The document provides updates on construction activities at the Leaside and Laird stations for the Crosstown LRT project. For Leaside Station, support of excavation and piling will continue through late 2018 in stages around the Eglinton and Bayview intersection. Utility works will also continue periodically over the next year. For Laird Station, 24-hour mining work is underway and will continue until late 2019. Ventilation fan works requiring lane reductions on Eglinton Avenue are planned for approximately three weeks to connect fans to the tunnels. Progress photos of both station construction sites were also included.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Many ways to support street children.pptxSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
Understanding the Challenges of Street ChildrenSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
A process server is a authorized person for delivering legal documents, such as summons, complaints, subpoenas, and other court papers, to peoples involved in legal proceedings.
This session provides a comprehensive overview of the latest updates to the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (commonly known as the Uniform Guidance) outlined in the 2 CFR 200.
With a focus on the 2024 revisions issued by the Office of Management and Budget (OMB), participants will gain insight into the key changes affecting federal grant recipients. The session will delve into critical regulatory updates, providing attendees with the knowledge and tools necessary to navigate and comply with the evolving landscape of federal grant management.
Learning Objectives:
- Understand the rationale behind the 2024 updates to the Uniform Guidance outlined in 2 CFR 200, and their implications for federal grant recipients.
- Identify the key changes and revisions introduced by the Office of Management and Budget (OMB) in the 2024 edition of 2 CFR 200.
- Gain proficiency in applying the updated regulations to ensure compliance with federal grant requirements and avoid potential audit findings.
- Develop strategies for effectively implementing the new guidelines within the grant management processes of their respective organizations, fostering efficiency and accountability in federal grant administration.
4. 4
Construction
Activities
Area & Impacts Duration
Tentative
Date
Stage 2 - Piling
& Shallow
excavation
- Road occupancy south side of Eglinton Avenue,
west side of Bayview, and small area east of
secondary entrance
- Main entrance & secondary Entrance
3-4 Months Underway
Wet Utilities
Works
- Work zone west of condo driveway Approx. 2 months Underway
Stage 3 - Piling
& Shallow
excavation
- North side of Eglinton Ave, east & west of
Bayview
- South east corner of Eglinton & Bayview
Approx. 3 months Spring 2018
Wet Utilities
works
- North side of Eglinton Avenue, west of
entrance to Metro
During stage 3 &
4, approx. 6
months
Spring 2018
Stage 4 - Piling
& Shallow
excavation
- North side of Eglinton Ave, east & west of
Bayview
- North west corner of Eglinton & Bayview
Approx. 3 months Summer
2018
Leaside Station: What to Expect January 2018
5. 5
Leaside Station: What to Expect
• Support of Excavation will continue to be underway until late
2018
• Support of Excavation includes:
– Piling
– Shallow Excavation
– Temporary decking installation
• Work is completed in stages around the intersection
• Temporary decking is installed over completed sections
• Once all the stages are complete, deep excavation will
continue beneath the decking.
• Utility works will continue periodically over the next year.
9. 9
Laird Station: What to Expect
24 Hour Mining
• Mining operations are included in the 2010 Toronto Transit Project Noise By-Law
Exemption to allow for tunneling and related work to occur 24 hours a day.
• A robust noise reduction plan based on major international projects such as the Boston
Big Dig, Crossrail in London and the Thames Tideway Tunnel has been developed to
minimize impacts on the local community.
– Implement noise reduction measures at the station construction sites
– Continually monitor noise and vibration throughout construction
– Adjust noise reduction measures at the construction sites as required
– If necessary, consider additional measures for residences in potentially sensitive zone
– Ensure proactive communications with the community before and during construction
Long Term Construction Activity Area Duration
24 hour mining work underway Main & Secondary Entrances Summer 2017 – to late 2019
10. 10
Ventilation Fan Works
• Crews will complete electrical connections for ventilation fans within the
existing tunnels
• An approximate 1' x 1' trench will be excavated in the eastbound curb lane
of Eglinton Avenue from the secondary entrance, east of Laird Drive to the
west side of Brentcliffe Road.
• At the east end of the trench, two boreholes will be drilled on both the
north and south side of Eglinton Avenue to connect to the tunnels.
• Work zones for the boreholes will be completed in a sequence to minimize
disruption.
• Work is expected to take approximately three (3) weeks.
11. 11
Ventilation Fan Works
• Lane reductions will be required to conduct this work safely
• No pedestrian impacts
• TTC Stop will be temporarily moved during the portion of work nearest the stop