More Related Content Similar to 3-Days Construction Schedule (20) More from Vladimir Popovic (20) 3-Days Construction Schedule1. Yesterday
(actual)
Time
(from)
Time
(until)
Today
(planned)
Time
(from)
Time
(until)
Tomorrow
(planned)
Time
(from)
Time
(until)
Day after Tomorrow
(planned) Notes
1 Excavation
1.1
1.2 Excavation Sta.8+500 / 8+625 08:00 18:00 Sta.9+000 / 9+125 Sta.9+500 / 9+625 Sta.10+000 / 10+125
Team 1 Sta.8+625 / 8+750 08:00 18:00 Sta.9+125 / 9+250 Sta.9+625 / 9+750 Sta.10+125 / 10+250
Team 2 Sta.8+750 / 8+875 08:00 18:00 Sta.9+250 / 9+375 Sta.9+750 / 9+875 Sta.10+250 / 10+375
Team 3 Sta.8+875 / 9+000 08:00 18:00 Sta.9+375 / 9+500 Sta.9+875 / 10+000 Sta.10+375 / 10+500
1.3 Drilling, jack & pick hammering / / / /
1.5 Trench Sub-grade Blasting / / / /
1.6 Clearing & excavation / / / /
1.7 Final trench elevation Survey Sta.8+000 / 8+500 12:00 18:00 Sta.8+500 / 9+000 Sta.9+000 / 9+500 Sta.9+500 / 10+000
1.8 Sta.8+000 / 8+500 16:30 17:30 Sta.8+500 / 9+000 Sta.9+000 / 9+500 Sta.9+500 / 10+000
1.9 Sta.7+500 / 8+000 08:00 15:00 Sta.8+000 / 8+500 Sta.8+500 / 9+000 Sta.9+000 / 9+500
1.10 Field Density Test (FDT) Sta.7+500 / 8+000 15:00 16:00 Sta.8+000 / 8+500 Sta.8+500 / 9+000 Sta.9+000 / 9+500
1.11 Sta.7+000 / 7+500 08:00 18:00 Sta.7+500 / 8+000 Sta.8+000 / 8+500 Sta.8+500 / 9+000
1.12 Sta.7+000 / 7+500 08:00 18:00 Sta.7+500 / 8+000 Sta.8+000 / 8+500 Sta.8+500 / 9+000
1.13 Sta.6+500 / 7+000 08:00 18:00 Sta.7+000 / 7+500 Sta.7+500 / 8+000 Sta.8+000 / 8+500
1.14 Sta.6+000 / 6+500 08:00 18:00 Sta.6+500 / 7+000 Sta.7+000 / 7+500 Sta.7+500 / 8+000
2 Backfilling
2.1 Sta.6+000 / 6+500 08:00 18:00 Sta.6+500 / 7+000 Sta.8+000 / 8+500 Sta.8+500 / 9+000
2.2 Field Density Test (FDT) Sta.5+500 / 6+000 13:30 14:30 Sta.6+000 / 6+500 Sta.6+500 / 7+000 Sta.8+000 / 8+500
2.3 Sta.5+500 / 6+000 14:30 18:00 Sta.6+000 / 6+500 Sta.6+500 / 7+000 Sta.8+000 / 8+500
2.4 Field Density Test (FDT) Sta.5+000 / 5+500 12:00 13:00 Sta.5+500 / 6+000 Sta.6+000 / 6+500 Sta.6+500 / 7+000
2.5 Sta.5+000 / 5+500 13:00 18:00 Sta.5+500 / 6+000 Sta.6+000 / 6+500 Sta.6+500 / 7+000
2.6 Field Density Test (FDT) Sta.4+500 / 5+000 10:30 11:30 Sta.5+000 / 5+500 Sta.5+500 / 6+000 Sta.6+000 / 6+500
2.7 Sta.4+500 / 5+000 11:30 18:00 Sta.5+000 / 5+500 Sta.5+500 / 6+000 Sta.6+000 / 6+500
2.8 Sta.4+000 / 4+500 09:00 10:00 Sta.4+500 / 5+000 Sta.5+000 / 5+500 Sta.5+500 / 6+000
3 Manholes
3.1 MH(43, 44, 45)
Final Backfilling & Compaction (20cm)
3-DAY PROGRESS SCHEDULE
Setting-Out, Routing, Clearing
Sand bedding, shaped bedding
Pipe-laying
Invert elevation verification (As Built)
House Connections installation
Sub-grade Verification (SPT-Standard
Penetration Test)
Survey marking (As Built)
Side-fill & Compaction
Initial backfilling (30cm above the crown)
Main Backfilling & Compaction
Plate Load test
Blinding Concrete3.1 MH(43, 44, 45)
3.2
3.3 MV(30), TO(13), MH(42)
3.4 Re-bar Inspection MV(30), TO(13), MH(42) 16:30 18:00 MV(30), TO(13), MH(42)
3.5 MV(30), TO(13), MH(42)
3.6 Formwork Inspection 16:30 18:00 MV(30), TO(13), MH(42)
3.7 AV(25), MH(39, 40) MV(30), TO(13), MH(42)
3.8 MH(31, 32, 33, 34) 09:00 11:00 MH(35, 36, 37, 38)
3.9 AV(24); MH(29, 30, 31) 08:00 18:00 MH(31, 32, 33, 34) MH(35, 36, 37, 38)
3.10 MV(28), TO(12) 11:00 16:30 AV(24); MH(29, 30, 31) MH(31, 32, 33, 34) MH(35, 36, 37, 38)
3.11 MV(28), TO(12) 11:00 18:00 AV(24); MH(29, 30, 31) MH(31, 32, 33, 34) MH(35, 36, 37, 38)
4 Testing
4.1 12:00 16:00 Sta.8+000 / 8+500 Sta.8+500 / 8+900
4.2 Sta.5+000 / 8+500
4.3
5 Reconnection
6 Final Reinstatement of Surfaces Sta.0+000 / 3+000 08:00 18:00 Sta.3+000 / 5+000
6.1 Sta.0+000 / 3+000 08:00 18:00 Sta.3+000 / 5+000
6.2 Sta.1+000 / 2+000 08:00 18:00 Sta.2+000 / 3+000 Sta.3+000 / 4+000 Sta.4+000 / 5+000
6.3 Sta.0+000 / 3+000
7 As Built Drawing
7.1
7.2
7.3
8 Taking Over Inspection
8.1
9 Final Taking Over Inspection
10 Material
10.1 Material Delivery
Gate Valves, Air Valves,
Hydrants
10.2 Material Inspection 10:00 12:00
(Gate Valves, Air Valves,
Hydrants)
Blinding Concrete
Reinforcement Works
Formworks
Concrete pouring
Tightness Testing
Outter Hydro-insulation
Backfilling & Compaction
Installation (Pre-fabricated)
Pre-backfilling inspection
Hydrostatic Pressure / Tightness Testing
CCTV Inspection (WW only)
Disinfection (WS only)
Green area
Asphalting
Asphalt testing - Kern sampling
Final Survey measurement
Preparation of As Built Drawings
Submission of As Built Drawings
Remedial Works