SlideShare a Scribd company logo
Rehabilitation of the Urban Water Supply & Sanitation in Sava River Basin (BMZ ID 2002 65 876) 
CURRENT SITUATION AND THE EXISTING PROBLEM 
The existing sewer system is a combined system, which collects the wastewater produced in households, industrial wastewater, and small companies as well as storm water. At the moment, approximate between 50% and 55% of the water consumers in the city of Derventa are connected to the sewer system, while the rest 45% discharge their wastewater into septic tanks and open pits. 
The pipe network consists of the pipes with the materials of PVC and concrete. 
The existing sewer system has the following defects to be improved through the works to being tendered: 
· The existing sewer system is insufficient to collect the wastewater produced in the city of Derventa. The piping system is in poor condition due to the poor maintenance and improper connections. 
· The discharge of the untreated wastewater without authorisation into the oxbow lake of the Ukrina river and other tributaries of the Ukrina river as well as the Ukrine river has caused not only the serious pollution in the Ukrina river but also in the downstream of the Sava river. 
· The hydraulic overload has caused the blockage of the collector in the Gakovac settlement, which has lead to a frequent overflow of the wastewater onto the ground surface. 
· The dimension of the existing collector on the left bank of the Ukrine river is not sufficient as to allow any more connection of sewerage pipe. Thus, a new collector is required to be constructed to collect and discharge the wastewater collected in the 
new settlement “Lug” on the left bank. 
· There are several “weak points”, which have insufficient hydraulic capacity due to the inadequate dimensions or gradients, in the existing sewage system.
Description of the Works: 
Lot B1 – In the northern part of the Derventa city, a new HDPE collector with diameters of DN 400-DN800 and length of ~2,000 m shall be laid along the road from the “Banja Luka”, in order to transport the wastewater collected by the existing branches to the future WWTP. 
The dimension of this new collector shall be calculated under consideration of the future development along the road “Banja Luka”. 
Under the new bridge, because the existing pumping station (PS 2) is out of the operation, the new collector shall be connected to the existing overflow structure (SWO 4). In this phase, the wastewater collected by the new collector will be discharged into the Ukraine River through the SWO4. 
The sewerage pipe (DN 300 – DN 500, concrete) which is laid in the northern part and connected to the Pump Station “PS3” shall be disconnected from the PS3 and connected to the new collector. 
Lot B2 - In order to collect the wastewater produced in the area along the road to “Banja Luka” and the refugee settlement “Lug” as well as the areas in the southern part of the Derventa City, the new sewerage networks which consists of ~ 2,400 m DN300-DN400 HDPE pipes shall be laid and the house connection shall be constructed. 
The wastewater collected by this new network will be discharged into the new main collector which shall be constructed in Lot B-1 by a new pump stations PS 4 & PS5 (LOT B-3) 
Lot B3: 
PS 1 and SWO 2 - Regarding to the Pumping Station PS 1, the investigation shall be carried out by the Contractor through pipe flushing and camera inspection (250 m from the starting point) to make clear if there is sewerage in the pipes, which should be connected to the pumps, 
and where the sewerage is discharged. 
2. PS 2 and SWO 4 - The Pumping Station PS 2 will not be in operation and therefore not be rehabilitated in this phase. The Pumping Station PS 2 will not be connected with the new sewage pipe within this project. The new sewage pipe will pass the PS 2 and will divert the sewage directly into Ukrina River. Future Project foresees operation of PS2 and downstream collector up to the Treatment Plant. 
3. PS 4 - In order to lift the wastewater collected by the new sewer network and the existing sewerage pipe (DN 300) to the new main collector, new pumping station PS 4 using submersible non-clog pumps shall be constructed. The two pumps will operate on an on- duty/stand-by basis. Each pump shall provide a capacity of 72 m³/h 
4. PS 5 – In order to lift the wastewater collected by new PS4, connection of existing collectors at abandoned PS3, new pumping station PS5 using 4nr submersible non-clog pumps shall be constructed. 2nr pumps will provide a capacity of 2x540m3/h and 2nr small pumps - 2x180m3/h.
CORRUGATED HDPE SN8 PIPES REHAU RAUVIA 
U-PVC SN8 PIPES REHAU
PREFABRICATED MANHOLES BINIS 
PREFABRICATED MANHOLES BINIS
MANHOLE COVERS – PAM REXESS 
DIRT CATCHERS
GEOTEXTILE: M-PROINTEX 
GRUNDFOS PUMPS (S, SE & SEV SERIES)
Lot B1 Collector Line 
DN800 – L=598m; 
DN600 – L=761m; 
DN400 – L=523m; 
DN300 – L=220m 
In total – 2.102,00m collector installed; 
38nr of prefabricated manholes
EXCAVATION WORKS 
TRENCH BRACING
USE OF PIPE LASER
MAGISTERIAL ROAD CROSSING 1 / UNDERGROUND DRILLING 
MAGISTERIAL ROAD CROSSING 2 / UNDERGROUND DRILLING
USE OF GEO-TEXTING ON HIGH UNDERGROUND WATER TRENCH SECTIONS 
INSPECTION MANHOLES ON EACH COLLECTOR DIRECTION CHANGE POINTS. MANHOLES PRODUCED BASED ON DETAILED DESIGN WITH SPECIFIED DIAMETERS AND ANGLES
SURVEY CONTROL
EXTENSION OF LOT B1 – DN300 COLLECTOR 
INSPECTION MANHOLE
INSPECTION MANHOLE “DIRT TRAP” 
MANHOLE COVER
TIGHTNESS TESTING AS PER EN1610
CCTV INSPECTION AS PER ATV M 14, PART 2
CCTV INSPECTION AS PER ATV M 14, PART 2
PLATE LOAD TEST ON ROAD CROSSINGS 
REINSTATEMENT OF SURFACES - ASPHALTING
Lot B2 Sewage Network 
DN400 – L=274m 
DN300 – L=1,844m 
In total: 2,118m of collector installed; 
House connections – 126nr; 
Prefabricated manholes – 61nr
COLLECTOR DN400 TRENCH EXCAVATION 
INSPECTION MANHOLE INSTALLATION
INSPECTION MANHOLE INSTALLATION 
PIPE LASER GUIDED INSTALLATION
PIPE LASER GUIDED INSTALLATION 
COLLECTOR DN300 TRENCH BRACING
INSPECTION MANHOLE INSTALLATION 
INSPECTION MANHOLE INSTALLATION
COLLECTION MANHOLES INSTALLATION
COLLECTION MANHOLES DRILLING FOR U-PVC HOUSE CONNECTION PIPE
U-PVC PIPE HOUSE CONNECTION TO THE COLLECTION MANHOLE
COLLECTION MANHOLE – U-PVC HOUSE CONNECTIONS 
COLLECTION MANHOLE INSTALLATION
Lot B3 Pumping Stations 
PS1 – Cleaning, rehabilitation of Pumps and inclusion into the SCADA System; 
PS2 – Connection of new B1 Collector to existing PS2, discharging into Ukrina River over SWO4 structure. Future development foresees engagement of PS2 to pump the waste water downstream further from the City until the new Treatment Plant 
PS3 – Existing PS3 is to be abandoned, belonging Collectors to be connected to new B1 collector, existing pumps to be rehabilitated and transferred to new PS4; 
PS4 – new PS to be built for lifting the collector B2 elevation, 2nr pumps to be installed (2x20l/s, Hmax=12.4m); water level sensors, control and power cabinet to be installed, inclusion into SCADA System 
PS5 – new PS was to be built lifting the elevation of B1 collector, 2+2 pumps (2x150l/s + 2x50l/s) with lifting heights of 7.72m & 7.15m to be installed, water level sensors, control and power cabinet to be installed, inclusion into SCADA System
EXISTING PUMPING STATION PS-1
EXISTING PUMPING STATION PS-1
EXISTING PUMPING STATION PS2 (CURRENTLY OUT OF FUNCTION) 
FUTURE PROJECT FORESEES OPERATION OF PS-2 AND TRANSPORT OF SEWAGE TO THE PLANNED DOWNSTREAM TREATMENT PLANT
EXISTING PUMPING STATION PS-2 TABLE VALVE ON SWO STRUCTURE 
EXISTING PS-2 / SWO4 OUTLET TO RIVER “UKRINA”
EXISTING PUMPING STATION PS-3, PLACED OUT OF OPERATION UNDER THE PROJECT 
ABANDONED PS3, PUMP REHABILITATED AND TRANSFERRED TO NEW PS4
NEW PUMPING STATION PS-4
PS-4 PENETRATING 1ST WALL ELEMENT
1ST WALL ELEMENT 
LOWERING OF 1ST ELEMENT
STORM WATER OVERFLOW STEEL DN400 PIPE
INLET HDPE DN400 PIPE – FROM LOT B2 NETWORK 
OVERFLOW STEEL DN300 PIPE
ROOF SLAB
PRESSURE PIPES 2NR SWING CHECK VALVES DN150 
TRANSITION DN300/150 WITH SWING CHECK VALVES
INSTALLED 2NR SUBMERSIBLE NON-CLOG 
GRUNDFOS “SEV” PUMPS 
(2X23.30L/S, H=12.4M, 50HZ) 
PS-4 OUTLET CHAMBER
PS-4 TIGHTNESS TESTING (AS PER EN1610), PLUGGING BALONS
LOCATION OF NEW PUMPING STATION PS-5
SEGMENTAL LOWERING – 1ST WALL’S SEGMENT
SEGMENTAL LOWERING – 1ST WALL’S SEGMENT
SEGMENTAL LOWERING – 1ST WALL’S SEGMENT 
LOWERING BY EXCAVATION
SEGMENTAL LOWERING – 1ST WALL’S SEGMENT 
SEGMENTAL LOWERING – 2ND WALL’S SEGMENT
SEGMENTAL LOWERING – 2ND WALL’S SEGMENT 
(INLET HDPE DN600 PIPE VISIBLE) 
UNDERGROUND LOWERING OF THE 2ND WALL’S SEGMENT
PREPARATION FOR UNDERWATER BASE PLUG CONCRETE INSTALLATION 
PREPARATION FOR BASE PLUG CONCRETE INSTALLATION
BASE PLUG CONCRETE INSTALLATION 
BASE SLAB REINFORCEMENT WORKS – OVER THE BASE PLUG CONCRETE SLAB
MIDDLE SLAB CONSTRUCTION 
(OUTLET DN800 PIPE VISIBLE)
TOP WALLS CONSTRUCTION 
INNER WALL – PRESSURE PIPES NOZZLE’S PENETRATIONS
OUTLET CHAMBER (PRESSURE PIPES AND HDPE DN800 OUTLET PIPE) 
TOP WALLS VIEW, DN500 OVERFLOW PIPE VISIBLE
INNER WALL, PRESSURE PIPE NOZZLES 
OUTLET DN800 PIPE
PS-5 ROOF SLAB REINFORCEMENT 
ROOF SLAB CONCRETE POURING
TIGHTNESS TESTING AS PER EN1610 
OVERFLOW DN500 PIPE
TIGHTNESS TESTING AS PER EN1610, PLUGGING BALLOONS
TIGHTNESS TESTING AS PER EN1610, PLUGGING BALLOONS 
TIGHTNESS TESTING AS PER EN1610, 
CALCULATED ADDING WATER 
(ABSORPTION OF CONCRETE SURFACES)
PRESSURE PIPES, SWING CHECK VALVES INSTALLATION 
PRESSURE PIPE PLINTH
CONTROL CABINET, SCADA SYSTEM 
VENTILATION PIPES AND ACCESS HATCHES
2NR SUBMERSIBLE NON-CLOG GRUNDFOS “S2” PUMPS 
(2X150L/S, H=7.72M, 50HZ)
WATER LEVEL SIGNALING PROBES; 
2NR SUBMERSIBLE NON-CLOG GRUNDFOS “SE” PUMPS 
(2X50L/S, H=7.15M, 50HZ)
OUTLET CHAMBER: 
PRESSURE PIPES, OUTLET DN800 HDPE PIPE
CONTROL CABINET 
PUMP / SYSTEM TEST
PUMP / SYSTEM TEST 
PUMP / SYSTEM TEST
PUMP / SYSTEM TEST 
PUMP / SYSTEM TEST
Lot A10 “Delivery of equipment for maintenance and proper operation”: 
Lot A10 “Delivery of equipment for maintenance and proper operation”: 
Pick-up vehicle 4WD: 
NISSAN NAVARA DC 2.5 DCI LE 
Backhoe Loader: 
KOMATSU WB97S-5 
Pipe Cutting Saw: 
STIHL TS420 
Flat Bed Vehicle: 
RENAULT MASTER 2.5 DCI 150 
Vibratory Rammer: 
WACKER BS 60-2i 
Asphalt Cutter: 
WACKER NEUSON BFS 1350 AL

More Related Content

What's hot

Rainplus Siphonic vs Conventional Drainage
Rainplus Siphonic vs Conventional DrainageRainplus Siphonic vs Conventional Drainage
Rainplus Siphonic vs Conventional Drainage
Jordan Smith
 
Full-Bore Siphonic Roof Drains Overview by Jay R. Smith Mfg. Co.
Full-Bore Siphonic Roof Drains Overview by Jay R. Smith Mfg. Co.Full-Bore Siphonic Roof Drains Overview by Jay R. Smith Mfg. Co.
Full-Bore Siphonic Roof Drains Overview by Jay R. Smith Mfg. Co.
Morris Group International
 
HydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof DrainageHydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax Inc. Limited
 
Pipeline construction management
Pipeline construction managementPipeline construction management
Pipeline construction management
Farraz Sarmento Salim
 
Jay R. Smith Mfg. Co. Full-bore Siphonic Roof Drains
Jay R. Smith Mfg. Co. Full-bore Siphonic Roof DrainsJay R. Smith Mfg. Co. Full-bore Siphonic Roof Drains
Jay R. Smith Mfg. Co. Full-bore Siphonic Roof Drains
Morris Group International
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Vladimir Popovic
 
Plumbing training
Plumbing training Plumbing training
Plumbing training
Monzer Salahdine
 
Il materiale - CIPP, Timo Münstermann
Il materiale - CIPP, Timo MünstermannIl materiale - CIPP, Timo Münstermann
Il materiale - CIPP, Timo Münstermann
Servizi a rete
 
Handbook of laying pipe sp57
Handbook of laying pipe sp57Handbook of laying pipe sp57
Handbook of laying pipe sp57
Yogesh Nema
 
Sewer Design - Conflict Resolution
Sewer Design  - Conflict ResolutionSewer Design  - Conflict Resolution
Sewer Design - Conflict Resolution
Dougyfreshaz
 
Traps and sewers
Traps and sewersTraps and sewers
Traps and sewers
Rohan Choudhary
 
Final year project
Final year projectFinal year project
Final year project
MohammadHasif
 
Hisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsHisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsSarah El Akkad
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2syed abdul wahab
 
SANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLYSANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLY
RIDDHESH VARIK
 

What's hot (17)

Rainplus Siphonic vs Conventional Drainage
Rainplus Siphonic vs Conventional DrainageRainplus Siphonic vs Conventional Drainage
Rainplus Siphonic vs Conventional Drainage
 
Fastflow Siphonic Systems
Fastflow Siphonic SystemsFastflow Siphonic Systems
Fastflow Siphonic Systems
 
Full-Bore Siphonic Roof Drains Overview by Jay R. Smith Mfg. Co.
Full-Bore Siphonic Roof Drains Overview by Jay R. Smith Mfg. Co.Full-Bore Siphonic Roof Drains Overview by Jay R. Smith Mfg. Co.
Full-Bore Siphonic Roof Drains Overview by Jay R. Smith Mfg. Co.
 
HydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof DrainageHydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof Drainage
 
Pipeline construction management
Pipeline construction managementPipeline construction management
Pipeline construction management
 
Jay R. Smith Mfg. Co. Full-bore Siphonic Roof Drains
Jay R. Smith Mfg. Co. Full-bore Siphonic Roof DrainsJay R. Smith Mfg. Co. Full-bore Siphonic Roof Drains
Jay R. Smith Mfg. Co. Full-bore Siphonic Roof Drains
 
Hydraulic Systems
Hydraulic SystemsHydraulic Systems
Hydraulic Systems
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
 
Plumbing training
Plumbing training Plumbing training
Plumbing training
 
Il materiale - CIPP, Timo Münstermann
Il materiale - CIPP, Timo MünstermannIl materiale - CIPP, Timo Münstermann
Il materiale - CIPP, Timo Münstermann
 
Handbook of laying pipe sp57
Handbook of laying pipe sp57Handbook of laying pipe sp57
Handbook of laying pipe sp57
 
Sewer Design - Conflict Resolution
Sewer Design  - Conflict ResolutionSewer Design  - Conflict Resolution
Sewer Design - Conflict Resolution
 
Traps and sewers
Traps and sewersTraps and sewers
Traps and sewers
 
Final year project
Final year projectFinal year project
Final year project
 
Hisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsHisham hajaj, stanley consultants
Hisham hajaj, stanley consultants
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
 
SANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLYSANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLY
 

Viewers also liked

Telecoms Document Manholes v1.1 - under Bergstan review 2016
Telecoms Document Manholes v1.1 - under Bergstan review 2016Telecoms Document Manholes v1.1 - under Bergstan review 2016
Telecoms Document Manholes v1.1 - under Bergstan review 2016David Jacobs
 
Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002
Aditya kumar
 
Drainage system Ar 308 unit-3
Drainage system Ar 308 unit-3Drainage system Ar 308 unit-3
Drainage system Ar 308 unit-3
Sudesh Chauhan
 
Interceptors and manholes
Interceptors and manholesInterceptors and manholes
Interceptors and manholes
Jem Ganacia
 
Different Types of Water Pipes And Their Uses
Different Types of Water Pipes And Their UsesDifferent Types of Water Pipes And Their Uses
Different Types of Water Pipes And Their Uses
Nitendra Kumar Singh
 
Types of pipes
Types of pipesTypes of pipes
Types of pipes
Kaustuv Ruhela
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
GAURAV. H .TANDON
 

Viewers also liked (10)

Telecoms Document Manholes v1.1 - under Bergstan review 2016
Telecoms Document Manholes v1.1 - under Bergstan review 2016Telecoms Document Manholes v1.1 - under Bergstan review 2016
Telecoms Document Manholes v1.1 - under Bergstan review 2016
 
Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002
 
Drainage system Ar 308 unit-3
Drainage system Ar 308 unit-3Drainage system Ar 308 unit-3
Drainage system Ar 308 unit-3
 
Manhole
ManholeManhole
Manhole
 
Interceptors and manholes
Interceptors and manholesInterceptors and manholes
Interceptors and manholes
 
types of pipes
types of pipestypes of pipes
types of pipes
 
Different Types of Water Pipes And Their Uses
Different Types of Water Pipes And Their UsesDifferent Types of Water Pipes And Their Uses
Different Types of Water Pipes And Their Uses
 
Types of pipes
Types of pipesTypes of pipes
Types of pipes
 
PIPE SYSTEMS1
PIPE SYSTEMS1PIPE SYSTEMS1
PIPE SYSTEMS1
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
 

Similar to Derventa City WW Project

Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosnia
Vladimir Popovic
 
Kakanj wastewater project
Kakanj wastewater projectKakanj wastewater project
Kakanj wastewater project
Vladimir Popovic
 
Kakanj City Waste Water Project
Kakanj City Waste Water ProjectKakanj City Waste Water Project
Kakanj City Waste Water Project
Vladimir Popovic
 
Kostajnica, ws, ww project
Kostajnica, ws, ww projectKostajnica, ws, ww project
Kostajnica, ws, ww project
Vladimir Popovic
 
Ws project ozurgeti, georgia
Ws project ozurgeti, georgiaWs project ozurgeti, georgia
Ws project ozurgeti, georgia
Vladimir Popovic
 
Derventa, Water Supply Project
Derventa, Water Supply ProjectDerventa, Water Supply Project
Derventa, Water Supply Project
Vladimir Popovic
 
Rehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgiaRehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgia
Vladimir Popovic
 
Ghadames project, conveyance pipeline
Ghadames project, conveyance pipelineGhadames project, conveyance pipeline
Ghadames project, conveyance pipeline
Vladimir Popovic
 
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Vladimir Popovic
 
EADIPS FGR annual journal 2010
EADIPS FGR annual journal 2010EADIPS FGR annual journal 2010
EADIPS FGR annual journal 2010
AlfredBirnhuber
 
STUDIO PRESENTATIO.pptx
STUDIO PRESENTATIO.pptxSTUDIO PRESENTATIO.pptx
STUDIO PRESENTATIO.pptx
AgohaChinonso
 
S06.s1 material de clase
S06.s1 material de claseS06.s1 material de clase
S06.s1 material de clase
PatyAranibar
 
Fundamentos Teóricos Cloacas
Fundamentos Teóricos CloacasFundamentos Teóricos Cloacas
Fundamentos Teóricos Cloacas
UbaldoJGarca
 
Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26
Uyanga Nyamkhuu
 
Short summary of PH4b Projects
Short summary of PH4b ProjectsShort summary of PH4b Projects
Short summary of PH4b ProjectsAnandhan Annasamy
 
Memoria técnica de los estudios hidrosanitarios
Memoria técnica de los estudios hidrosanitariosMemoria técnica de los estudios hidrosanitarios
Memoria técnica de los estudios hidrosanitarios
Go>Arch Studio
 
EADIPS FGR annual journal 2012
EADIPS FGR annual journal 2012EADIPS FGR annual journal 2012
EADIPS FGR annual journal 2012
AlfredBirnhuber
 

Similar to Derventa City WW Project (20)

Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosnia
 
Kakanj wastewater project
Kakanj wastewater projectKakanj wastewater project
Kakanj wastewater project
 
Kakanj City Waste Water Project
Kakanj City Waste Water ProjectKakanj City Waste Water Project
Kakanj City Waste Water Project
 
Kostajnica, ws, ww project
Kostajnica, ws, ww projectKostajnica, ws, ww project
Kostajnica, ws, ww project
 
Ws project ozurgeti, georgia
Ws project ozurgeti, georgiaWs project ozurgeti, georgia
Ws project ozurgeti, georgia
 
Derventa, Water Supply Project
Derventa, Water Supply ProjectDerventa, Water Supply Project
Derventa, Water Supply Project
 
Rehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgiaRehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgia
 
Ghadames project, conveyance pipeline
Ghadames project, conveyance pipelineGhadames project, conveyance pipeline
Ghadames project, conveyance pipeline
 
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
 
EADIPS FGR annual journal 2010
EADIPS FGR annual journal 2010EADIPS FGR annual journal 2010
EADIPS FGR annual journal 2010
 
STUDIO PRESENTATIO.pptx
STUDIO PRESENTATIO.pptxSTUDIO PRESENTATIO.pptx
STUDIO PRESENTATIO.pptx
 
Projects alrawan
Projects alrawanProjects alrawan
Projects alrawan
 
S06.s1 material de clase
S06.s1 material de claseS06.s1 material de clase
S06.s1 material de clase
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
 
Fundamentos Teóricos Cloacas
Fundamentos Teóricos CloacasFundamentos Teóricos Cloacas
Fundamentos Teóricos Cloacas
 
Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26
 
Short summary of PH4b Projects
Short summary of PH4b ProjectsShort summary of PH4b Projects
Short summary of PH4b Projects
 
Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12
 
Memoria técnica de los estudios hidrosanitarios
Memoria técnica de los estudios hidrosanitariosMemoria técnica de los estudios hidrosanitarios
Memoria técnica de los estudios hidrosanitarios
 
EADIPS FGR annual journal 2012
EADIPS FGR annual journal 2012EADIPS FGR annual journal 2012
EADIPS FGR annual journal 2012
 

More from Vladimir Popovic

Seismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoirSeismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
Vladimir Popovic
 
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Vladimir Popovic
 
Tightness testing of gravity pipelines
Tightness testing of gravity pipelinesTightness testing of gravity pipelines
Tightness testing of gravity pipelines
Vladimir Popovic
 
3-Days Construction Schedule
3-Days Construction Schedule3-Days Construction Schedule
3-Days Construction Schedule
Vladimir Popovic
 
Water Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing ExamplesWater Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing Examples
Vladimir Popovic
 
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Vladimir Popovic
 
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Vladimir Popovic
 
Sealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod HolesSealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod Holes
Vladimir Popovic
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
Vladimir Popovic
 
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopConstruction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Vladimir Popovic
 
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 ConstructionMan Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Vladimir Popovic
 
Standard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elementsStandard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elements
Vladimir Popovic
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Vladimir Popovic
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Vladimir Popovic
 
Man Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor StructuresMan Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor Structures
Vladimir Popovic
 

More from Vladimir Popovic (16)

Seismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoirSeismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
 
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
 
Tightness testing of gravity pipelines
Tightness testing of gravity pipelinesTightness testing of gravity pipelines
Tightness testing of gravity pipelines
 
3-Days Construction Schedule
3-Days Construction Schedule3-Days Construction Schedule
3-Days Construction Schedule
 
Water Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing ExamplesWater Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing Examples
 
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
 
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
 
Sealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod HolesSealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod Holes
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
 
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopConstruction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-Stop
 
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 ConstructionMan Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
 
Standard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elementsStandard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elements
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)
 
Man Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor StructuresMan Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor Structures
 
Vani Water Supply Project
Vani Water Supply ProjectVani Water Supply Project
Vani Water Supply Project
 

Recently uploaded

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 

Recently uploaded (20)

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 

Derventa City WW Project

  • 1.
  • 2. Rehabilitation of the Urban Water Supply & Sanitation in Sava River Basin (BMZ ID 2002 65 876) CURRENT SITUATION AND THE EXISTING PROBLEM The existing sewer system is a combined system, which collects the wastewater produced in households, industrial wastewater, and small companies as well as storm water. At the moment, approximate between 50% and 55% of the water consumers in the city of Derventa are connected to the sewer system, while the rest 45% discharge their wastewater into septic tanks and open pits. The pipe network consists of the pipes with the materials of PVC and concrete. The existing sewer system has the following defects to be improved through the works to being tendered: · The existing sewer system is insufficient to collect the wastewater produced in the city of Derventa. The piping system is in poor condition due to the poor maintenance and improper connections. · The discharge of the untreated wastewater without authorisation into the oxbow lake of the Ukrina river and other tributaries of the Ukrina river as well as the Ukrine river has caused not only the serious pollution in the Ukrina river but also in the downstream of the Sava river. · The hydraulic overload has caused the blockage of the collector in the Gakovac settlement, which has lead to a frequent overflow of the wastewater onto the ground surface. · The dimension of the existing collector on the left bank of the Ukrine river is not sufficient as to allow any more connection of sewerage pipe. Thus, a new collector is required to be constructed to collect and discharge the wastewater collected in the new settlement “Lug” on the left bank. · There are several “weak points”, which have insufficient hydraulic capacity due to the inadequate dimensions or gradients, in the existing sewage system.
  • 3. Description of the Works: Lot B1 – In the northern part of the Derventa city, a new HDPE collector with diameters of DN 400-DN800 and length of ~2,000 m shall be laid along the road from the “Banja Luka”, in order to transport the wastewater collected by the existing branches to the future WWTP. The dimension of this new collector shall be calculated under consideration of the future development along the road “Banja Luka”. Under the new bridge, because the existing pumping station (PS 2) is out of the operation, the new collector shall be connected to the existing overflow structure (SWO 4). In this phase, the wastewater collected by the new collector will be discharged into the Ukraine River through the SWO4. The sewerage pipe (DN 300 – DN 500, concrete) which is laid in the northern part and connected to the Pump Station “PS3” shall be disconnected from the PS3 and connected to the new collector. Lot B2 - In order to collect the wastewater produced in the area along the road to “Banja Luka” and the refugee settlement “Lug” as well as the areas in the southern part of the Derventa City, the new sewerage networks which consists of ~ 2,400 m DN300-DN400 HDPE pipes shall be laid and the house connection shall be constructed. The wastewater collected by this new network will be discharged into the new main collector which shall be constructed in Lot B-1 by a new pump stations PS 4 & PS5 (LOT B-3) Lot B3: PS 1 and SWO 2 - Regarding to the Pumping Station PS 1, the investigation shall be carried out by the Contractor through pipe flushing and camera inspection (250 m from the starting point) to make clear if there is sewerage in the pipes, which should be connected to the pumps, and where the sewerage is discharged. 2. PS 2 and SWO 4 - The Pumping Station PS 2 will not be in operation and therefore not be rehabilitated in this phase. The Pumping Station PS 2 will not be connected with the new sewage pipe within this project. The new sewage pipe will pass the PS 2 and will divert the sewage directly into Ukrina River. Future Project foresees operation of PS2 and downstream collector up to the Treatment Plant. 3. PS 4 - In order to lift the wastewater collected by the new sewer network and the existing sewerage pipe (DN 300) to the new main collector, new pumping station PS 4 using submersible non-clog pumps shall be constructed. The two pumps will operate on an on- duty/stand-by basis. Each pump shall provide a capacity of 72 m³/h 4. PS 5 – In order to lift the wastewater collected by new PS4, connection of existing collectors at abandoned PS3, new pumping station PS5 using 4nr submersible non-clog pumps shall be constructed. 2nr pumps will provide a capacity of 2x540m3/h and 2nr small pumps - 2x180m3/h.
  • 4. CORRUGATED HDPE SN8 PIPES REHAU RAUVIA U-PVC SN8 PIPES REHAU
  • 5. PREFABRICATED MANHOLES BINIS PREFABRICATED MANHOLES BINIS
  • 6. MANHOLE COVERS – PAM REXESS DIRT CATCHERS
  • 7. GEOTEXTILE: M-PROINTEX GRUNDFOS PUMPS (S, SE & SEV SERIES)
  • 8. Lot B1 Collector Line DN800 – L=598m; DN600 – L=761m; DN400 – L=523m; DN300 – L=220m In total – 2.102,00m collector installed; 38nr of prefabricated manholes
  • 10. USE OF PIPE LASER
  • 11.
  • 12. MAGISTERIAL ROAD CROSSING 1 / UNDERGROUND DRILLING MAGISTERIAL ROAD CROSSING 2 / UNDERGROUND DRILLING
  • 13. USE OF GEO-TEXTING ON HIGH UNDERGROUND WATER TRENCH SECTIONS INSPECTION MANHOLES ON EACH COLLECTOR DIRECTION CHANGE POINTS. MANHOLES PRODUCED BASED ON DETAILED DESIGN WITH SPECIFIED DIAMETERS AND ANGLES
  • 15. EXTENSION OF LOT B1 – DN300 COLLECTOR INSPECTION MANHOLE
  • 16. INSPECTION MANHOLE “DIRT TRAP” MANHOLE COVER
  • 17. TIGHTNESS TESTING AS PER EN1610
  • 18. CCTV INSPECTION AS PER ATV M 14, PART 2
  • 19. CCTV INSPECTION AS PER ATV M 14, PART 2
  • 20. PLATE LOAD TEST ON ROAD CROSSINGS REINSTATEMENT OF SURFACES - ASPHALTING
  • 21. Lot B2 Sewage Network DN400 – L=274m DN300 – L=1,844m In total: 2,118m of collector installed; House connections – 126nr; Prefabricated manholes – 61nr
  • 22. COLLECTOR DN400 TRENCH EXCAVATION INSPECTION MANHOLE INSTALLATION
  • 23. INSPECTION MANHOLE INSTALLATION PIPE LASER GUIDED INSTALLATION
  • 24. PIPE LASER GUIDED INSTALLATION COLLECTOR DN300 TRENCH BRACING
  • 25. INSPECTION MANHOLE INSTALLATION INSPECTION MANHOLE INSTALLATION
  • 27. COLLECTION MANHOLES DRILLING FOR U-PVC HOUSE CONNECTION PIPE
  • 28. U-PVC PIPE HOUSE CONNECTION TO THE COLLECTION MANHOLE
  • 29. COLLECTION MANHOLE – U-PVC HOUSE CONNECTIONS COLLECTION MANHOLE INSTALLATION
  • 30. Lot B3 Pumping Stations PS1 – Cleaning, rehabilitation of Pumps and inclusion into the SCADA System; PS2 – Connection of new B1 Collector to existing PS2, discharging into Ukrina River over SWO4 structure. Future development foresees engagement of PS2 to pump the waste water downstream further from the City until the new Treatment Plant PS3 – Existing PS3 is to be abandoned, belonging Collectors to be connected to new B1 collector, existing pumps to be rehabilitated and transferred to new PS4; PS4 – new PS to be built for lifting the collector B2 elevation, 2nr pumps to be installed (2x20l/s, Hmax=12.4m); water level sensors, control and power cabinet to be installed, inclusion into SCADA System PS5 – new PS was to be built lifting the elevation of B1 collector, 2+2 pumps (2x150l/s + 2x50l/s) with lifting heights of 7.72m & 7.15m to be installed, water level sensors, control and power cabinet to be installed, inclusion into SCADA System
  • 33. EXISTING PUMPING STATION PS2 (CURRENTLY OUT OF FUNCTION) FUTURE PROJECT FORESEES OPERATION OF PS-2 AND TRANSPORT OF SEWAGE TO THE PLANNED DOWNSTREAM TREATMENT PLANT
  • 34. EXISTING PUMPING STATION PS-2 TABLE VALVE ON SWO STRUCTURE EXISTING PS-2 / SWO4 OUTLET TO RIVER “UKRINA”
  • 35. EXISTING PUMPING STATION PS-3, PLACED OUT OF OPERATION UNDER THE PROJECT ABANDONED PS3, PUMP REHABILITATED AND TRANSFERRED TO NEW PS4
  • 36.
  • 38. PS-4 PENETRATING 1ST WALL ELEMENT
  • 39. 1ST WALL ELEMENT LOWERING OF 1ST ELEMENT
  • 40.
  • 41.
  • 42. STORM WATER OVERFLOW STEEL DN400 PIPE
  • 43. INLET HDPE DN400 PIPE – FROM LOT B2 NETWORK OVERFLOW STEEL DN300 PIPE
  • 45. PRESSURE PIPES 2NR SWING CHECK VALVES DN150 TRANSITION DN300/150 WITH SWING CHECK VALVES
  • 46. INSTALLED 2NR SUBMERSIBLE NON-CLOG GRUNDFOS “SEV” PUMPS (2X23.30L/S, H=12.4M, 50HZ) PS-4 OUTLET CHAMBER
  • 47. PS-4 TIGHTNESS TESTING (AS PER EN1610), PLUGGING BALONS
  • 48.
  • 49. LOCATION OF NEW PUMPING STATION PS-5
  • 50. SEGMENTAL LOWERING – 1ST WALL’S SEGMENT
  • 51. SEGMENTAL LOWERING – 1ST WALL’S SEGMENT
  • 52. SEGMENTAL LOWERING – 1ST WALL’S SEGMENT LOWERING BY EXCAVATION
  • 53. SEGMENTAL LOWERING – 1ST WALL’S SEGMENT SEGMENTAL LOWERING – 2ND WALL’S SEGMENT
  • 54. SEGMENTAL LOWERING – 2ND WALL’S SEGMENT (INLET HDPE DN600 PIPE VISIBLE) UNDERGROUND LOWERING OF THE 2ND WALL’S SEGMENT
  • 55. PREPARATION FOR UNDERWATER BASE PLUG CONCRETE INSTALLATION PREPARATION FOR BASE PLUG CONCRETE INSTALLATION
  • 56. BASE PLUG CONCRETE INSTALLATION BASE SLAB REINFORCEMENT WORKS – OVER THE BASE PLUG CONCRETE SLAB
  • 57. MIDDLE SLAB CONSTRUCTION (OUTLET DN800 PIPE VISIBLE)
  • 58. TOP WALLS CONSTRUCTION INNER WALL – PRESSURE PIPES NOZZLE’S PENETRATIONS
  • 59. OUTLET CHAMBER (PRESSURE PIPES AND HDPE DN800 OUTLET PIPE) TOP WALLS VIEW, DN500 OVERFLOW PIPE VISIBLE
  • 60. INNER WALL, PRESSURE PIPE NOZZLES OUTLET DN800 PIPE
  • 61. PS-5 ROOF SLAB REINFORCEMENT ROOF SLAB CONCRETE POURING
  • 62.
  • 63. TIGHTNESS TESTING AS PER EN1610 OVERFLOW DN500 PIPE
  • 64. TIGHTNESS TESTING AS PER EN1610, PLUGGING BALLOONS
  • 65. TIGHTNESS TESTING AS PER EN1610, PLUGGING BALLOONS TIGHTNESS TESTING AS PER EN1610, CALCULATED ADDING WATER (ABSORPTION OF CONCRETE SURFACES)
  • 66. PRESSURE PIPES, SWING CHECK VALVES INSTALLATION PRESSURE PIPE PLINTH
  • 67.
  • 68. CONTROL CABINET, SCADA SYSTEM VENTILATION PIPES AND ACCESS HATCHES
  • 69. 2NR SUBMERSIBLE NON-CLOG GRUNDFOS “S2” PUMPS (2X150L/S, H=7.72M, 50HZ)
  • 70. WATER LEVEL SIGNALING PROBES; 2NR SUBMERSIBLE NON-CLOG GRUNDFOS “SE” PUMPS (2X50L/S, H=7.15M, 50HZ)
  • 71. OUTLET CHAMBER: PRESSURE PIPES, OUTLET DN800 HDPE PIPE
  • 72. CONTROL CABINET PUMP / SYSTEM TEST
  • 73. PUMP / SYSTEM TEST PUMP / SYSTEM TEST
  • 74. PUMP / SYSTEM TEST PUMP / SYSTEM TEST
  • 75. Lot A10 “Delivery of equipment for maintenance and proper operation”: Lot A10 “Delivery of equipment for maintenance and proper operation”: Pick-up vehicle 4WD: NISSAN NAVARA DC 2.5 DCI LE Backhoe Loader: KOMATSU WB97S-5 Pipe Cutting Saw: STIHL TS420 Flat Bed Vehicle: RENAULT MASTER 2.5 DCI 150 Vibratory Rammer: WACKER BS 60-2i Asphalt Cutter: WACKER NEUSON BFS 1350 AL