SlideShare a Scribd company logo
“Big Dig” Project
THE CENTRAL ARTERY/TUNNEL PROJECT (CA/T)
A CASE STUDY ON PROJECT COMPLEXITY.
Project Description
Located in Boston, MA, on the
northeast coast of the United
States.
 Includes tunnels, highway
interchange connections, bridges
and pedestrian facilities
Project Map
Project Description
Rerouted the Central Artery (Interstate 93),
into a 3.5-mile (5.6-km) tunnel.
 Construction of the Ted Williams Tunnel.
 Construction of the Leonard P. Zakim Bunker
Hill Memorial Bridge over the Charles River.
 Construction of the Rose Kennedy
Greenway in the space vacated by the
previous I-93 elevated roadway.
Project Description
 Planning Phase started in 1982
 Construction work – 1991-2006
 Estimated Completion - 1998
 Actual Completion – Dec 31, 2007
Estimated Cost - $2.8 billion
Final Cost - $14.6 billion
Cost over run – 190%
Official project owner - Massachusetts
Turnpike Authority
 Joint venture of Bechtel and Parson
Brinkerhoff
Source: http://www.roadtraffic-technology.com
Why Boston Needed the Big Dig?
Traffic improvements and
substantial reductions in
congestion
 Improving mobility in
downtown Boston
 Reconnect neighborhoods
severed by the old elevated
highway
Source: http://www.massdot.state.ma.us
Central Artery: Before and After
Source:http://www.bigdig.com
Problems faced
Escalating costs
Scheduling overruns
Design flaws
Charges of poor execution and use of
substandard materials
Fatal Ceiling Collapse
Criminal arrests and one death
Source: http://www.roadtraffic-technology.com
Complexity Factors - Cost
Contingency Usage
◦ Construction Contracts
◦ Management Contingency
◦ Massachusetts Turnpike Authority CEO Contingency
Risk Analysis
◦ Location
◦ Utilities
Estimate Formation
◦ Ted Williams Tunnel
◦ Zakim Bunker Hill Bridge
◦ Center Artery (I-93)
Complexity Factors - Cost
Figure. Big Dig Project Cost Growth (National Research Council 2003)
55%
15%
8%
7%
5%
3%
2%
5% Inflation
Environmental/Mitigation
Scope Growth
Accounting Changes
Traffic
Schedule Maintenance
Contingency for Unknowns
Other
Complexity Factors - Schedule
Timeline Requirements
◦ Community Conflicts
Milestones
Schedule Control
◦ Software Programs
Complexity Factors - Technical
Scope of Project
Owner’s Internal Structure
Design Method
Complexity Factors - Context
Public
◦ Economic Value of Boston
Utility Coordination
◦ 29 Miles of Underground Utility Relocation and Updating
Land Use Impact
◦ 300 acres of Green Space
Complexity Factors - Financing
Federal Funding
State Funding
Borrowing Against Future Funding
Project Dimension Complexity
Ranking
DIMENSION RANK
Context 5
Cost 4
Technical 3
Financing 2
Schedule 1
Project Dimension Complexity
Rating
DIMENSIONS SCALE (0 – 100)
Cost Dimension
Complexity
99
Schedule Dimension
Complexity
90
Technical Dimension Complexity 95
Context
Dimension Complexity
100
Financing Dimension Complexity 92
Complexity Map
The Big Dig Project
0
10
20
30
40
50
60
70
80
90
100
Technical
Cost
FinancingContext
Schedule
Critical Planning and
Analysis Methods
Method 1: Define Critical Success Factors
◦ Community Needs
◦ Political Restrictions
◦ Federal and State Funding
◦ Major Project Components
◦ Center Artery (I-93)
◦ Ted Williams Tunnel
◦ Zakim Bunker Hill Bridge
Method 2: Assemble Project Team
Communication
Collaboration
◦ Example
◦ Ted Williams Tunnel Ceiling Panel Collapse
Method 3: Project Arrangements
Design-Bid-Build
Value Engineering
Dispute Resolution
Dispute Resolution Board
Method 4: Early Cost Model
and Finance Plan
Incorrect Initial Cost Model and Finance Plan
The cost model would have included
◦ Inflation
◦ Project Risk- Account for Cost Overruns
◦ More detail over Design Costs
Method 5: Develop
Project Action Plans
Major Obstacles
◦ Restrictive Legislation
◦ Acquisition of ROW
◦ Cooperation of Utilities
◦ Community Support
Tools for Managing Complex Projects
The following tools were used in the Big Dig Project:
•Public involvement plan
•Critical permit issues
•Offsite fabrication
•Co-locate team
•Dispute resolution plan
Public Involvement Plan
◦ Project planners worked with community groups, government & business leaders to
create a consensus of how the project would be built
◦ Mitigation: The process of keeping the city open and making certain all
affected groups would be treated fairly
◦ Informed, organized interest groups press for their demands
◦ Public involvement plan produces early project wins of consensus but at the
expense of late project soaring project costs
Critical Permit Issues
◦ Bechtel/Parsons Brinkerhoff (B/PB):
◦ Engineering authority that approved, permitted, and released designs for construction
◦ Construction managers in charge of contractors & sub-contractors
◦ B/PB operated the project with the philosophy of getting this done, ask questions later
◦ Many plans that were permitted and released for construction were incomplete, contained
numerous errors, and lacked proper subsurface exploration
◦ The lax oversight produced an estimated $750 million in construction over-runs
Offsite Fabrication
◦ Utilized successfully on the CA/T project
◦ Several examples are:
◦ Immersed steel tubes for the Ted Williams Tunnel
◦ Steel box girder sections for the Bunker Hill Bridge
◦ Utilized successfully on the CA/T project
◦ Offsite fabrication of box girders and steel tubes produced accurate sections per specification that could
be test connected at the factory to insure smooth and timely installation
◦ Quicker assembly time at the job site with smaller construction crews as compared to onsite fabrication
◦ Exposure of construction workers to difficult job environments was reduced as compared to onsite
fabrication
Co-Locate Team
◦ Co-Locate elements of the project team to produce a cohesive team effort to complete a project
◦ Perhaps the most controversial tool
◦ In 1998, State of Massachusetts combined B/PB with state workers into one integrated project
organization
◦ Massachusetts Turnpike Authority was at the top of the organization chart
◦ State of Massachusetts designated B/PB as “owner’s representative” in several instances
◦ Who is in charge?
Dispute Resolution Plan
◦ Two noteworthy dispute resolution plan techniques were utilized on the CA/T project:
◦ Partnering
◦ Mediation
◦ Partnering was practiced on the CA/T project for construction projects with a duration of least
one year and a value of $1 million or more
◦ Mediation was utilized to resolve the dispute of responsibility for leaks at the Fort Point
Channel tunnel area
References
◦ Bartlett School of Planning (UCL). (2011). “The Central Artery/Third Harbor Tunnel Project (‘The Big Dig’), Omega Centre.” Bloomsbury, London.
◦ Gelinas, N. (2007). “Lessons of Boston’s Big Dig.” City Journal Autumn. New York, New York.
◦ Greirman, V. (2010). “The Big Dig: Learning from a Mega Project.” NASA, <http://appel.nasa.gov/2010/07/15/the-big-dig-learning-from-a-mega-project/>
(November 13, 2013).
◦ Hsu, J. Mckay, S., McKnight, M. (2003). “Cost-Benefit Analysis of Boston’s Central Artery/Tunnel Project” Carnegie Mello University. Pittsburgh, PA.
◦ Lewis, R. and Murphy, S. (2003). “Artery Errors Cost More Than $1b.” The Boston Globe, <http://www.boston.com/globe/metro/packages/bechtel/>
(November 13, 2013).
◦ Massachusetts Department of Transportation (MassDOT). (2013). “The Central Artery/Tunnel Project-The Big Dig.” MassDOT Highway Division.
<http://www.massdot.state.ma.us/highway/TheBigDig.aspx> (October 5, 2013).
◦ National Research Council. “Completing the "Big Dig": Managing the Final Stages of Boston's Central Artery/Tunnel Project. Washington, DC: The National
Academies Press, 2003.
◦ Poole, R.W., Samuel, P. (2011). “Transportation Mega-Projects and Risk.” Reason Foundation Policy Brief 97. Los Angeles, CA.
◦ Saltzman, J. (2009). “Big Dig Contractor Modern Continental Pleads Guilty.” Boston Globe.
<http://www.boston.com/news/local/breaking_news/2009/05/modern_continen_2.html> (October 5, 2013).
◦ Salvucci, F. P. (2008). “Unearthing the Big Dig.” Massachusetts Institute of Technology. Cambridge, MA.
◦ Wood, D. (2001). “Learning From the Big Dig.” Federal Highway Administration: Public Roads,
<http://www.fhwa.dot.gov/publications/publicroads/01julaug/bigdig.cfm> (November 13, 2013).

More Related Content

What's hot

Formula F1 Project Management
Formula F1 Project ManagementFormula F1 Project Management
Formula F1 Project Management
Muhammad Awais
 
Float in Projects
Float in ProjectsFloat in Projects
Float in Projects
Rd Pokhrel
 
A case study presentation on Dabhol Power Plant
A case study presentation on Dabhol Power PlantA case study presentation on Dabhol Power Plant
A case study presentation on Dabhol Power Plant
Ashutosh Singh
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.
Yousef Abujubba
 
Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group Assignment
Arissa Loh
 
report
reportreport
report
Ravi Panchal
 
BTT - bigger better bolder BT - 20130501
BTT -  bigger better bolder BT - 20130501BTT -  bigger better bolder BT - 20130501
BTT - bigger better bolder BT - 20130501
George Gabriel
 
Engl3355 case analysis group 6
Engl3355 case analysis group 6Engl3355 case analysis group 6
Engl3355 case analysis group 6Aneth Sanchez
 
Boston creamery final
Boston creamery finalBoston creamery final
Boston creamery final
Neeta Pai
 
Summary chunnel tunnel project management
Summary chunnel tunnel project managementSummary chunnel tunnel project management
Summary chunnel tunnel project management
Nilesh Dhotre
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
Kishan Solankimbaccepmp
 
Boeing 767 Case Study
Boeing 767 Case StudyBoeing 767 Case Study
Boeing 767 Case Study
Manish Bhangre
 
Roles of project managers in oe
Roles of project managers in oeRoles of project managers in oe
Roles of project managers in oe
Aswin prakash i , Xantus Technologies
 
Project Management Report
Project Management ReportProject Management Report
Project Management Report
SANKET SENAPATI
 
BOOT, BOT, Management Contracts & Turnkey PROJECTS
BOOT, BOT, Management Contracts & Turnkey PROJECTSBOOT, BOT, Management Contracts & Turnkey PROJECTS
BOOT, BOT, Management Contracts & Turnkey PROJECTS
aly_ayk
 
Cash flow report using ms project
Cash flow report  using ms projectCash flow report  using ms project
Cash flow report using ms project
Kundan Sanap
 
Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and features
Bimenpreet Kaur
 
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
TEJPRAKASH KUMAWAT
 
Construction delays
Construction delaysConstruction delays
Construction delays
Saida Njim
 
The Army Crew casestudy
The Army Crew casestudyThe Army Crew casestudy
The Army Crew casestudy
Elina
 

What's hot (20)

Formula F1 Project Management
Formula F1 Project ManagementFormula F1 Project Management
Formula F1 Project Management
 
Float in Projects
Float in ProjectsFloat in Projects
Float in Projects
 
A case study presentation on Dabhol Power Plant
A case study presentation on Dabhol Power PlantA case study presentation on Dabhol Power Plant
A case study presentation on Dabhol Power Plant
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.
 
Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group Assignment
 
report
reportreport
report
 
BTT - bigger better bolder BT - 20130501
BTT -  bigger better bolder BT - 20130501BTT -  bigger better bolder BT - 20130501
BTT - bigger better bolder BT - 20130501
 
Engl3355 case analysis group 6
Engl3355 case analysis group 6Engl3355 case analysis group 6
Engl3355 case analysis group 6
 
Boston creamery final
Boston creamery finalBoston creamery final
Boston creamery final
 
Summary chunnel tunnel project management
Summary chunnel tunnel project managementSummary chunnel tunnel project management
Summary chunnel tunnel project management
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Boeing 767 Case Study
Boeing 767 Case StudyBoeing 767 Case Study
Boeing 767 Case Study
 
Roles of project managers in oe
Roles of project managers in oeRoles of project managers in oe
Roles of project managers in oe
 
Project Management Report
Project Management ReportProject Management Report
Project Management Report
 
BOOT, BOT, Management Contracts & Turnkey PROJECTS
BOOT, BOT, Management Contracts & Turnkey PROJECTSBOOT, BOT, Management Contracts & Turnkey PROJECTS
BOOT, BOT, Management Contracts & Turnkey PROJECTS
 
Cash flow report using ms project
Cash flow report  using ms projectCash flow report  using ms project
Cash flow report using ms project
 
Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and features
 
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
The Army Crew casestudy
The Army Crew casestudyThe Army Crew casestudy
The Army Crew casestudy
 

Similar to Project Complexity (Case study)

ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
Lucas de Brito Nascimento
 
Resume
ResumeResume
Walton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the YearWalton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the Year
OHM Advisors
 
Torrey pines road corridor study final
Torrey pines road corridor study finalTorrey pines road corridor study final
Torrey pines road corridor study finalkday1
 
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_AkhtarJavad Akhtar
 
Resume pe civil
Resume pe civilResume pe civil
Resume pe civil
Kim D. Scattarella
 
2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs2016-07-28 Martin Jacobs
2016-07-28 Martin JacobsMartin Jacobs
 
megaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdfmegaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdf
Adina Levin
 
Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017
melissanatech
 
LEADERSHIP ROLES With a project of this magnitude, it .docx
LEADERSHIP ROLES With a project of this magnitude, it .docxLEADERSHIP ROLES With a project of this magnitude, it .docx
LEADERSHIP ROLES With a project of this magnitude, it .docx
croysierkathey
 
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnelsProposal to reclaim Chicago's lakefront from the highway using immersed tunnels
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
James Chuck
 
Tim McAnallen - Construction Inspector 2104
Tim McAnallen - Construction Inspector 2104Tim McAnallen - Construction Inspector 2104
Tim McAnallen - Construction Inspector 2104Timothy McAnallen
 
Cover Letter & Resume
Cover Letter & ResumeCover Letter & Resume
Cover Letter & ResumeRichard Rask
 
OTEC Presentation: Complete Streets for Akron's East End Development
OTEC Presentation: Complete Streets for Akron's East End DevelopmentOTEC Presentation: Complete Streets for Akron's East End Development
OTEC Presentation: Complete Streets for Akron's East End Development
Francesca Wagner
 
Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010
Daniel X. O'Neil
 
228 congressparkway overview_jan2010
228 congressparkway overview_jan2010228 congressparkway overview_jan2010
228 congressparkway overview_jan2010
Daniel X. O'Neil
 
PaulR.Blaetz021816RR
PaulR.Blaetz021816RRPaulR.Blaetz021816RR
PaulR.Blaetz021816RRPaul Blaetz
 

Similar to Project Complexity (Case study) (20)

BigDig_KeyFacts_Dec2006
BigDig_KeyFacts_Dec2006BigDig_KeyFacts_Dec2006
BigDig_KeyFacts_Dec2006
 
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
 
Resume
ResumeResume
Resume
 
Walton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the YearWalton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the Year
 
Torrey pines road corridor study final
Torrey pines road corridor study finalTorrey pines road corridor study final
Torrey pines road corridor study final
 
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
 
Resume pe civil
Resume pe civilResume pe civil
Resume pe civil
 
2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs
 
megaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdfmegaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdf
 
Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017
 
LEADERSHIP ROLES With a project of this magnitude, it .docx
LEADERSHIP ROLES With a project of this magnitude, it .docxLEADERSHIP ROLES With a project of this magnitude, it .docx
LEADERSHIP ROLES With a project of this magnitude, it .docx
 
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnelsProposal to reclaim Chicago's lakefront from the highway using immersed tunnels
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Tim McAnallen - Construction Inspector 2104
Tim McAnallen - Construction Inspector 2104Tim McAnallen - Construction Inspector 2104
Tim McAnallen - Construction Inspector 2104
 
Cover Letter & Resume
Cover Letter & ResumeCover Letter & Resume
Cover Letter & Resume
 
WALID_TANBEDAWY_2016 R Dom Comp
WALID_TANBEDAWY_2016 R Dom CompWALID_TANBEDAWY_2016 R Dom Comp
WALID_TANBEDAWY_2016 R Dom Comp
 
OTEC Presentation: Complete Streets for Akron's East End Development
OTEC Presentation: Complete Streets for Akron's East End DevelopmentOTEC Presentation: Complete Streets for Akron's East End Development
OTEC Presentation: Complete Streets for Akron's East End Development
 
Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010
 
228 congressparkway overview_jan2010
228 congressparkway overview_jan2010228 congressparkway overview_jan2010
228 congressparkway overview_jan2010
 
PaulR.Blaetz021816RR
PaulR.Blaetz021816RRPaulR.Blaetz021816RR
PaulR.Blaetz021816RR
 

More from Sunny Mahajan

Usage of RAP on gravel roads
Usage of RAP on gravel roadsUsage of RAP on gravel roads
Usage of RAP on gravel roads
Sunny Mahajan
 
Off site fabrication
Off site fabricationOff site fabrication
Off site fabrication
Sunny Mahajan
 
Frugal innovation-sankalp
Frugal innovation-sankalpFrugal innovation-sankalp
Frugal innovation-sankalp
Sunny Mahajan
 
Marketing101-The Geek
Marketing101-The GeekMarketing101-The Geek
Marketing101-The Geek
Sunny Mahajan
 
Optimal RAP content for Minnesota Roads
Optimal RAP content for Minnesota RoadsOptimal RAP content for Minnesota Roads
Optimal RAP content for Minnesota Roads
Sunny Mahajan
 
BIM case study
BIM case studyBIM case study
BIM case study
Sunny Mahajan
 
Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)
Sunny Mahajan
 

More from Sunny Mahajan (7)

Usage of RAP on gravel roads
Usage of RAP on gravel roadsUsage of RAP on gravel roads
Usage of RAP on gravel roads
 
Off site fabrication
Off site fabricationOff site fabrication
Off site fabrication
 
Frugal innovation-sankalp
Frugal innovation-sankalpFrugal innovation-sankalp
Frugal innovation-sankalp
 
Marketing101-The Geek
Marketing101-The GeekMarketing101-The Geek
Marketing101-The Geek
 
Optimal RAP content for Minnesota Roads
Optimal RAP content for Minnesota RoadsOptimal RAP content for Minnesota Roads
Optimal RAP content for Minnesota Roads
 
BIM case study
BIM case studyBIM case study
BIM case study
 
Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)
 

Recently uploaded

在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 

Recently uploaded (20)

在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 

Project Complexity (Case study)

  • 1. “Big Dig” Project THE CENTRAL ARTERY/TUNNEL PROJECT (CA/T) A CASE STUDY ON PROJECT COMPLEXITY.
  • 2. Project Description Located in Boston, MA, on the northeast coast of the United States.  Includes tunnels, highway interchange connections, bridges and pedestrian facilities
  • 4. Project Description Rerouted the Central Artery (Interstate 93), into a 3.5-mile (5.6-km) tunnel.  Construction of the Ted Williams Tunnel.  Construction of the Leonard P. Zakim Bunker Hill Memorial Bridge over the Charles River.  Construction of the Rose Kennedy Greenway in the space vacated by the previous I-93 elevated roadway.
  • 5. Project Description  Planning Phase started in 1982  Construction work – 1991-2006  Estimated Completion - 1998  Actual Completion – Dec 31, 2007 Estimated Cost - $2.8 billion Final Cost - $14.6 billion Cost over run – 190% Official project owner - Massachusetts Turnpike Authority  Joint venture of Bechtel and Parson Brinkerhoff Source: http://www.roadtraffic-technology.com
  • 6. Why Boston Needed the Big Dig? Traffic improvements and substantial reductions in congestion  Improving mobility in downtown Boston  Reconnect neighborhoods severed by the old elevated highway Source: http://www.massdot.state.ma.us
  • 7. Central Artery: Before and After Source:http://www.bigdig.com
  • 8. Problems faced Escalating costs Scheduling overruns Design flaws Charges of poor execution and use of substandard materials Fatal Ceiling Collapse Criminal arrests and one death Source: http://www.roadtraffic-technology.com
  • 9. Complexity Factors - Cost Contingency Usage ◦ Construction Contracts ◦ Management Contingency ◦ Massachusetts Turnpike Authority CEO Contingency Risk Analysis ◦ Location ◦ Utilities Estimate Formation ◦ Ted Williams Tunnel ◦ Zakim Bunker Hill Bridge ◦ Center Artery (I-93)
  • 10. Complexity Factors - Cost Figure. Big Dig Project Cost Growth (National Research Council 2003) 55% 15% 8% 7% 5% 3% 2% 5% Inflation Environmental/Mitigation Scope Growth Accounting Changes Traffic Schedule Maintenance Contingency for Unknowns Other
  • 11. Complexity Factors - Schedule Timeline Requirements ◦ Community Conflicts Milestones Schedule Control ◦ Software Programs
  • 12. Complexity Factors - Technical Scope of Project Owner’s Internal Structure Design Method
  • 13. Complexity Factors - Context Public ◦ Economic Value of Boston Utility Coordination ◦ 29 Miles of Underground Utility Relocation and Updating Land Use Impact ◦ 300 acres of Green Space
  • 14. Complexity Factors - Financing Federal Funding State Funding Borrowing Against Future Funding
  • 15. Project Dimension Complexity Ranking DIMENSION RANK Context 5 Cost 4 Technical 3 Financing 2 Schedule 1
  • 16. Project Dimension Complexity Rating DIMENSIONS SCALE (0 – 100) Cost Dimension Complexity 99 Schedule Dimension Complexity 90 Technical Dimension Complexity 95 Context Dimension Complexity 100 Financing Dimension Complexity 92
  • 17. Complexity Map The Big Dig Project 0 10 20 30 40 50 60 70 80 90 100 Technical Cost FinancingContext Schedule
  • 18. Critical Planning and Analysis Methods Method 1: Define Critical Success Factors ◦ Community Needs ◦ Political Restrictions ◦ Federal and State Funding ◦ Major Project Components ◦ Center Artery (I-93) ◦ Ted Williams Tunnel ◦ Zakim Bunker Hill Bridge
  • 19. Method 2: Assemble Project Team Communication Collaboration ◦ Example ◦ Ted Williams Tunnel Ceiling Panel Collapse
  • 20. Method 3: Project Arrangements Design-Bid-Build Value Engineering Dispute Resolution Dispute Resolution Board
  • 21. Method 4: Early Cost Model and Finance Plan Incorrect Initial Cost Model and Finance Plan The cost model would have included ◦ Inflation ◦ Project Risk- Account for Cost Overruns ◦ More detail over Design Costs
  • 22. Method 5: Develop Project Action Plans Major Obstacles ◦ Restrictive Legislation ◦ Acquisition of ROW ◦ Cooperation of Utilities ◦ Community Support
  • 23. Tools for Managing Complex Projects The following tools were used in the Big Dig Project: •Public involvement plan •Critical permit issues •Offsite fabrication •Co-locate team •Dispute resolution plan
  • 24. Public Involvement Plan ◦ Project planners worked with community groups, government & business leaders to create a consensus of how the project would be built ◦ Mitigation: The process of keeping the city open and making certain all affected groups would be treated fairly ◦ Informed, organized interest groups press for their demands ◦ Public involvement plan produces early project wins of consensus but at the expense of late project soaring project costs
  • 25. Critical Permit Issues ◦ Bechtel/Parsons Brinkerhoff (B/PB): ◦ Engineering authority that approved, permitted, and released designs for construction ◦ Construction managers in charge of contractors & sub-contractors ◦ B/PB operated the project with the philosophy of getting this done, ask questions later ◦ Many plans that were permitted and released for construction were incomplete, contained numerous errors, and lacked proper subsurface exploration ◦ The lax oversight produced an estimated $750 million in construction over-runs
  • 26. Offsite Fabrication ◦ Utilized successfully on the CA/T project ◦ Several examples are: ◦ Immersed steel tubes for the Ted Williams Tunnel ◦ Steel box girder sections for the Bunker Hill Bridge ◦ Utilized successfully on the CA/T project ◦ Offsite fabrication of box girders and steel tubes produced accurate sections per specification that could be test connected at the factory to insure smooth and timely installation ◦ Quicker assembly time at the job site with smaller construction crews as compared to onsite fabrication ◦ Exposure of construction workers to difficult job environments was reduced as compared to onsite fabrication
  • 27. Co-Locate Team ◦ Co-Locate elements of the project team to produce a cohesive team effort to complete a project ◦ Perhaps the most controversial tool ◦ In 1998, State of Massachusetts combined B/PB with state workers into one integrated project organization ◦ Massachusetts Turnpike Authority was at the top of the organization chart ◦ State of Massachusetts designated B/PB as “owner’s representative” in several instances ◦ Who is in charge?
  • 28. Dispute Resolution Plan ◦ Two noteworthy dispute resolution plan techniques were utilized on the CA/T project: ◦ Partnering ◦ Mediation ◦ Partnering was practiced on the CA/T project for construction projects with a duration of least one year and a value of $1 million or more ◦ Mediation was utilized to resolve the dispute of responsibility for leaks at the Fort Point Channel tunnel area
  • 29. References ◦ Bartlett School of Planning (UCL). (2011). “The Central Artery/Third Harbor Tunnel Project (‘The Big Dig’), Omega Centre.” Bloomsbury, London. ◦ Gelinas, N. (2007). “Lessons of Boston’s Big Dig.” City Journal Autumn. New York, New York. ◦ Greirman, V. (2010). “The Big Dig: Learning from a Mega Project.” NASA, <http://appel.nasa.gov/2010/07/15/the-big-dig-learning-from-a-mega-project/> (November 13, 2013). ◦ Hsu, J. Mckay, S., McKnight, M. (2003). “Cost-Benefit Analysis of Boston’s Central Artery/Tunnel Project” Carnegie Mello University. Pittsburgh, PA. ◦ Lewis, R. and Murphy, S. (2003). “Artery Errors Cost More Than $1b.” The Boston Globe, <http://www.boston.com/globe/metro/packages/bechtel/> (November 13, 2013). ◦ Massachusetts Department of Transportation (MassDOT). (2013). “The Central Artery/Tunnel Project-The Big Dig.” MassDOT Highway Division. <http://www.massdot.state.ma.us/highway/TheBigDig.aspx> (October 5, 2013). ◦ National Research Council. “Completing the "Big Dig": Managing the Final Stages of Boston's Central Artery/Tunnel Project. Washington, DC: The National Academies Press, 2003. ◦ Poole, R.W., Samuel, P. (2011). “Transportation Mega-Projects and Risk.” Reason Foundation Policy Brief 97. Los Angeles, CA. ◦ Saltzman, J. (2009). “Big Dig Contractor Modern Continental Pleads Guilty.” Boston Globe. <http://www.boston.com/news/local/breaking_news/2009/05/modern_continen_2.html> (October 5, 2013). ◦ Salvucci, F. P. (2008). “Unearthing the Big Dig.” Massachusetts Institute of Technology. Cambridge, MA. ◦ Wood, D. (2001). “Learning From the Big Dig.” Federal Highway Administration: Public Roads, <http://www.fhwa.dot.gov/publications/publicroads/01julaug/bigdig.cfm> (November 13, 2013).