (2000). Fuzzy Control and Modeling analytical Foundations and Applications. IEEE Press.
 Z. Xu, K. Gao, T.M. Khoshgoftaar. (2005). Application of fuzzy expert system in test case selection for
system regression test. Proceedings of IEEE International Conference on Information Reuse and Integration, August,
pp. 120-125.
18
M. L. Zalmai, C. Akçay, E. Manisalı
THANK YOU FOR
YOUR PATIENCE
19
MSc. Mohammad Lemar ZALMAI (lemar_zalmai07@hotmail.com)
Yrd. Doç. Dr. Cemil AKÇAY (cakcay@istanbul.edu.tr)
Prof. Dr. Ekrem MANİSALI (ekmanisa@istanbul.edu.tr)
DETERMINING COSTS OF
CONSTRUCTION ERRORS, BASED ON
FUZZY LOGIC SYSTEMS

More Related Content

What's hot

A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
Alexander Decker
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
IAEME Publication
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...
eSAT Journals
 
Review on cost estimation technque for web application [part 1]
Review on cost estimation technque for web application [part 1]Review on cost estimation technque for web application [part 1]
Review on cost estimation technque for web application [part 1]
Sayed Mohsin Reza
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET Journal
 
A NEW HYBRID FOR SOFTWARE COST ESTIMATION USING PARTICLE SWARM OPTIMIZATION A...
A NEW HYBRID FOR SOFTWARE COST ESTIMATION USING PARTICLE SWARM OPTIMIZATION A...A NEW HYBRID FOR SOFTWARE COST ESTIMATION USING PARTICLE SWARM OPTIMIZATION A...
A NEW HYBRID FOR SOFTWARE COST ESTIMATION USING PARTICLE SWARM OPTIMIZATION A...
ieijjournal
 
Ijetr012001
Ijetr012001Ijetr012001
Ijetr012001
ER Publication.org
 
A new model for software costestimation
A new model for software costestimationA new model for software costestimation
A new model for software costestimation
ijfcstjournal
 
Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...
eSAT Journals
 
Time overruns
Time overrunsTime overruns
Time overruns
Bhalchandra Tankkar
 
Numerical analysis historicl devpt
Numerical analysis  historicl devptNumerical analysis  historicl devpt
Numerical analysis historicl devpt
SHAMJITH KM
 
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
IJSRED
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
Oyeniyi Samuel
 
J0313052055
J0313052055J0313052055
J0313052055
theijes
 
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case StudyTime-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
ijceronline
 
Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...
International Journal of Engineering Inventions www.ijeijournal.com
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
IRJET Journal
 
Schwalbe 07 projectcost
Schwalbe 07 projectcostSchwalbe 07 projectcost
Schwalbe 07 projectcost
ProjectManager247
 

What's hot (18)

A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...
 
Review on cost estimation technque for web application [part 1]
Review on cost estimation technque for web application [part 1]Review on cost estimation technque for web application [part 1]
Review on cost estimation technque for web application [part 1]
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
A NEW HYBRID FOR SOFTWARE COST ESTIMATION USING PARTICLE SWARM OPTIMIZATION A...
A NEW HYBRID FOR SOFTWARE COST ESTIMATION USING PARTICLE SWARM OPTIMIZATION A...A NEW HYBRID FOR SOFTWARE COST ESTIMATION USING PARTICLE SWARM OPTIMIZATION A...
A NEW HYBRID FOR SOFTWARE COST ESTIMATION USING PARTICLE SWARM OPTIMIZATION A...
 
Ijetr012001
Ijetr012001Ijetr012001
Ijetr012001
 
A new model for software costestimation
A new model for software costestimationA new model for software costestimation
A new model for software costestimation
 
Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...
 
Time overruns
Time overrunsTime overruns
Time overruns
 
Numerical analysis historicl devpt
Numerical analysis  historicl devptNumerical analysis  historicl devpt
Numerical analysis historicl devpt
 
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
J0313052055
J0313052055J0313052055
J0313052055
 
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case StudyTime-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
 
Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
Schwalbe 07 projectcost
Schwalbe 07 projectcostSchwalbe 07 projectcost
Schwalbe 07 projectcost
 

Similar to Determining Costs of Construction Errors, Based on Fuzzy Logic Systems

An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
Nat Rice
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
IRJET Journal
 
Earned_Value_Method_EVM_for_Construction_Projects_.pdf
Earned_Value_Method_EVM_for_Construction_Projects_.pdfEarned_Value_Method_EVM_for_Construction_Projects_.pdf
Earned_Value_Method_EVM_for_Construction_Projects_.pdf
Shashi Ranjan
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET Journal
 
Cost Effective Methods in Construction Engineering
Cost Effective Methods in Construction EngineeringCost Effective Methods in Construction Engineering
Cost Effective Methods in Construction Engineering
civejjour
 
Cost Effective Methods in Construction Engineering
Cost Effective Methods in Construction EngineeringCost Effective Methods in Construction Engineering
Cost Effective Methods in Construction Engineering
civejjour
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
Newman Jonathan
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET Journal
 
IRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction ProjectsIRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction Projects
IRJET Journal
 
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
IJMIT JOURNAL
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projects
iaemedu
 
B1303020508
B1303020508B1303020508
B1303020508
IOSR Journals
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
IJAEMSJORNAL
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
IJERA Editor
 
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
vickeryr87
 
Earned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of ProjectsEarned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of Projects
Ricardo Viana Vargas
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
IOSR Journals
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
kiebut
 

Similar to Determining Costs of Construction Errors, Based on Fuzzy Logic Systems (20)

An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Earned_Value_Method_EVM_for_Construction_Projects_.pdf
Earned_Value_Method_EVM_for_Construction_Projects_.pdfEarned_Value_Method_EVM_for_Construction_Projects_.pdf
Earned_Value_Method_EVM_for_Construction_Projects_.pdf
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
Cost Effective Methods in Construction Engineering
Cost Effective Methods in Construction EngineeringCost Effective Methods in Construction Engineering
Cost Effective Methods in Construction Engineering
 
Cost Effective Methods in Construction Engineering
Cost Effective Methods in Construction EngineeringCost Effective Methods in Construction Engineering
Cost Effective Methods in Construction Engineering
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction ProjectsIRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction Projects
 
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projects
 
B1303020508
B1303020508B1303020508
B1303020508
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
1Running Head RISK MANAGEMENT PLAN FOR BUILDING A BRIDGE16R.docx
 
Earned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of ProjectsEarned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of Projects
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
 

More from Mohammad Lemar ZALMAİ

Implementation of Building Information Modelling in Turkish Government Sector...
Implementation of Building Information Modelling in Turkish Government Sector...Implementation of Building Information Modelling in Turkish Government Sector...
Implementation of Building Information Modelling in Turkish Government Sector...
Mohammad Lemar ZALMAİ
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Mohammad Lemar ZALMAİ
 
Determining costs of construction errors, based on fuzzy logic systems ipcmc2...
Determining costs of construction errors, based on fuzzy logic systems ipcmc2...Determining costs of construction errors, based on fuzzy logic systems ipcmc2...
Determining costs of construction errors, based on fuzzy logic systems ipcmc2...
Mohammad Lemar ZALMAİ
 
Time cost trade off optimization using harmony search and Monte-Carlo Method
Time cost trade off optimization using harmony search and Monte-Carlo MethodTime cost trade off optimization using harmony search and Monte-Carlo Method
Time cost trade off optimization using harmony search and Monte-Carlo Method
Mohammad Lemar ZALMAİ
 
Implementation of-building-information-modeling-in-turkish-government-sector-...
Implementation of-building-information-modeling-in-turkish-government-sector-...Implementation of-building-information-modeling-in-turkish-government-sector-...
Implementation of-building-information-modeling-in-turkish-government-sector-...
Mohammad Lemar ZALMAİ
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Mohammad Lemar ZALMAİ
 
Yasal (hukuki) yapılarına göre işletmeler
Yasal (hukuki) yapılarına göre işletmelerYasal (hukuki) yapılarına göre işletmeler
Yasal (hukuki) yapılarına göre işletmeler
Mohammad Lemar ZALMAİ
 
WaterCAD Programı Yardımıyla İsale Hattı Tasarımı
WaterCAD Programı Yardımıyla İsale Hattı TasarımıWaterCAD Programı Yardımıyla İsale Hattı Tasarımı
WaterCAD Programı Yardımıyla İsale Hattı Tasarımı
Mohammad Lemar ZALMAİ
 
Time-cost optimization using harmony search algorithm in construction projects
Time-cost optimization using harmony search algorithm in construction projectsTime-cost optimization using harmony search algorithm in construction projects
Time-cost optimization using harmony search algorithm in construction projects
Mohammad Lemar ZALMAİ
 
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Mohammad Lemar ZALMAİ
 
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Mohammad Lemar ZALMAİ
 
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
Mohammad Lemar ZALMAİ
 
AFGANİSTAN'ın kısaca tanıtım sunumu/ briefly introduction of AFGHANISTAN in T...
AFGANİSTAN'ın kısaca tanıtım sunumu/ briefly introduction of AFGHANISTAN in T...AFGANİSTAN'ın kısaca tanıtım sunumu/ briefly introduction of AFGHANISTAN in T...
AFGANİSTAN'ın kısaca tanıtım sunumu/ briefly introduction of AFGHANISTAN in T...
Mohammad Lemar ZALMAİ
 

More from Mohammad Lemar ZALMAİ (13)

Implementation of Building Information Modelling in Turkish Government Sector...
Implementation of Building Information Modelling in Turkish Government Sector...Implementation of Building Information Modelling in Turkish Government Sector...
Implementation of Building Information Modelling in Turkish Government Sector...
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
Determining costs of construction errors, based on fuzzy logic systems ipcmc2...
Determining costs of construction errors, based on fuzzy logic systems ipcmc2...Determining costs of construction errors, based on fuzzy logic systems ipcmc2...
Determining costs of construction errors, based on fuzzy logic systems ipcmc2...
 
Time cost trade off optimization using harmony search and Monte-Carlo Method
Time cost trade off optimization using harmony search and Monte-Carlo MethodTime cost trade off optimization using harmony search and Monte-Carlo Method
Time cost trade off optimization using harmony search and Monte-Carlo Method
 
Implementation of-building-information-modeling-in-turkish-government-sector-...
Implementation of-building-information-modeling-in-turkish-government-sector-...Implementation of-building-information-modeling-in-turkish-government-sector-...
Implementation of-building-information-modeling-in-turkish-government-sector-...
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
Yasal (hukuki) yapılarına göre işletmeler
Yasal (hukuki) yapılarına göre işletmelerYasal (hukuki) yapılarına göre işletmeler
Yasal (hukuki) yapılarına göre işletmeler
 
WaterCAD Programı Yardımıyla İsale Hattı Tasarımı
WaterCAD Programı Yardımıyla İsale Hattı TasarımıWaterCAD Programı Yardımıyla İsale Hattı Tasarımı
WaterCAD Programı Yardımıyla İsale Hattı Tasarımı
 
Time-cost optimization using harmony search algorithm in construction projects
Time-cost optimization using harmony search algorithm in construction projectsTime-cost optimization using harmony search algorithm in construction projects
Time-cost optimization using harmony search algorithm in construction projects
 
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
 
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
Bir Kamu İnşaat Projesinde CPM Uygulamamasından Dolayı Ortaya Çıkan Problemle...
 
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
 
AFGANİSTAN'ın kısaca tanıtım sunumu/ briefly introduction of AFGHANISTAN in T...
AFGANİSTAN'ın kısaca tanıtım sunumu/ briefly introduction of AFGHANISTAN in T...AFGANİSTAN'ın kısaca tanıtım sunumu/ briefly introduction of AFGHANISTAN in T...
AFGANİSTAN'ın kısaca tanıtım sunumu/ briefly introduction of AFGHANISTAN in T...
 

Recently uploaded

Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 

Recently uploaded (20)

Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 

Determining Costs of Construction Errors, Based on Fuzzy Logic Systems

  • 1. DETERMINING COSTS OF CONSTRUCTION ERRORS, BASED ON FUZZY LOGIC SYSTEMS Presentation Date : 16/11/2018 Authors: M.Sc. Civil Eng. M. Lemar ZALMAI Assist. Prof. Dr. Cemil AKÇAY Prof. Dr. Ekrem MANİSALI 1
  • 2. Contents  Introduction  Research Question  Construction Project Life Cycle  Fuzzy Expert Systems  Case Study  Discussion and Conclusion 2 M. L. Zalmai, C. Akçay, E. Manisalı
  • 3. Introduction 3 In construction projects, construction errors affect negatively to the production, that influences the overall of the project in both time and budget. Generally, construction companies could not estimate this kind of errors during the bidding process. In this case, these companies did not consider important issues on the budget of the contract, and in the contracting period, project participants assumed that the project would be executed as it scheduled and designed. During the project, different construction processes’ costs are higher than estimated values due to construction errors. M. L. Zalmai, C. Akçay, E. Manisalı
  • 4. 4 The errors that were recognized during the construction process cause time and financial losses, on the other hand, the errors that were noticed after the project’s termination cause repair and correction costs. Moreover, the company may gain a bad reputation in the sector. The key points of this study are to analyze project costs by considering construction errors and re-construction costs due to labor errors by using fuzzy interpretation mechanism. This methodology is applied to a residential construction project. With using of this methodology, forthcoming extra costs related to construction errors can be estimated. And some precautions can be taken for further legal conflicts between parties. M. L. Zalmai, C. Akçay, E. Manisalı
  • 5. Construction projects' life cycle 5Figure 1: Representative construction project life cycle (PBOK Guide, 2004)
  • 6. Construction projects' life cycle 6 The Construction projects' life cycle is shown in the figure as above; this process starts with the feasibility and will be continuing with designing and planning. For the construction firms, most of the errors are happened in the production process and the main construction's contract affected in both time and financial issues. The intent of this study is to remove the error from the estimated budget and finding the most important factors to achieve the project in expected duration as well as control the technical staff during the project activities. M. L. Zalmai, C. Akçay, E. Manisalı
  • 7. Fuzzy Expert Systems 7 A fuzzy expert system is comprised of fuzzy membership functions and rules. It contains four main parts: fuzzification, inference, composition, and defuzzification Figure 2: Architecture of a fuzzy expert system M. L. Zalmai, C. Akçay, E. Manisalı
  • 8. Fuzzy Expert Systems 8 The fuzzification process transforms the crisp input into a fuzzy input set. The inference process uses the fuzzy input set to determine the fuzzy output set using rules formulated in the knowledge base and the membership functions. The composition process aggregates all output fuzzy sets into a single fuzzy set. Finally, the defuzzification process calculates a crisp output using the fuzzy set produced by the composition process. M. L. Zalmai, C. Akçay, E. Manisalı
  • 9. Case Study 9 1. Fuzzification a. Project Duration The average standard duration of the residential construction projects is 18 months. The completion of the project period less than 10 months and more than 28 months will be out of assessment, it will be related to the abnormal condition. Among this interval, duration has obscured and defined in the table below: M. L. Zalmai, C. Akçay, E. Manisalı
  • 10. 10 b. Technical Staff Ratio: The numbers of manufacturing controller staff should be converted to a common control ratio because the numbers of manufacturing controller staff are different according to the project's size. The Controller staff per construction m2 will be a correct approach. In a housing project with a total construction area of 50,000 m2, 20 technical staff is considered within normal standards. With this approach, the manufacturing controller technical staffs per construction m2 data are illustrating as follows:
  • 11. 11 c. Error Cost Ratio: The error cost ratio is the construction direct cost or the construction incorrect cost. This ratio is reflected according to the company's experiences as follows; M. L. Zalmai, C. Akçay, E. Manisalı
  • 12. 12 2. Rule Case The base on experiences of previous projects, tow rules were created in the following manners: a. If the project duration is short and technical staff ratio is low, then the error cost is high. b. If the project duration is short and technical staff ratio is normal, then the error cost is normal. M. L. Zalmai, C. Akçay, E. Manisalı
  • 13. 13 3. Fuzzy Interpretation In this study, under the rules described above, the fuzzy interpretation of a project with a project duration of 17 months and a technical staff ratio of 3.6x10-4 will be done. Integration process according to Mamdani interpretation;
  • 14. 14 4. Defuzzification There are different types of defuzzifiers. The two popular techniques used for defuzzification process are called Mamdani inference method and Center of Gravity method modeling. (Yeng, 2000). In this study, the Center of Gravity method modeling has been used. The final step in this study, the defuzzification process of results which was obtained according to the fuzzy rule base that created before. the following method was preferred due to the symmetrical output values. With this method has been found as follows;
  • 15. 15 These results found the indicates that the error costs rate of a project which the construction company wants to show the realization in the 17 months with 3.6x10-4 technical staff ratio, the project direct cost will be 0.75 percent. According to the past data and defined the rules, for a project with a direct cost of 100.000.000 TL. the error cost will be 750.000 TL. Results: M. L. Zalmai, C. Akçay, E. Manisalı
  • 16. Conclusions In this study, a fuzzy rule-based model was established based on a construction company's experience and the company’s previous project data including error cost rates, project durations and technical staff ratio over total employee number in each project. The error cost of the as-planned project is calculated by using the Mamdani Fuzzy interpretation mechanism with this rule base and data. 16 M. L. Zalmai, C. Akçay, E. Manisalı
  • 17. Conclusions Also, besides the possibility of estimating error costs by using technical staff rates before the project, contractors can organize their technical staff number to adjust error cost rates and project durations. In this study, a generic methodology is proposed that different kind of risk factors such as occupational health safety, accident rates, and budget variance rates can be estimated by using previous data and expert opinion. 17 M. L. Zalmai, C. Akçay, E. Manisalı
  • 18. References  A. Schwartz, H. Do. (2013). A fuzzy expert system for cost-effective regression testing strategies. Proceedings of the 29th IEEE International Conference on Sofware Maintenance (ICSM), September, pp. 1-10.  E. H. Mamdani, S. Assilian. (1975). An experiment in linguistic synthesis with a fuzzy logic controller, Int. J. Man-Mach. Stud. 1-13.  Idri, A. and Abran, A. (2001). Towards a fuzzy logic based measures for software projects similarity. 7th International Symposium on Software Metrics, pp. 85-96, England, UK.  Simon, D. (2003). Introduction to fuzzy control. Courtesy of Embedded Systems Programming. http://www.embedded.com/showArticle.jhtml?articleID=10700619.  Sivanandam, S., Sumathi, S. and Deepa, S. (2007). Introduction to Fuzzy Logic using MATLAB. Springer-Verlag Berlin Heidelberg.  Ying, h, (2000). Fuzzy Control and Modeling analytical Foundations and Applications. IEEE Press.  Z. Xu, K. Gao, T.M. Khoshgoftaar. (2005). Application of fuzzy expert system in test case selection for system regression test. Proceedings of IEEE International Conference on Information Reuse and Integration, August, pp. 120-125. 18 M. L. Zalmai, C. Akçay, E. Manisalı
  • 19. THANK YOU FOR YOUR PATIENCE 19 MSc. Mohammad Lemar ZALMAI (lemar_zalmai07@hotmail.com) Yrd. Doç. Dr. Cemil AKÇAY (cakcay@istanbul.edu.tr) Prof. Dr. Ekrem MANİSALI (ekmanisa@istanbul.edu.tr) DETERMINING COSTS OF CONSTRUCTION ERRORS, BASED ON FUZZY LOGIC SYSTEMS