SlideShare a Scribd company logo
Activities of Pipeline constructionActivities of Pipeline construction
PROCEDUREPROCEDURE
Right of Way clearing and gradingRight of Way clearing and grading
Delivery, Transportation, Handling,Delivery, Transportation, Handling,
Hauling, Stringing of pipesHauling, Stringing of pipes
Trenching Normal & RockTrenching Normal & Rock
BendingBending
Lining up and WeldingLining up and Welding
Radiographic InspectionRadiographic Inspection
IndianOil
Activities of Pipeline constructionActivities of Pipeline construction
Application of Joint CoatingApplication of Joint Coating
Lowering & back fillingLowering & back filling
Tie-insTie-ins
River and Road crossingsRiver and Road crossings
Cleanup and Restoration of ROWCleanup and Restoration of ROW
Air Pigging cleaning and GaugingAir Pigging cleaning and Gauging
Hydrostatic testingHydrostatic testing
IndianOil
Activities of Pipeline constructionActivities of Pipeline construction
De watering cleaning and SwabbingDe watering cleaning and Swabbing
Golden Tie insGolden Tie ins
Valve installationValve installation
Caliper survey and dent repairsCaliper survey and dent repairs
Line PreservationLine Preservation
IndianOil
IndianOil
WORK PROCEDURE
Purpose:
The purpose of work procedure is to
stipulate the method that shall be used for
a particular activity covering even minute
steps in details.
 The work procedure is to be prepared by agency
responsible for execution of work.
 The work procedure is examined criticaly and
approved by owner/owner representative.
 No deviation from work procedure is accepted.
IndianOil
NEED FOR WORK PROCEDURE
It helps:
1.In clearly defining the procedure to be
adopted in execution of activity.
2.In establishing QAP a tool for inspection.
3.In developing records for future
reference.
4.In case of any dispute arising at later
stage.
IndianOil
IndianOil
Document Number TITLE/Remarks
XX/WP/100 Survey,Clearing & Grade
XX/WP/101 Trench
XX/WP/102 Blasting
XX/WP/103 Pipe Handling And Stringing
XX/WP/104 Bending
XX/WP/105 Concrete coating by casting procedure
XX/WP/106 Tie-in
XX/WP/107 NDT Procedure for Mainline Welding
XX/WP/108 Applications of Heat shrinkable sleeves
XX/WP/109 Lowering in and rock shield applications
XX/WP/110 Backfill
XX/WP/111 Cathodic protection installation
XX/WP/112 Pre testing of Pipeline crossings
IndianOil
Document Number TITLE/Remarks
XX/WP/113 Pipeweld numbering
XX/WP/114 Casting and placing of precast weights
XX/WP/115 Concrete coating of pipes impingement method
XX/WP/116 handling over coated pipes at Coating yard
XX/WP/117 Cased crossings
XX/WP/118 Repair of accidental arc strikes
XX/WP/119 TCP
XX/WP/120 Ultrasonics
XX/WP/121 DP & MPI
XX/WP/122 final cleanup and restoration
XX/WP/123 Open cut Crossings
XX/WP/124 Major River crossings
HOME
 Centre line of ROW is marked based on IP and
TP fixed during detailed route survey
 Wooden pegs are put on either side of the center
line at a distance of 9 meters for 18 m ROW.
 ROW width is kept as 6 m on left of Pipeline for
storing the excavated soil and 12 m on right side
for movement of equipments.
IndianOil
ROW Clearing and GradingROW Clearing and Grading
 Dozer with flat front blade is used to clear the
vegetation and trees
 Prior information to land owners to clear the land
of their crops before entering
IndianOil
ROW Clearing and GradingROW Clearing and Grading
HOME
PHOTO
 To prevent transit damage nylon rope rings are
tied at every three meter distance
 Profiled wooden supports are required to place
first layer of the pipes on the trailer
 To avoid damage to pipe bevel, though the bevel
protectors are provided on pipe ends, crane
hooks shall be provided with rubber pads for
additional safety.
 Careful stacking of pipes over sand bags, visual
inspection of bevel ends to avoid welding
defects.
IndianOil
Transportation Handling and StringingTransportation Handling and Stringing
of the Pipesof the Pipes
PHOTOPHOTO
 In cultivable land, to strip top soil (30 cm depth)
& store separately along ROW for replacement
on top of backfilled ditch.
 Provide suitable crossings across open ROW
for land owners/ public.
 Width of trench : Pipe OD + 300 mm.
 Depth of trench to be measured from original
ground/ graded surface/ top of road/ bottom of
rail, whichever is lower.
IndianOil
TRENCHINGTRENCHING
 Provide 300 mm additional cover where pipeline
is within 15 m of private dwelling, industrial
buildings or public places.
 Provide temp. diversions/ bridges at road
crossings to allow passage of normal traffic
with min. inconvenience.
 Provide warning/ traffic signs, lights,
barricades, fencing, watchmen as required by
local authorities.
 Provide extra depth to fit min. radius of bend at
crossings.
IndianOil
TRENCHINGTRENCHING
Sl.Sl.
No.No.
LocationLocation Min. CoverMin. Cover
(m)(m)
11 Industrial, Commercial, Residential Areas (NormalIndustrial, Commercial, Residential Areas (Normal
Terrain)Terrain)
1.251.25
22 Uncased/ Cased Road CrossingsUncased/ Cased Road Crossings
& Cart-Track Crossings& Cart-Track Crossings
1.251.25
33 Railway CrossingsRailway Crossings 1.701.70
44 Normal Terrain / Drainage ditches at Railways,Normal Terrain / Drainage ditches at Railways,
Highways etc.Highways etc.
1.201.20
55 Minor Water Course CrossingsMinor Water Course Crossings 1.501.50
66 Marshy Areas/ Water reservoir Areas/ PondsMarshy Areas/ Water reservoir Areas/ Ponds 1.501.50
77 Submerged River CrossingsSubmerged River Crossings 2.502.50
88 Rocky AreasRocky Areas 1.001.00
PHOTOPHOTO
HOMEHOME
 Cold field bends for change of vertical & horizontal
alignment by using bending machine & mandrel.
 Bends to be made without causing wrinkles,
buckles, stretching & damage to pipe coating.
 Bending procedure to be established including step
length & max. degree per pull per foot (0.9550 for
18” OD pipes).
 Over bends to be made to clear high points of the
trench bottom.
IndianOil
BENDINGBENDING
 Sag bends to fit the bottom of the trench.
 Side bends to leave min. clearance to trench wall.
 Radius of curvature > 40 D upto 18” OD & > 60 D for
above 18” OD pipes.
 End of bend should not be closer than 2 m from
girth weld or pipe end.
 Bends to be installed by positioning longitudinal
welds in upper quadrant.
IndianOil
BENDINGBENDING
 Ovality of bent pipe < 2.5 % of nominal dia. at any
point; to be checked by passing a gauge consisting
of two discs of 95% nominal pipe internal dia.
 To layout pipes in such a way that Nos. of pieces cut
off less than 2 m are held min.
 No Mitre bends are permitted.
 Hot pulled bends may be used in unavoidable
circumstances.
IndianOil
BENDINGBENDING
PHOTOPHOTO
 STANDARDS/CODES.
 WELDING TECHNIQUES.
 WELDING PROCEDURES.
 WELDER’S QUALIFICATION TEST.
IndianOil
MAINLINE WELDINGMAINLINE WELDING
FOLLOWING STANDARDS/CODES ARE
REFFERED IN INSPECTION & TESTING OF
WELD.
 API 1104, Welding of pipelines and related
facilities.
 ASME Sec IX, Boiler & Pressure vessel Code.
IndianOil
STANDARDS/CODESSTANDARDS/CODES
PHOTOPHOTO
A) Tensile strength test
B) Nick break test
C) Root, face and side bend test
IndianOil
Destructive TestDestructive Test
Scope of work includes 100% Radiographic
inspection of all joints for the initial 1 Km of
the pipeline in each spread. For balance
portion of the pipeline ,20% of all joints shall
be radio-graphically inspected except for
specific crossings and tie-ins which need
100% radio-graphic inspection
IndianOil
RadiographyRadiography
PHOTOPHOTO
 COATING CLEARANCE IS AVAILABLE FROM
RADIOGRAPHY CREW.
 HUMIDITY <85%, IF BETWEEN 75% TO 85%
PREHEAT BEFORE BLASTING.
 CLEANING OF JOINT AREA AND ADJACENT
COATING DONE UPTO 100MM ON CTE COATING
ON BOTH PIPES
 CHAMPER THE PIPE COATING TO AN ANGLE<30
 PREHEAT THE WELDED JOINT AREA TO 60-80 C
IndianOil
JOINT COATINGJOINT COATING
 SANDBLASTING IS DONE UPTO 100 MM ON CTE
COATING ON BOTH PIPES
 ENTIRE SAND BLAST SURFACE IS FREE FROM
MOISTURE.
 THE ROUGHNESS OF SAND BLASTED SURFACES
IS BETWEEN 50-70 MICRON AS MEASURED BY
PRESS-O-FILM/ELCOMETER.
 PART A(60+10ml)PRIMER & PART B(30+10ml)
EPOXY IS MIXED FOR MIN 30 SEC
 PREHEATING OF PIPE TO A TEMPERATURE OF 60-
80o
C DONE.
IndianOil
JOINT COATINGJOINT COATING
 THE OVERLAP POSITION OF THE SLEEVE IS AT 2
OR 10 ‘O’ CLOCK.
 WET FILM THICKNESS OF PRIMER IS BETWEEN 50-
70 MICRONS.
 SIDE OF OVERLAP PORTION HEATED & PRESSED
WITH SILICON ROLLERS.
 THE CLOSURE PATCH IS HEATED, PRESSED &
SEALED ON THE SLEEVE.
 DIRECTION OF FLAME IS CIRCULAR & FROM ONE
END TO OTHER END.
 THE SLEEVE IS COMPLETELY SHRUNK AND
CONFORMS TO PIPE
IndianOil
JOINT COATINGJOINT COATING
 SLEEVE IS FREE FROM WRINKLES, COLD SPOTS,
ENTRAPPED AIR IS EXPELLED BY HEATING &
PRESSING WITH ROLLER OR BY HAND.
 THICKNES OF SLEEVE ON WELD SEEM IS MIN
1.7MM AND ON PARENT METAL IS MIN 2MM.
 PEEL TEST DONE ONE IN EVERY 100 JOINTS OR
DAY’S PRODUCTION WHICHEVER IS LOWER ON
SUBSEQUENT MORNING.
IndianOil
JOINT COATINGJOINT COATING
 PEEL TEST PROCEDURE
PEEL SIZED 1” BY 8” PEEL CUT UPTO BARE PIPE
ANY LOCATION- AT WELDED SEAM, ON PIPE AND
ON CTE COATING
FAILS IF PEEL OF FORCE IS LESS AT OBSERVED
TEMP. OR ADHESIVE LAYER OF SLEEVE IS
PEELED OFF FROM PIPE.
PEEL TESTED PORTION IS REPAIRED.
IndianOil
JOINT COATINGJOINT COATING
PHOTOPHOTO
Before lowering of pipeline in the trench,
 To clear the trench of all debris, stones, pipe
cut pieces, welding rods, hard clods, skids etc.
before lowering of pipeline.
 To drain out water from the trench (if any) to
avoid floatation.
 To carry out complete check by full circle
holiday detector.
IndianOil
PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
Before lowering of pipeline in the trench,
 To repair all coating damages.
 To provide sand padding (150 mm thick) free
from gravel/ pebbles in rocky areas.
 Pipeline to be lifted & laid by using non-
abrasive material (Teflon) coated hooks.
IndianOil
PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
Before lowering of pipeline in the trench,
 No sling to be put around field joint coating.
 Adequate Nos. of side booms to be used for holding the
pipeline in gentle S-curve maintaining elastic bend
radius.
 Pipeline not to be laid in tension. Trench to be rectified
(if required) so that the pipeline fits the excavation and
rests on the trench bed.
 To avoid movement of pipeline in the trench.
IndianOil
PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
 BACKFILLING OF PREVIOUS SECTION HAS
BEEN COMPLETED.
 LOWERING CLEARANCE FROM JOINT COATING
SITE IS AVAILABLE.
 RADIOGRAPHY CLEARANCE FOR LEFT OUT
JOINTS IS AVAILABLE.
 COATING CHECKED VISUALLY FOR DEFECTS
AND REPAIRS DONE, IF REQUIRED.
 HOLIDAY DONE AT 15 KV
 DEPTH AT 4 LOCATIONS IS CHECKED AND
FOUND .1.5 M
IndianOil
PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
 WIDTH CHECKED AT BOTTOM OF TRENCH AT 4
LOCATIONS AND FOUND . 1.2 m
 TRENCH BOTTOM IS FREE FROM ROCKY
STRATA
 SOFT PADDING ON THE BOTTOM OF TRENCH
DONE
 NIGHT CAPS ARE PROVIDED ON OPEN ENDS OF
PIPE SECTION.
 SLING OF SIDE BOOM IS NOT BE ON FIELD
JOINT COATING.
 PIPE IS LOWERED IN THE RIGHT SIDE OF THE
TRENCH.
 DISTANCE OF HDPE PIPE FROM MAIN PIPE IS
400MM.
IndianOil
PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
 SPIKES PROVIDED AT 10 M INTERVAL ALONG
THE ROUTE OF HDPE PIPE.
 SPIKE REMOVED AFTER PADING.
 WARNING TAPE IS LAID AT 400 MM ABOVE
HDPE PIPE
IndianOil
PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
PHOTOPHOTO
The gaps which are left out during mainline
welding due to road/railway crossing,
canal/river crossings etc are connected in
the form of Tie-in joints
IndianOil
Tie- InsTie- Ins
PHOTOPHOTO
1. Cased crossings for Railways & Highways (NH/ SH)
 Casing pipe: 24” OD x 0.281” WT API 5L Gr. B
 Carrier Pipe: 18” OD x 0.250” WT API 5L X65
2. Uncased crossings (open cut) for minor roads/ cart –
tracks using heavy wall pipe (18” OD x 0.281” WT API
5L X65).
3. Minor water course crossings (open cut) using normal
pipe (18” OD x 0.250” WT API 5L X65)
IndianOil
TYPES OF CROSSINGSTYPES OF CROSSINGS
4. Submerged river crossings (open cut) using heavier
wall pipe (18” OD x 0. 375” WT API 5L X65) with
concrete coating/ HDD XING
5. Crossings for existing underground facilities like
pipelines, cables using normal pipe (18” OD x 0.250”
WT API 5L X65) with min. clearance of 500 mm.
Crossings at Sl. No. 2, 3 & 5 above are part of mainline
item.
Cased and submerged river crossings are separate
items.
IndianOil
TYPES OF CROSSINGSTYPES OF CROSSINGS
 Execute crossing work as per concerned Statutory Authority
permission conditions.
 Highways, main roads, rail roads & their verges and banks of water
courses not to be used for loading, unloading or stacking of
materials or equipment.
 Roads or water courses not to be closed or diverted without prior
permission of concerned Statutory Authority.
 Before execution of cased and submerged river crossings, detailed
methodology to be submitted by contractor containing:
 Time schedule,
 Working method,
 Equipment to be deployed
 Test procedure
 Manning
 Soil Investigations.
IndianOil
CROSSINGSCROSSINGS
 To be executed by horizontal boring technique.
 Casing pipe to be 6” larger in dia. than carrier
pipe.
 Carrier pipes to be 3 LPE coated. No coating of
casing pipes.
 Ground water table (if encountered) over length
of boring to be lowered up to at least 0.5 m
below bottom of the pipeline.
IndianOil
CASED CROSSINGSCASED CROSSINGS
 For boring pits in unstable soils, closed sheet
piling to be used.
 Boring/ exit pit bottom to be graded for min. 12
m at the approach to each end of casing.
 Backfill in boring/ exit pits to be compacted in
15 cm layers to 90% proctor density by mech.
compactor after dewatering.
IndianOil
CASED CROSSINGSCASED CROSSINGS
 Dia. of bored hole to be almost same as casing
pipe OD.
 Vent pipes to be provided on both ends of
casing in such a way that there is no contact
with carrier pipe.
 100% radiographic inspection of weld joints of
carrier pipes.
IndianOil
CASED CROSSINGSCASED CROSSINGS
 Prior to installation, hydrostatic pre-testing of
the carrier pipeline section to be carried out at a
pressure corresponding to 95% SMYS of pipe
material (120.62 kg/cm2 for SSPL) . Test
pressure to be maintained for min. 4 hrs.
 Insulators to be securely fastened to carrier
pipes @ 1 m c/c.
IndianOil
CASED CROSSINGSCASED CROSSINGS
 At both ends of casing, double set of insulators
to be installed.
 Carrier pipe to be pulled/ pushed into casing in
such a way that insulators are not disturbed.
 Annular space between casing and carrier
pipes at both ends to be packed tightly with jute
and bitumen before fixing end seals in order to
prevent ingress of moisture/ water.
IndianOil
CASED CROSSINGSCASED CROSSINGS
 After installation, electrical test to be conducted
to determine resistance between carrier pipe &
casing pipe or carrier pipe & soil, which should
be min. 1 mega ohm.
 The earth to be properly compacted up to a
distance of 3 m from end of casing pipe on both
sides to avoid uneven settlement of carrier
pipe.
IndianOil
CASED CROSSINGSCASED CROSSINGS
IndianOil
TYPICAL CASED RAILWAYTYPICAL CASED RAILWAY
CROSSINGCROSSING
1.25 m
1.0 m Min.
1.7 m Min.
Vent Pipe
(80mm dia. MS pipe)
18 OD x 0.250” WT API 5L-X65 Grade Carrier Pipe
24 OD x 0..312” WT API 5L Grade B Casing Pipe
HDPE End SealHDPE Insulators
@ 1 m c/c
Boring Pit Exit Pit
1.0 m Min.1.0 m Min.
Railway
0.3 m.
0.5 m
GL
GL
PHOTOPHOTO
 Clear the site by removing all rubbish,broken
skids, empty canes,pieces of electrodes and other
construction material
 Restore ROW to the satisfaction of farmers and
obtain NOC from them
 Restore cut roads, canals, river banks etc and
obtain NOC from concerned Government
Department
IndianOil
Clean-Up and RestorationClean-Up and Restoration
PHOTOPHOTO
 Cleaning with compressed air with the help
of series of brush pigs
 Gauge plate of softer metal like Al of 95%
of ID of highest wall thickness pipe is
fastened to pig
 Retrieved gauge plate is analyzed and
preserved
IndianOil
Air pigging cleaning and GaugingAir pigging cleaning and Gauging
PIGPIG
HOMEHOME
 MECHANICAL CLEARANCE IS AVAILABLE. (Pipe
book completed)
 INSTRUMENTS AND EQUIPMENT TO BE USED ARE
WITH VALID CALIBRATION AND OF REQUIRED
RATING.
 WATER TESTING CERTIFICATE AND CORROSION
INHIBITOR DOSAGE RECOMMENDATION
AVAILABLE.
IndianOil
Hydrostatic TestingHydrostatic Testing
 GAUGE PLATE OF 95% ID AND 10 MM THICKNESS
SHALL BE PASSED THROUGH THE SECTION
AFTER CLEANING OF THE PIPE.
 GAUGE PLATE WITH < 2 MM SCRATCH ON SIDE
WALL AND WITH NO DENT IS ACCEPTABLE.
 CHECKING THE CONDITION AND SEQUENCE OF
PIGS IN THE HYDROSTATIC HEADER.
IndianOil
Hydrostatic TestingHydrostatic Testing
 ONLY QUALIFIED WELDER IS ALLOWED TO
PERFORM WELDING OF HEADER.
 CHECK RATING AND CONDITION OF HEADER
FITTINGS.
 USE THE FILLING WATER FROM TESTED
WATER SOURCE ONLY.
 FILL 500 MTRS. OF WATER BEFORE FIRST PIG
AND 1000 MTR WATER BETWEEN FIRST AND
SECOND PIG.
 FINAL FILLING SHALL BE DONE WITH FILL RATE
OF 2 KM/HRS.
IndianOil
Hydrostatic TestingHydrostatic Testing
 AFTER RECEIPT OF PIGS AT RECIVER MINIMUM
2 HRS. WATER FLUSHING SHALL BE ENSURED.
 TURBINE METER READING RECORDING SHALL
BE PRESERVED.
 THERMAL STABILIZATION FOR 24 HRS. SHALL
BE DONE AND SECTION IS SAID TO BE
THERMALLY STABILIZED IF DIFFERENCE NOT
HIGHER THAN 1 DEGREE IS ATTAINED
BETWEEN THE AVERAGE VALUE OF SOIL
TEMPERATURE READINGS
IndianOil
Hydrostatic TestingHydrostatic Testing
 PRESSURISE THE SECTION NOT MORE THAN 2
BAR/MIN RATE.
 FOLLOWING THE SEQUENCE MENTIONED BELOW:-
  a) PRESSURE THE PIPE SECTION TO 50%HOLD FOR I HR.
b) DROP 0.5 BAR DO AIR VOLUME CALCULATION.
c) DROP PRESSURE TO STATIC +1 BAR.
d) FOLLOW B & C FOR 75% PRESSURISATION.
e) IF AIR VOLUME CALCULATION VALUE IS BETWEEN 1
TO 1.06, THEN FILLING IS ACCEPTED.
IndianOil
Hydrostatic TestingHydrostatic Testing
 PRESSURE THE PIPE TO 125.18 TO 118.55 KG/CM2
(DEPENDING UPON PIPE SECTION PROFILE) AND
HOLD IT FOR 24 HRS.
 USE DWT AND RECORDING SYSTEM DURING
TESTING.
 THE TEST IS CONSIDERED ACCEPTABLE IF
DIFFERENCE IS LESS OR EQUAL TO 0.3 BAR IN
CASE OF DOUBT TESTING PERIOD SHALL BE
EXTENDED.
IndianOil
Hydrostatic TestingHydrostatic Testing
PHOTOPHOTO
 Need of cleaning and gauging
 Cleaning with compressed air with the help of
series of brush pigs
 Gauge plate of softer metal like Al of 95% of ID of
highest wall thickness pipe is fastened to pig
 Retrieved gauge plate is analyzed and preserved
IndianOil
Cleaning and Gauging OperationCleaning and Gauging Operation
 Boundary Pillars ( A set at every 250 m)
 Kilometer post
 Turning Point marker
 Direction Marker( Before and after a TP 200m)
 Warning Sign
Valve Installation:
Pre tested valves are installed at designated
locations after completion of hydrotest
IndianOil
Markers and Valve InstallationMarkers and Valve Installation
HOMEHOME
 To establish a benchmark of internal
conditions of pipeline viz dents,ovalities for
future references and surveys
 Dewatering by foam pigging
 Cleaning by brush pigging
 Magnetic pigging
 Programmed caliper pigging
 Downloading and interpretation
IndianOil
Caliper SurveyCaliper Survey
HOMEHOME
PHOTOPHOTO
 To preserve the line from internal corrosion
for a prescribed period due to non-
commissioning
 Pressurize pipe with inhibited water
 Dosage of inhibitor depending on duration of
preservation monthly, half yearly,yearly etc
and Quality of water to be filled
 Keep line in air tight condition by monitoring
pressure
IndianOil
Line PreservationLine Preservation
HOMEHOME
IndianOil
TYPICAL HEAVY WALL PIPE ROAD
CROSSINGS
δ
ROAD TOPGL
1.25 M min. cover
DRAINAGE DITCH
1.0 M min. cover
GL
PIPELINE
δ
δ
IndianOil
IndianOil
ROWROW
HOMEHOME
HOMEHOME
OFC
HDPE PIPE
HOMEHOME
HOMEHOME
HOMEHOME
HOMEHOME
HOMEHOME
HOMEHOME
HOMEHOME
HOMEHOME
HOMEHOME
HOMEHOME
AIR-VOLUME CALCULATION
AIR-VOLUME RATIO=Vi/Vp (Acceptable limit is 1.06 at
75%of test pressure cycle)
Vi=Actual volume of water drained to drop pressure by
0.05 Kg/Cm2
Vp=(0.884 ri / ti+A)X10-6 X Vt X P X K
Vp=Computed water amount required to raise by P the
pressure in the section to be tested (M3)
Vt=Geomatrical volume of the section (M3)
ri=Nominal inner radius of the pipe (mm)(Average)
ti=Nominal wall thickness of the pipe (mm)(Average)
A=Isothermal compressibility value for water at the
pressurization tempreture in the P range (bar-1)x106.
Ref graph.
P=Pressure Raise (bar)
K=A dimensionless coefficient that is equal to 1.02 for
longitudinally welded pipe.
Pipeline construction management

More Related Content

What's hot

Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
IEI GSC
 
Quality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionQuality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline construction
Suresh Zanwar
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Varun Patel
 
Introduction to piping design
Introduction to piping designIntroduction to piping design
Introduction to piping design
Ahmad Akileh, PE, PMP
 
Part 5 structural design of pipelines
Part 5 structural design of pipelinesPart 5 structural design of pipelines
Part 5 structural design of pipelinesGasforlife Polysource
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
Himanshu Gupta
 
valve maintenance
valve maintenancevalve maintenance
valve maintenance
Izzuwan Yusoff
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
Akhilesh Shukla
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
Piping Technology & Products, Inc.
 
Piping basics knowledge
Piping basics knowledgePiping basics knowledge
Piping basics knowledge
ARINDAM BANERJEE
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
MobinVarghese8
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
MFaridGeonova
 
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & GasResume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
jaison varkey
 
Steel pipeline laying in City Gas Distribution industry
Steel pipeline laying in City Gas Distribution industrySteel pipeline laying in City Gas Distribution industry
Steel pipeline laying in City Gas Distribution industry
Akshay Toraskar
 
Gas Pipeline Design
Gas Pipeline DesignGas Pipeline Design
Gas Pipeline Design
iyaselex
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and CommissioningWendy Soerachman
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
ignitetribes
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
Velmurugan Sivaraman
 

What's hot (20)

Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
 
Quality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionQuality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline construction
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
 
Introduction to piping design
Introduction to piping designIntroduction to piping design
Introduction to piping design
 
Part 5 structural design of pipelines
Part 5 structural design of pipelinesPart 5 structural design of pipelines
Part 5 structural design of pipelines
 
Basic piping
Basic pipingBasic piping
Basic piping
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
valve maintenance
valve maintenancevalve maintenance
valve maintenance
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
 
Piping basics knowledge
Piping basics knowledgePiping basics knowledge
Piping basics knowledge
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
 
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & GasResume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
 
Steel pipeline laying in City Gas Distribution industry
Steel pipeline laying in City Gas Distribution industrySteel pipeline laying in City Gas Distribution industry
Steel pipeline laying in City Gas Distribution industry
 
Gas Pipeline Design
Gas Pipeline DesignGas Pipeline Design
Gas Pipeline Design
 
Pigging In OIL INDUSTRY
Pigging In OIL INDUSTRY Pigging In OIL INDUSTRY
Pigging In OIL INDUSTRY
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
 

Viewers also liked

2. pipeline materials overview
2. pipeline materials overview2. pipeline materials overview
2. pipeline materials overviewWillam Le
 
Pipeline basic
Pipeline basicPipeline basic
Pipeline basic
mageshyess
 
Pipeline Inspection
Pipeline InspectionPipeline Inspection
Pipeline Inspection
LeakTech Australia
 
Pipeline Inspection in North America
Pipeline Inspection in North AmericaPipeline Inspection in North America
Pipeline Inspection in North America
Matej Makovický
 
Os f101 2013-10-2
Os f101 2013-10-2Os f101 2013-10-2
Os f101 2013-10-2
jpegd
 
Cp
CpCp
Rp e101 2012-01
Rp e101 2012-01Rp e101 2012-01
Rp e101 2012-01
jpegd
 
PPEJ.090.2010 rev2
PPEJ.090.2010 rev2PPEJ.090.2010 rev2
PPEJ.090.2010 rev2Rahmat Riski
 
Pipeline weld inspection
Pipeline weld inspectionPipeline weld inspection
Pipeline weld inspection
David Gray
 
Indramayu Subsea Pipeline
Indramayu Subsea PipelineIndramayu Subsea Pipeline
Indramayu Subsea Pipeline
arifsarwo
 
CD March 2015 - Bentley presentation about current BIM thinking
CD March 2015 - Bentley presentation about current BIM thinkingCD March 2015 - Bentley presentation about current BIM thinking
CD March 2015 - Bentley presentation about current BIM thinking
Comit Projects Ltd
 
Terms defenations-abriviations
Terms defenations-abriviationsTerms defenations-abriviations
Terms defenations-abriviationsAta Alvi
 
As 4822 2008 external field joint coatings for steel pipelines
As 4822 2008 external field joint coatings for steel pipelinesAs 4822 2008 external field joint coatings for steel pipelines
As 4822 2008 external field joint coatings for steel pipelines
toddfly
 
1st technical dinner meeting
1st technical dinner meeting1st technical dinner meeting
1st technical dinner meetingfatimah-h
 
3.1 Cleaning and Maintenance
3.1 Cleaning and Maintenance3.1 Cleaning and Maintenance
3.1 Cleaning and Maintenance
nurulaziaain
 
The Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
The Use of GIS and GPS in Pipeline Permitting and Regulatory ComplianceThe Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
The Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
wlgardnerjr
 
POWER POINT PRESENTATION-MSC PROJECT
POWER POINT PRESENTATION-MSC PROJECTPOWER POINT PRESENTATION-MSC PROJECT
POWER POINT PRESENTATION-MSC PROJECTWasiu Oseni
 

Viewers also liked (20)

2. pipeline materials overview
2. pipeline materials overview2. pipeline materials overview
2. pipeline materials overview
 
Pipeline Construction
Pipeline ConstructionPipeline Construction
Pipeline Construction
 
Pipeline basic
Pipeline basicPipeline basic
Pipeline basic
 
Pipeline Inspection
Pipeline InspectionPipeline Inspection
Pipeline Inspection
 
Pipeline Inspection in North America
Pipeline Inspection in North AmericaPipeline Inspection in North America
Pipeline Inspection in North America
 
Os f101 2013-10-2
Os f101 2013-10-2Os f101 2013-10-2
Os f101 2013-10-2
 
Cp
CpCp
Cp
 
Rp e101 2012-01
Rp e101 2012-01Rp e101 2012-01
Rp e101 2012-01
 
PPEJ.090.2010 rev2
PPEJ.090.2010 rev2PPEJ.090.2010 rev2
PPEJ.090.2010 rev2
 
Pipeline weld inspection
Pipeline weld inspectionPipeline weld inspection
Pipeline weld inspection
 
ashraf letest cv.
ashraf letest cv.ashraf letest cv.
ashraf letest cv.
 
Indramayu Subsea Pipeline
Indramayu Subsea PipelineIndramayu Subsea Pipeline
Indramayu Subsea Pipeline
 
CD March 2015 - Bentley presentation about current BIM thinking
CD March 2015 - Bentley presentation about current BIM thinkingCD March 2015 - Bentley presentation about current BIM thinking
CD March 2015 - Bentley presentation about current BIM thinking
 
Terms defenations-abriviations
Terms defenations-abriviationsTerms defenations-abriviations
Terms defenations-abriviations
 
As 4822 2008 external field joint coatings for steel pipelines
As 4822 2008 external field joint coatings for steel pipelinesAs 4822 2008 external field joint coatings for steel pipelines
As 4822 2008 external field joint coatings for steel pipelines
 
1st technical dinner meeting
1st technical dinner meeting1st technical dinner meeting
1st technical dinner meeting
 
3.1 Cleaning and Maintenance
3.1 Cleaning and Maintenance3.1 Cleaning and Maintenance
3.1 Cleaning and Maintenance
 
Saudi Aramco Inspection Procedure (SAIP)
Saudi Aramco Inspection Procedure (SAIP)Saudi Aramco Inspection Procedure (SAIP)
Saudi Aramco Inspection Procedure (SAIP)
 
The Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
The Use of GIS and GPS in Pipeline Permitting and Regulatory ComplianceThe Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
The Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
 
POWER POINT PRESENTATION-MSC PROJECT
POWER POINT PRESENTATION-MSC PROJECTPOWER POINT PRESENTATION-MSC PROJECT
POWER POINT PRESENTATION-MSC PROJECT
 

Similar to Pipeline construction management

Prism Group's corporate Presentation
Prism Group's corporate PresentationPrism Group's corporate Presentation
Prism Group's corporate Presentation
PRISM SURFACE COATINGS PVT LTD
 
269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf
moumo1
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
National Productivity Council, Hyderabad, India
 
Sewerage design
Sewerage designSewerage design
Sewerage design
Sharifah Ain
 
Wetpoint Aqua Equipments Pvt Ltd, Gwalior, Timber Cooling Towers
Wetpoint Aqua Equipments Pvt Ltd, Gwalior, Timber Cooling TowersWetpoint Aqua Equipments Pvt Ltd, Gwalior, Timber Cooling Towers
Wetpoint Aqua Equipments Pvt Ltd, Gwalior, Timber Cooling Towers
IndiaMART InterMESH Limited
 
Pipeline Construct.pptx
Pipeline Construct.pptxPipeline Construct.pptx
Pipeline Construct.pptx
ssuserfc98db
 
Idol Plasto Pvt. Ltd., Rajkot, UPVC Plumbing Pipes Fittings
Idol Plasto Pvt. Ltd., Rajkot, UPVC Plumbing Pipes FittingsIdol Plasto Pvt. Ltd., Rajkot, UPVC Plumbing Pipes Fittings
Idol Plasto Pvt. Ltd., Rajkot, UPVC Plumbing Pipes Fittings
IndiaMART InterMESH Limited
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologykumarrajagp
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
Loay Ghazaleh MBA, BSc Civil Eng.
 
casestudytrilium-190419191926.pdf
casestudytrilium-190419191926.pdfcasestudytrilium-190419191926.pdf
casestudytrilium-190419191926.pdf
Pradeep889886
 
Case study trilium MALL AMRITSAR
Case study trilium MALL AMRITSARCase study trilium MALL AMRITSAR
Case study trilium MALL AMRITSAR
Prince Pathania
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
Elsayed Amer
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
Elsayed Amer
 
SPC HDPE BROCHURE NEW
SPC HDPE BROCHURE NEWSPC HDPE BROCHURE NEW
SPC HDPE BROCHURE NEWLia Collatz
 
Pigging Pipelines.pdf
Pigging Pipelines.pdfPigging Pipelines.pdf
Pigging Pipelines.pdf
Fast name Last name
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Gaurav Singh Rajput
 
CRPS_The_IPV_System
CRPS_The_IPV_SystemCRPS_The_IPV_System
CRPS_The_IPV_SystemPaul Francis
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular Concrete
Jill Reeves
 
2376 robor ductile_iron_brochure5
2376 robor ductile_iron_brochure52376 robor ductile_iron_brochure5
2376 robor ductile_iron_brochure5
Joshua Ting
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologyRemya Rajeev
 

Similar to Pipeline construction management (20)

Prism Group's corporate Presentation
Prism Group's corporate PresentationPrism Group's corporate Presentation
Prism Group's corporate Presentation
 
269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Sewerage design
Sewerage designSewerage design
Sewerage design
 
Wetpoint Aqua Equipments Pvt Ltd, Gwalior, Timber Cooling Towers
Wetpoint Aqua Equipments Pvt Ltd, Gwalior, Timber Cooling TowersWetpoint Aqua Equipments Pvt Ltd, Gwalior, Timber Cooling Towers
Wetpoint Aqua Equipments Pvt Ltd, Gwalior, Timber Cooling Towers
 
Pipeline Construct.pptx
Pipeline Construct.pptxPipeline Construct.pptx
Pipeline Construct.pptx
 
Idol Plasto Pvt. Ltd., Rajkot, UPVC Plumbing Pipes Fittings
Idol Plasto Pvt. Ltd., Rajkot, UPVC Plumbing Pipes FittingsIdol Plasto Pvt. Ltd., Rajkot, UPVC Plumbing Pipes Fittings
Idol Plasto Pvt. Ltd., Rajkot, UPVC Plumbing Pipes Fittings
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
casestudytrilium-190419191926.pdf
casestudytrilium-190419191926.pdfcasestudytrilium-190419191926.pdf
casestudytrilium-190419191926.pdf
 
Case study trilium MALL AMRITSAR
Case study trilium MALL AMRITSARCase study trilium MALL AMRITSAR
Case study trilium MALL AMRITSAR
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
SPC HDPE BROCHURE NEW
SPC HDPE BROCHURE NEWSPC HDPE BROCHURE NEW
SPC HDPE BROCHURE NEW
 
Pigging Pipelines.pdf
Pigging Pipelines.pdfPigging Pipelines.pdf
Pigging Pipelines.pdf
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
CRPS_The_IPV_System
CRPS_The_IPV_SystemCRPS_The_IPV_System
CRPS_The_IPV_System
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular Concrete
 
2376 robor ductile_iron_brochure5
2376 robor ductile_iron_brochure52376 robor ductile_iron_brochure5
2376 robor ductile_iron_brochure5
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 

Recently uploaded

6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 

Recently uploaded (20)

6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 

Pipeline construction management

  • 1.
  • 2. Activities of Pipeline constructionActivities of Pipeline construction PROCEDUREPROCEDURE Right of Way clearing and gradingRight of Way clearing and grading Delivery, Transportation, Handling,Delivery, Transportation, Handling, Hauling, Stringing of pipesHauling, Stringing of pipes Trenching Normal & RockTrenching Normal & Rock BendingBending Lining up and WeldingLining up and Welding Radiographic InspectionRadiographic Inspection IndianOil
  • 3. Activities of Pipeline constructionActivities of Pipeline construction Application of Joint CoatingApplication of Joint Coating Lowering & back fillingLowering & back filling Tie-insTie-ins River and Road crossingsRiver and Road crossings Cleanup and Restoration of ROWCleanup and Restoration of ROW Air Pigging cleaning and GaugingAir Pigging cleaning and Gauging Hydrostatic testingHydrostatic testing IndianOil
  • 4. Activities of Pipeline constructionActivities of Pipeline construction De watering cleaning and SwabbingDe watering cleaning and Swabbing Golden Tie insGolden Tie ins Valve installationValve installation Caliper survey and dent repairsCaliper survey and dent repairs Line PreservationLine Preservation IndianOil
  • 5. IndianOil WORK PROCEDURE Purpose: The purpose of work procedure is to stipulate the method that shall be used for a particular activity covering even minute steps in details.  The work procedure is to be prepared by agency responsible for execution of work.  The work procedure is examined criticaly and approved by owner/owner representative.  No deviation from work procedure is accepted.
  • 6. IndianOil NEED FOR WORK PROCEDURE It helps: 1.In clearly defining the procedure to be adopted in execution of activity. 2.In establishing QAP a tool for inspection. 3.In developing records for future reference. 4.In case of any dispute arising at later stage.
  • 8. IndianOil Document Number TITLE/Remarks XX/WP/100 Survey,Clearing & Grade XX/WP/101 Trench XX/WP/102 Blasting XX/WP/103 Pipe Handling And Stringing XX/WP/104 Bending XX/WP/105 Concrete coating by casting procedure XX/WP/106 Tie-in XX/WP/107 NDT Procedure for Mainline Welding XX/WP/108 Applications of Heat shrinkable sleeves XX/WP/109 Lowering in and rock shield applications XX/WP/110 Backfill XX/WP/111 Cathodic protection installation XX/WP/112 Pre testing of Pipeline crossings
  • 9. IndianOil Document Number TITLE/Remarks XX/WP/113 Pipeweld numbering XX/WP/114 Casting and placing of precast weights XX/WP/115 Concrete coating of pipes impingement method XX/WP/116 handling over coated pipes at Coating yard XX/WP/117 Cased crossings XX/WP/118 Repair of accidental arc strikes XX/WP/119 TCP XX/WP/120 Ultrasonics XX/WP/121 DP & MPI XX/WP/122 final cleanup and restoration XX/WP/123 Open cut Crossings XX/WP/124 Major River crossings HOME
  • 10.  Centre line of ROW is marked based on IP and TP fixed during detailed route survey  Wooden pegs are put on either side of the center line at a distance of 9 meters for 18 m ROW.  ROW width is kept as 6 m on left of Pipeline for storing the excavated soil and 12 m on right side for movement of equipments. IndianOil ROW Clearing and GradingROW Clearing and Grading
  • 11.  Dozer with flat front blade is used to clear the vegetation and trees  Prior information to land owners to clear the land of their crops before entering IndianOil ROW Clearing and GradingROW Clearing and Grading HOME PHOTO
  • 12.  To prevent transit damage nylon rope rings are tied at every three meter distance  Profiled wooden supports are required to place first layer of the pipes on the trailer  To avoid damage to pipe bevel, though the bevel protectors are provided on pipe ends, crane hooks shall be provided with rubber pads for additional safety.  Careful stacking of pipes over sand bags, visual inspection of bevel ends to avoid welding defects. IndianOil Transportation Handling and StringingTransportation Handling and Stringing of the Pipesof the Pipes PHOTOPHOTO
  • 13.  In cultivable land, to strip top soil (30 cm depth) & store separately along ROW for replacement on top of backfilled ditch.  Provide suitable crossings across open ROW for land owners/ public.  Width of trench : Pipe OD + 300 mm.  Depth of trench to be measured from original ground/ graded surface/ top of road/ bottom of rail, whichever is lower. IndianOil TRENCHINGTRENCHING
  • 14.  Provide 300 mm additional cover where pipeline is within 15 m of private dwelling, industrial buildings or public places.  Provide temp. diversions/ bridges at road crossings to allow passage of normal traffic with min. inconvenience.  Provide warning/ traffic signs, lights, barricades, fencing, watchmen as required by local authorities.  Provide extra depth to fit min. radius of bend at crossings. IndianOil TRENCHINGTRENCHING
  • 15. Sl.Sl. No.No. LocationLocation Min. CoverMin. Cover (m)(m) 11 Industrial, Commercial, Residential Areas (NormalIndustrial, Commercial, Residential Areas (Normal Terrain)Terrain) 1.251.25 22 Uncased/ Cased Road CrossingsUncased/ Cased Road Crossings & Cart-Track Crossings& Cart-Track Crossings 1.251.25 33 Railway CrossingsRailway Crossings 1.701.70 44 Normal Terrain / Drainage ditches at Railways,Normal Terrain / Drainage ditches at Railways, Highways etc.Highways etc. 1.201.20 55 Minor Water Course CrossingsMinor Water Course Crossings 1.501.50 66 Marshy Areas/ Water reservoir Areas/ PondsMarshy Areas/ Water reservoir Areas/ Ponds 1.501.50 77 Submerged River CrossingsSubmerged River Crossings 2.502.50 88 Rocky AreasRocky Areas 1.001.00
  • 17.  Cold field bends for change of vertical & horizontal alignment by using bending machine & mandrel.  Bends to be made without causing wrinkles, buckles, stretching & damage to pipe coating.  Bending procedure to be established including step length & max. degree per pull per foot (0.9550 for 18” OD pipes).  Over bends to be made to clear high points of the trench bottom. IndianOil BENDINGBENDING
  • 18.  Sag bends to fit the bottom of the trench.  Side bends to leave min. clearance to trench wall.  Radius of curvature > 40 D upto 18” OD & > 60 D for above 18” OD pipes.  End of bend should not be closer than 2 m from girth weld or pipe end.  Bends to be installed by positioning longitudinal welds in upper quadrant. IndianOil BENDINGBENDING
  • 19.  Ovality of bent pipe < 2.5 % of nominal dia. at any point; to be checked by passing a gauge consisting of two discs of 95% nominal pipe internal dia.  To layout pipes in such a way that Nos. of pieces cut off less than 2 m are held min.  No Mitre bends are permitted.  Hot pulled bends may be used in unavoidable circumstances. IndianOil BENDINGBENDING PHOTOPHOTO
  • 20.  STANDARDS/CODES.  WELDING TECHNIQUES.  WELDING PROCEDURES.  WELDER’S QUALIFICATION TEST. IndianOil MAINLINE WELDINGMAINLINE WELDING
  • 21. FOLLOWING STANDARDS/CODES ARE REFFERED IN INSPECTION & TESTING OF WELD.  API 1104, Welding of pipelines and related facilities.  ASME Sec IX, Boiler & Pressure vessel Code. IndianOil STANDARDS/CODESSTANDARDS/CODES
  • 23. A) Tensile strength test B) Nick break test C) Root, face and side bend test IndianOil Destructive TestDestructive Test
  • 24. Scope of work includes 100% Radiographic inspection of all joints for the initial 1 Km of the pipeline in each spread. For balance portion of the pipeline ,20% of all joints shall be radio-graphically inspected except for specific crossings and tie-ins which need 100% radio-graphic inspection IndianOil RadiographyRadiography
  • 26.  COATING CLEARANCE IS AVAILABLE FROM RADIOGRAPHY CREW.  HUMIDITY <85%, IF BETWEEN 75% TO 85% PREHEAT BEFORE BLASTING.  CLEANING OF JOINT AREA AND ADJACENT COATING DONE UPTO 100MM ON CTE COATING ON BOTH PIPES  CHAMPER THE PIPE COATING TO AN ANGLE<30  PREHEAT THE WELDED JOINT AREA TO 60-80 C IndianOil JOINT COATINGJOINT COATING
  • 27.  SANDBLASTING IS DONE UPTO 100 MM ON CTE COATING ON BOTH PIPES  ENTIRE SAND BLAST SURFACE IS FREE FROM MOISTURE.  THE ROUGHNESS OF SAND BLASTED SURFACES IS BETWEEN 50-70 MICRON AS MEASURED BY PRESS-O-FILM/ELCOMETER.  PART A(60+10ml)PRIMER & PART B(30+10ml) EPOXY IS MIXED FOR MIN 30 SEC  PREHEATING OF PIPE TO A TEMPERATURE OF 60- 80o C DONE. IndianOil JOINT COATINGJOINT COATING
  • 28.  THE OVERLAP POSITION OF THE SLEEVE IS AT 2 OR 10 ‘O’ CLOCK.  WET FILM THICKNESS OF PRIMER IS BETWEEN 50- 70 MICRONS.  SIDE OF OVERLAP PORTION HEATED & PRESSED WITH SILICON ROLLERS.  THE CLOSURE PATCH IS HEATED, PRESSED & SEALED ON THE SLEEVE.  DIRECTION OF FLAME IS CIRCULAR & FROM ONE END TO OTHER END.  THE SLEEVE IS COMPLETELY SHRUNK AND CONFORMS TO PIPE IndianOil JOINT COATINGJOINT COATING
  • 29.  SLEEVE IS FREE FROM WRINKLES, COLD SPOTS, ENTRAPPED AIR IS EXPELLED BY HEATING & PRESSING WITH ROLLER OR BY HAND.  THICKNES OF SLEEVE ON WELD SEEM IS MIN 1.7MM AND ON PARENT METAL IS MIN 2MM.  PEEL TEST DONE ONE IN EVERY 100 JOINTS OR DAY’S PRODUCTION WHICHEVER IS LOWER ON SUBSEQUENT MORNING. IndianOil JOINT COATINGJOINT COATING
  • 30.  PEEL TEST PROCEDURE PEEL SIZED 1” BY 8” PEEL CUT UPTO BARE PIPE ANY LOCATION- AT WELDED SEAM, ON PIPE AND ON CTE COATING FAILS IF PEEL OF FORCE IS LESS AT OBSERVED TEMP. OR ADHESIVE LAYER OF SLEEVE IS PEELED OFF FROM PIPE. PEEL TESTED PORTION IS REPAIRED. IndianOil JOINT COATINGJOINT COATING PHOTOPHOTO
  • 31. Before lowering of pipeline in the trench,  To clear the trench of all debris, stones, pipe cut pieces, welding rods, hard clods, skids etc. before lowering of pipeline.  To drain out water from the trench (if any) to avoid floatation.  To carry out complete check by full circle holiday detector. IndianOil PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
  • 32. Before lowering of pipeline in the trench,  To repair all coating damages.  To provide sand padding (150 mm thick) free from gravel/ pebbles in rocky areas.  Pipeline to be lifted & laid by using non- abrasive material (Teflon) coated hooks. IndianOil PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
  • 33. Before lowering of pipeline in the trench,  No sling to be put around field joint coating.  Adequate Nos. of side booms to be used for holding the pipeline in gentle S-curve maintaining elastic bend radius.  Pipeline not to be laid in tension. Trench to be rectified (if required) so that the pipeline fits the excavation and rests on the trench bed.  To avoid movement of pipeline in the trench. IndianOil PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
  • 34.  BACKFILLING OF PREVIOUS SECTION HAS BEEN COMPLETED.  LOWERING CLEARANCE FROM JOINT COATING SITE IS AVAILABLE.  RADIOGRAPHY CLEARANCE FOR LEFT OUT JOINTS IS AVAILABLE.  COATING CHECKED VISUALLY FOR DEFECTS AND REPAIRS DONE, IF REQUIRED.  HOLIDAY DONE AT 15 KV  DEPTH AT 4 LOCATIONS IS CHECKED AND FOUND .1.5 M IndianOil PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
  • 35.  WIDTH CHECKED AT BOTTOM OF TRENCH AT 4 LOCATIONS AND FOUND . 1.2 m  TRENCH BOTTOM IS FREE FROM ROCKY STRATA  SOFT PADDING ON THE BOTTOM OF TRENCH DONE  NIGHT CAPS ARE PROVIDED ON OPEN ENDS OF PIPE SECTION.  SLING OF SIDE BOOM IS NOT BE ON FIELD JOINT COATING.  PIPE IS LOWERED IN THE RIGHT SIDE OF THE TRENCH.  DISTANCE OF HDPE PIPE FROM MAIN PIPE IS 400MM. IndianOil PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
  • 36.  SPIKES PROVIDED AT 10 M INTERVAL ALONG THE ROUTE OF HDPE PIPE.  SPIKE REMOVED AFTER PADING.  WARNING TAPE IS LAID AT 400 MM ABOVE HDPE PIPE IndianOil PIPELINE LOWERING IN TRENCHPIPELINE LOWERING IN TRENCH
  • 38. The gaps which are left out during mainline welding due to road/railway crossing, canal/river crossings etc are connected in the form of Tie-in joints IndianOil Tie- InsTie- Ins PHOTOPHOTO
  • 39. 1. Cased crossings for Railways & Highways (NH/ SH)  Casing pipe: 24” OD x 0.281” WT API 5L Gr. B  Carrier Pipe: 18” OD x 0.250” WT API 5L X65 2. Uncased crossings (open cut) for minor roads/ cart – tracks using heavy wall pipe (18” OD x 0.281” WT API 5L X65). 3. Minor water course crossings (open cut) using normal pipe (18” OD x 0.250” WT API 5L X65) IndianOil TYPES OF CROSSINGSTYPES OF CROSSINGS
  • 40. 4. Submerged river crossings (open cut) using heavier wall pipe (18” OD x 0. 375” WT API 5L X65) with concrete coating/ HDD XING 5. Crossings for existing underground facilities like pipelines, cables using normal pipe (18” OD x 0.250” WT API 5L X65) with min. clearance of 500 mm. Crossings at Sl. No. 2, 3 & 5 above are part of mainline item. Cased and submerged river crossings are separate items. IndianOil TYPES OF CROSSINGSTYPES OF CROSSINGS
  • 41.  Execute crossing work as per concerned Statutory Authority permission conditions.  Highways, main roads, rail roads & their verges and banks of water courses not to be used for loading, unloading or stacking of materials or equipment.  Roads or water courses not to be closed or diverted without prior permission of concerned Statutory Authority.  Before execution of cased and submerged river crossings, detailed methodology to be submitted by contractor containing:  Time schedule,  Working method,  Equipment to be deployed  Test procedure  Manning  Soil Investigations. IndianOil CROSSINGSCROSSINGS
  • 42.  To be executed by horizontal boring technique.  Casing pipe to be 6” larger in dia. than carrier pipe.  Carrier pipes to be 3 LPE coated. No coating of casing pipes.  Ground water table (if encountered) over length of boring to be lowered up to at least 0.5 m below bottom of the pipeline. IndianOil CASED CROSSINGSCASED CROSSINGS
  • 43.  For boring pits in unstable soils, closed sheet piling to be used.  Boring/ exit pit bottom to be graded for min. 12 m at the approach to each end of casing.  Backfill in boring/ exit pits to be compacted in 15 cm layers to 90% proctor density by mech. compactor after dewatering. IndianOil CASED CROSSINGSCASED CROSSINGS
  • 44.  Dia. of bored hole to be almost same as casing pipe OD.  Vent pipes to be provided on both ends of casing in such a way that there is no contact with carrier pipe.  100% radiographic inspection of weld joints of carrier pipes. IndianOil CASED CROSSINGSCASED CROSSINGS
  • 45.  Prior to installation, hydrostatic pre-testing of the carrier pipeline section to be carried out at a pressure corresponding to 95% SMYS of pipe material (120.62 kg/cm2 for SSPL) . Test pressure to be maintained for min. 4 hrs.  Insulators to be securely fastened to carrier pipes @ 1 m c/c. IndianOil CASED CROSSINGSCASED CROSSINGS
  • 46.  At both ends of casing, double set of insulators to be installed.  Carrier pipe to be pulled/ pushed into casing in such a way that insulators are not disturbed.  Annular space between casing and carrier pipes at both ends to be packed tightly with jute and bitumen before fixing end seals in order to prevent ingress of moisture/ water. IndianOil CASED CROSSINGSCASED CROSSINGS
  • 47.  After installation, electrical test to be conducted to determine resistance between carrier pipe & casing pipe or carrier pipe & soil, which should be min. 1 mega ohm.  The earth to be properly compacted up to a distance of 3 m from end of casing pipe on both sides to avoid uneven settlement of carrier pipe. IndianOil CASED CROSSINGSCASED CROSSINGS
  • 48. IndianOil TYPICAL CASED RAILWAYTYPICAL CASED RAILWAY CROSSINGCROSSING 1.25 m 1.0 m Min. 1.7 m Min. Vent Pipe (80mm dia. MS pipe) 18 OD x 0.250” WT API 5L-X65 Grade Carrier Pipe 24 OD x 0..312” WT API 5L Grade B Casing Pipe HDPE End SealHDPE Insulators @ 1 m c/c Boring Pit Exit Pit 1.0 m Min.1.0 m Min. Railway 0.3 m. 0.5 m GL GL PHOTOPHOTO
  • 49.  Clear the site by removing all rubbish,broken skids, empty canes,pieces of electrodes and other construction material  Restore ROW to the satisfaction of farmers and obtain NOC from them  Restore cut roads, canals, river banks etc and obtain NOC from concerned Government Department IndianOil Clean-Up and RestorationClean-Up and Restoration PHOTOPHOTO
  • 50.  Cleaning with compressed air with the help of series of brush pigs  Gauge plate of softer metal like Al of 95% of ID of highest wall thickness pipe is fastened to pig  Retrieved gauge plate is analyzed and preserved IndianOil Air pigging cleaning and GaugingAir pigging cleaning and Gauging PIGPIG
  • 52.  MECHANICAL CLEARANCE IS AVAILABLE. (Pipe book completed)  INSTRUMENTS AND EQUIPMENT TO BE USED ARE WITH VALID CALIBRATION AND OF REQUIRED RATING.  WATER TESTING CERTIFICATE AND CORROSION INHIBITOR DOSAGE RECOMMENDATION AVAILABLE. IndianOil Hydrostatic TestingHydrostatic Testing
  • 53.  GAUGE PLATE OF 95% ID AND 10 MM THICKNESS SHALL BE PASSED THROUGH THE SECTION AFTER CLEANING OF THE PIPE.  GAUGE PLATE WITH < 2 MM SCRATCH ON SIDE WALL AND WITH NO DENT IS ACCEPTABLE.  CHECKING THE CONDITION AND SEQUENCE OF PIGS IN THE HYDROSTATIC HEADER. IndianOil Hydrostatic TestingHydrostatic Testing
  • 54.  ONLY QUALIFIED WELDER IS ALLOWED TO PERFORM WELDING OF HEADER.  CHECK RATING AND CONDITION OF HEADER FITTINGS.  USE THE FILLING WATER FROM TESTED WATER SOURCE ONLY.  FILL 500 MTRS. OF WATER BEFORE FIRST PIG AND 1000 MTR WATER BETWEEN FIRST AND SECOND PIG.  FINAL FILLING SHALL BE DONE WITH FILL RATE OF 2 KM/HRS. IndianOil Hydrostatic TestingHydrostatic Testing
  • 55.  AFTER RECEIPT OF PIGS AT RECIVER MINIMUM 2 HRS. WATER FLUSHING SHALL BE ENSURED.  TURBINE METER READING RECORDING SHALL BE PRESERVED.  THERMAL STABILIZATION FOR 24 HRS. SHALL BE DONE AND SECTION IS SAID TO BE THERMALLY STABILIZED IF DIFFERENCE NOT HIGHER THAN 1 DEGREE IS ATTAINED BETWEEN THE AVERAGE VALUE OF SOIL TEMPERATURE READINGS IndianOil Hydrostatic TestingHydrostatic Testing
  • 56.  PRESSURISE THE SECTION NOT MORE THAN 2 BAR/MIN RATE.  FOLLOWING THE SEQUENCE MENTIONED BELOW:-   a) PRESSURE THE PIPE SECTION TO 50%HOLD FOR I HR. b) DROP 0.5 BAR DO AIR VOLUME CALCULATION. c) DROP PRESSURE TO STATIC +1 BAR. d) FOLLOW B & C FOR 75% PRESSURISATION. e) IF AIR VOLUME CALCULATION VALUE IS BETWEEN 1 TO 1.06, THEN FILLING IS ACCEPTED. IndianOil Hydrostatic TestingHydrostatic Testing
  • 57.  PRESSURE THE PIPE TO 125.18 TO 118.55 KG/CM2 (DEPENDING UPON PIPE SECTION PROFILE) AND HOLD IT FOR 24 HRS.  USE DWT AND RECORDING SYSTEM DURING TESTING.  THE TEST IS CONSIDERED ACCEPTABLE IF DIFFERENCE IS LESS OR EQUAL TO 0.3 BAR IN CASE OF DOUBT TESTING PERIOD SHALL BE EXTENDED. IndianOil Hydrostatic TestingHydrostatic Testing
  • 59.  Need of cleaning and gauging  Cleaning with compressed air with the help of series of brush pigs  Gauge plate of softer metal like Al of 95% of ID of highest wall thickness pipe is fastened to pig  Retrieved gauge plate is analyzed and preserved IndianOil Cleaning and Gauging OperationCleaning and Gauging Operation
  • 60.  Boundary Pillars ( A set at every 250 m)  Kilometer post  Turning Point marker  Direction Marker( Before and after a TP 200m)  Warning Sign Valve Installation: Pre tested valves are installed at designated locations after completion of hydrotest IndianOil Markers and Valve InstallationMarkers and Valve Installation HOMEHOME
  • 61.  To establish a benchmark of internal conditions of pipeline viz dents,ovalities for future references and surveys  Dewatering by foam pigging  Cleaning by brush pigging  Magnetic pigging  Programmed caliper pigging  Downloading and interpretation IndianOil Caliper SurveyCaliper Survey HOMEHOME PHOTOPHOTO
  • 62.  To preserve the line from internal corrosion for a prescribed period due to non- commissioning  Pressurize pipe with inhibited water  Dosage of inhibitor depending on duration of preservation monthly, half yearly,yearly etc and Quality of water to be filled  Keep line in air tight condition by monitoring pressure IndianOil Line PreservationLine Preservation HOMEHOME
  • 63. IndianOil TYPICAL HEAVY WALL PIPE ROAD CROSSINGS δ ROAD TOPGL 1.25 M min. cover DRAINAGE DITCH 1.0 M min. cover GL PIPELINE δ δ
  • 66.
  • 67.
  • 68.
  • 70.
  • 72.
  • 74.
  • 77.
  • 81.
  • 82.
  • 83.
  • 84.
  • 85.
  • 86.
  • 87.
  • 88.
  • 89.
  • 90.
  • 92.
  • 94.
  • 95.
  • 98. AIR-VOLUME CALCULATION AIR-VOLUME RATIO=Vi/Vp (Acceptable limit is 1.06 at 75%of test pressure cycle) Vi=Actual volume of water drained to drop pressure by 0.05 Kg/Cm2 Vp=(0.884 ri / ti+A)X10-6 X Vt X P X K Vp=Computed water amount required to raise by P the pressure in the section to be tested (M3) Vt=Geomatrical volume of the section (M3) ri=Nominal inner radius of the pipe (mm)(Average) ti=Nominal wall thickness of the pipe (mm)(Average) A=Isothermal compressibility value for water at the pressurization tempreture in the P range (bar-1)x106. Ref graph. P=Pressure Raise (bar) K=A dimensionless coefficient that is equal to 1.02 for longitudinally welded pipe.