SlideShare a Scribd company logo
 Rehabilitation of the UrbanWater Supply & Sanitation in Sava River Basin (BMZ ID 2002 65 876)
 The existing sewer system has the following defects:
 · Low connection rate. In the city centre of Kakanj, the existing sewer system serves only 35 % of the inhabitants,
who are connected to the public water supply system of. The other inhabitants discharge the wastewater without
authorization on to the land, which has caused severe environmental and public health problems.
 · In the settlement, where a separate sewer system is existent, some house connections have been connected to the
storm water pipes instead of to the wastewater pipes. This will cause the pollution of the water body if the
wastewater shall be treated in aWWTP in the future.
 · An important drinking water source “Pitka Voda”, which is situated near the city centre and is recharged with water
from the Zgosca river by bank filtration. The nearby discharge of the untreated wastewater into the Zgosca river will
cause severe damage to the drinking water supply.
 Some sewers don not discharge the collected waster water into a receiving water body, e.g. the Zgošća river or
Bosna river, but without authorization on to the land, which has caused severe environmental and public health
problems.
 · The sewerage collectors in the settlements of Mile and New Bare discharge the wastewater into the nearby creeks,
which flows through a valley before it reaches the Bosna river. This caused, the valley is very often flooded by
wastewater.
 Lot 1: Construction of a separate sewer system in Zone 1 - DN250-400, L=4,623m
 Lot 2: Construction of a separate sewer system in Zone 2 - DN250, L=1,546m
 Lot 3: Construction of a separate sewer system in Zone 3 – DN250, L=1,098m
 Lot 4: Rehabilitation of the existing sewer system in Zone 4 - DN1000, L=30m
 Lot 5: Rehabilitation of the existing sewer system in Zone 5 – DN400, L=437m
 Lot 6: Rehabilitation of the existing sewer system in Zone 6 – DN350-400, L=1,150m
 Designed length in total – 8,854m
 Storm Water Overflows - the construction of three storm water overflow structures shall be also included in the
scope of works. Two storm water overflow structures shall be integrated into the existing sewer mains. One storm
water overflow structure shall be constructed at the connection of the existing and the new sewer mains.
 Inspection / Maintenance Shafts - the construction and integration of approximately 298 maintenance shafts (incl. 18
backdrop shafts) into the existing sewer mains shall be included in the scope of works.
 Bridge Foundation Crossing: the bridge crossing is located at the end of Zone 1. The main collector will run through
the foundation of the city bridge.
 House Connections – The Contractor is to provide material and construct approx.294pcs, while as a part of Water
Utility’s “contribution”, Water Utility is to construct approx.293pcs of House Connections from material provided by
the Contract
 Water Utility Kakanj is to be provided with the following mechanization: Hydraulic Excavator, Backhoe Loader &
Pick-up vehicle
 Project Budget – 2,000,000.00EUR
PROJECT SIGN BOARD
PIPE MATERIAL:
CORRUGATED HDPE SN8 PIPES (DN250-1200)
PVC SN4 (DN160-200)
SHAFT COVERS, VARIOUS MATERIAL PREFABRICATED MAINTENANCE SHAFTS
PREFABRICATED MAINTENANCE SHAFTS PREFABRICATED COLLECTION SHAFTS
WU PROVIDED UNDER CONTRACT WITH:
HYDRAULIC EXCAVATOR NEW HOLLAND
BACKHOE LOADER NEW HOLLAND &
PICK-UP VEHICLE TOYOTA HILUX 4X4
GEO-TEXTILE PIPE WRAPPING
Bridge Foundation /
Pipe Jacking
PIPE-SADDLE CONNECTION OF HOUSE CONNECTION
PREFABRICATED COLLECTION SHAFT IN-SITY DRILLING FOR
HOUSE CONNECTION
COLLECTION SHAFT
CASCADE SHAFT
CONCRETE CULVERT INSPECTION SHAFT
STROM WATER OVERFLOW (SWO1) WITH OUTLET
STRUCTURE
STORM WATER OVERFLOW WITH OUTLET STRUCTURE
STORM WATER OVERFLOW (SWO3)
STORM WATER OVERFLOW (SWO3)
OUTLET STRUCTURE WITH FLAP VALVE
LAID ALONG THE MAGISTERIAL ROAD RIVER BOSNA OUTLET STRUCTURE
RIVER BOSNA OUTLET STRUCTURE RIVER BOSNA OUTLET STRUCTURE
DOWNSTREAM PIPE CLOGGED BY BALLON UPSTREAM SHAFT FILLED WITH WATER
COLLECTOR FLUSHING CCTV INSPECTION
Zone 1 –Take Over
Inspection
In total installed:
HDPE (SN8) DN250 – 3,801m;
HDPE (SN8) DN300 – 580m;
HDPE (SN8) DN350 – 21m;
HDPE (SN8) DN400 – 16m;
Total Collector length 4,418m;
Total House Connections – 277nr
Zone 2 –TakeOver
Inspection
In total installed:
HDPE (SN8) DN250 – 1,781m;
Total House Connections – 87nr
CASCADE SHAFT
Zone 3 -Take Over
Inspection
In total installed:
HDPE (SN8) DN250 – 95.35m
Total House Connections – 2nr
Zone 4 -TakeOver
Inspection
In total installed:
HDPE (SN8) DN500 – 80m
HDPE (SN8) DN1000 – 20m
Total Collector length 100m;
Zone 5 –Take Over
Inspection
In total installed:
HDPE (SN8) DN250 – 590m
HDPE (SN8) DN400 – 424m
Total Collector length 1014m;
Total House Connections – 51nr
Zone 6 –Take Over
Inspection
In total installed:
HDPE (SN8) DN250 – 340m
HDPE (SN8) DN350 – 200m
HDPE (SN8) DN400 – 935m
Total Collector length 1,475m;
Total House Connections – 73nr
CONNECTION TO EXISTING SYSTEM
MainCity Collector
DN1200Take Over
Inspection
In total installed:
HDPE (SN8), DN1200 – 382m
Remaining Budget
Considering the remaining Budget,
the following material has been
provided for WU “Vodokom” Kakanj :
HDPE (SN8) Pipes:
DN250 Pipes – 1,000m;
DN400 Pipes – 250m;
PVC (SN4) Pipes
DN160 – 1,500m;
DN200 – 1,500m;
Pipe saddles DN250/160 – 100pcs;
Flat Bed Vehicle IVECO
In total 265nr maintenance shafts
have been installed under the Project,
139nr of House Connection Collection
Shafts.
Total number of installed House
Connections (households connected)
to new WW System – 496nr.

More Related Content

What's hot

Presentation CS_update
Presentation CS_updatePresentation CS_update
Presentation CS_update
Boris Markov
 
EQUITABLE Water Supply PROJECT for Pune City
EQUITABLE Water  Supply PROJECT for Pune CityEQUITABLE Water  Supply PROJECT for Pune City
EQUITABLE Water Supply PROJECT for Pune City
pmcpune
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Vladimir Popovic
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
Fairfax County
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Vladimir Popovic
 
Short summary of PH4b Projects
Short summary of PH4b ProjectsShort summary of PH4b Projects
Short summary of PH4b Projects
Anandhan Annasamy
 
3rww comprehensive report site photos version 2
3rww comprehensive report site photos version 23rww comprehensive report site photos version 2
3rww comprehensive report site photos version 2
Gbemisola Arike Agbaje
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
Fairfax County
 
Low-Carbon Urban Infrastrucure Projects 2
Low-Carbon Urban Infrastrucure Projects 2Low-Carbon Urban Infrastrucure Projects 2
Low-Carbon Urban Infrastrucure Projects 2
Global Infrastructure Basel Foundation
 
2. glof
2. glof2. glof
2. glof
Nishan Sharma
 
Glacial Lake Outburst Floods in the Karakoram Mountains, P.R. China
Glacial Lake Outburst Floods in the Karakoram Mountains, P.R. ChinaGlacial Lake Outburst Floods in the Karakoram Mountains, P.R. China
Glacial Lake Outburst Floods in the Karakoram Mountains, P.R. China
InfoAndina CONDESAN
 
Solids Processing Rehabilitation Phase II
Solids Processing Rehabilitation Phase IISolids Processing Rehabilitation Phase II
Solids Processing Rehabilitation Phase II
Fairfax County
 

What's hot (12)

Presentation CS_update
Presentation CS_updatePresentation CS_update
Presentation CS_update
 
EQUITABLE Water Supply PROJECT for Pune City
EQUITABLE Water  Supply PROJECT for Pune CityEQUITABLE Water  Supply PROJECT for Pune City
EQUITABLE Water Supply PROJECT for Pune City
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
 
Short summary of PH4b Projects
Short summary of PH4b ProjectsShort summary of PH4b Projects
Short summary of PH4b Projects
 
3rww comprehensive report site photos version 2
3rww comprehensive report site photos version 23rww comprehensive report site photos version 2
3rww comprehensive report site photos version 2
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
 
Low-Carbon Urban Infrastrucure Projects 2
Low-Carbon Urban Infrastrucure Projects 2Low-Carbon Urban Infrastrucure Projects 2
Low-Carbon Urban Infrastrucure Projects 2
 
2. glof
2. glof2. glof
2. glof
 
Glacial Lake Outburst Floods in the Karakoram Mountains, P.R. China
Glacial Lake Outburst Floods in the Karakoram Mountains, P.R. ChinaGlacial Lake Outburst Floods in the Karakoram Mountains, P.R. China
Glacial Lake Outburst Floods in the Karakoram Mountains, P.R. China
 
Solids Processing Rehabilitation Phase II
Solids Processing Rehabilitation Phase IISolids Processing Rehabilitation Phase II
Solids Processing Rehabilitation Phase II
 

Similar to Kakanj wastewater project

Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosnia
Vladimir Popovic
 
Kostajnica, ws, ww project
Kostajnica, ws, ww projectKostajnica, ws, ww project
Kostajnica, ws, ww project
Vladimir Popovic
 
Derventa, Water Supply Project
Derventa, Water Supply ProjectDerventa, Water Supply Project
Derventa, Water Supply Project
Vladimir Popovic
 
Bihac WS Project
Bihac WS ProjectBihac WS Project
Bihac WS Project
Vladimir Popovic
 
Rehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgiaRehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgia
Vladimir Popovic
 
Ee ii ce(pc)505- module 1_2_3
Ee ii ce(pc)505- module 1_2_3Ee ii ce(pc)505- module 1_2_3
Ee ii ce(pc)505- module 1_2_3
SamirDas66
 
HATS 2A
HATS 2AHATS 2A
HATS 2A
Desmond Yuen
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
Richard Barker
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
Aonghus Murray
 
New Persentation
New PersentationNew Persentation
New Persentation
Tarek Fagal
 
Jaipur_water supply service.pdf
Jaipur_water supply service.pdfJaipur_water supply service.pdf
Jaipur_water supply service.pdf
AKASHICWORLD
 
Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606 Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606
John M Riggs
 
Hydraulic Systems
Hydraulic SystemsHydraulic Systems
Hydraulic Systems
Daniel Campos
 
Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26
Uyanga Nyamkhuu
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
DEEPAK MALLICK
 
Building Services Project 2: How Seng Guan
Building Services Project 2: How Seng GuanBuilding Services Project 2: How Seng Guan
Building Services Project 2: How Seng Guan
shacjhow
 
School Services
School ServicesSchool Services
School Services
Ashraf Ahmad
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Fairfax County
 
Trenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water NetworksTrenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water Networks
Loay Ghazaleh MBA, BSc Civil Eng.
 
Building Services Project 02
Building Services Project 02Building Services Project 02
Building Services Project 02
Bolin Loong
 

Similar to Kakanj wastewater project (20)

Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosnia
 
Kostajnica, ws, ww project
Kostajnica, ws, ww projectKostajnica, ws, ww project
Kostajnica, ws, ww project
 
Derventa, Water Supply Project
Derventa, Water Supply ProjectDerventa, Water Supply Project
Derventa, Water Supply Project
 
Bihac WS Project
Bihac WS ProjectBihac WS Project
Bihac WS Project
 
Rehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgiaRehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgia
 
Ee ii ce(pc)505- module 1_2_3
Ee ii ce(pc)505- module 1_2_3Ee ii ce(pc)505- module 1_2_3
Ee ii ce(pc)505- module 1_2_3
 
HATS 2A
HATS 2AHATS 2A
HATS 2A
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
 
New Persentation
New PersentationNew Persentation
New Persentation
 
Jaipur_water supply service.pdf
Jaipur_water supply service.pdfJaipur_water supply service.pdf
Jaipur_water supply service.pdf
 
Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606 Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606
 
Hydraulic Systems
Hydraulic SystemsHydraulic Systems
Hydraulic Systems
 
Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26Intro infrastructure project 2015.02.26
Intro infrastructure project 2015.02.26
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
 
Building Services Project 2: How Seng Guan
Building Services Project 2: How Seng GuanBuilding Services Project 2: How Seng Guan
Building Services Project 2: How Seng Guan
 
School Services
School ServicesSchool Services
School Services
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2
 
Trenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water NetworksTrenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water Networks
 
Building Services Project 02
Building Services Project 02Building Services Project 02
Building Services Project 02
 

More from Vladimir Popovic

Ws project ozurgeti, georgia
Ws project ozurgeti, georgiaWs project ozurgeti, georgia
Ws project ozurgeti, georgia
Vladimir Popovic
 
Rehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgiaRehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgia
Vladimir Popovic
 
Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3
Vladimir Popovic
 
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstructionLanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Vladimir Popovic
 
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitationLanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Vladimir Popovic
 
Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3
Vladimir Popovic
 
Ghadames project, minor structures
Ghadames project, minor structuresGhadames project, minor structures
Ghadames project, minor structures
Vladimir Popovic
 
Ghadames project, conveyance pipeline
Ghadames project, conveyance pipelineGhadames project, conveyance pipeline
Ghadames project, conveyance pipeline
Vladimir Popovic
 
Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3
Vladimir Popovic
 
Debeljaca WS Reservoir 700m3
Debeljaca WS Reservoir 700m3Debeljaca WS Reservoir 700m3
Debeljaca WS Reservoir 700m3
Vladimir Popovic
 
Al Jewaibyah Regulating Tank 70,000m3
Al Jewaibyah Regulating Tank  70,000m3Al Jewaibyah Regulating Tank  70,000m3
Al Jewaibyah Regulating Tank 70,000m3
Vladimir Popovic
 

More from Vladimir Popovic (11)

Ws project ozurgeti, georgia
Ws project ozurgeti, georgiaWs project ozurgeti, georgia
Ws project ozurgeti, georgia
 
Rehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgiaRehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgia
 
Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3
 
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstructionLanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
 
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitationLanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
 
Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3
 
Ghadames project, minor structures
Ghadames project, minor structuresGhadames project, minor structures
Ghadames project, minor structures
 
Ghadames project, conveyance pipeline
Ghadames project, conveyance pipelineGhadames project, conveyance pipeline
Ghadames project, conveyance pipeline
 
Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3
 
Debeljaca WS Reservoir 700m3
Debeljaca WS Reservoir 700m3Debeljaca WS Reservoir 700m3
Debeljaca WS Reservoir 700m3
 
Al Jewaibyah Regulating Tank 70,000m3
Al Jewaibyah Regulating Tank  70,000m3Al Jewaibyah Regulating Tank  70,000m3
Al Jewaibyah Regulating Tank 70,000m3
 

Recently uploaded

一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
snaprevwdev
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
Kamal Acharya
 
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
DharmaBanothu
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
MuhammadJazib15
 
smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...
um7474492
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
Assistant Engineer (Chemical) Interview Questions.pdf
Assistant Engineer (Chemical) Interview Questions.pdfAssistant Engineer (Chemical) Interview Questions.pdf
Assistant Engineer (Chemical) Interview Questions.pdf
Seetal Daas
 
Unit -II Spectroscopy - EC I B.Tech.pdf
Unit -II Spectroscopy - EC  I B.Tech.pdfUnit -II Spectroscopy - EC  I B.Tech.pdf
Unit -II Spectroscopy - EC I B.Tech.pdf
TeluguBadi
 
FULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back EndFULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back End
PreethaV16
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
Power Electronics- AC -AC Converters.pptx
Power Electronics- AC -AC Converters.pptxPower Electronics- AC -AC Converters.pptx
Power Electronics- AC -AC Converters.pptx
Poornima D
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
Indrajeet sahu
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
MadhavJungKarki
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
ijaia
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Transcat
 

Recently uploaded (20)

一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
 
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
 
smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
Assistant Engineer (Chemical) Interview Questions.pdf
Assistant Engineer (Chemical) Interview Questions.pdfAssistant Engineer (Chemical) Interview Questions.pdf
Assistant Engineer (Chemical) Interview Questions.pdf
 
Unit -II Spectroscopy - EC I B.Tech.pdf
Unit -II Spectroscopy - EC  I B.Tech.pdfUnit -II Spectroscopy - EC  I B.Tech.pdf
Unit -II Spectroscopy - EC I B.Tech.pdf
 
FULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back EndFULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back End
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
Power Electronics- AC -AC Converters.pptx
Power Electronics- AC -AC Converters.pptxPower Electronics- AC -AC Converters.pptx
Power Electronics- AC -AC Converters.pptx
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
 

Kakanj wastewater project

  • 1.
  • 2.  Rehabilitation of the UrbanWater Supply & Sanitation in Sava River Basin (BMZ ID 2002 65 876)  The existing sewer system has the following defects:  · Low connection rate. In the city centre of Kakanj, the existing sewer system serves only 35 % of the inhabitants, who are connected to the public water supply system of. The other inhabitants discharge the wastewater without authorization on to the land, which has caused severe environmental and public health problems.  · In the settlement, where a separate sewer system is existent, some house connections have been connected to the storm water pipes instead of to the wastewater pipes. This will cause the pollution of the water body if the wastewater shall be treated in aWWTP in the future.  · An important drinking water source “Pitka Voda”, which is situated near the city centre and is recharged with water from the Zgosca river by bank filtration. The nearby discharge of the untreated wastewater into the Zgosca river will cause severe damage to the drinking water supply.  Some sewers don not discharge the collected waster water into a receiving water body, e.g. the Zgošća river or Bosna river, but without authorization on to the land, which has caused severe environmental and public health problems.  · The sewerage collectors in the settlements of Mile and New Bare discharge the wastewater into the nearby creeks, which flows through a valley before it reaches the Bosna river. This caused, the valley is very often flooded by wastewater.
  • 3.  Lot 1: Construction of a separate sewer system in Zone 1 - DN250-400, L=4,623m  Lot 2: Construction of a separate sewer system in Zone 2 - DN250, L=1,546m  Lot 3: Construction of a separate sewer system in Zone 3 – DN250, L=1,098m  Lot 4: Rehabilitation of the existing sewer system in Zone 4 - DN1000, L=30m  Lot 5: Rehabilitation of the existing sewer system in Zone 5 – DN400, L=437m  Lot 6: Rehabilitation of the existing sewer system in Zone 6 – DN350-400, L=1,150m  Designed length in total – 8,854m  Storm Water Overflows - the construction of three storm water overflow structures shall be also included in the scope of works. Two storm water overflow structures shall be integrated into the existing sewer mains. One storm water overflow structure shall be constructed at the connection of the existing and the new sewer mains.  Inspection / Maintenance Shafts - the construction and integration of approximately 298 maintenance shafts (incl. 18 backdrop shafts) into the existing sewer mains shall be included in the scope of works.  Bridge Foundation Crossing: the bridge crossing is located at the end of Zone 1. The main collector will run through the foundation of the city bridge.  House Connections – The Contractor is to provide material and construct approx.294pcs, while as a part of Water Utility’s “contribution”, Water Utility is to construct approx.293pcs of House Connections from material provided by the Contract  Water Utility Kakanj is to be provided with the following mechanization: Hydraulic Excavator, Backhoe Loader & Pick-up vehicle  Project Budget – 2,000,000.00EUR
  • 4.
  • 5. PROJECT SIGN BOARD PIPE MATERIAL: CORRUGATED HDPE SN8 PIPES (DN250-1200) PVC SN4 (DN160-200)
  • 6. SHAFT COVERS, VARIOUS MATERIAL PREFABRICATED MAINTENANCE SHAFTS
  • 7. PREFABRICATED MAINTENANCE SHAFTS PREFABRICATED COLLECTION SHAFTS
  • 8. WU PROVIDED UNDER CONTRACT WITH: HYDRAULIC EXCAVATOR NEW HOLLAND BACKHOE LOADER NEW HOLLAND & PICK-UP VEHICLE TOYOTA HILUX 4X4
  • 9.
  • 11.
  • 12.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18. PIPE-SADDLE CONNECTION OF HOUSE CONNECTION
  • 19.
  • 20. PREFABRICATED COLLECTION SHAFT IN-SITY DRILLING FOR HOUSE CONNECTION
  • 24. STROM WATER OVERFLOW (SWO1) WITH OUTLET STRUCTURE
  • 25. STORM WATER OVERFLOW WITH OUTLET STRUCTURE
  • 28. OUTLET STRUCTURE WITH FLAP VALVE
  • 29.
  • 30.
  • 31.
  • 32.
  • 33. LAID ALONG THE MAGISTERIAL ROAD RIVER BOSNA OUTLET STRUCTURE
  • 34. RIVER BOSNA OUTLET STRUCTURE RIVER BOSNA OUTLET STRUCTURE
  • 35. DOWNSTREAM PIPE CLOGGED BY BALLON UPSTREAM SHAFT FILLED WITH WATER
  • 37.
  • 38.
  • 39. Zone 1 –Take Over Inspection In total installed: HDPE (SN8) DN250 – 3,801m; HDPE (SN8) DN300 – 580m; HDPE (SN8) DN350 – 21m; HDPE (SN8) DN400 – 16m; Total Collector length 4,418m; Total House Connections – 277nr
  • 40.
  • 41.
  • 42. Zone 2 –TakeOver Inspection In total installed: HDPE (SN8) DN250 – 1,781m; Total House Connections – 87nr
  • 43.
  • 45. Zone 3 -Take Over Inspection In total installed: HDPE (SN8) DN250 – 95.35m Total House Connections – 2nr
  • 46. Zone 4 -TakeOver Inspection In total installed: HDPE (SN8) DN500 – 80m HDPE (SN8) DN1000 – 20m Total Collector length 100m;
  • 47. Zone 5 –Take Over Inspection In total installed: HDPE (SN8) DN250 – 590m HDPE (SN8) DN400 – 424m Total Collector length 1014m; Total House Connections – 51nr
  • 48. Zone 6 –Take Over Inspection In total installed: HDPE (SN8) DN250 – 340m HDPE (SN8) DN350 – 200m HDPE (SN8) DN400 – 935m Total Collector length 1,475m; Total House Connections – 73nr
  • 49.
  • 51. MainCity Collector DN1200Take Over Inspection In total installed: HDPE (SN8), DN1200 – 382m
  • 52. Remaining Budget Considering the remaining Budget, the following material has been provided for WU “Vodokom” Kakanj : HDPE (SN8) Pipes: DN250 Pipes – 1,000m; DN400 Pipes – 250m; PVC (SN4) Pipes DN160 – 1,500m; DN200 – 1,500m; Pipe saddles DN250/160 – 100pcs; Flat Bed Vehicle IVECO In total 265nr maintenance shafts have been installed under the Project, 139nr of House Connection Collection Shafts. Total number of installed House Connections (households connected) to new WW System – 496nr.