SlideShare a Scribd company logo
In Plant Training 
PROMOTION OF VILLA 
-Gs Mohan (1011210335)
CASA GRANDE focus on “Promotion of Villa” 
STEPS IN PROMOTION OF VILLA: 
• FEASIBILITY OF LAYOUT 
• VILLA APPROVAL FROM LOCAL BODIES LIKE DTCP 
• FEASIBILITY OF INFRASTRUCTURE LIKE STP 
• PLANNING FOR VILLA 
• COSTING 
• EXECUTION OF VILLA LIKE PLASTERING,PAINTING,TILE FINISHING,WIRING,PLUMBING ,ETC.. 
• DELIVERY
TYPES OF CONSTRUCTION: 
Villa – 112 nos. 
Row House – 64 nos. 
VILLA ROW HOUSE 
Ground +2 Designed Structures Ground +2 Designed Structures 
1600 sq.ft land area , 
Built up area 2325 sq.ft 
Land Area 700 sq.ft 
Built Up Area 1121 sq.ft 
18 acre expanse 18 acre expanse 
4 Bed Rooms and 2 Living Rooms 2 Bed Rooms and 2 Living Rooms 
Two Exclusive Car Parks Two Exclusive Car Parks 
Exclusive Garden Area & Open Terrace Space Exclusive Garden Area & Open Terrace Space 
Contemporary New Age Architecture 
& Dinning Area Opening to Garden 
Contemporary New Age Architecture 
& Dinning Area Opening to Garden
BRICK: 
SOLID BLOCK,AERAGON BLOCK,NORMAL BLOCK,HOLLOW BLOCK 
SOLID BLOCK for wall or block construction , 
CONCRETE: 
M20 (cement: sand: gravel=1: 1.5: 3), M25 (cement: sand: gravel=1: 1: 2) 
REINFORCEMENT: 
Fe500 
WOOD: 
Dock wood, ascetic purpose in Elevation. 
Thick wood or Rubber wood used for windows and Doors.
VILLA APPROVAL FROM LOCAL BODIES LIKE DTCP 
Approval for Villa Promotion is Non-Corporative Limit. 
If the land area is more than one acre, DTCP Approval and Local Bodies counter sign is 
Required. 
FEASIBILITY OF INFRASTRUCTURE LIKE STP 
Generally water has two types of hardness one is Temporary hardness and other is 
Permanent hardness. 
In the site we have two types of Treatment plants they are: 
Water Treatment Plant (WTP) 
Sewage Treatment Plant(STP)
PLUMBING: 
There are two types of plumbing system. They are 
Internal Plumbing. 
External Plumbing. 
INTERNAL PLUMBING: 
There are two methods of internal plumbing they are 
Wall mounted closet 
Floor mounted closet
DECK
PLANNING FOR VILLA AND ROW HOUSE: 
There are two types of planning . 
Pre Planning. 
Post Planning. 
Pre Planning is the one in which planning is done before starting of any project and Post Planning is the one in which 
planning is made after the starting of the work. 
Generally for construction of Villas. Engineers follow "120 DAYS MANTRA" 
It means a Villa should be completed within 120 days. 
The steps are as follow: 
Footing work 
Plinth beam 20 days 
Basement 10 days 
Ground floor slab 25 days 
First floor slab 15 days 
Second floor slab 15 days 
Ground floor block work 20 days 
First floor block work 15 days 
After completing each and every work it should be recorded in office.
PLASTERING: 
MESH:
WATER PROOFING: 
Generally leakage of water occurs from the Terrace and mostly from the corners of 
the wall.To avoid Leakage water proofing is used. 
V-shaped groove cut is made on the coeners of the wall and it cleaned by iron 
brushes. Then Ceralastic coating is laid on the terrace. Ceralastic coating contains some 
Ceramic chemicals. 
Above the coating we mortar of ratio 1:4:8 is laid and after that again Ceralastic 
coating is laid. 
And then Hantching of walls is done i.e.,making slope like structure in between the 
walls and the floor is called Hantching. 
Sloping is made because when the rain water falls on the sloped area it is drained to 
the opening that is provided in the terrace. And above this 1:2 ratio of plastering work is 
done.
STEPS FOLLOWED IN WATER PROOFING AT ROOF: 
• Dead Mortar removal 
• Beams and Bricks clearing 
• Cleaning with Iron brush 
• Laying of coating 
• Slope work 
• Using Styrene Butadyene rubber 
• Final Finishing PCC is laid.
And for Door work, if there is any gap between the door 
and the wall it is filled up the “Foam”. 
And for window work, if there is any gap between the window and wall it is filled with 
the chemical called “Sealant“.
SAFETY RULES: 
Unauthorized over-age / child labor is restricted at site / labor colony. 
Women workers are not allowed to work at site above 5PM. 
Helmet and Safety shoes are compulsory at site work. 
Nobody allow at site until safety induction, medical test and PPE’s(personal protective 
equpiments) are not provide. 
All personnel are required to wear a High visibility vest if working in vehicle movement 
areas. 
The consumption of alcohol and drugs is prohibited. 
No person is to operate any mechanical plant or equipment unless they have been 
trained and have been certificated as competent.
SAFTEY SIGN BOARDS:
GROUTING: 
If there is any leakage in the corners of the walls Grouting is one of the method to avoid. 
In this method, In a pipe Expance 250 is filled and it is injected at the damaged area or where 
leakage occurs.
ROOF WORK: 
• Initially Shuttering work. 
• "TUBE LEVEL“ is used to maintain the horizontal level. 
• After Beam works and slab works are done. 
• Here for Beams, maximum of 16mm diameter and minimum 12mm diameter bars 
are used. 
• 16mm bar is placed at the upper part of beam and 12mm bar is placed at the lower 
part. 
• Usually rods are 12m in length and they are not enough in reinforcement so two 
rods are connected by Lap joint.
• Finally the reinforcement rods are placed and concrete is laid. 
• Beam Work: 
• For checking the horizontal level of slab ,steps, etc.. Tube level is used. Tube level is the 
instrument made with transparent tube which filled with water. 
• By placing one end of the tube level at one level and other end at some of the structure. If on both 
ends of the tube, water level remains in the same level then the structure is in correct horizontal 
level. 
• If there is any air bubble/obstacle in the tube it will not show the correct level.so air bubbles in the 
tube should be removed.
ELECTRICAL WORK : 
-For all the Villas and the Row houses Earthing lines are given outside the building. 
-for the Villas there are 
-> 34 light points 
-> 7 AC points 
-> 3 TV points 
-> 3 Telephone points 
-> 19 sockets 
-> 7 fan points 
->3 phase plug in used 
colors of the different wires as follows: 
> Earthing wire -Green color 
> Power wire -Red color 
> Fan wires -Yellow color 
> Neutral wires -Black color
STAGES OF ELECTRICAL WORK: 
- Ground floor work - 3 hours 
- First floor work - 3 hours 
- Second floor work - 1 hour 
- Wall chase - 4 days 
- Wiring - 2 days Inverter point: 
Junction box:
DIFFERENT DIAMETERS OF REINFORCEMENT RODS 
ARE AS FOLLOWS: 
• 8mm,10mm,12mm,16mm,20mm,25mm,32mm,.and tensile strength is Fe500,Fe415 
etc., 
• The unit weight of Rod is identified by d2/162 kg/m ( d is the diameter). 
• In general, the length of reinforcement rod is 12 meters.
LAP JOINT 
• If we have any structure of beam or column which exceeds the 12 meter we can join two 
rods. By the way span of length that is used to join the two rods is called 
"lap length". 
• The lap length should be of 50 times the diameter of the rod
STERUPS: 
CLEAR COVER: 
The distance between the stirrups and the end of the beam work.
COSTING: 
• Before taking up any kind projects first we should estimate the cost of the project and we should 
take care that the project should be completed within the estimation cost. 
• These kind of works are taken up by planning engineer. 
• Here the estimation is done by calculating the cost of each and every substance that is used in the 
construction like brick,cementetc., 
• If we are using any machineries in the work then we should take care of fuel cost and the wage of 
person who is doing the work with that machine. 
• For example if we are using any Cranes in the field then the driver beta and fuel that is used, is also 
to be calculated. 
• The basic step for calculating the cost is BOQ (Bill of quantity). 
• Intially we prepare the zero cost report based on that we proceed for the further steps. 
•
• The price of steel bars and cement in the market changes from day to day.so if we planned initially 
according to the price that is in the market we will get some amount of money and if there is any 
sudden increase in the market price of these materials then our estimation will be wrong. 
• So to avoid that for only steel bars and cement we will prepare the ESCALAMATION CLAIM 
• Costing is an office work so it is prepared in the 
excel. The steps as follows 
Gist, Basic cost, planning and machinery, general plant and machinery, 
concrete(RMC),curinganalysis, External scafolding, shuttering analysis, shuttering abstract, Rate 
analysis etc., 
• Here the rate analysis is important among the all process.
PAINTING: 
• The main function of the painting is to reduce the corrosion of materials form the 
weather. 
• To decorate the structure by giving smooth and colorful finish. 
• Painting the building is done after the completion of all kinds of civil works. 
• So it is like makeup the structure. 
STEPS FOLLOWED IN THE PAINTING THE WALL: 
1) putty - 2 coats 
2) primer - 1 coat 
3) emulsion (internal walls) - 2 coats emulsion gives the color to the paint 
Initially putty is applied over the wall
Scratch work is done to give smoothness to the wall. Here the wall is rubbed with the 
sand paper to get the smoothness. sand paper particles may be of different micron sizes. 
Use of primer is to give good bond strength between the putty and the paint. 
For painting the external wall we should take care of weather conditions like rain fall, 
sun light and other parameter for the selection of the paint.
• For painting the steel and wood the process is same as mentioned above but instead 
of emulsion, “Enamel“ is used. 
• After painting, the even flat surface of the wall is made by Hand or Holler . In 
general Roller process is beneficial. 
• Generally the time period for the painting the building depends up on the area to be 
painted, number of labors available. 
• But for the completion of the work it takes minimum 7 days.
THANK YOU

More Related Content

What's hot

Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
Dexter Ng
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Md Raijul Islam
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
Edel Fox
 
School Buildings of the Future
School Buildings of the FutureSchool Buildings of the Future
School Buildings of the Future
Edel Fox
 
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structuresRestoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Edel Fox
 
F.A.R., Ground Coverage and Height Permissible as per Bye Laws
F.A.R., Ground Coverage and Height Permissible as per Bye LawsF.A.R., Ground Coverage and Height Permissible as per Bye Laws
F.A.R., Ground Coverage and Height Permissible as per Bye Laws
Ar. Md Shahroz Alam
 
Making Buildings Cost- Effective through Building Design
Making Buildings  Cost- Effective through  Building DesignMaking Buildings  Cost- Effective through  Building Design
Making Buildings Cost- Effective through Building Design
JIT KUMAR GUPTA
 
Glass Fiber Reinforced Gypsum (GFRG)
Glass Fiber Reinforced Gypsum (GFRG)Glass Fiber Reinforced Gypsum (GFRG)
Glass Fiber Reinforced Gypsum (GFRG)
Mukul Saini
 
D18cl124 internship_report
D18cl124 internship_reportD18cl124 internship_report
D18cl124 internship_report
CHARUSSAT UNIVERSITY
 
Cost effective materials
Cost effective materialsCost effective materials
Cost effective materials
Sarthak Kaura
 
Building Bye Laws and Green Buildings
Building Bye Laws and Green BuildingsBuilding Bye Laws and Green Buildings
Building Bye Laws and Green Buildings
suneelkumar chalavadi kali
 
AintreeInfra Gypsum Block
AintreeInfra Gypsum BlockAintreeInfra Gypsum Block
AintreeInfra Gypsum Block
Merina Kunjumon
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
Umair Ali
 
Low cost residential building using locally available materials
Low cost residential building using locally available materialsLow cost residential building using locally available materials
Low cost residential building using locally available materials
Puspendu Ray
 
Affordable Housing company in India WorldHaus Inc.
Affordable Housing company in India WorldHaus Inc.Affordable Housing company in India WorldHaus Inc.
Affordable Housing company in India WorldHaus Inc.
WorldHaus
 
Q1 presentation
Q1 presentationQ1 presentation
Q1 presentation
AaronYongLuoZhou
 
Advanced construction equipments and techniques
Advanced construction equipments and techniquesAdvanced construction equipments and techniques
Advanced construction equipments and techniques
selva ganesh
 
IRJET- Comparative Study on Cost Estimation of GFRG Wall Panel System wit...
IRJET-  	  Comparative Study on Cost Estimation of GFRG Wall Panel System wit...IRJET-  	  Comparative Study on Cost Estimation of GFRG Wall Panel System wit...
IRJET- Comparative Study on Cost Estimation of GFRG Wall Panel System wit...
IRJET Journal
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
taufiqahmad_87
 
Low cost housing India
Low cost housing IndiaLow cost housing India

What's hot (20)

Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
 
School Buildings of the Future
School Buildings of the FutureSchool Buildings of the Future
School Buildings of the Future
 
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structuresRestoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
 
F.A.R., Ground Coverage and Height Permissible as per Bye Laws
F.A.R., Ground Coverage and Height Permissible as per Bye LawsF.A.R., Ground Coverage and Height Permissible as per Bye Laws
F.A.R., Ground Coverage and Height Permissible as per Bye Laws
 
Making Buildings Cost- Effective through Building Design
Making Buildings  Cost- Effective through  Building DesignMaking Buildings  Cost- Effective through  Building Design
Making Buildings Cost- Effective through Building Design
 
Glass Fiber Reinforced Gypsum (GFRG)
Glass Fiber Reinforced Gypsum (GFRG)Glass Fiber Reinforced Gypsum (GFRG)
Glass Fiber Reinforced Gypsum (GFRG)
 
D18cl124 internship_report
D18cl124 internship_reportD18cl124 internship_report
D18cl124 internship_report
 
Cost effective materials
Cost effective materialsCost effective materials
Cost effective materials
 
Building Bye Laws and Green Buildings
Building Bye Laws and Green BuildingsBuilding Bye Laws and Green Buildings
Building Bye Laws and Green Buildings
 
AintreeInfra Gypsum Block
AintreeInfra Gypsum BlockAintreeInfra Gypsum Block
AintreeInfra Gypsum Block
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
 
Low cost residential building using locally available materials
Low cost residential building using locally available materialsLow cost residential building using locally available materials
Low cost residential building using locally available materials
 
Affordable Housing company in India WorldHaus Inc.
Affordable Housing company in India WorldHaus Inc.Affordable Housing company in India WorldHaus Inc.
Affordable Housing company in India WorldHaus Inc.
 
Q1 presentation
Q1 presentationQ1 presentation
Q1 presentation
 
Advanced construction equipments and techniques
Advanced construction equipments and techniquesAdvanced construction equipments and techniques
Advanced construction equipments and techniques
 
IRJET- Comparative Study on Cost Estimation of GFRG Wall Panel System wit...
IRJET-  	  Comparative Study on Cost Estimation of GFRG Wall Panel System wit...IRJET-  	  Comparative Study on Cost Estimation of GFRG Wall Panel System wit...
IRJET- Comparative Study on Cost Estimation of GFRG Wall Panel System wit...
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
 
Low cost housing India
Low cost housing IndiaLow cost housing India
Low cost housing India
 

Similar to Construction & Management

Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
Ravi Shankar
 
Building maintenance
Building maintenance Building maintenance
Building maintenance
Janki Patel
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
ErLavKushPrasad
 
DAMP PROOFING TREATMENT FOR FLAT ROOF.
DAMP PROOFING TREATMENT FOR FLAT ROOF.DAMP PROOFING TREATMENT FOR FLAT ROOF.
DAMP PROOFING TREATMENT FOR FLAT ROOF.
ATUL KISHOR
 
Residential building construction
Residential building constructionResidential building construction
Residential building construction
Civil Manage
 
house construction
house constructionhouse construction
house construction
Abhinav Saha
 
Finishing work,Construction workshop.
Finishing work,Construction workshop.Finishing work,Construction workshop.
Finishing work,Construction workshop.
Md Hasibul islam Rifat
 
Heals - structural presentation
Heals -  structural presentationHeals -  structural presentation
Heals - structural presentation
Tanvir Khan
 
CIVIL SITE SOP.pptx
CIVIL SITE SOP.pptxCIVIL SITE SOP.pptx
CIVIL SITE SOP.pptx
aslemjalaludeen
 
Construction Site Visit
Construction Site VisitConstruction Site Visit
Construction Site Visit
Maliha Mehr
 
Finishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinningFinishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinning
ANURAG KASHYAP
 
New Building Materials
New Building MaterialsNew Building Materials
New Building Materials
Dr K M SONI
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
DougDos
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
Jaspreet singh
 
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptxMAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
NamanGhevariya
 
siddhant .construction field visit.pptx
siddhant .construction field visit.pptxsiddhant .construction field visit.pptx
siddhant .construction field visit.pptx
SiddhantAshokSuryawa
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
Shariful Haque Robin
 
General Specifications (Architecture)
General Specifications (Architecture)General Specifications (Architecture)
General Specifications (Architecture)
Shivang Madaan
 
working in a building and all the procedures
working in a building and all the proceduresworking in a building and all the procedures
working in a building and all the procedures
azharbhattumz
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
Himanshumangal12
 

Similar to Construction & Management (20)

Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
 
Building maintenance
Building maintenance Building maintenance
Building maintenance
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
DAMP PROOFING TREATMENT FOR FLAT ROOF.
DAMP PROOFING TREATMENT FOR FLAT ROOF.DAMP PROOFING TREATMENT FOR FLAT ROOF.
DAMP PROOFING TREATMENT FOR FLAT ROOF.
 
Residential building construction
Residential building constructionResidential building construction
Residential building construction
 
house construction
house constructionhouse construction
house construction
 
Finishing work,Construction workshop.
Finishing work,Construction workshop.Finishing work,Construction workshop.
Finishing work,Construction workshop.
 
Heals - structural presentation
Heals -  structural presentationHeals -  structural presentation
Heals - structural presentation
 
CIVIL SITE SOP.pptx
CIVIL SITE SOP.pptxCIVIL SITE SOP.pptx
CIVIL SITE SOP.pptx
 
Construction Site Visit
Construction Site VisitConstruction Site Visit
Construction Site Visit
 
Finishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinningFinishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinning
 
New Building Materials
New Building MaterialsNew Building Materials
New Building Materials
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptxMAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
 
siddhant .construction field visit.pptx
siddhant .construction field visit.pptxsiddhant .construction field visit.pptx
siddhant .construction field visit.pptx
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
General Specifications (Architecture)
General Specifications (Architecture)General Specifications (Architecture)
General Specifications (Architecture)
 
working in a building and all the procedures
working in a building and all the proceduresworking in a building and all the procedures
working in a building and all the procedures
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 

Recently uploaded

Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
Aditya Rajan Patra
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 

Recently uploaded (20)

Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 

Construction & Management

  • 1. In Plant Training PROMOTION OF VILLA -Gs Mohan (1011210335)
  • 2. CASA GRANDE focus on “Promotion of Villa” STEPS IN PROMOTION OF VILLA: • FEASIBILITY OF LAYOUT • VILLA APPROVAL FROM LOCAL BODIES LIKE DTCP • FEASIBILITY OF INFRASTRUCTURE LIKE STP • PLANNING FOR VILLA • COSTING • EXECUTION OF VILLA LIKE PLASTERING,PAINTING,TILE FINISHING,WIRING,PLUMBING ,ETC.. • DELIVERY
  • 3. TYPES OF CONSTRUCTION: Villa – 112 nos. Row House – 64 nos. VILLA ROW HOUSE Ground +2 Designed Structures Ground +2 Designed Structures 1600 sq.ft land area , Built up area 2325 sq.ft Land Area 700 sq.ft Built Up Area 1121 sq.ft 18 acre expanse 18 acre expanse 4 Bed Rooms and 2 Living Rooms 2 Bed Rooms and 2 Living Rooms Two Exclusive Car Parks Two Exclusive Car Parks Exclusive Garden Area & Open Terrace Space Exclusive Garden Area & Open Terrace Space Contemporary New Age Architecture & Dinning Area Opening to Garden Contemporary New Age Architecture & Dinning Area Opening to Garden
  • 4. BRICK: SOLID BLOCK,AERAGON BLOCK,NORMAL BLOCK,HOLLOW BLOCK SOLID BLOCK for wall or block construction , CONCRETE: M20 (cement: sand: gravel=1: 1.5: 3), M25 (cement: sand: gravel=1: 1: 2) REINFORCEMENT: Fe500 WOOD: Dock wood, ascetic purpose in Elevation. Thick wood or Rubber wood used for windows and Doors.
  • 5. VILLA APPROVAL FROM LOCAL BODIES LIKE DTCP Approval for Villa Promotion is Non-Corporative Limit. If the land area is more than one acre, DTCP Approval and Local Bodies counter sign is Required. FEASIBILITY OF INFRASTRUCTURE LIKE STP Generally water has two types of hardness one is Temporary hardness and other is Permanent hardness. In the site we have two types of Treatment plants they are: Water Treatment Plant (WTP) Sewage Treatment Plant(STP)
  • 6. PLUMBING: There are two types of plumbing system. They are Internal Plumbing. External Plumbing. INTERNAL PLUMBING: There are two methods of internal plumbing they are Wall mounted closet Floor mounted closet
  • 8. PLANNING FOR VILLA AND ROW HOUSE: There are two types of planning . Pre Planning. Post Planning. Pre Planning is the one in which planning is done before starting of any project and Post Planning is the one in which planning is made after the starting of the work. Generally for construction of Villas. Engineers follow "120 DAYS MANTRA" It means a Villa should be completed within 120 days. The steps are as follow: Footing work Plinth beam 20 days Basement 10 days Ground floor slab 25 days First floor slab 15 days Second floor slab 15 days Ground floor block work 20 days First floor block work 15 days After completing each and every work it should be recorded in office.
  • 10. WATER PROOFING: Generally leakage of water occurs from the Terrace and mostly from the corners of the wall.To avoid Leakage water proofing is used. V-shaped groove cut is made on the coeners of the wall and it cleaned by iron brushes. Then Ceralastic coating is laid on the terrace. Ceralastic coating contains some Ceramic chemicals. Above the coating we mortar of ratio 1:4:8 is laid and after that again Ceralastic coating is laid. And then Hantching of walls is done i.e.,making slope like structure in between the walls and the floor is called Hantching. Sloping is made because when the rain water falls on the sloped area it is drained to the opening that is provided in the terrace. And above this 1:2 ratio of plastering work is done.
  • 11. STEPS FOLLOWED IN WATER PROOFING AT ROOF: • Dead Mortar removal • Beams and Bricks clearing • Cleaning with Iron brush • Laying of coating • Slope work • Using Styrene Butadyene rubber • Final Finishing PCC is laid.
  • 12. And for Door work, if there is any gap between the door and the wall it is filled up the “Foam”. And for window work, if there is any gap between the window and wall it is filled with the chemical called “Sealant“.
  • 13. SAFETY RULES: Unauthorized over-age / child labor is restricted at site / labor colony. Women workers are not allowed to work at site above 5PM. Helmet and Safety shoes are compulsory at site work. Nobody allow at site until safety induction, medical test and PPE’s(personal protective equpiments) are not provide. All personnel are required to wear a High visibility vest if working in vehicle movement areas. The consumption of alcohol and drugs is prohibited. No person is to operate any mechanical plant or equipment unless they have been trained and have been certificated as competent.
  • 15. GROUTING: If there is any leakage in the corners of the walls Grouting is one of the method to avoid. In this method, In a pipe Expance 250 is filled and it is injected at the damaged area or where leakage occurs.
  • 16. ROOF WORK: • Initially Shuttering work. • "TUBE LEVEL“ is used to maintain the horizontal level. • After Beam works and slab works are done. • Here for Beams, maximum of 16mm diameter and minimum 12mm diameter bars are used. • 16mm bar is placed at the upper part of beam and 12mm bar is placed at the lower part. • Usually rods are 12m in length and they are not enough in reinforcement so two rods are connected by Lap joint.
  • 17. • Finally the reinforcement rods are placed and concrete is laid. • Beam Work: • For checking the horizontal level of slab ,steps, etc.. Tube level is used. Tube level is the instrument made with transparent tube which filled with water. • By placing one end of the tube level at one level and other end at some of the structure. If on both ends of the tube, water level remains in the same level then the structure is in correct horizontal level. • If there is any air bubble/obstacle in the tube it will not show the correct level.so air bubbles in the tube should be removed.
  • 18. ELECTRICAL WORK : -For all the Villas and the Row houses Earthing lines are given outside the building. -for the Villas there are -> 34 light points -> 7 AC points -> 3 TV points -> 3 Telephone points -> 19 sockets -> 7 fan points ->3 phase plug in used colors of the different wires as follows: > Earthing wire -Green color > Power wire -Red color > Fan wires -Yellow color > Neutral wires -Black color
  • 19. STAGES OF ELECTRICAL WORK: - Ground floor work - 3 hours - First floor work - 3 hours - Second floor work - 1 hour - Wall chase - 4 days - Wiring - 2 days Inverter point: Junction box:
  • 20. DIFFERENT DIAMETERS OF REINFORCEMENT RODS ARE AS FOLLOWS: • 8mm,10mm,12mm,16mm,20mm,25mm,32mm,.and tensile strength is Fe500,Fe415 etc., • The unit weight of Rod is identified by d2/162 kg/m ( d is the diameter). • In general, the length of reinforcement rod is 12 meters.
  • 21. LAP JOINT • If we have any structure of beam or column which exceeds the 12 meter we can join two rods. By the way span of length that is used to join the two rods is called "lap length". • The lap length should be of 50 times the diameter of the rod
  • 22. STERUPS: CLEAR COVER: The distance between the stirrups and the end of the beam work.
  • 23. COSTING: • Before taking up any kind projects first we should estimate the cost of the project and we should take care that the project should be completed within the estimation cost. • These kind of works are taken up by planning engineer. • Here the estimation is done by calculating the cost of each and every substance that is used in the construction like brick,cementetc., • If we are using any machineries in the work then we should take care of fuel cost and the wage of person who is doing the work with that machine. • For example if we are using any Cranes in the field then the driver beta and fuel that is used, is also to be calculated. • The basic step for calculating the cost is BOQ (Bill of quantity). • Intially we prepare the zero cost report based on that we proceed for the further steps. •
  • 24. • The price of steel bars and cement in the market changes from day to day.so if we planned initially according to the price that is in the market we will get some amount of money and if there is any sudden increase in the market price of these materials then our estimation will be wrong. • So to avoid that for only steel bars and cement we will prepare the ESCALAMATION CLAIM • Costing is an office work so it is prepared in the excel. The steps as follows Gist, Basic cost, planning and machinery, general plant and machinery, concrete(RMC),curinganalysis, External scafolding, shuttering analysis, shuttering abstract, Rate analysis etc., • Here the rate analysis is important among the all process.
  • 25. PAINTING: • The main function of the painting is to reduce the corrosion of materials form the weather. • To decorate the structure by giving smooth and colorful finish. • Painting the building is done after the completion of all kinds of civil works. • So it is like makeup the structure. STEPS FOLLOWED IN THE PAINTING THE WALL: 1) putty - 2 coats 2) primer - 1 coat 3) emulsion (internal walls) - 2 coats emulsion gives the color to the paint Initially putty is applied over the wall
  • 26. Scratch work is done to give smoothness to the wall. Here the wall is rubbed with the sand paper to get the smoothness. sand paper particles may be of different micron sizes. Use of primer is to give good bond strength between the putty and the paint. For painting the external wall we should take care of weather conditions like rain fall, sun light and other parameter for the selection of the paint.
  • 27. • For painting the steel and wood the process is same as mentioned above but instead of emulsion, “Enamel“ is used. • After painting, the even flat surface of the wall is made by Hand or Holler . In general Roller process is beneficial. • Generally the time period for the painting the building depends up on the area to be painted, number of labors available. • But for the completion of the work it takes minimum 7 days.