 Rehabilitation of the UrbanWater Supply & Sanitation in Sava River Basin (BMZ ID 2002 65 876)
 Project Scope – due to frequent pipe bursting and significant water loss a replacement of existing asbestos cement and zinc
Pipelines has been defined through 7nr priority sectors / zones:
 Lot A1 - a part of the existing asbestos cement pressure transmission main, which conveys the water from the well field
“Korace” to the reservoir “Bijelo Brdo”, was to be replaced.
 Lot A2 - two sections of the asbestos cement gravity transmission main, which conveys water from the reservoir “Bijelo Brdo”
to the reservoir “Babino Brdo” was to be replaced.
 Lot A3 - The gravity asbestos cement transmission main, which conveys water from the reservoir Babino Brdo“ to the reservoir
„Gakovac”, shall be partly replaced. The other gravity asbestos cement transmission main, which delivers water from the
reservoir “Babino Brdo“ to the Water Supply Zone 1 in the city of “Derventa”, was also to be partly replaced.
 Lot A4 - the Reservoir “Gakovac”- City Network Feeder Line located in Stevana Nemanje Street was to be replaced.
 Lot A5 - a distribution asbestos cement pipes which are located in “Srpske Vojske”street was to be replaced, new house
connections installed
 Lot A6 – a distribution asbestos cement pipeline in “Stefana Nemanje Street” with belonging house connections were to be
replaced.
 Lot A7 – The distribution Zinc-pipes which are located in “Radnička street” together with belonging house connections were to
be replaced.
 Lot A8 – Provision and installation of SCADA System with associated software, equipments, ultrasonic flow meters, pressure
reducing valves on critical locations, integration into the SCADA System.
 Lot A9 – provision of Water Meters, PE Shafts and associated fittings for Water Utility “Komunalac”
 In total - 12,630.52m of DI & PE Pipelines have been installed under the Project, 309nr of house connections, 14nr of supporting
concrete manholes. From remaining budget – several pipelines were extended (Lot A3, A5, A6, A7).
 Project Budget – 2,000,000.00EUR
PROJECT’S SIGN BOARD WS PIPE MATERIAL – DUCTILE IRON “PAM” NATURAL PIPES
WS PIPE MATERIAL – DUCTILE IRON “PAM” NATURAL PIPES
, TYTON-SIT JOINTS
WS PIPE MATERIAL – HDPE100, SDR11-17, PN10, PN16
“PIPELIFE” PIPES
LOT A-1
(Transmission Main DI
DN300; L = 2.207,80m)
A part of the existing asbestos cement
pressure transmission main, which
conveys the water from the well field
“Korace” to the reservoir “Bijelo
Brdo”, was to be replaced.
Pipe material:
DI DN300, PN16 in 2,207.80m Length
with 1nr new Mud Outlet Valve Shaft.
Considering this previously war-
affected area has present mine fields,
it was required that demining of pipe
route corridor is conducted prior of
any construction works.
BHMAC DEMINING AREA SAFE DEMINED 20M WIDE PIPE-ROUTE CORRIDOR
DI DN300 PIPE MATERIAL DELIVERY WITHIN SAFETY
CORRIDOR
DI DN300 INSTALLATION
TITANIUM SITS JOINTS
PRESSURE TEST AS PER EN805, PIPE ANCHORING
MUD OUTLET VALVE MANHOLE
MUD OUTLET VALVE MANHOLE
LotA2
Transmission main
HDPE DN300
Two sections of the asbestos cement
gravity transmission main, which
conveys water from the reservoir
“Bijelo Brdo” to the reservoir “Babino
Brdo” was to be replaced.
Pipe material:
HDPE100, PN10, SDR17, OD315mm,
L=843.10m with 2nr House
Connections
PE PIPE WELDING PRESSURE TESTING – EN805
REPLACEMENT OF VALVES, FITTINGS AT EXISTING MUD
OUTLET VALVE MANHOLE
REPLACEMENT OF AIR VALVE AT EXISTING AIR VALVE
MANHOLE
REPLACEMENT OF AIR VALVE AT EXISTING AIR VALVE
MANHOLE
REPLACEMENT OF AIR VALVE AT EXISTING AIR VALVE
MANHOLE
LotA3
Transmission Main
The gravity asbestos cement
transmission main, which conveys
water from the reservoir Babino Brdo“
to the reservoir „Gakovac”, shall be
partly replaced.
The other gravity asbestos cement
transmission main, which delivers
water from the reservoir “Babino
Brdo“ to the Water Supply Zone 1 in
the city of “Derventa”, was also to be
partly replaced
Extension of City Network:
Pipe Material:
DI DN400, PN16 – L=253m;
DI DN300, PN16 – L=485m;
HDPE ID315, PN16 – 1,760m;
3nr new Shafts – 2 Mud Outlets, 1nr
Air Valves
PIPE ROUTE CORRIDOR DEMINED BY BHMAC
REGARDLESS, UNEXPLODED MINE ENCOUNTERED DURING
TRENCH EXCAVATION WORKS, WORKS ABORTED UNTIL
DEMINING COMPLETION
DI DN300 PIPE CONNECTION TO RESERVOIR “BABNO BRDO” DOWNSTREAM PIPE ROUTE
MUD OUTLET VALVE SHAFTS (DI DN300, DN400) MUD OUTLET VALVE SHAFTS (DI DN300, DN400)
DISCHARGE PIPES WITH “FROG FLAP VALVES”
AIR VALVE MANHOLE AT DI DN300 AIR VALVE MANHOLE AT DI DN300
TRANSITION TO HDPE OD315, PN16 EXTENSION OF TRANSMISSION MAIN HDPE OD315, PN16
LotA4
Feeder Line
The Reservoir “Gakovac”- City
Network Feeder Line located in
Stevana Nemanje Street was to be
replaced
Pipe material:
HDPE PN10, PN16:
OD315 – L=577m
1nr Air Valve Shaft
1nr Flow Meter Shaft (Lot A8)
HDPE OD315, PN16 PIPE CONNECTION TO “GAKOVAC”
WATER RESERVOIR
HDPE OD315, PN16 PIPE CONNECTION TO “GAKOVAC”
WATER RESERVOIR
GRAVITY FEEDER LINE AIR VALVE MANHOLE
GRAVITY FEEDER LINE AIR VALVE MANHOLE GRAVITY FEEDER LINE AIR VALVE
JOINT FLOW METER MANHOLE FLOW METERS / PART OF SCADA SYSTEM
LotA5
Distribution Pipeline
The distribution asbestos cement
pipes which are located in “Srpske
Vojske”street shall be replaced, new
house connections installed
Distribution Pipeline:
HDPE OD180, PN10 – 1,502m;
House Connections – 46nr
HDPE OD180, PN10 PIPE
LotA6
Distribution Pipeline
Distribution asbestos cement pipeline
in “Stefana Nemanje Street” with
belonging house connections to be
replaced:
Pipe material – HDPE PN16:
OD125 – 3,224m;
OD63-282m;
House Connections – 188nr;
2nr new shafts
HDPE OD125, PN16 PIPE
WATER METER PE SHAFTS R=1.0M, H=1.0M (PROVIDED
UNDER LOT A9)
INSTALLATION OF HOUSE CONNECTION’S WATER METERS
PE WATER METER SHAFT
TRANSITION FROM OD125 TO OD63MM PIPE
GATEVALVE MANHOLE
PRESSURE REDUCING VALVE SHAFT PRESSURE REDUCING VALVE
GREEN AREA HYDRANT COVER COMMISSIONING ON TAKE OVER INSPECTION
GREEN AREA GATE VALVES COVER, SURFACE CAPS
LotA7
Distribution Pipeline
The distribution Zinc-pipes which are
located in “Radnička street” together
with belonging house connections
were to be replaced.
Pipe Material -HDPE PN16:
OD125 – L=1,022m;
OD63 – L=474m;
House Connections – 73nr;
1nr Pressure Reducing Valve Shaft
PIPE TRENCH EXCAVATION HDPE OD125MM PN16 PIPE LAYING
PRESSURE REDUCING VALVE SHAFT-TO-BE PRESSURE REDUCING VALVE SHAFT-TO-BE
PRESSURE REDUCINGVALVE SHAFT PRESSURE REDUCING VALVE
LotA8
SCADA System
SCADA System:
Fm-01 PS “Korace”; (Flow Meter)
Fm-02 “Lupljanica”; (Flow Meter)
Fm-03 “Bilica Vrelo”; (Flow Meter)
Fm-04 “Bilica Vrelo”; (Flow Meter)
Fm-05 Reservoir “Babino Brdo”; (Flow
Meter)
Fm-06 Reservoir ”Babino Brdo”,
existing shaft; (Flow Meter)
Fm-07, 08 Reservoir ”Gakovac”; (Flow
Meter)
Pr-02 Reservoir “Vrhovi” (Pressure
Reducing Valve)
SCADA Control Center – PS “Korace”
1nr Buster Pump – PS “Bilica Vrelo”
8nr new shafts constructed
LotA8
SCADA System
Fm-01 PS “Korace”; (Flow Meter)
LotA8
SCADA System
Fm-02 PS “Lupljanica”; (Flow Meter)
LotA8
SCADA System
Fm-03 “Bilica Vrelo”; (Flow Meter)
LotA8
SCADA System
Fm-04 “Bilica Vrelo”; (Flow Meter)
LotA8
SCADA System
Fm-05 Reservoir “Babino Brdo” Inlet;
(Flow Meter)
LotA8
SCADA System
Fm-06 Reservoir ”Babino Brdo”
Outlet, existing shaft; (Flow Meter)
LotA8
SCADA System
Fm-07 Reservoir ”Gakovac”; (Flow
Meter)
LotA8
SCADA System
Fm-08, 09 Reservoir ”Gakovac” Inlet /
Outlet; (Flow Meter)
LotA8
SCADA System
Pr-02 Reservoir “Vrhovi” (Pressure
Reducing Valve)
LotA8
SCADA System
1nr Buster Pump – PS “Bilica Vrelo”
LotA9
“Delivery ofWS
material”
Lot A9 “Delivery of WS material”:
Water Meters (Qn = 1.5m³/h, dry type)
INSA (1/2“, 3/4", 1“, 5/4“, 6/4“, 2“)–
3,000nr
HDPE WM shafts 1.0x1.0m – 500nr
Shut-off valves (DN3/4“, 1“, 5/4“, 6/4“,
2“) – 6,000nr
Various fittings and valves.

Derventa City Water Supply Project

  • 2.
     Rehabilitation ofthe UrbanWater Supply & Sanitation in Sava River Basin (BMZ ID 2002 65 876)  Project Scope – due to frequent pipe bursting and significant water loss a replacement of existing asbestos cement and zinc Pipelines has been defined through 7nr priority sectors / zones:  Lot A1 - a part of the existing asbestos cement pressure transmission main, which conveys the water from the well field “Korace” to the reservoir “Bijelo Brdo”, was to be replaced.  Lot A2 - two sections of the asbestos cement gravity transmission main, which conveys water from the reservoir “Bijelo Brdo” to the reservoir “Babino Brdo” was to be replaced.  Lot A3 - The gravity asbestos cement transmission main, which conveys water from the reservoir Babino Brdo“ to the reservoir „Gakovac”, shall be partly replaced. The other gravity asbestos cement transmission main, which delivers water from the reservoir “Babino Brdo“ to the Water Supply Zone 1 in the city of “Derventa”, was also to be partly replaced.  Lot A4 - the Reservoir “Gakovac”- City Network Feeder Line located in Stevana Nemanje Street was to be replaced.  Lot A5 - a distribution asbestos cement pipes which are located in “Srpske Vojske”street was to be replaced, new house connections installed  Lot A6 – a distribution asbestos cement pipeline in “Stefana Nemanje Street” with belonging house connections were to be replaced.  Lot A7 – The distribution Zinc-pipes which are located in “Radnička street” together with belonging house connections were to be replaced.  Lot A8 – Provision and installation of SCADA System with associated software, equipments, ultrasonic flow meters, pressure reducing valves on critical locations, integration into the SCADA System.  Lot A9 – provision of Water Meters, PE Shafts and associated fittings for Water Utility “Komunalac”  In total - 12,630.52m of DI & PE Pipelines have been installed under the Project, 309nr of house connections, 14nr of supporting concrete manholes. From remaining budget – several pipelines were extended (Lot A3, A5, A6, A7).  Project Budget – 2,000,000.00EUR
  • 3.
    PROJECT’S SIGN BOARDWS PIPE MATERIAL – DUCTILE IRON “PAM” NATURAL PIPES
  • 4.
    WS PIPE MATERIAL– DUCTILE IRON “PAM” NATURAL PIPES , TYTON-SIT JOINTS WS PIPE MATERIAL – HDPE100, SDR11-17, PN10, PN16 “PIPELIFE” PIPES
  • 5.
    LOT A-1 (Transmission MainDI DN300; L = 2.207,80m) A part of the existing asbestos cement pressure transmission main, which conveys the water from the well field “Korace” to the reservoir “Bijelo Brdo”, was to be replaced. Pipe material: DI DN300, PN16 in 2,207.80m Length with 1nr new Mud Outlet Valve Shaft. Considering this previously war- affected area has present mine fields, it was required that demining of pipe route corridor is conducted prior of any construction works.
  • 6.
    BHMAC DEMINING AREASAFE DEMINED 20M WIDE PIPE-ROUTE CORRIDOR
  • 7.
    DI DN300 PIPEMATERIAL DELIVERY WITHIN SAFETY CORRIDOR DI DN300 INSTALLATION
  • 8.
  • 9.
    PRESSURE TEST ASPER EN805, PIPE ANCHORING
  • 10.
  • 11.
  • 12.
    LotA2 Transmission main HDPE DN300 Twosections of the asbestos cement gravity transmission main, which conveys water from the reservoir “Bijelo Brdo” to the reservoir “Babino Brdo” was to be replaced. Pipe material: HDPE100, PN10, SDR17, OD315mm, L=843.10m with 2nr House Connections
  • 14.
    PE PIPE WELDINGPRESSURE TESTING – EN805
  • 15.
    REPLACEMENT OF VALVES,FITTINGS AT EXISTING MUD OUTLET VALVE MANHOLE REPLACEMENT OF AIR VALVE AT EXISTING AIR VALVE MANHOLE
  • 16.
    REPLACEMENT OF AIRVALVE AT EXISTING AIR VALVE MANHOLE REPLACEMENT OF AIR VALVE AT EXISTING AIR VALVE MANHOLE
  • 17.
    LotA3 Transmission Main The gravityasbestos cement transmission main, which conveys water from the reservoir Babino Brdo“ to the reservoir „Gakovac”, shall be partly replaced. The other gravity asbestos cement transmission main, which delivers water from the reservoir “Babino Brdo“ to the Water Supply Zone 1 in the city of “Derventa”, was also to be partly replaced Extension of City Network: Pipe Material: DI DN400, PN16 – L=253m; DI DN300, PN16 – L=485m; HDPE ID315, PN16 – 1,760m; 3nr new Shafts – 2 Mud Outlets, 1nr Air Valves
  • 18.
    PIPE ROUTE CORRIDORDEMINED BY BHMAC REGARDLESS, UNEXPLODED MINE ENCOUNTERED DURING TRENCH EXCAVATION WORKS, WORKS ABORTED UNTIL DEMINING COMPLETION
  • 19.
    DI DN300 PIPECONNECTION TO RESERVOIR “BABNO BRDO” DOWNSTREAM PIPE ROUTE
  • 21.
    MUD OUTLET VALVESHAFTS (DI DN300, DN400) MUD OUTLET VALVE SHAFTS (DI DN300, DN400)
  • 23.
    DISCHARGE PIPES WITH“FROG FLAP VALVES”
  • 24.
    AIR VALVE MANHOLEAT DI DN300 AIR VALVE MANHOLE AT DI DN300
  • 26.
    TRANSITION TO HDPEOD315, PN16 EXTENSION OF TRANSMISSION MAIN HDPE OD315, PN16
  • 27.
    LotA4 Feeder Line The Reservoir“Gakovac”- City Network Feeder Line located in Stevana Nemanje Street was to be replaced Pipe material: HDPE PN10, PN16: OD315 – L=577m 1nr Air Valve Shaft 1nr Flow Meter Shaft (Lot A8)
  • 28.
    HDPE OD315, PN16PIPE CONNECTION TO “GAKOVAC” WATER RESERVOIR HDPE OD315, PN16 PIPE CONNECTION TO “GAKOVAC” WATER RESERVOIR
  • 29.
    GRAVITY FEEDER LINEAIR VALVE MANHOLE
  • 30.
    GRAVITY FEEDER LINEAIR VALVE MANHOLE GRAVITY FEEDER LINE AIR VALVE
  • 31.
    JOINT FLOW METERMANHOLE FLOW METERS / PART OF SCADA SYSTEM
  • 32.
    LotA5 Distribution Pipeline The distributionasbestos cement pipes which are located in “Srpske Vojske”street shall be replaced, new house connections installed Distribution Pipeline: HDPE OD180, PN10 – 1,502m; House Connections – 46nr
  • 33.
  • 35.
    LotA6 Distribution Pipeline Distribution asbestoscement pipeline in “Stefana Nemanje Street” with belonging house connections to be replaced: Pipe material – HDPE PN16: OD125 – 3,224m; OD63-282m; House Connections – 188nr; 2nr new shafts
  • 36.
  • 37.
    WATER METER PESHAFTS R=1.0M, H=1.0M (PROVIDED UNDER LOT A9) INSTALLATION OF HOUSE CONNECTION’S WATER METERS
  • 38.
  • 39.
    TRANSITION FROM OD125TO OD63MM PIPE
  • 40.
  • 41.
    PRESSURE REDUCING VALVESHAFT PRESSURE REDUCING VALVE
  • 43.
    GREEN AREA HYDRANTCOVER COMMISSIONING ON TAKE OVER INSPECTION
  • 44.
    GREEN AREA GATEVALVES COVER, SURFACE CAPS
  • 45.
    LotA7 Distribution Pipeline The distributionZinc-pipes which are located in “Radnička street” together with belonging house connections were to be replaced. Pipe Material -HDPE PN16: OD125 – L=1,022m; OD63 – L=474m; House Connections – 73nr; 1nr Pressure Reducing Valve Shaft
  • 46.
    PIPE TRENCH EXCAVATIONHDPE OD125MM PN16 PIPE LAYING
  • 47.
    PRESSURE REDUCING VALVESHAFT-TO-BE PRESSURE REDUCING VALVE SHAFT-TO-BE
  • 48.
    PRESSURE REDUCINGVALVE SHAFTPRESSURE REDUCING VALVE
  • 49.
    LotA8 SCADA System SCADA System: Fm-01PS “Korace”; (Flow Meter) Fm-02 “Lupljanica”; (Flow Meter) Fm-03 “Bilica Vrelo”; (Flow Meter) Fm-04 “Bilica Vrelo”; (Flow Meter) Fm-05 Reservoir “Babino Brdo”; (Flow Meter) Fm-06 Reservoir ”Babino Brdo”, existing shaft; (Flow Meter) Fm-07, 08 Reservoir ”Gakovac”; (Flow Meter) Pr-02 Reservoir “Vrhovi” (Pressure Reducing Valve) SCADA Control Center – PS “Korace” 1nr Buster Pump – PS “Bilica Vrelo” 8nr new shafts constructed
  • 50.
    LotA8 SCADA System Fm-01 PS“Korace”; (Flow Meter)
  • 51.
    LotA8 SCADA System Fm-02 PS“Lupljanica”; (Flow Meter)
  • 52.
    LotA8 SCADA System Fm-03 “BilicaVrelo”; (Flow Meter)
  • 53.
    LotA8 SCADA System Fm-04 “BilicaVrelo”; (Flow Meter)
  • 54.
    LotA8 SCADA System Fm-05 Reservoir“Babino Brdo” Inlet; (Flow Meter)
  • 55.
    LotA8 SCADA System Fm-06 Reservoir”Babino Brdo” Outlet, existing shaft; (Flow Meter)
  • 56.
    LotA8 SCADA System Fm-07 Reservoir”Gakovac”; (Flow Meter)
  • 57.
    LotA8 SCADA System Fm-08, 09Reservoir ”Gakovac” Inlet / Outlet; (Flow Meter)
  • 58.
    LotA8 SCADA System Pr-02 Reservoir“Vrhovi” (Pressure Reducing Valve)
  • 59.
    LotA8 SCADA System 1nr BusterPump – PS “Bilica Vrelo”
  • 60.
    LotA9 “Delivery ofWS material” Lot A9“Delivery of WS material”: Water Meters (Qn = 1.5m³/h, dry type) INSA (1/2“, 3/4", 1“, 5/4“, 6/4“, 2“)– 3,000nr HDPE WM shafts 1.0x1.0m – 500nr Shut-off valves (DN3/4“, 1“, 5/4“, 6/4“, 2“) – 6,000nr Various fittings and valves.