The document summarizes a contract for materials and works provided to the Bihac Water Utility. It details the pipe materials, fittings, valves, and other equipment delivered totaling 741,000EUR. It also describes the scope of works carried out in zones 1, 4, 5, 10 including replacing old pipes with new PE pipes and installing over 1,000 meters of connections to homes. Additional works included constructing a new 700 cubic meter reservoir and over 800 meters of transmission pipelines.