Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023
DOI:10.5121/civej.2023.10301 1
COST EFFECTIVE METHODS IN CONSTRUCTION
ENGINEERING
Tatapudi Gopikrishna Vasista1
and Manohar Prasad Jakhanwal2
1
Department of Civil Engineering, Sri Venkateswara College of Engineering
& Technology, Chittor
2
Former, Vice-Chancellor, AP Goyal Shimla University, Muzaffarpur, Shimla (HP) India
ABSTRACT
The economic impact of construction cost overrun is a possible loss of the economic justification for the
project. The financial impact of a cost overrun results in demand for construction investment credits.
Therefore reliable estimates of construction cost are an important aspect to the contemporary construction
companies especially during the conceptual phase of lifecycle management. In this paper a cost-effective
analysis is done using one of the cost effective construction technique called Rat Trap Bond versus Flemish
bond and when estimated with CPWD 2012 schedule of rates it is proved that Low cost techniques such as
rat trap bond provides better cost effectiveness as compared to conventional Flemish bond construction
method.
KEYWORDS
Cost effective construction, Low cost construction methods, Conceptual Phase construction estimation,
Construction cost estimating, comparative estimation analysis
1. INTRODUCTION
In the construction projects, cost and time are the main aspects to be considered in the project
management. It is a challenging task for the Project managers to evaluate the plan, take corrective
actions and constantly measuring progress (Rajguru and Mahatme, 2016). Overcoming the delay
of construction, reducing the time and cost will help obtaining the cost effectiveness (Subramani,
Lishitha and Kavitha, 2014). The economic impact of a construction cost overrun is the possible
loss of the economic justification for the project. The financial impact of a cost overrun results in
demand for construction investment credits. Therefore reliable estimates of construction cost and
schedules are important aspects to contemporary construction companies (Stasiak-Betlejewska
and Potkany, 2015). Effective cost and time management play an important role to achieve
project success in the construction industry. Various cost and time management techniques help
to control cost and time overrun in the construction industry (Shanmuganathan and Baskar,
2016).
Cost effectiveness studies and research encompasses methods that determine the cost of
construction, which could consider the involvement of more competing technologies and
interventions too (Young, Kelly and Holloway, 2013).
Cost-effectiveness analysis is a technique to compare strategies intended to produce the same
effect. In its most common form, a new strategy is compared with current practice and in is
given the equation form as follows (Azimi and Welch, 1998):
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023
2
Cost-Effectiveness ratio = (Cost of New strategy – Cost of current practice) / (Effect of new
strategy – Effect of current practice)
2. CONSTRUCTION COST ESTIMATING
The purpose of estimating is to determine the forecasting costs required to complete a project in
accordance with the contract plan and specifications. The estimator can Conceptual estimate as
the name suggests are generally made during the initial stages of a project. It helps reveal whether
a project is economically feasible. Once the decision has been made then the estimates may be
refined into a detailed design phase. It produces and estimates with reasonable accuracy of
providing total costs for a given project (Deshpande, 1999).
The conceptual phase is of strategic importance in the project environment (Abdul-Kadir and
Price, 1995). The lifecycle of a construction project includes the conceptual phase, planning and
design procurement, construction, operation and maintenance (Ozorhon, Abbott and Aouad ,
2016). In the conceptual phase, cost estimate with a reasonable accuracy is required within a
limited time period. Various estimation methods for the conceptual phase have been proposed
earlier such as simple square foot method, regression analysis, probabilistic estimating, new
network, case-based reasoning and fuzzy models etc. In this conceptual phase, cost estimators
commonly use analogy-based estimating methods, i.e. an estimator selects a similar one from the
past projects and adjusts it based on similarities and differences perceived by the estimator, which
also depends on the individual experience or perception. A simple square foot or assembly costs
method are also preferred by many cost estimators in the conceptual phase. However when
historical data is not available it could lead to estimator’s bias which would estimate under
budget or over budget. Therefore estimators usually desire to have their estimates compared with
the actual costs of past similar projects. Then they prepare a list of quantities and costs in the
form of cost breakdown structure. For example, a building is decomposed into work elements
whereas unit cost of each element can be assessed and the total cost is the sum of the products of
the quantities multiplied by their corresponding unit costs (Kim and Seo, 2011).
3. COST EFFECTIVE BUILDING MATERIALS AND TECHNIQUES
Cost effective building materials has taken off by many builders for new home owners.
Construction of low cost housing by using the low cost building materials increases the access to
building by low income group people. Low cost housing can be achieved by using low cost
materials, economical construction technologies and use of alternate methods of building
construction, The profit gained from using such methods can decrease the cost of construction
make the low cost housing accessible to all. The use of low cost alternate building materials also
prevents the rise of construction due to use of scarce building materials. In the proposed research,
the project involves the use of conventional building materials and then determines the total cost
reduced by using alternative building construction techniques (Singh and Kumar, 2016).
Affordable housing is possible mainly by dealing with effective costing and following sustainable
building techniques, which helps in reducing the cost of construction without sacrificing the
strength durability and performance. For example, a residential building can be divided into two
parts viz. structural and non-structural. As the cost of cement takes major part of total building
cost, it can be partially replaced by cement with 30%, 40% and 50% for structural elements.
When strength tests such as compressive, split test, flexural test have been calculated, the 40%
replacement of fly ash gave required strength for single storey building. For non-structural
elements, the low cost materials such as concrete frames, hollow concrete blocks etc can be
adopted. It can be concluded that the overall cost can be reduced up to 30% using these
construction methods as compared to conventional building cost. It is also found that about
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023
3
26.11% and 22.68% of building cost can be saved with low cost housing technologies as
compared to traditional construction methods (Tam, 2011).
Previous research on low cost housing techniques include: Tam et al. (2011) and Sinha, Mihsra,
Kumar & Saurabh (2020) in passing. However, the following are some of the low cost
techniques discussed by Dharma Raja (2009):
(i) Hollow concrete blocks: Empty solid pieces by and large are made of size 40x20x20cm and
will cover a volume of around 11 national blazed blocks. The cost reserve funds are on three
checks prompting to around 23% sparing in cost. (ii) With Soil cement blocks there will be a
sparing cost of 28%. (iii) With concrete door and window frames using M20 concrete, it is
assessed that the cost diminishment for solid casing will be no less than 31%. (iv) Filler slabs
when opted for Rooftops and middle of the road floors, it lessen the undesirable dead heap
material.
Other cost effective construction techniques include, rat trap bond with 20 percent cost reduction,
filler slab roofing with 20 percent reduction, brick on edge lintels with 50% cost reduction and
precast sunshades with 10 percent reduction of cost.
4. METHODOLOGY, HYPOTHESIS AND ITS TESTING
The primary function of approximate estimating is to produce a forecast of the future project,
before the building has been designed in detail and contract particulars prepared. Estimators have
the responsibility of the challenging role of basing the most important business decisions when
there is still very little information is available.
The first step is the definition of a general work breakdown structure (WBS) able to properly
account for and compare the construction costs of the company projects. Though there are several
estimations are done as indicated earlier about different low cost techniques applied at different
types of building elements, only one case is presented here in this paper. In the academy,
acceptable margins range from + or – 10% to + or – 5%, regardless of the level of detail of the
projects and despite the information that can be available (Bettini, Longo, Alcoforado and Maia,
2016). According to Halpin (2004), still in the preliminary phases of design, an error up to 10%
would be totally acceptable. But for a fully detailed estimate the percentage of error of any
estimation will never be less than 5% (Limmer, 1997).
4.1. Hypothesis Declaration
H01= Rat Trap Bond construction techniques is more cost effective than Flemish Bond
construction technique.
H02 = Filler Slab construction technique is more cost effective than convention R. C. C slab.
4.2. Hypothesis Testing
4.2.1.Rat Trap Bond Vs. Flemish Bond:
A comparison of two techniques such as rat trap bond and Flemish bond cost estimation is
done to show that Rat trap bond provides more cost effective than Flemish bond cost in a tabular
format considering one cubic meter volume of brick work.
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023
4
(i) Brick work of 23 cm thickness in Rat trap bond using 1:6 cement mortars with cut bricks for
the super structure (Rat trap bond method).
Table 1. Estimation of Rat Trap bond for 1m3
brick work
Fig.1: Rat Trap Bond vs. Flemish Bond, (Source: Google Search Image)
ii) Brick work with 23cm thick Flemish bond using 1:6 cement mortars with wire cut bricks for
the super structure (conventional method).
Table 2. Estimation of Flemish bond for 1m3
brick work
The difference in rate comes to 141/m3
(5495-5354). An average of 38m3
of brickwork will be
required for a 100m2
plinth area of building. For a total of 10000m2
of plinth the saving comes to
(0.38 x 141 x 10000) = Rs. 5, 35, 800/-; Where it is seen clearly 5354/ m3
< 5495/m3
Sl. No. Item Qty Unit Rate Amount
1. Bricks 420 No. s 8 3360.00
2. Sand 0.2 m3
2777 555.40
3. Cement 44 Kg 5.94 261.36
4. Brick Mason 1.5 Nos 471 706.50
5. Man 0.75 Nos 377 282.75
6. Woman 0.2 Nos 377 75.40
7. Scaffolding 6.25
8. Add 10% of Labor
For the super structure
106.47
Total 5354.13
Sl. No. Item Qty Unit Rate Amount
1. Bricks 460 No. s 8 3680.00
2. Sand 0.24 m3
2777 666.48
3. Cement 58 Kg 5.94 344.52
4. Brick Mason 0.7 Nos 471 329.70
5. Man 1 Nos 377 131.95
6. Woman 1 Nos 377 263.90
7. Scaffolding 6.25
8. Add 10% of Labor
For the super structure
72.55
Total 5495.35
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023
5
Note: The data for the Rat Trap bond is estimated based on the CPWD-Delhi schedule of rates
during the year 2021 and the rates of materials and labour are taken from the CPWD-Delhi
schedule of rates during the year 2021.
4.2.2.Filler Slab Vs. R. C. C Slab:
People look for attractive houses, more environmental friendly and cheaper but also want more
life span and to have roofs over larger space areas (e.g. Halls in houses). Using cost-effective
technology not only saves money but also reduce CO2emissions. When filler slab can be used as
an alternative to conventional slab, the cost of construction can reduce up to 25% (Srivastava &
Kumar, 2018). The basic principle in a filler slab is that the concrete in the bottom half of the
RCC slab is simply considered dead weight and does not take up any compressive loads, but the
RCC slab takes up such load. Thus filler in the redundant concrete in tension zone of the slab can
be replaced by a suitable lightweight filler material (Sinha, Mishra, Kumar & Saurabh, 2020).
Filler slab consists of light weight modest material such as poor quality Mangalore tiles, blocks,
coconut shells, glass bottles and so forth. These materials are laid in the steel reinforcement
framework (bars of 6mm or 8mm dia.) and cementing is done over them. The Mangalore tiles of
size of 23cm x 40 cm and the network size of 33cm x50 cm can be used in the section thickness
of 10cm. In specific, RCC filler space of 1:1.5:3 utilizing 20mm broken stone and poor quality
Mangalore tiles as filler materials are used.
Fig. 2 Filler (Roof) Slab (Source: Vasista, 2017)
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023
6
Filler Slab (Roof) Rate Analysis as per CPWD-Delhi Schedule of Rates 2021
Sl. No. Unit Rate Item Qty Units Amount
1 8364.20/cum 20mm Metal 0.74 cum 6190
2 1500/cum Sand 0.37 cum 555
3 6.26/kg Cement 350 kg 2191
4 784/ day Mason 1 No.s 784
5 645/day Man 1 No.s 645
6 645/day Woman 4 No.s 2580
7 9.5/1 No. MP Tiles 85 No.s 808
8 48.50/kg Reinforcement 19.35 kg 939
9 772.1/sqm. Formwork 10 sqm 7721
10 Total 22413
(Rounded to next Rupee)
Concrete Roof Slab Rate Analysis as per CPWD-Delhi Schedule of Rates 2021
Sl. No. Unit Rate Item Qty Units Amount
1 8364.20/cum 20mm Metal 0.9 cum 7528
2 1500/cum Sand 0.45 cum 675
3 6.26/kg Cement 432 kg 2191
4 784/ day Mason 1 No.s 784
5 645/day Man 1 No.s 645
6 645/day Woman 4 No.s 2580
7 48.50/kg Reinforcement 49.77 kg 2414
8 772.1/sqm. Formwork 10 sqm 7721
9 Total 24538
(Rounded to next Rupee)
The difference in rate comes to 24538-22413 = 2125
As per the estimated records, 12.73 cum of concrete is needed for concrete roof slab for every
100 sqm plinth area of a building. Hence on an average, for a total o 10000sqm of plinth area, the
savings comes to 0.1273x2125x10000 = 27, 05,125/-
Reduction in CO2 emission for a 50 sqm building (Source: Sengupta, 2008)
Sl. No. Building Materials
Required by
Conventional Methods
Reduction by using cost effective
Construction Technology
(Rat-Trap bond, Filler Slab)
Reduction in CO2
Emission in Kg
1. Bricks – 20000 No.s 20% i.e. 4000 1440
2. Cement 60 bags or 3t 20% i.e. 0.6 t 540
3. Steel – 500 Kg or 0.5 t 25% i.e. 0.125 t 375
Total Reduction in CO2 emission 2355 (say 2.4 t)
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023
7
5. CONCLUSION
Hence it can be concluded that Rat Trap bond and Filler (Roof) Slab are more cost effective
building construction techniques than Flemish bond and Conventional RCC slab construction
technique. It means the null hypothesis is accepted
Project managers need to put cost reduction strategies that construction project management
imposes in order to achieve success in their projects. A comparative analysis is done on building
construction modules through estimation. The cost effectiveness is more evident from comparing
low cost house construction techniques with conventional construction techniques.
It is found otherwise that about 22%-26% range of construction cost can be saved using low cost
housing techniques as compared to traditional construction methods related to wall and roofing
constructions (Tam, 2011).
REFERENCES
[1] Abdul-Kadir M R and Price A D F 1995, Conceptual Phase of construction projects, International
Journal of Project Management, vol. 13, Iss. 6, pp. 387-393.
[2] Azimi N A and Welch H G 1998, The effectiveness of cost-effective analysis in containing costs.
Journal of General Internal Medicine, vol. 13, no. 10, pp. 664-669.
[3] Bettini C R, Longo O C, Alcoforado L F and Maia A C G 2016, Method of estimating of construction
cost of a building based on previous experiences, Open Journal of Civil Engineering, vol. 6, No. 5,
pp. 749-763
[4] Deshpande P V 1999. Preliminary cost estimate and scheduling of MIT’s Civil and Environmental
Engineering Building. A Master of Engineering thesis submitted at Massachusetts Institute of
Technology, 1999.
[5] Halpin D W and Woodhead R W 1998. Construction Management. 2nd Edition, John Wiley & Sons
Ltd. New York
[6] Kim H-J and Seo Y-C 2011. An economic evaluation system for building construction projects in the
conceptual phase. In Proceedings of 28th International symposium on Automation and Robotics in
construction, Seoul, Korea Jun 29-Jul 2, pp. 467-472.
[7] Limmer, C V 1997. Planejamento, Orcamentacao e Controle de Projetos e obras. 1st Edition, LTC,
Rio de Janeiro.
[8] Ozorhon B, Abbott C and Aouad G, 2016. Innovation in construction: A Project lifecycle approach.
URL: https://www.irbnet.de/daten/iconda/CIB16211.pdf
[9] Rajaguru A and Mahatme P 2016. Effective techniques in cost optimization of construction projects.
International Journal of Informative and Futuristic research, IJIFR/V3/E5/031, pp. 1646-1658.
[10] Sengupta, N. 2008, Use of Cost-Effective construction technologies in India to mitigate climate
change, Current Science, vol. 96, Iss. 1, pp. 38-43
[11] Shanmuganathan N and Baskar G 2016. Effective cost and time management techniques in
construction industry. International Journal of Advanced Engineering Technology, vol. VII, iss. II,
April-June, pp. 743-747.
[12] Singh P and Kumar G 2016, Low cost housing need for today’s world, International Journal of
Engineering Research-online, vol. 4, iss. 3.
[13] Sinha, S., MIhsra, S., Kumar, P. & Saurabh, S. (2020). Sustainable Low-Cost Housing using cost
effective construction technology “Rat Trap Bond Masonry” and Filler Roof Slab” in Bihar,
International Journal of Engineering Research and Technology, vol. 13, No. 7. Pp. 1780-1785.
[14] Srivastava, M. & Kumar, V. 2018, The methods of using low cost housing techniques in India,
Journal of Building Engineering, pp. 102-108
[15] Stasiak-Betejewska R and Potkany M 2015, Construction costs analysis and its importance to the
economy. Procedia Economics and Finance, 34, pp. 35-42.
[16] Subramani T, Lishitha P T and Kavitha M 2014, Time Overrun and cost effectiveness in the
construction industry, International Journal of Engineering Research and Applications, vol. 4 and No.
5, pp. 111-116.
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023
8
[17] Tam, V W Y 2011, Cost effectiveness of using low cost housing technologies in construction,
Procedia Engg, 14, pp. 156-160.
[18] Vasista, T. G., 2017, Six Effective Stages in Building-Construction Engineering and Management:
COSTFORD vs. CONVENTIONAL, A PhD Thesis submitted to SunRise University, Alwar,
Rajasthan, India.
[19] Young KC, Kelly A G and Holloway R G 2013, Reading cost-effectiveness or decision analysis
study, Neurol Clinical Practice, vol. 3, Iss. 5, pp. 413-420.

More Related Content

Similar to Cost Effective Methods in Construction Engineering

Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
IAEME Publication
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projects
iaemedu
 
Time-cost optimization using harmony search algorithm in construction projects
Time-cost optimization using harmony search algorithm in construction projectsTime-cost optimization using harmony search algorithm in construction projects
Time-cost optimization using harmony search algorithm in construction projects
Mohammad Lemar ZALMAİ
 
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case StudyTime-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
ijceronline
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
kiebut
 
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisProject Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Seta Ohanesian, PMP, LEED AP
 

Similar to Cost Effective Methods in Construction Engineering (20)

BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building Construction
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction Projects
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projects
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
Time-cost optimization using harmony search algorithm in construction projects
Time-cost optimization using harmony search algorithm in construction projectsTime-cost optimization using harmony search algorithm in construction projects
Time-cost optimization using harmony search algorithm in construction projects
 
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case StudyTime-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
 
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisProject Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative Analysis
 
Strategic Cost Management for Construction Project Success : A Systematic Study
Strategic Cost Management for Construction Project Success : A Systematic StudyStrategic Cost Management for Construction Project Success : A Systematic Study
Strategic Cost Management for Construction Project Success : A Systematic Study
 
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDYSTRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
 
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDYSTRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
 
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTIONEFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To Concrete
 

More from civejjour

Geotechnical Characterization on the Soyo Road Section using Electrical Resis...
Geotechnical Characterization on the Soyo Road Section using Electrical Resis...Geotechnical Characterization on the Soyo Road Section using Electrical Resis...
Geotechnical Characterization on the Soyo Road Section using Electrical Resis...
civejjour
 
STUDYING THE EFFECTS OF AIRCRAFT NOISE AROUND ABU DHABI INTERNATIONAL AIRPORT...
STUDYING THE EFFECTS OF AIRCRAFT NOISE AROUND ABU DHABI INTERNATIONAL AIRPORT...STUDYING THE EFFECTS OF AIRCRAFT NOISE AROUND ABU DHABI INTERNATIONAL AIRPORT...
STUDYING THE EFFECTS OF AIRCRAFT NOISE AROUND ABU DHABI INTERNATIONAL AIRPORT...
civejjour
 
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
civejjour
 
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
civejjour
 
Remote Sensing and Geographic Information System Based Route Planning
Remote Sensing and Geographic Information System Based Route PlanningRemote Sensing and Geographic Information System Based Route Planning
Remote Sensing and Geographic Information System Based Route Planning
civejjour
 

More from civejjour (20)

The Dynamics of Man's History and Economic Development: A Refocus on Ecologic...
The Dynamics of Man's History and Economic Development: A Refocus on Ecologic...The Dynamics of Man's History and Economic Development: A Refocus on Ecologic...
The Dynamics of Man's History and Economic Development: A Refocus on Ecologic...
 
Geotechnical Characterization on the Soyo Road Section using Electrical Resis...
Geotechnical Characterization on the Soyo Road Section using Electrical Resis...Geotechnical Characterization on the Soyo Road Section using Electrical Resis...
Geotechnical Characterization on the Soyo Road Section using Electrical Resis...
 
The Impact of Aspect Ratio on the Behaviour of Rigid Water Storage Tanks
The Impact of Aspect Ratio on the Behaviour of Rigid Water Storage TanksThe Impact of Aspect Ratio on the Behaviour of Rigid Water Storage Tanks
The Impact of Aspect Ratio on the Behaviour of Rigid Water Storage Tanks
 
Incorporating Participatory Planning and Quality Function Deployment in Urban...
Incorporating Participatory Planning and Quality Function Deployment in Urban...Incorporating Participatory Planning and Quality Function Deployment in Urban...
Incorporating Participatory Planning and Quality Function Deployment in Urban...
 
Biogas Technology as a Sustainable Domestic Organic Waste Management Measure ...
Biogas Technology as a Sustainable Domestic Organic Waste Management Measure ...Biogas Technology as a Sustainable Domestic Organic Waste Management Measure ...
Biogas Technology as a Sustainable Domestic Organic Waste Management Measure ...
 
STUDYING THE EFFECTS OF AIRCRAFT NOISE AROUND ABU DHABI INTERNATIONAL AIRPORT...
STUDYING THE EFFECTS OF AIRCRAFT NOISE AROUND ABU DHABI INTERNATIONAL AIRPORT...STUDYING THE EFFECTS OF AIRCRAFT NOISE AROUND ABU DHABI INTERNATIONAL AIRPORT...
STUDYING THE EFFECTS OF AIRCRAFT NOISE AROUND ABU DHABI INTERNATIONAL AIRPORT...
 
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
 
Evaluation of the Superplasticizer Effect on the Concrete Compressive Strengt...
Evaluation of the Superplasticizer Effect on the Concrete Compressive Strengt...Evaluation of the Superplasticizer Effect on the Concrete Compressive Strengt...
Evaluation of the Superplasticizer Effect on the Concrete Compressive Strengt...
 
Incorporating Participatory Planning and Quality Function Deployment in Urban...
Incorporating Participatory Planning and Quality Function Deployment in Urban...Incorporating Participatory Planning and Quality Function Deployment in Urban...
Incorporating Participatory Planning and Quality Function Deployment in Urban...
 
Biogas Technology as a Sustainable Domestic Organic Waste Management Measure ...
Biogas Technology as a Sustainable Domestic Organic Waste Management Measure ...Biogas Technology as a Sustainable Domestic Organic Waste Management Measure ...
Biogas Technology as a Sustainable Domestic Organic Waste Management Measure ...
 
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
Studying the Effects of Aircraft Noise Around Abu Dhabi International Airport...
 
Evaluation of Performance of High Calcium Fly Ash as a Mineral Filler in Mix ...
Evaluation of Performance of High Calcium Fly Ash as a Mineral Filler in Mix ...Evaluation of Performance of High Calcium Fly Ash as a Mineral Filler in Mix ...
Evaluation of Performance of High Calcium Fly Ash as a Mineral Filler in Mix ...
 
Intelligent Transportation System Based Traffic Congestion Modeling for Urban...
Intelligent Transportation System Based Traffic Congestion Modeling for Urban...Intelligent Transportation System Based Traffic Congestion Modeling for Urban...
Intelligent Transportation System Based Traffic Congestion Modeling for Urban...
 
The Impact of Waiting Time on Pedestrian Violations at Signalized Intersections
The Impact of Waiting Time on Pedestrian Violations at Signalized IntersectionsThe Impact of Waiting Time on Pedestrian Violations at Signalized Intersections
The Impact of Waiting Time on Pedestrian Violations at Signalized Intersections
 
Philosophical Investigation of Technology and its Effect on Human and Archite...
Philosophical Investigation of Technology and its Effect on Human and Archite...Philosophical Investigation of Technology and its Effect on Human and Archite...
Philosophical Investigation of Technology and its Effect on Human and Archite...
 
Civil Engineering and Urban Planning: An International Journal (CiVEJ)
Civil Engineering and Urban Planning: An International Journal (CiVEJ)Civil Engineering and Urban Planning: An International Journal (CiVEJ)
Civil Engineering and Urban Planning: An International Journal (CiVEJ)
 
Remote Sensing and Geographic Information System Based Route Planning
Remote Sensing and Geographic Information System Based Route PlanningRemote Sensing and Geographic Information System Based Route Planning
Remote Sensing and Geographic Information System Based Route Planning
 
Towards more Community-Oriented and Collaborative Planning for Alaska Native ...
Towards more Community-Oriented and Collaborative Planning for Alaska Native ...Towards more Community-Oriented and Collaborative Planning for Alaska Native ...
Towards more Community-Oriented and Collaborative Planning for Alaska Native ...
 
Research on the Relationship between Architectural Decorative Patterns and th...
Research on the Relationship between Architectural Decorative Patterns and th...Research on the Relationship between Architectural Decorative Patterns and th...
Research on the Relationship between Architectural Decorative Patterns and th...
 
Deep Learning Neural Network Approaches to Land Use-demographic- Temporal bas...
Deep Learning Neural Network Approaches to Land Use-demographic- Temporal bas...Deep Learning Neural Network Approaches to Land Use-demographic- Temporal bas...
Deep Learning Neural Network Approaches to Land Use-demographic- Temporal bas...
 

Recently uploaded

VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 

Recently uploaded (20)

Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 

Cost Effective Methods in Construction Engineering

  • 1. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023 DOI:10.5121/civej.2023.10301 1 COST EFFECTIVE METHODS IN CONSTRUCTION ENGINEERING Tatapudi Gopikrishna Vasista1 and Manohar Prasad Jakhanwal2 1 Department of Civil Engineering, Sri Venkateswara College of Engineering & Technology, Chittor 2 Former, Vice-Chancellor, AP Goyal Shimla University, Muzaffarpur, Shimla (HP) India ABSTRACT The economic impact of construction cost overrun is a possible loss of the economic justification for the project. The financial impact of a cost overrun results in demand for construction investment credits. Therefore reliable estimates of construction cost are an important aspect to the contemporary construction companies especially during the conceptual phase of lifecycle management. In this paper a cost-effective analysis is done using one of the cost effective construction technique called Rat Trap Bond versus Flemish bond and when estimated with CPWD 2012 schedule of rates it is proved that Low cost techniques such as rat trap bond provides better cost effectiveness as compared to conventional Flemish bond construction method. KEYWORDS Cost effective construction, Low cost construction methods, Conceptual Phase construction estimation, Construction cost estimating, comparative estimation analysis 1. INTRODUCTION In the construction projects, cost and time are the main aspects to be considered in the project management. It is a challenging task for the Project managers to evaluate the plan, take corrective actions and constantly measuring progress (Rajguru and Mahatme, 2016). Overcoming the delay of construction, reducing the time and cost will help obtaining the cost effectiveness (Subramani, Lishitha and Kavitha, 2014). The economic impact of a construction cost overrun is the possible loss of the economic justification for the project. The financial impact of a cost overrun results in demand for construction investment credits. Therefore reliable estimates of construction cost and schedules are important aspects to contemporary construction companies (Stasiak-Betlejewska and Potkany, 2015). Effective cost and time management play an important role to achieve project success in the construction industry. Various cost and time management techniques help to control cost and time overrun in the construction industry (Shanmuganathan and Baskar, 2016). Cost effectiveness studies and research encompasses methods that determine the cost of construction, which could consider the involvement of more competing technologies and interventions too (Young, Kelly and Holloway, 2013). Cost-effectiveness analysis is a technique to compare strategies intended to produce the same effect. In its most common form, a new strategy is compared with current practice and in is given the equation form as follows (Azimi and Welch, 1998):
  • 2. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023 2 Cost-Effectiveness ratio = (Cost of New strategy – Cost of current practice) / (Effect of new strategy – Effect of current practice) 2. CONSTRUCTION COST ESTIMATING The purpose of estimating is to determine the forecasting costs required to complete a project in accordance with the contract plan and specifications. The estimator can Conceptual estimate as the name suggests are generally made during the initial stages of a project. It helps reveal whether a project is economically feasible. Once the decision has been made then the estimates may be refined into a detailed design phase. It produces and estimates with reasonable accuracy of providing total costs for a given project (Deshpande, 1999). The conceptual phase is of strategic importance in the project environment (Abdul-Kadir and Price, 1995). The lifecycle of a construction project includes the conceptual phase, planning and design procurement, construction, operation and maintenance (Ozorhon, Abbott and Aouad , 2016). In the conceptual phase, cost estimate with a reasonable accuracy is required within a limited time period. Various estimation methods for the conceptual phase have been proposed earlier such as simple square foot method, regression analysis, probabilistic estimating, new network, case-based reasoning and fuzzy models etc. In this conceptual phase, cost estimators commonly use analogy-based estimating methods, i.e. an estimator selects a similar one from the past projects and adjusts it based on similarities and differences perceived by the estimator, which also depends on the individual experience or perception. A simple square foot or assembly costs method are also preferred by many cost estimators in the conceptual phase. However when historical data is not available it could lead to estimator’s bias which would estimate under budget or over budget. Therefore estimators usually desire to have their estimates compared with the actual costs of past similar projects. Then they prepare a list of quantities and costs in the form of cost breakdown structure. For example, a building is decomposed into work elements whereas unit cost of each element can be assessed and the total cost is the sum of the products of the quantities multiplied by their corresponding unit costs (Kim and Seo, 2011). 3. COST EFFECTIVE BUILDING MATERIALS AND TECHNIQUES Cost effective building materials has taken off by many builders for new home owners. Construction of low cost housing by using the low cost building materials increases the access to building by low income group people. Low cost housing can be achieved by using low cost materials, economical construction technologies and use of alternate methods of building construction, The profit gained from using such methods can decrease the cost of construction make the low cost housing accessible to all. The use of low cost alternate building materials also prevents the rise of construction due to use of scarce building materials. In the proposed research, the project involves the use of conventional building materials and then determines the total cost reduced by using alternative building construction techniques (Singh and Kumar, 2016). Affordable housing is possible mainly by dealing with effective costing and following sustainable building techniques, which helps in reducing the cost of construction without sacrificing the strength durability and performance. For example, a residential building can be divided into two parts viz. structural and non-structural. As the cost of cement takes major part of total building cost, it can be partially replaced by cement with 30%, 40% and 50% for structural elements. When strength tests such as compressive, split test, flexural test have been calculated, the 40% replacement of fly ash gave required strength for single storey building. For non-structural elements, the low cost materials such as concrete frames, hollow concrete blocks etc can be adopted. It can be concluded that the overall cost can be reduced up to 30% using these construction methods as compared to conventional building cost. It is also found that about
  • 3. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023 3 26.11% and 22.68% of building cost can be saved with low cost housing technologies as compared to traditional construction methods (Tam, 2011). Previous research on low cost housing techniques include: Tam et al. (2011) and Sinha, Mihsra, Kumar & Saurabh (2020) in passing. However, the following are some of the low cost techniques discussed by Dharma Raja (2009): (i) Hollow concrete blocks: Empty solid pieces by and large are made of size 40x20x20cm and will cover a volume of around 11 national blazed blocks. The cost reserve funds are on three checks prompting to around 23% sparing in cost. (ii) With Soil cement blocks there will be a sparing cost of 28%. (iii) With concrete door and window frames using M20 concrete, it is assessed that the cost diminishment for solid casing will be no less than 31%. (iv) Filler slabs when opted for Rooftops and middle of the road floors, it lessen the undesirable dead heap material. Other cost effective construction techniques include, rat trap bond with 20 percent cost reduction, filler slab roofing with 20 percent reduction, brick on edge lintels with 50% cost reduction and precast sunshades with 10 percent reduction of cost. 4. METHODOLOGY, HYPOTHESIS AND ITS TESTING The primary function of approximate estimating is to produce a forecast of the future project, before the building has been designed in detail and contract particulars prepared. Estimators have the responsibility of the challenging role of basing the most important business decisions when there is still very little information is available. The first step is the definition of a general work breakdown structure (WBS) able to properly account for and compare the construction costs of the company projects. Though there are several estimations are done as indicated earlier about different low cost techniques applied at different types of building elements, only one case is presented here in this paper. In the academy, acceptable margins range from + or – 10% to + or – 5%, regardless of the level of detail of the projects and despite the information that can be available (Bettini, Longo, Alcoforado and Maia, 2016). According to Halpin (2004), still in the preliminary phases of design, an error up to 10% would be totally acceptable. But for a fully detailed estimate the percentage of error of any estimation will never be less than 5% (Limmer, 1997). 4.1. Hypothesis Declaration H01= Rat Trap Bond construction techniques is more cost effective than Flemish Bond construction technique. H02 = Filler Slab construction technique is more cost effective than convention R. C. C slab. 4.2. Hypothesis Testing 4.2.1.Rat Trap Bond Vs. Flemish Bond: A comparison of two techniques such as rat trap bond and Flemish bond cost estimation is done to show that Rat trap bond provides more cost effective than Flemish bond cost in a tabular format considering one cubic meter volume of brick work.
  • 4. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023 4 (i) Brick work of 23 cm thickness in Rat trap bond using 1:6 cement mortars with cut bricks for the super structure (Rat trap bond method). Table 1. Estimation of Rat Trap bond for 1m3 brick work Fig.1: Rat Trap Bond vs. Flemish Bond, (Source: Google Search Image) ii) Brick work with 23cm thick Flemish bond using 1:6 cement mortars with wire cut bricks for the super structure (conventional method). Table 2. Estimation of Flemish bond for 1m3 brick work The difference in rate comes to 141/m3 (5495-5354). An average of 38m3 of brickwork will be required for a 100m2 plinth area of building. For a total of 10000m2 of plinth the saving comes to (0.38 x 141 x 10000) = Rs. 5, 35, 800/-; Where it is seen clearly 5354/ m3 < 5495/m3 Sl. No. Item Qty Unit Rate Amount 1. Bricks 420 No. s 8 3360.00 2. Sand 0.2 m3 2777 555.40 3. Cement 44 Kg 5.94 261.36 4. Brick Mason 1.5 Nos 471 706.50 5. Man 0.75 Nos 377 282.75 6. Woman 0.2 Nos 377 75.40 7. Scaffolding 6.25 8. Add 10% of Labor For the super structure 106.47 Total 5354.13 Sl. No. Item Qty Unit Rate Amount 1. Bricks 460 No. s 8 3680.00 2. Sand 0.24 m3 2777 666.48 3. Cement 58 Kg 5.94 344.52 4. Brick Mason 0.7 Nos 471 329.70 5. Man 1 Nos 377 131.95 6. Woman 1 Nos 377 263.90 7. Scaffolding 6.25 8. Add 10% of Labor For the super structure 72.55 Total 5495.35
  • 5. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023 5 Note: The data for the Rat Trap bond is estimated based on the CPWD-Delhi schedule of rates during the year 2021 and the rates of materials and labour are taken from the CPWD-Delhi schedule of rates during the year 2021. 4.2.2.Filler Slab Vs. R. C. C Slab: People look for attractive houses, more environmental friendly and cheaper but also want more life span and to have roofs over larger space areas (e.g. Halls in houses). Using cost-effective technology not only saves money but also reduce CO2emissions. When filler slab can be used as an alternative to conventional slab, the cost of construction can reduce up to 25% (Srivastava & Kumar, 2018). The basic principle in a filler slab is that the concrete in the bottom half of the RCC slab is simply considered dead weight and does not take up any compressive loads, but the RCC slab takes up such load. Thus filler in the redundant concrete in tension zone of the slab can be replaced by a suitable lightweight filler material (Sinha, Mishra, Kumar & Saurabh, 2020). Filler slab consists of light weight modest material such as poor quality Mangalore tiles, blocks, coconut shells, glass bottles and so forth. These materials are laid in the steel reinforcement framework (bars of 6mm or 8mm dia.) and cementing is done over them. The Mangalore tiles of size of 23cm x 40 cm and the network size of 33cm x50 cm can be used in the section thickness of 10cm. In specific, RCC filler space of 1:1.5:3 utilizing 20mm broken stone and poor quality Mangalore tiles as filler materials are used. Fig. 2 Filler (Roof) Slab (Source: Vasista, 2017)
  • 6. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023 6 Filler Slab (Roof) Rate Analysis as per CPWD-Delhi Schedule of Rates 2021 Sl. No. Unit Rate Item Qty Units Amount 1 8364.20/cum 20mm Metal 0.74 cum 6190 2 1500/cum Sand 0.37 cum 555 3 6.26/kg Cement 350 kg 2191 4 784/ day Mason 1 No.s 784 5 645/day Man 1 No.s 645 6 645/day Woman 4 No.s 2580 7 9.5/1 No. MP Tiles 85 No.s 808 8 48.50/kg Reinforcement 19.35 kg 939 9 772.1/sqm. Formwork 10 sqm 7721 10 Total 22413 (Rounded to next Rupee) Concrete Roof Slab Rate Analysis as per CPWD-Delhi Schedule of Rates 2021 Sl. No. Unit Rate Item Qty Units Amount 1 8364.20/cum 20mm Metal 0.9 cum 7528 2 1500/cum Sand 0.45 cum 675 3 6.26/kg Cement 432 kg 2191 4 784/ day Mason 1 No.s 784 5 645/day Man 1 No.s 645 6 645/day Woman 4 No.s 2580 7 48.50/kg Reinforcement 49.77 kg 2414 8 772.1/sqm. Formwork 10 sqm 7721 9 Total 24538 (Rounded to next Rupee) The difference in rate comes to 24538-22413 = 2125 As per the estimated records, 12.73 cum of concrete is needed for concrete roof slab for every 100 sqm plinth area of a building. Hence on an average, for a total o 10000sqm of plinth area, the savings comes to 0.1273x2125x10000 = 27, 05,125/- Reduction in CO2 emission for a 50 sqm building (Source: Sengupta, 2008) Sl. No. Building Materials Required by Conventional Methods Reduction by using cost effective Construction Technology (Rat-Trap bond, Filler Slab) Reduction in CO2 Emission in Kg 1. Bricks – 20000 No.s 20% i.e. 4000 1440 2. Cement 60 bags or 3t 20% i.e. 0.6 t 540 3. Steel – 500 Kg or 0.5 t 25% i.e. 0.125 t 375 Total Reduction in CO2 emission 2355 (say 2.4 t)
  • 7. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023 7 5. CONCLUSION Hence it can be concluded that Rat Trap bond and Filler (Roof) Slab are more cost effective building construction techniques than Flemish bond and Conventional RCC slab construction technique. It means the null hypothesis is accepted Project managers need to put cost reduction strategies that construction project management imposes in order to achieve success in their projects. A comparative analysis is done on building construction modules through estimation. The cost effectiveness is more evident from comparing low cost house construction techniques with conventional construction techniques. It is found otherwise that about 22%-26% range of construction cost can be saved using low cost housing techniques as compared to traditional construction methods related to wall and roofing constructions (Tam, 2011). REFERENCES [1] Abdul-Kadir M R and Price A D F 1995, Conceptual Phase of construction projects, International Journal of Project Management, vol. 13, Iss. 6, pp. 387-393. [2] Azimi N A and Welch H G 1998, The effectiveness of cost-effective analysis in containing costs. Journal of General Internal Medicine, vol. 13, no. 10, pp. 664-669. [3] Bettini C R, Longo O C, Alcoforado L F and Maia A C G 2016, Method of estimating of construction cost of a building based on previous experiences, Open Journal of Civil Engineering, vol. 6, No. 5, pp. 749-763 [4] Deshpande P V 1999. Preliminary cost estimate and scheduling of MIT’s Civil and Environmental Engineering Building. A Master of Engineering thesis submitted at Massachusetts Institute of Technology, 1999. [5] Halpin D W and Woodhead R W 1998. Construction Management. 2nd Edition, John Wiley & Sons Ltd. New York [6] Kim H-J and Seo Y-C 2011. An economic evaluation system for building construction projects in the conceptual phase. In Proceedings of 28th International symposium on Automation and Robotics in construction, Seoul, Korea Jun 29-Jul 2, pp. 467-472. [7] Limmer, C V 1997. Planejamento, Orcamentacao e Controle de Projetos e obras. 1st Edition, LTC, Rio de Janeiro. [8] Ozorhon B, Abbott C and Aouad G, 2016. Innovation in construction: A Project lifecycle approach. URL: https://www.irbnet.de/daten/iconda/CIB16211.pdf [9] Rajaguru A and Mahatme P 2016. Effective techniques in cost optimization of construction projects. International Journal of Informative and Futuristic research, IJIFR/V3/E5/031, pp. 1646-1658. [10] Sengupta, N. 2008, Use of Cost-Effective construction technologies in India to mitigate climate change, Current Science, vol. 96, Iss. 1, pp. 38-43 [11] Shanmuganathan N and Baskar G 2016. Effective cost and time management techniques in construction industry. International Journal of Advanced Engineering Technology, vol. VII, iss. II, April-June, pp. 743-747. [12] Singh P and Kumar G 2016, Low cost housing need for today’s world, International Journal of Engineering Research-online, vol. 4, iss. 3. [13] Sinha, S., MIhsra, S., Kumar, P. & Saurabh, S. (2020). Sustainable Low-Cost Housing using cost effective construction technology “Rat Trap Bond Masonry” and Filler Roof Slab” in Bihar, International Journal of Engineering Research and Technology, vol. 13, No. 7. Pp. 1780-1785. [14] Srivastava, M. & Kumar, V. 2018, The methods of using low cost housing techniques in India, Journal of Building Engineering, pp. 102-108 [15] Stasiak-Betejewska R and Potkany M 2015, Construction costs analysis and its importance to the economy. Procedia Economics and Finance, 34, pp. 35-42. [16] Subramani T, Lishitha P T and Kavitha M 2014, Time Overrun and cost effectiveness in the construction industry, International Journal of Engineering Research and Applications, vol. 4 and No. 5, pp. 111-116.
  • 8. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.10, No.2/3, September 2023 8 [17] Tam, V W Y 2011, Cost effectiveness of using low cost housing technologies in construction, Procedia Engg, 14, pp. 156-160. [18] Vasista, T. G., 2017, Six Effective Stages in Building-Construction Engineering and Management: COSTFORD vs. CONVENTIONAL, A PhD Thesis submitted to SunRise University, Alwar, Rajasthan, India. [19] Young KC, Kelly A G and Holloway R G 2013, Reading cost-effectiveness or decision analysis study, Neurol Clinical Practice, vol. 3, Iss. 5, pp. 413-420.