SlideShare a Scribd company logo
1 of 1
Download to read offline
Yesterday
(actual)
Time
(from)
Time
(until)
Today
(planned)
Time
(from)
Time
(until)
Tomorrow
(planned)
Time
(from)
Time
(until)
Day after Tomorrow
(planned) Notes
1 Excavation
1.1
1.2 Excavation Sta.8+500 / 8+625 08:00 18:00 Sta.9+000 / 9+125 Sta.9+500 / 9+625 Sta.10+000 / 10+125
Team 1 Sta.8+625 / 8+750 08:00 18:00 Sta.9+125 / 9+250 Sta.9+625 / 9+750 Sta.10+125 / 10+250
Team 2 Sta.8+750 / 8+875 08:00 18:00 Sta.9+250 / 9+375 Sta.9+750 / 9+875 Sta.10+250 / 10+375
Team 3 Sta.8+875 / 9+000 08:00 18:00 Sta.9+375 / 9+500 Sta.9+875 / 10+000 Sta.10+375 / 10+500
1.3 Drilling, jack & pick hammering / / / /
1.5 Trench Sub-grade Blasting / / / /
1.6 Clearing & excavation / / / /
1.7 Final trench elevation Survey Sta.8+000 / 8+500 12:00 18:00 Sta.8+500 / 9+000 Sta.9+000 / 9+500 Sta.9+500 / 10+000
1.8 Sta.8+000 / 8+500 16:30 17:30 Sta.8+500 / 9+000 Sta.9+000 / 9+500 Sta.9+500 / 10+000
1.9 Sta.7+500 / 8+000 08:00 15:00 Sta.8+000 / 8+500 Sta.8+500 / 9+000 Sta.9+000 / 9+500
1.10 Field Density Test (FDT) Sta.7+500 / 8+000 15:00 16:00 Sta.8+000 / 8+500 Sta.8+500 / 9+000 Sta.9+000 / 9+500
1.11 Sta.7+000 / 7+500 08:00 18:00 Sta.7+500 / 8+000 Sta.8+000 / 8+500 Sta.8+500 / 9+000
1.12 Sta.7+000 / 7+500 08:00 18:00 Sta.7+500 / 8+000 Sta.8+000 / 8+500 Sta.8+500 / 9+000
1.13 Sta.6+500 / 7+000 08:00 18:00 Sta.7+000 / 7+500 Sta.7+500 / 8+000 Sta.8+000 / 8+500
1.14 Sta.6+000 / 6+500 08:00 18:00 Sta.6+500 / 7+000 Sta.7+000 / 7+500 Sta.7+500 / 8+000
2 Backfilling
2.1 Sta.6+000 / 6+500 08:00 18:00 Sta.6+500 / 7+000 Sta.8+000 / 8+500 Sta.8+500 / 9+000
2.2 Field Density Test (FDT) Sta.5+500 / 6+000 13:30 14:30 Sta.6+000 / 6+500 Sta.6+500 / 7+000 Sta.8+000 / 8+500
2.3 Sta.5+500 / 6+000 14:30 18:00 Sta.6+000 / 6+500 Sta.6+500 / 7+000 Sta.8+000 / 8+500
2.4 Field Density Test (FDT) Sta.5+000 / 5+500 12:00 13:00 Sta.5+500 / 6+000 Sta.6+000 / 6+500 Sta.6+500 / 7+000
2.5 Sta.5+000 / 5+500 13:00 18:00 Sta.5+500 / 6+000 Sta.6+000 / 6+500 Sta.6+500 / 7+000
2.6 Field Density Test (FDT) Sta.4+500 / 5+000 10:30 11:30 Sta.5+000 / 5+500 Sta.5+500 / 6+000 Sta.6+000 / 6+500
2.7 Sta.4+500 / 5+000 11:30 18:00 Sta.5+000 / 5+500 Sta.5+500 / 6+000 Sta.6+000 / 6+500
2.8 Sta.4+000 / 4+500 09:00 10:00 Sta.4+500 / 5+000 Sta.5+000 / 5+500 Sta.5+500 / 6+000
3 Manholes
3.1 MH(43, 44, 45)
Final Backfilling & Compaction (20cm)
3-DAY PROGRESS SCHEDULE
Setting-Out, Routing, Clearing
Sand bedding, shaped bedding
Pipe-laying
Invert elevation verification (As Built)
House Connections installation
Sub-grade Verification (SPT-Standard
Penetration Test)
Survey marking (As Built)
Side-fill & Compaction
Initial backfilling (30cm above the crown)
Main Backfilling & Compaction
Plate Load test
Blinding Concrete3.1 MH(43, 44, 45)
3.2
3.3 MV(30), TO(13), MH(42)
3.4 Re-bar Inspection MV(30), TO(13), MH(42) 16:30 18:00 MV(30), TO(13), MH(42)
3.5 MV(30), TO(13), MH(42)
3.6 Formwork Inspection 16:30 18:00 MV(30), TO(13), MH(42)
3.7 AV(25), MH(39, 40) MV(30), TO(13), MH(42)
3.8 MH(31, 32, 33, 34) 09:00 11:00 MH(35, 36, 37, 38)
3.9 AV(24); MH(29, 30, 31) 08:00 18:00 MH(31, 32, 33, 34) MH(35, 36, 37, 38)
3.10 MV(28), TO(12) 11:00 16:30 AV(24); MH(29, 30, 31) MH(31, 32, 33, 34) MH(35, 36, 37, 38)
3.11 MV(28), TO(12) 11:00 18:00 AV(24); MH(29, 30, 31) MH(31, 32, 33, 34) MH(35, 36, 37, 38)
4 Testing
4.1 12:00 16:00 Sta.8+000 / 8+500 Sta.8+500 / 8+900
4.2 Sta.5+000 / 8+500
4.3
5 Reconnection
6 Final Reinstatement of Surfaces Sta.0+000 / 3+000 08:00 18:00 Sta.3+000 / 5+000
6.1 Sta.0+000 / 3+000 08:00 18:00 Sta.3+000 / 5+000
6.2 Sta.1+000 / 2+000 08:00 18:00 Sta.2+000 / 3+000 Sta.3+000 / 4+000 Sta.4+000 / 5+000
6.3 Sta.0+000 / 3+000
7 As Built Drawing
7.1
7.2
7.3
8 Taking Over Inspection
8.1
9 Final Taking Over Inspection
10 Material
10.1 Material Delivery
Gate Valves, Air Valves,
Hydrants
10.2 Material Inspection 10:00 12:00
(Gate Valves, Air Valves,
Hydrants)
Blinding Concrete
Reinforcement Works
Formworks
Concrete pouring
Tightness Testing
Outter Hydro-insulation
Backfilling & Compaction
Installation (Pre-fabricated)
Pre-backfilling inspection
Hydrostatic Pressure / Tightness Testing
CCTV Inspection (WW only)
Disinfection (WS only)
Green area
Asphalting
Asphalt testing - Kern sampling
Final Survey measurement
Preparation of As Built Drawings
Submission of As Built Drawings
Remedial Works

More Related Content

Viewers also liked (6)

Standard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elementsStandard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elements
 
Water Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing ExamplesWater Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing Examples
 
50338447 checklist-concrete-works
50338447 checklist-concrete-works50338447 checklist-concrete-works
50338447 checklist-concrete-works
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
Sewer Appurtenances
Sewer AppurtenancesSewer Appurtenances
Sewer Appurtenances
 
Water supply
Water supplyWater supply
Water supply
 

Similar to 3-Days Construction Schedule

REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2 REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2
Chandra sekhar sahoo
 
Friction loss tables
Friction loss tablesFriction loss tables
Friction loss tables
beqs
 
SPECTRAL-BASED FATIGUE ASSESSMENT OF FSO
SPECTRAL-BASED FATIGUE ASSESSMENT OF FSOSPECTRAL-BASED FATIGUE ASSESSMENT OF FSO
SPECTRAL-BASED FATIGUE ASSESSMENT OF FSO
SUMARDIONO .
 
(597922903) trabajo sobre aguas residuales 1
(597922903) trabajo sobre aguas residuales 1(597922903) trabajo sobre aguas residuales 1
(597922903) trabajo sobre aguas residuales 1
Juliana Hincapié Rojo
 
Historical IBM quarterly dividend rates and payable and records dates.
Historical IBM quarterly dividend rates and payable and records dates. Historical IBM quarterly dividend rates and payable and records dates.
Historical IBM quarterly dividend rates and payable and records dates.
QuarterlyEarningsReports3
 
The use of waveform cross correlation for creation of an accurate catalogue o...
The use of waveform cross correlation for creation of an accurate catalogue o...The use of waveform cross correlation for creation of an accurate catalogue o...
The use of waveform cross correlation for creation of an accurate catalogue o...
Ivan Kitov
 
City council 8 6-13 ai 32 vv ground water group presentation
City council 8 6-13 ai 32 vv ground water group presentationCity council 8 6-13 ai 32 vv ground water group presentation
City council 8 6-13 ai 32 vv ground water group presentation
City of San Angelo Texas
 

Similar to 3-Days Construction Schedule (20)

P1111149078
P1111149078P1111149078
P1111149078
 
St st pipe_pressure_rating_charts_rev_sep_2010
St st pipe_pressure_rating_charts_rev_sep_2010St st pipe_pressure_rating_charts_rev_sep_2010
St st pipe_pressure_rating_charts_rev_sep_2010
 
REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2 REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2
 
FAST実験4:大気蛍光望遠鏡による極高エネルギー宇宙線観測報告
FAST実験4:大気蛍光望遠鏡による極高エネルギー宇宙線観測報告FAST実験4:大気蛍光望遠鏡による極高エネルギー宇宙線観測報告
FAST実験4:大気蛍光望遠鏡による極高エネルギー宇宙線観測報告
 
ABB POLIM-K High Voltage Surge Arresters AC up to 52 kV - AC Surge Arresters ...
ABB POLIM-K High Voltage Surge Arresters AC up to 52 kV - AC Surge Arresters ...ABB POLIM-K High Voltage Surge Arresters AC up to 52 kV - AC Surge Arresters ...
ABB POLIM-K High Voltage Surge Arresters AC up to 52 kV - AC Surge Arresters ...
 
Friction loss tables
Friction loss tablesFriction loss tables
Friction loss tables
 
SPECTRAL-BASED FATIGUE ASSESSMENT OF FSO
SPECTRAL-BASED FATIGUE ASSESSMENT OF FSOSPECTRAL-BASED FATIGUE ASSESSMENT OF FSO
SPECTRAL-BASED FATIGUE ASSESSMENT OF FSO
 
(597922903) trabajo sobre aguas residuales 1
(597922903) trabajo sobre aguas residuales 1(597922903) trabajo sobre aguas residuales 1
(597922903) trabajo sobre aguas residuales 1
 
Depositiondata
DepositiondataDepositiondata
Depositiondata
 
ES&FX.singlepweb email
ES&FX.singlepweb emailES&FX.singlepweb email
ES&FX.singlepweb email
 
Jardim bot2010 jc
Jardim bot2010 jcJardim bot2010 jc
Jardim bot2010 jc
 
கணிதம் எண்ணும் எழுத்தும்
கணிதம் எண்ணும் எழுத்தும்கணிதம் எண்ணும் எழுத்தும்
கணிதம் எண்ணும் எழுத்தும்
 
Historical IBM quarterly dividend rates and payable and records dates.
Historical IBM quarterly dividend rates and payable and records dates. Historical IBM quarterly dividend rates and payable and records dates.
Historical IBM quarterly dividend rates and payable and records dates.
 
The use of waveform cross correlation for creation of an accurate catalogue o...
The use of waveform cross correlation for creation of an accurate catalogue o...The use of waveform cross correlation for creation of an accurate catalogue o...
The use of waveform cross correlation for creation of an accurate catalogue o...
 
City council 8 6-13 ai 32 vv ground water group presentation
City council 8 6-13 ai 32 vv ground water group presentationCity council 8 6-13 ai 32 vv ground water group presentation
City council 8 6-13 ai 32 vv ground water group presentation
 
Result book santiago_2020
Result book santiago_2020Result book santiago_2020
Result book santiago_2020
 
PCD and CBN Tools
PCD and CBN ToolsPCD and CBN Tools
PCD and CBN Tools
 
FAST実験5:新型大気蛍光望遠鏡の遠隔運用と宇宙線観測報告
FAST実験5:新型大気蛍光望遠鏡の遠隔運用と宇宙線観測報告FAST実験5:新型大気蛍光望遠鏡の遠隔運用と宇宙線観測報告
FAST実験5:新型大気蛍光望遠鏡の遠隔運用と宇宙線観測報告
 
[BLT] 연구개발 프로세스에 따른_강한_특허_전략_v1.3_엄
[BLT] 연구개발 프로세스에 따른_강한_특허_전략_v1.3_엄[BLT] 연구개발 프로세스에 따른_강한_특허_전략_v1.3_엄
[BLT] 연구개발 프로세스에 따른_강한_특허_전략_v1.3_엄
 
H25 Mỹ Phước 3. Cơ hội lớn nhất trong năm . Call 24/24 097.98.99.207
H25 Mỹ Phước 3. Cơ hội lớn nhất trong năm . Call 24/24 097.98.99.207H25 Mỹ Phước 3. Cơ hội lớn nhất trong năm . Call 24/24 097.98.99.207
H25 Mỹ Phước 3. Cơ hội lớn nhất trong năm . Call 24/24 097.98.99.207
 

More from Vladimir Popovic

Lanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewLanchkhuti WS Project Overview
Lanchkhuti WS Project Overview
Vladimir Popovic
 

More from Vladimir Popovic (20)

Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
 
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoirSeismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
 
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
 
Tightness testing of gravity pipelines
Tightness testing of gravity pipelinesTightness testing of gravity pipelines
Tightness testing of gravity pipelines
 
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
 
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
 
Sealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod HolesSealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod Holes
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
 
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopConstruction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-Stop
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
 
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 ConstructionMan Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
 
Ozurgeti City / Water Supply Project
Ozurgeti City / Water Supply ProjectOzurgeti City / Water Supply Project
Ozurgeti City / Water Supply Project
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)
 
Man Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor StructuresMan Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor Structures
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
 
Kostajnica City - WS/WW Project
Kostajnica City - WS/WW ProjectKostajnica City - WS/WW Project
Kostajnica City - WS/WW Project
 
Derventa City Water Supply Project
Derventa City Water Supply ProjectDerventa City Water Supply Project
Derventa City Water Supply Project
 
Kakanj City Waste Water Project
Kakanj City Waste Water ProjectKakanj City Waste Water Project
Kakanj City Waste Water Project
 
Lanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewLanchkhuti WS Project Overview
Lanchkhuti WS Project Overview
 

Recently uploaded

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 

Recently uploaded (20)

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 

3-Days Construction Schedule

  • 1. Yesterday (actual) Time (from) Time (until) Today (planned) Time (from) Time (until) Tomorrow (planned) Time (from) Time (until) Day after Tomorrow (planned) Notes 1 Excavation 1.1 1.2 Excavation Sta.8+500 / 8+625 08:00 18:00 Sta.9+000 / 9+125 Sta.9+500 / 9+625 Sta.10+000 / 10+125 Team 1 Sta.8+625 / 8+750 08:00 18:00 Sta.9+125 / 9+250 Sta.9+625 / 9+750 Sta.10+125 / 10+250 Team 2 Sta.8+750 / 8+875 08:00 18:00 Sta.9+250 / 9+375 Sta.9+750 / 9+875 Sta.10+250 / 10+375 Team 3 Sta.8+875 / 9+000 08:00 18:00 Sta.9+375 / 9+500 Sta.9+875 / 10+000 Sta.10+375 / 10+500 1.3 Drilling, jack & pick hammering / / / / 1.5 Trench Sub-grade Blasting / / / / 1.6 Clearing & excavation / / / / 1.7 Final trench elevation Survey Sta.8+000 / 8+500 12:00 18:00 Sta.8+500 / 9+000 Sta.9+000 / 9+500 Sta.9+500 / 10+000 1.8 Sta.8+000 / 8+500 16:30 17:30 Sta.8+500 / 9+000 Sta.9+000 / 9+500 Sta.9+500 / 10+000 1.9 Sta.7+500 / 8+000 08:00 15:00 Sta.8+000 / 8+500 Sta.8+500 / 9+000 Sta.9+000 / 9+500 1.10 Field Density Test (FDT) Sta.7+500 / 8+000 15:00 16:00 Sta.8+000 / 8+500 Sta.8+500 / 9+000 Sta.9+000 / 9+500 1.11 Sta.7+000 / 7+500 08:00 18:00 Sta.7+500 / 8+000 Sta.8+000 / 8+500 Sta.8+500 / 9+000 1.12 Sta.7+000 / 7+500 08:00 18:00 Sta.7+500 / 8+000 Sta.8+000 / 8+500 Sta.8+500 / 9+000 1.13 Sta.6+500 / 7+000 08:00 18:00 Sta.7+000 / 7+500 Sta.7+500 / 8+000 Sta.8+000 / 8+500 1.14 Sta.6+000 / 6+500 08:00 18:00 Sta.6+500 / 7+000 Sta.7+000 / 7+500 Sta.7+500 / 8+000 2 Backfilling 2.1 Sta.6+000 / 6+500 08:00 18:00 Sta.6+500 / 7+000 Sta.8+000 / 8+500 Sta.8+500 / 9+000 2.2 Field Density Test (FDT) Sta.5+500 / 6+000 13:30 14:30 Sta.6+000 / 6+500 Sta.6+500 / 7+000 Sta.8+000 / 8+500 2.3 Sta.5+500 / 6+000 14:30 18:00 Sta.6+000 / 6+500 Sta.6+500 / 7+000 Sta.8+000 / 8+500 2.4 Field Density Test (FDT) Sta.5+000 / 5+500 12:00 13:00 Sta.5+500 / 6+000 Sta.6+000 / 6+500 Sta.6+500 / 7+000 2.5 Sta.5+000 / 5+500 13:00 18:00 Sta.5+500 / 6+000 Sta.6+000 / 6+500 Sta.6+500 / 7+000 2.6 Field Density Test (FDT) Sta.4+500 / 5+000 10:30 11:30 Sta.5+000 / 5+500 Sta.5+500 / 6+000 Sta.6+000 / 6+500 2.7 Sta.4+500 / 5+000 11:30 18:00 Sta.5+000 / 5+500 Sta.5+500 / 6+000 Sta.6+000 / 6+500 2.8 Sta.4+000 / 4+500 09:00 10:00 Sta.4+500 / 5+000 Sta.5+000 / 5+500 Sta.5+500 / 6+000 3 Manholes 3.1 MH(43, 44, 45) Final Backfilling & Compaction (20cm) 3-DAY PROGRESS SCHEDULE Setting-Out, Routing, Clearing Sand bedding, shaped bedding Pipe-laying Invert elevation verification (As Built) House Connections installation Sub-grade Verification (SPT-Standard Penetration Test) Survey marking (As Built) Side-fill & Compaction Initial backfilling (30cm above the crown) Main Backfilling & Compaction Plate Load test Blinding Concrete3.1 MH(43, 44, 45) 3.2 3.3 MV(30), TO(13), MH(42) 3.4 Re-bar Inspection MV(30), TO(13), MH(42) 16:30 18:00 MV(30), TO(13), MH(42) 3.5 MV(30), TO(13), MH(42) 3.6 Formwork Inspection 16:30 18:00 MV(30), TO(13), MH(42) 3.7 AV(25), MH(39, 40) MV(30), TO(13), MH(42) 3.8 MH(31, 32, 33, 34) 09:00 11:00 MH(35, 36, 37, 38) 3.9 AV(24); MH(29, 30, 31) 08:00 18:00 MH(31, 32, 33, 34) MH(35, 36, 37, 38) 3.10 MV(28), TO(12) 11:00 16:30 AV(24); MH(29, 30, 31) MH(31, 32, 33, 34) MH(35, 36, 37, 38) 3.11 MV(28), TO(12) 11:00 18:00 AV(24); MH(29, 30, 31) MH(31, 32, 33, 34) MH(35, 36, 37, 38) 4 Testing 4.1 12:00 16:00 Sta.8+000 / 8+500 Sta.8+500 / 8+900 4.2 Sta.5+000 / 8+500 4.3 5 Reconnection 6 Final Reinstatement of Surfaces Sta.0+000 / 3+000 08:00 18:00 Sta.3+000 / 5+000 6.1 Sta.0+000 / 3+000 08:00 18:00 Sta.3+000 / 5+000 6.2 Sta.1+000 / 2+000 08:00 18:00 Sta.2+000 / 3+000 Sta.3+000 / 4+000 Sta.4+000 / 5+000 6.3 Sta.0+000 / 3+000 7 As Built Drawing 7.1 7.2 7.3 8 Taking Over Inspection 8.1 9 Final Taking Over Inspection 10 Material 10.1 Material Delivery Gate Valves, Air Valves, Hydrants 10.2 Material Inspection 10:00 12:00 (Gate Valves, Air Valves, Hydrants) Blinding Concrete Reinforcement Works Formworks Concrete pouring Tightness Testing Outter Hydro-insulation Backfilling & Compaction Installation (Pre-fabricated) Pre-backfilling inspection Hydrostatic Pressure / Tightness Testing CCTV Inspection (WW only) Disinfection (WS only) Green area Asphalting Asphalt testing - Kern sampling Final Survey measurement Preparation of As Built Drawings Submission of As Built Drawings Remedial Works