SlideShare a Scribd company logo
CASE
STUDY ON
DAM GATES
PRESENTED BY :-
ANIKET SUL (103)
JAMIR SHAIKH(123)
SANKET KALE(132)
AVINASH PALVE (133)
KAMLESH CHAVAN(137)
TYPES OF GATES
A) CLASSIFICATION ON THE BASIS OF SHAPE OF THE GATES :
• 1) RADIAL GATES
• 2) CYLINDRICAL GATES.
• 3) PLANE RECTANGULAR GATES
• 4) SECTOR OR DRUM GATES.
B) CLASSIFICATION ON THE BASIS MODE OF MOVEMENT OF THE GATES.
• 1) VERTICAL LIFT TYPE: WIRE ROPE LIFTING (SCREW STEM TYPE LIFTING)
• 2 )GATES ROTATING ABOUT A FIXED TRUNNION POINT E.G. RADIAL GATES, ETC.
• 3) AUTOMATIC FUNCTIONING GATE.
HOISTING ARRANGEMENT
• A HOIST IS AN EQUIPMENT WITH WHICH THE GATE CAN BE LOWERED OR LIFTED AT THE
REQUIRED SPEED OF TRAVEL.
• HOISTS ARE INSTALLED ON A HOIST BRIDGE SUPPORTED BY THE PIERS.
• THE HOIST MAY BE SUPPORTED ON THE UNDER DECK BELOW THE ROAD WAY. IN SUCH A WAY
THAT THE HOISTING ANGLE DOES NOT CHANGE CONSIDERABLE DURING THE HOISTING
OPERATION.
• SUCH A HOIST IS AVAILABLE AT A LOCATION ON THE DOWNSTREAM SIDE OF THE CREST OF
THE DAM. THIS HOWEVER INVOLVES LARGER PIER SIZES. AN ALTERNATIVE OF THE
ARRANGEMENT COULD BE UPSTREAM HOIST LOCATION INVOLVING LARGER HOISTING
CAPACITIES.
• IF THE RESERVOIR WATER IS OF CORROSIVE NATURE, THE HOISTING CABLE IS TIED TO STREAM
SIDE OF THE LEAF SO THAT IT REMAINS PROTECTED AGAINST CORROSION.
REQUIREMENTS
• THE ESSENTIAL REQUIREMENTS OF THE HOIST ARE :
1. RELIABLE IN OPERATION.
2. SMOOTH WORKING (AVOID ANY JERKS WHILE OPERATING).
3. ABILITY TO SUSTAIN THE VIBRATIONS OF THE GATE, HELD AT PARTIAL OPENINGS.
4. SELF LOCKING ARRANGEMENTS.
• MAIN COMPONENTS OF HOISTS MECHANISM:
1)HOIST FRAME
2)DRIVE UNIT
3)GEAR TRAINS WITH WIRE ROPE DRUM.
4)WIRE ROPES, EQUALIZER PLATES, LIME SHAFTS AND COUPLING ETC.
COMPONENETS OF HOISTING ARRANGEMENT.
PROBLEM DEFINITION
• THE DAM IDENTIFIED FOR CASE STUDY IS ARUNAWATI DAM IN YAVATMAL
DISTRICT NEAR ABOUT 120 KM FROM NAGPUR IN MAHARASHTRA STATE.
• THE SIZE OF GATES ARE 12*5M, 12*6.5M, 12*8M
• THE TYPE OF HOIST MECHANISM USED TO LIFT THE GATE IS WIRE ROPE DRUM.
SO TO GET THE RELEVANT DATA REGARDING FAILURE LOAD AS WELL AS THE
LOAD AT WHICH HOIST CAN WORK EFFICIENTLY
• WE HAVE TO DESIGN AND ANALYZE THE GEAR WITH WOUND ROPE WHICH IS A
KEY PART OF HOIST AT DIFFERENT LOADS.
OBJECTIVE
• 1) TO FIND THE OPTIMUM DESIGN OF LIFTING MECHANISM ,WELL EQUIPPED AND
EFFICIENT CONTROL MECHANISM TO LIFT THE GATE.
• 2) TO DESIGN AND ANALYZE THE LOAD AT WHICH THE HOIST CAN WORK & THE
LOAD AT WHICH IT WORK
• 3) WHEN THERE IS ELECTRICITY FAILURE DUE TO STORMS OR ANY OTHER
NATURAL CRISIS THEN IT IS NECESSARY THAT THERE MUST BE PROVISION FOR
OPENING THE DAM GATE MANUALLY.
DESIGN ASPECT- HOIST CAPACITY:
Type of Gate Minimum Seating Load
Load head fixed wheel gates or radial for
spillway crest gate
205 kN/m length of gate
Medium Head gates 5.0 kN/m length of gate
High head sluice gate 10.0 kN/m length of gate
High head radial gate 10.0 kN/m length of gate
DESIGN OF MECHANICAL PARTS:
• GENERAL REQUIREMENTS:
• I) WIRE ROPES: THE WIRE ROPE SHALL BE MADE FROM IMPROVED PLOUGH STEEL,
GALVANIZED(IF REQUIRED) LANG’S LAY AND FIBER CORE OR NORMALLY OF 6/36 OR
6/37 CONSTRUCTION AND SHALL BE CONFORM TO IS 2266:1977.
• II) BREAKING STRENGTH: THE BREAKING STRENGTH OF WIRE ROPE, IF NOT GIVEN BY
THE MANUFACTURER OF ROPE, SHALL BE CALCULATED ON THE BASIS OF IS
2266:1977.
• THE MINIMUM FACTOR OF SAFETY BASED ON MINIMUM BREAKING STRENGTH AND
SAFE WORKING LOAD OF THE WIRE ROPE SHALL BE AS GIVEN IN TABLE:
Operation Condition Minimum factor of Safety
Normal Operation condition 6
Break down torque condition 3
For Counter Weight Suspension 5
• III) FIXING OF ROPE: THE ENDS OF THE ROPE SHALL BE FIXED AT THE MINIMUM TWO
POINTS ON THE DRUM IN SUCH A WAY THAT THE FIXING DEVICE IS EASILY
ACCESSIBLE AND THE ROPE IS NOT SUBJECTED TO UNDUE TWISTS AND TURNS. EACH
ROPE SHALL HAVE NOT LESS THAN TWO FULL TURNS ON THE DRUM BEFORE IT IS
FIXED.
• IV) GEARING MATERIAL: ALL SPUR GEAR SHALL BE OF CAST STEEL, FORGED STEEL,
CARBON STEEL SURFACE HARDEN STEEL OR FABRICATED MILD STEEL. THE GEAR AND
PINION SHALL BE MADE FROM TWO DIFFERENT GRADES OF MATERIALS; HIGHER
STRENGTH GRADE SHALL BE USED FOR PINION AND LOWER STRENGTH GRADE FOR
SPUR GEAR.KEYS IN GEAR TRAINS SHALL BE SO FITTED AND SECURED THAT THEY
SHOULD NOT BECOME LOOSE WHEN IN SERVICE.
• V) SHAFT: THE SHAFT SHALL BE DESIGNED FOR APPROPRIATE LOAD/TORQUE THAT
IS BEING TRANSMITTED. SHAFTS SHALL HAVE AMPLE STRENGTH 7 RIGIDITY AND
ADEQUATE BEARING SURFACES. THEY SHALL BE FINISHED SMOOTHLY & IF
SHOULDERED SHALL BE PROVIDED WITH FILLETS OF LARGE RADIUS.
• DIMENSIONING OF SHAFT: IN DIMENSIONING THE WITH RATIO(L/D)=50, THE ANGLE
OF TWIST AND THE REVOLUTIONS PER MINUTE SHALL BE TAKEN INTO ACCOUNT, IN
ADDITION TO SIMPLE BENDING, PURE TORSION, OR THE COMBINED EFFECT OF
BENDING AND TORSION. THAT SHALL BE PERMITTED IS 1/40 TO 1/30 PER M. LINEAR
DEFLECTION IN THE SHAFT SHALL NOT EXCEED ONE MM PER M OF LENGTH.
• VI) ALLOWABLE STRESSES: THE ALLOWABLE STRESS FOR SOLID SHAFT SHALL BE AS
FOLLOWS3.
A) MAXIMUM ALLOWABLE BENDING STRESS EITHER IN TENSION OR COMPRESSION
ONLY = 0.5 YIELD POINT OR 20 PERCENT OF ULTIMATE STRENGTH WHICHEVER IS LESS.
B) MAXIMUM ALLOWABLE TORSIONAL SHEAR STRESS = 30 PERCENT OF THE YIELD
POINT STRESS
• 1) TWISTING SQRT(T2+M2)
WHERE TE=EQUIVALENT TWISTING MOMENT IN NM
T= TWISTING MOMENT IN NM
M= BENDING MOMENT IN NM.
• 2) BENDING:
WHERE, ME=EQUIVALENT BENDING MOMENT IN NM.
M =BENDING MOMENT IN NM.
T =TWISTING MOMENT IN NM.
• VII) TYPES OF BEARINGS:
ALL THE RUNNING SHAFTS SHALL BE PROVIDED WITH BALL, ROLLER OR BUSH
BEARINGS. SELECTION OF BEARING SHALL BE DONE ON CONSIDERATION OF DUTY,
LOAD AND SPEED OF THE SHAFT .BEARING SHALL BE EASILY ACCESSIBLE FOR
LUBRICATION AND /OR REPLACEMENT. IF THERE IS MORE THAN ONE BEARING ON
SHAFT, EVERY BEARING SHALL BE PROVIDED WITH INDIVIDUAL LUBRICATION
ARRANGEMENT.
• EFFICIENCY OF SYSTEM
• THE OVERALL EFFICIENCY OF THE SYSTEM WHICH IS THE PRODUCT OF INDIVIDUAL
EFFICIENCY OF ELEMENTS SHALL THEN BE WORKED OUT. THIS OVERALL EFFICIENCY
OF THE SYSTEM SHALL BE USED IN CALCULATING THE CAPACITY OF THE ELECTRIC
MOTOR.
• MOTORS
• THE MOTOR SHALL BE TOTALLY ENCLOSED FAN COOLED ,HIGH STARTING TORQUE,
SQUIRREL CAGE, THREE PHASE INDUCTION MOTOR OF RATED CAPACITY
CONFORMING TO IS 325:1978. MOTORS CHOSEN SHALL HAVE RATED SPEED NOT
MORE THAN 1000 REV/MIN.
CONCLUSION:
• VARIOUS COMPONENT OF HOIST MECHANISM HAVE BEEN MADE SO
PROPORTIONAL AS TO TAKE THE WORST LOAD COMING ON INDIVIDUAL
COMPONENT. THE VARIOUS STRESSES INDUCED ALONG WITH MANUAL
CALCULATION CHECK DURING DESIGN PROCEDURE FOR SAFE VALUE.
REFERENCES:
• [1] C.K.SEHGAL AND F.C.ALA, “OPERATIONS AND MAINTAINENECE OF HOIST
EQUIPMENT FOR FLOOD GATES FOR LOCKS AND DAMS.”ASME 2ND BIENNIAL
,MOVABLE BRIDGE SYMPOSIUM,NOV-10-12 1987.
• [2] M.BARKER,B.VIVIAN, “SPILLWAY GATE RELIABILITY & HANDLING OF RISK FOR
RADIAL AND DRUM GATES.”J.MATHEWS AND P-OLIVER.
• [3] REDDY J.N ,FINITE ELEMENT METHODS. TATA MCGRAW HILLS EDITION.1977
• [4] R.S.KHURMI AND J.K.GUPTA , “TEXTBOOK OF MACHINE DESIGN “S.CHAND
PUBLICATION, FIRST EDITION.
• [5] ROBERT.D.COOK ,CONCEPTS AND APPLICATION OF FINITE ELEMENTS METHOD
,3RD EDITION, JOHN WILEY AND SONS.
• [6] MECHANICAL CHARTS-GREY IRON CASTINGS (IS:210- 1970).
• [7]STANDARD SPECIFICATION FOR SELECTION OF MOTORS. (IS 325:1978)
FOLSOM DAM (CALIFORNIA),1995)
• LOCATED APPROXIMATELY 20 MILES NORTHEAST OF CALIFORNIA, FOLSOM DAM
WAS DESIGNED AND CONSTRUCTED BY THE U.S. ARMY CORPS OF ENGINEERS TO
GENERATE HYDROPOWER ALONG THE AMERICAN RIVER.
• THE 340-FOOT HIGH CONCRETE GRAVITY FOLSOM DAM ALONG WITH TWO
EARTHEN WING DIKES ON EACH OF ITS SIDES CREATE FOLSOM LAKE.
• CAPICITY(977,000 acre-ft)
• THE SPILLWAY CONSISTS OF EIGHT 42-FOOT-WIDE BAYS EQUIPPED WITH FIVE 50-
FOOT-HIGH RADIAL SERVICE GATES AS WELL AS THREE 53-FOOT-HIGH RADIAL
EMERGENCY GATES THAT RELEASE WATER FROM THE RESERVOIR.

More Related Content

What's hot

Motion stability and control in marine surface vessels
Motion stability and control in marine surface vesselsMotion stability and control in marine surface vessels
Motion stability and control in marine surface vessels
Parijat Sinha
 

What's hot (20)

Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
 
ground tackle (anchoring and mooring)
ground tackle (anchoring and mooring)ground tackle (anchoring and mooring)
ground tackle (anchoring and mooring)
 
Marine operations
Marine operationsMarine operations
Marine operations
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.
 
Comparison between skip winding and high angle conveyor for vertical transport
Comparison between skip winding and high angle conveyor for vertical transportComparison between skip winding and high angle conveyor for vertical transport
Comparison between skip winding and high angle conveyor for vertical transport
 
Ship Construction (Structure Part)
Ship Construction (Structure Part)Ship Construction (Structure Part)
Ship Construction (Structure Part)
 
2.2 rig components
2.2 rig components2.2 rig components
2.2 rig components
 
Various types of gates, their important components
Various types of gates, their important componentsVarious types of gates, their important components
Various types of gates, their important components
 
An Overview of Design, Analysis, Construction and Installation of Offshore Pe...
An Overview of Design, Analysis, Construction and Installation of Offshore Pe...An Overview of Design, Analysis, Construction and Installation of Offshore Pe...
An Overview of Design, Analysis, Construction and Installation of Offshore Pe...
 
Stern Tube and Shafting Arrangements
Stern Tube and Shafting ArrangementsStern Tube and Shafting Arrangements
Stern Tube and Shafting Arrangements
 
Introduction to offshore structure
Introduction to offshore structure Introduction to offshore structure
Introduction to offshore structure
 
RAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERINGRAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERING
 
Shaft sinking 1
Shaft sinking 1Shaft sinking 1
Shaft sinking 1
 
Longwall machinery
Longwall  machineryLongwall  machinery
Longwall machinery
 
Download here
Download hereDownload here
Download here
 
Ship terms
Ship termsShip terms
Ship terms
 
Ship Structural Components
Ship Structural ComponentsShip Structural Components
Ship Structural Components
 
Rig types and components
Rig types and componentsRig types and components
Rig types and components
 
Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge Training
 
Motion stability and control in marine surface vessels
Motion stability and control in marine surface vesselsMotion stability and control in marine surface vessels
Motion stability and control in marine surface vessels
 

Similar to Case study metalic gates of dams

BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
Utsav Tripathy
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCH
Apoorv Dhawan
 
Tolomatic mxe electric_actuators_catalog
Tolomatic mxe electric_actuators_catalogTolomatic mxe electric_actuators_catalog
Tolomatic mxe electric_actuators_catalog
Electromate
 
3. construction equipment subsystems
3. construction equipment subsystems3. construction equipment subsystems
3. construction equipment subsystems
Jeet Pawar
 

Similar to Case study metalic gates of dams (20)

Tower crane safety
Tower crane safetyTower crane safety
Tower crane safety
 
Track
TrackTrack
Track
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridge
 
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
 
Industrial visit(ved kumar -1216540115)
Industrial visit(ved kumar -1216540115)Industrial visit(ved kumar -1216540115)
Industrial visit(ved kumar -1216540115)
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
Innovative Technology for Steel Melt Shop
Innovative Technology for Steel Melt ShopInnovative Technology for Steel Melt Shop
Innovative Technology for Steel Melt Shop
 
Seismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresSeismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear Structures
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCH
 
Transocean offshore operation 2
Transocean   offshore operation 2Transocean   offshore operation 2
Transocean offshore operation 2
 
Presentation on Highwall Mining
Presentation on Highwall MiningPresentation on Highwall Mining
Presentation on Highwall Mining
 
Metso mineral india ltd.
Metso mineral india ltd.Metso mineral india ltd.
Metso mineral india ltd.
 
Flash butt welding
Flash butt weldingFlash butt welding
Flash butt welding
 
Grua titan de 26 ton international sterling 900 a
Grua titan de 26 ton international sterling 900 aGrua titan de 26 ton international sterling 900 a
Grua titan de 26 ton international sterling 900 a
 
Tolomatic mxe electric_actuators_catalog
Tolomatic mxe electric_actuators_catalogTolomatic mxe electric_actuators_catalog
Tolomatic mxe electric_actuators_catalog
 
Rocker bogie mechanism
Rocker bogie mechanismRocker bogie mechanism
Rocker bogie mechanism
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx
 
3. construction equipment subsystems
3. construction equipment subsystems3. construction equipment subsystems
3. construction equipment subsystems
 
Design of stator & rotor for Wound Induction Motor
Design of stator & rotor for Wound Induction MotorDesign of stator & rotor for Wound Induction Motor
Design of stator & rotor for Wound Induction Motor
 

More from mechmitaoe (8)

Case study- rolling barrier system
Case study- rolling barrier systemCase study- rolling barrier system
Case study- rolling barrier system
 
Case study KUKA 6 dof robotic arm
Case study   KUKA 6 dof robotic armCase study   KUKA 6 dof robotic arm
Case study KUKA 6 dof robotic arm
 
Stress analysis in chair- Case study
Stress analysis in chair- Case studyStress analysis in chair- Case study
Stress analysis in chair- Case study
 
Study of jaw crusher
Study of jaw crusherStudy of jaw crusher
Study of jaw crusher
 
Gun mechanism study
Gun mechanism studyGun mechanism study
Gun mechanism study
 
Disc brake rotor analysis case study
Disc brake rotor analysis case studyDisc brake rotor analysis case study
Disc brake rotor analysis case study
 
CVT- case study of all terrain vehicle
CVT- case study of all terrain vehicleCVT- case study of all terrain vehicle
CVT- case study of all terrain vehicle
 
Design of bailong elevator case study
Design of bailong elevator   case studyDesign of bailong elevator   case study
Design of bailong elevator case study
 

Recently uploaded

Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
Kamal Acharya
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdf
Kamal Acharya
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
Kamal Acharya
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
Kamal Acharya
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
Atif Razi
 

Recently uploaded (20)

Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdf
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 

Case study metalic gates of dams

  • 1. CASE STUDY ON DAM GATES PRESENTED BY :- ANIKET SUL (103) JAMIR SHAIKH(123) SANKET KALE(132) AVINASH PALVE (133) KAMLESH CHAVAN(137)
  • 2. TYPES OF GATES A) CLASSIFICATION ON THE BASIS OF SHAPE OF THE GATES : • 1) RADIAL GATES • 2) CYLINDRICAL GATES. • 3) PLANE RECTANGULAR GATES • 4) SECTOR OR DRUM GATES.
  • 3. B) CLASSIFICATION ON THE BASIS MODE OF MOVEMENT OF THE GATES. • 1) VERTICAL LIFT TYPE: WIRE ROPE LIFTING (SCREW STEM TYPE LIFTING) • 2 )GATES ROTATING ABOUT A FIXED TRUNNION POINT E.G. RADIAL GATES, ETC. • 3) AUTOMATIC FUNCTIONING GATE.
  • 4. HOISTING ARRANGEMENT • A HOIST IS AN EQUIPMENT WITH WHICH THE GATE CAN BE LOWERED OR LIFTED AT THE REQUIRED SPEED OF TRAVEL. • HOISTS ARE INSTALLED ON A HOIST BRIDGE SUPPORTED BY THE PIERS. • THE HOIST MAY BE SUPPORTED ON THE UNDER DECK BELOW THE ROAD WAY. IN SUCH A WAY THAT THE HOISTING ANGLE DOES NOT CHANGE CONSIDERABLE DURING THE HOISTING OPERATION. • SUCH A HOIST IS AVAILABLE AT A LOCATION ON THE DOWNSTREAM SIDE OF THE CREST OF THE DAM. THIS HOWEVER INVOLVES LARGER PIER SIZES. AN ALTERNATIVE OF THE ARRANGEMENT COULD BE UPSTREAM HOIST LOCATION INVOLVING LARGER HOISTING CAPACITIES. • IF THE RESERVOIR WATER IS OF CORROSIVE NATURE, THE HOISTING CABLE IS TIED TO STREAM SIDE OF THE LEAF SO THAT IT REMAINS PROTECTED AGAINST CORROSION.
  • 5. REQUIREMENTS • THE ESSENTIAL REQUIREMENTS OF THE HOIST ARE : 1. RELIABLE IN OPERATION. 2. SMOOTH WORKING (AVOID ANY JERKS WHILE OPERATING). 3. ABILITY TO SUSTAIN THE VIBRATIONS OF THE GATE, HELD AT PARTIAL OPENINGS. 4. SELF LOCKING ARRANGEMENTS. • MAIN COMPONENTS OF HOISTS MECHANISM: 1)HOIST FRAME 2)DRIVE UNIT 3)GEAR TRAINS WITH WIRE ROPE DRUM. 4)WIRE ROPES, EQUALIZER PLATES, LIME SHAFTS AND COUPLING ETC.
  • 6. COMPONENETS OF HOISTING ARRANGEMENT.
  • 7. PROBLEM DEFINITION • THE DAM IDENTIFIED FOR CASE STUDY IS ARUNAWATI DAM IN YAVATMAL DISTRICT NEAR ABOUT 120 KM FROM NAGPUR IN MAHARASHTRA STATE. • THE SIZE OF GATES ARE 12*5M, 12*6.5M, 12*8M • THE TYPE OF HOIST MECHANISM USED TO LIFT THE GATE IS WIRE ROPE DRUM. SO TO GET THE RELEVANT DATA REGARDING FAILURE LOAD AS WELL AS THE LOAD AT WHICH HOIST CAN WORK EFFICIENTLY • WE HAVE TO DESIGN AND ANALYZE THE GEAR WITH WOUND ROPE WHICH IS A KEY PART OF HOIST AT DIFFERENT LOADS.
  • 8. OBJECTIVE • 1) TO FIND THE OPTIMUM DESIGN OF LIFTING MECHANISM ,WELL EQUIPPED AND EFFICIENT CONTROL MECHANISM TO LIFT THE GATE. • 2) TO DESIGN AND ANALYZE THE LOAD AT WHICH THE HOIST CAN WORK & THE LOAD AT WHICH IT WORK • 3) WHEN THERE IS ELECTRICITY FAILURE DUE TO STORMS OR ANY OTHER NATURAL CRISIS THEN IT IS NECESSARY THAT THERE MUST BE PROVISION FOR OPENING THE DAM GATE MANUALLY.
  • 9. DESIGN ASPECT- HOIST CAPACITY: Type of Gate Minimum Seating Load Load head fixed wheel gates or radial for spillway crest gate 205 kN/m length of gate Medium Head gates 5.0 kN/m length of gate High head sluice gate 10.0 kN/m length of gate High head radial gate 10.0 kN/m length of gate
  • 10. DESIGN OF MECHANICAL PARTS: • GENERAL REQUIREMENTS: • I) WIRE ROPES: THE WIRE ROPE SHALL BE MADE FROM IMPROVED PLOUGH STEEL, GALVANIZED(IF REQUIRED) LANG’S LAY AND FIBER CORE OR NORMALLY OF 6/36 OR 6/37 CONSTRUCTION AND SHALL BE CONFORM TO IS 2266:1977. • II) BREAKING STRENGTH: THE BREAKING STRENGTH OF WIRE ROPE, IF NOT GIVEN BY THE MANUFACTURER OF ROPE, SHALL BE CALCULATED ON THE BASIS OF IS 2266:1977. • THE MINIMUM FACTOR OF SAFETY BASED ON MINIMUM BREAKING STRENGTH AND SAFE WORKING LOAD OF THE WIRE ROPE SHALL BE AS GIVEN IN TABLE:
  • 11. Operation Condition Minimum factor of Safety Normal Operation condition 6 Break down torque condition 3 For Counter Weight Suspension 5
  • 12. • III) FIXING OF ROPE: THE ENDS OF THE ROPE SHALL BE FIXED AT THE MINIMUM TWO POINTS ON THE DRUM IN SUCH A WAY THAT THE FIXING DEVICE IS EASILY ACCESSIBLE AND THE ROPE IS NOT SUBJECTED TO UNDUE TWISTS AND TURNS. EACH ROPE SHALL HAVE NOT LESS THAN TWO FULL TURNS ON THE DRUM BEFORE IT IS FIXED. • IV) GEARING MATERIAL: ALL SPUR GEAR SHALL BE OF CAST STEEL, FORGED STEEL, CARBON STEEL SURFACE HARDEN STEEL OR FABRICATED MILD STEEL. THE GEAR AND PINION SHALL BE MADE FROM TWO DIFFERENT GRADES OF MATERIALS; HIGHER STRENGTH GRADE SHALL BE USED FOR PINION AND LOWER STRENGTH GRADE FOR SPUR GEAR.KEYS IN GEAR TRAINS SHALL BE SO FITTED AND SECURED THAT THEY SHOULD NOT BECOME LOOSE WHEN IN SERVICE.
  • 13. • V) SHAFT: THE SHAFT SHALL BE DESIGNED FOR APPROPRIATE LOAD/TORQUE THAT IS BEING TRANSMITTED. SHAFTS SHALL HAVE AMPLE STRENGTH 7 RIGIDITY AND ADEQUATE BEARING SURFACES. THEY SHALL BE FINISHED SMOOTHLY & IF SHOULDERED SHALL BE PROVIDED WITH FILLETS OF LARGE RADIUS. • DIMENSIONING OF SHAFT: IN DIMENSIONING THE WITH RATIO(L/D)=50, THE ANGLE OF TWIST AND THE REVOLUTIONS PER MINUTE SHALL BE TAKEN INTO ACCOUNT, IN ADDITION TO SIMPLE BENDING, PURE TORSION, OR THE COMBINED EFFECT OF BENDING AND TORSION. THAT SHALL BE PERMITTED IS 1/40 TO 1/30 PER M. LINEAR DEFLECTION IN THE SHAFT SHALL NOT EXCEED ONE MM PER M OF LENGTH.
  • 14. • VI) ALLOWABLE STRESSES: THE ALLOWABLE STRESS FOR SOLID SHAFT SHALL BE AS FOLLOWS3. A) MAXIMUM ALLOWABLE BENDING STRESS EITHER IN TENSION OR COMPRESSION ONLY = 0.5 YIELD POINT OR 20 PERCENT OF ULTIMATE STRENGTH WHICHEVER IS LESS. B) MAXIMUM ALLOWABLE TORSIONAL SHEAR STRESS = 30 PERCENT OF THE YIELD POINT STRESS • 1) TWISTING SQRT(T2+M2) WHERE TE=EQUIVALENT TWISTING MOMENT IN NM T= TWISTING MOMENT IN NM M= BENDING MOMENT IN NM. • 2) BENDING: WHERE, ME=EQUIVALENT BENDING MOMENT IN NM. M =BENDING MOMENT IN NM. T =TWISTING MOMENT IN NM.
  • 15. • VII) TYPES OF BEARINGS: ALL THE RUNNING SHAFTS SHALL BE PROVIDED WITH BALL, ROLLER OR BUSH BEARINGS. SELECTION OF BEARING SHALL BE DONE ON CONSIDERATION OF DUTY, LOAD AND SPEED OF THE SHAFT .BEARING SHALL BE EASILY ACCESSIBLE FOR LUBRICATION AND /OR REPLACEMENT. IF THERE IS MORE THAN ONE BEARING ON SHAFT, EVERY BEARING SHALL BE PROVIDED WITH INDIVIDUAL LUBRICATION ARRANGEMENT.
  • 16. • EFFICIENCY OF SYSTEM • THE OVERALL EFFICIENCY OF THE SYSTEM WHICH IS THE PRODUCT OF INDIVIDUAL EFFICIENCY OF ELEMENTS SHALL THEN BE WORKED OUT. THIS OVERALL EFFICIENCY OF THE SYSTEM SHALL BE USED IN CALCULATING THE CAPACITY OF THE ELECTRIC MOTOR. • MOTORS • THE MOTOR SHALL BE TOTALLY ENCLOSED FAN COOLED ,HIGH STARTING TORQUE, SQUIRREL CAGE, THREE PHASE INDUCTION MOTOR OF RATED CAPACITY CONFORMING TO IS 325:1978. MOTORS CHOSEN SHALL HAVE RATED SPEED NOT MORE THAN 1000 REV/MIN.
  • 17.
  • 18.
  • 19. CONCLUSION: • VARIOUS COMPONENT OF HOIST MECHANISM HAVE BEEN MADE SO PROPORTIONAL AS TO TAKE THE WORST LOAD COMING ON INDIVIDUAL COMPONENT. THE VARIOUS STRESSES INDUCED ALONG WITH MANUAL CALCULATION CHECK DURING DESIGN PROCEDURE FOR SAFE VALUE.
  • 20. REFERENCES: • [1] C.K.SEHGAL AND F.C.ALA, “OPERATIONS AND MAINTAINENECE OF HOIST EQUIPMENT FOR FLOOD GATES FOR LOCKS AND DAMS.”ASME 2ND BIENNIAL ,MOVABLE BRIDGE SYMPOSIUM,NOV-10-12 1987. • [2] M.BARKER,B.VIVIAN, “SPILLWAY GATE RELIABILITY & HANDLING OF RISK FOR RADIAL AND DRUM GATES.”J.MATHEWS AND P-OLIVER. • [3] REDDY J.N ,FINITE ELEMENT METHODS. TATA MCGRAW HILLS EDITION.1977 • [4] R.S.KHURMI AND J.K.GUPTA , “TEXTBOOK OF MACHINE DESIGN “S.CHAND PUBLICATION, FIRST EDITION. • [5] ROBERT.D.COOK ,CONCEPTS AND APPLICATION OF FINITE ELEMENTS METHOD ,3RD EDITION, JOHN WILEY AND SONS. • [6] MECHANICAL CHARTS-GREY IRON CASTINGS (IS:210- 1970). • [7]STANDARD SPECIFICATION FOR SELECTION OF MOTORS. (IS 325:1978)
  • 21. FOLSOM DAM (CALIFORNIA),1995) • LOCATED APPROXIMATELY 20 MILES NORTHEAST OF CALIFORNIA, FOLSOM DAM WAS DESIGNED AND CONSTRUCTED BY THE U.S. ARMY CORPS OF ENGINEERS TO GENERATE HYDROPOWER ALONG THE AMERICAN RIVER. • THE 340-FOOT HIGH CONCRETE GRAVITY FOLSOM DAM ALONG WITH TWO EARTHEN WING DIKES ON EACH OF ITS SIDES CREATE FOLSOM LAKE. • CAPICITY(977,000 acre-ft) • THE SPILLWAY CONSISTS OF EIGHT 42-FOOT-WIDE BAYS EQUIPPED WITH FIVE 50- FOOT-HIGH RADIAL SERVICE GATES AS WELL AS THREE 53-FOOT-HIGH RADIAL EMERGENCY GATES THAT RELEASE WATER FROM THE RESERVOIR.