Project Schedule
Management
PMP Workgroup
Outline
● Project Schedule Knowledge Area
● ...
● Sequence Activities
● ...
Project Schedule Management Processes Project Schedule Management
includes the processes required to manage the timely completion of the project.
Project scheduling provides a detailed plan that represents how and when the
project will deliver the products, services, and results defined in the project
scope and serves as a tool for communication, managing stakeholders’
expectations, and as a basis for performance reporting.
The team selects a scheduling method (e.g., critical path/agile approach) to enter
the project-specific data (e.g., activities, planned dates, durations, resources,
dependencies & constraints) into the scheduling tool to create a schedule model
for the project.
When possible, the detailed project schedule should remain flexible throughout
the project to adjust for knowledge gained, increased understanding of the risk,
and value-added activities.
Key Concepts
Schedule Model
Trends & Emerging Practices
Adaptive planning defines a plan but acknowledges that once work starts, the
priorities may change and the plan needs to reflect this new knowledge.
● Iterative scheduling (with a backlog): a form of rolling wave planning based
on adaptive life cycles.The requirements are documented in user stories that
are then prioritized and refined just prior to construction, and the product
features are developed using time-boxed periods of work.
○ This approach is often used to deliver incremental value to the customer or when
multiple teams can concurrently develop a large number of features that have few
interconnected dependencies.
○ The benefit of this approach is that it welcomes changes throughout the development life
cycle.
Trends & Emerging Practices (cont.)
● On-demand scheduling: pulls work from a backlog or intermediate queue of
work to be done immediately as resources become available.
○ This approach, typically used in a Kanban system, is based on the theory-of-constraints
and pull-based scheduling concepts from lean manufacturing to limit a team’s work in
progress in order to balance demand against the team’s delivery throughput.
○ On-demand scheduling is often used for projects that evolve the product incrementally
in operational or sustainment environments, and where tasks may be made relatively
similar in size and scope or can be bundled by size and scope.
Tailoring Considerations
● Life cycle approach. What is the most appropriate life cycle approach that
allows for a more detailed schedule?
● Resource availability. What are the factors influencing durations (such as the
correlation between available resources and their productivity)?
● Project dimensions. How will the presence of project complexity,
technological uncertainty, product novelty, pace, or progress tracking (such
as earned value, percentage complete, red-yellow-green (stop light)
indicators) impact the desired level of control?
● Technology support. Is technology used to develop, record, transmit, receive,
and store project schedule model information and is it readily accessible?
Considerations for Agile/Adaptive Environments
Adaptive approaches use short cycles to undertake work, review the results, and
adapt as necessary. These cycles generally manifest as iterative scheduling and
on-demand, pull-based scheduling.
In large organizations, it may require long-term roadmaps to manage the
development of various programs using scaling factors (e.g., team size,
geographical distribution, regulatory compliance, organizational complexity, and
technical complexity).
● A range of techniques utilizing a predictive approach, adaptive approach, or a hybrid of both,
may need to be adopted.
● The organization may need to combine practices from several core methods, or adopt a
method that has already done so, and adopt a few principles and practices of more
traditional techniques.
6.3 Sequence Activities
Sequence Activities - IT&TO
The process of identifying and documenting relationships among the project
activities.
● Key Benefits: it defines the logical sequence of work to obtain the greatest
efficiency given all project constraints.
This process is performed throughout the project.
6.3 > Data Flow Diagram
6.3 > Outputs
6.3 > Outputs: Project Schedule Network Diagrams
A graphical representation of the logical relationships, also referred to as
dependencies, among the project schedule activities.
A summary narrative can accompany the diagram and describe the basic
approach used to sequence the activities.
Activities that have multiple predecessor activities indicate a path convergence.
Activities that have multiple successor activities indicate a path divergence.
Activities with divergence and convergence are at greater risk as they are
affected by multiple activities or can affect multiple activities.
6.3 > Outputs: Project Schedule Network Diagrams (2)
A path convergence - has more
than one predecessor.
A path divergence - has more
than one successor.
Multiple relationships between the
same activities are not recommended
(so selecting the relationship with the
highest impact).
Closed loops are also not
recommended in logical relationships.
6.3 > Outputs: Project Schedule Network Diagrams (3)
6.3 > Outputs: Project Documents Updates
● Activity attributes. Activity attributes may describe a necessary sequence of
events or defined predecessor or successor relationships, as well as defined
lead and lag and logical relationships between the activities.
● Activity list. The activity list may be impacted by the change in relationships
among the project activities during the sequencing activities.
● Assumption log. Assumptions and constraints recorded in the assumption
log may need to be updated based on the sequencing, relationship
determination, and leads and lags, and may give rise to individual project
risks that may impact the project schedule.
● Milestone list. The scheduled dates for specific milestones may be impacted
by changes in relationships among the project activities during the
sequencing activities.
6.3 > Inputs
6.3 > Tools & Techniques
6.3 > T&T: Precedence Diagramming Method (PDM)
A technique used for constructing a schedule model in which activities are
represented by nodes and are graphically linked by one or more logical
relationships to show the sequence in which the activities are to be performed.
PDM includes four types of dependencies or logical relationships: Finish-to-start
(FS), Finish-to-finish (FF), Start-to-start (SS) and Start-to-finish (SF).
● FS is the most commonly used type of precedence relationship while the SF
relationship is very rarely used,
● Multiple relationships between the same activities are not recommended, so
a decision has to be made to select the relationship with the highest impact.
● Closed loops are also not recommended in logical relationships.
6.3 > T&T: Dependency Determination and Integration
Dependencies may be characterized by the following attributes: mandatory or
discretionary, internal or external.
Dependency has four attributes, but two can be applicable at the same time in
the following ways: mandatory external dependencies, mandatory internal
dependencies, discretionary external dependencies, or discretionary internal
dependencies.
6.3 > T&T: Mandatory vs. Discretionary dependencies
Mandatory dependencies Discretionary dependencies
Mandatory dependencies are those that are legally
or contractually required or inherent in the nature
of the work.
Discretionary dependencies are established based on
knowledge of best practices within a particular
application area or some unusual aspect of the
project where a specific sequence is desired, even
though there may be other acceptable sequences.
Mandatory dependencies are sometimes referred to
as hard logic or hard dependencies.
Discretionary dependencies are sometimes referred
to as preferred logic,
preferential logic, or soft logic.
The project team determines which dependencies
are mandatory during the process of sequencing the
activities.
The project team determines which dependencies
are discretionary during the process of sequencing
the activities.
Mandatory dependencies should not be confused
with assigning schedule constraints in the
scheduling tool.
Discretionary dependencies should be fully
documented since they can create arbitrary total
float values and can limit later scheduling options.
When fast tracking techniques are employed, these
discretionary dependencies should be reviewed and
considered for modification or removal.
6.3 > T&T: Internal vs External dependencies
External dependencies Internal dependencies
External dependencies involve a relationship
between project activities and non-project
activities.
Internal dependencies involve a precedence
relationship between project activities.
These dependencies are usually outside of
the project team’s control.
These dependencies are generally inside the
project team’s control.
The project management team determines
which dependencies are external during the
process of sequencing the activities.
The project management team determines
which dependencies are internal during the
process of sequencing the activities.
6.3 > T&T: Leads & Lags
A lead is the amount of time a
successor activity can be advanced with
respect to a predecessor activity.
Photoshoot
(Est.: 4 days)
Photo Editing
(Est.: 6 days)
FS (3 days lead)
A lag is the amount of time a successor
activity is required to be delayed with
respect to a predecessor activity.
10 days
7 days
Blaster Paint of Wall
FS+1d
Send the photos
Photo Printing
+ Billing
SS+14d
Discretionary internal dependency
Mandatory external dependency
Mandatory internal dependency
6.3 > T&T: Lead vs. Lag
Writing Document
Reviewing
Document
FS-5d
Writing Document
Reviewing
Document
SS+5dvs.
Lead Lag
Discretionary dependency Mandatory dependency
Lead is only found activities
with FS relationships.
Lag may be found in activities with all
relationship types: FS, SS, FF, and SF.
Lead time can also be used in
conjunction with schedule
compression techniques such
as fast tracking.
Notes
● The use of leads and lags should not replace schedule logic.
● Duration estimates do not include any leads or lags.
● Activities and their related assumptions should be documented.
6.3 > T&T: PMIS
Project management information systems (PMIS) includes scheduling software
that has the capability to help plan, organize, and adjust the sequence of the
activities; insert the logical relationships, lead and lag values; and differentiate
the different types of dependencies.
6.3 > Example
Sequence the following activities (with dependencies) of developing the
requirement below
● Requirement: Develop a login page from scratch*.
● Activities (not in the correct order)
○ Review (and merge) code (who: Technical Lead)
○ Develop the login API (Backend developer)
○ Write the UI automation test (QC engineer)**
○ Develop the login page (Frontend developer)
○ Write the test cases (QC engineer)
○ Test (manually) the login page (QC engineer)
○ Write API unit test (Backend developer)
○ Deploy the ticket to staging env. (Technical Lead)
○ Deploy the ticket to integration env. (Technical Lead)
○ Deploy the ticket to production env. (Technical Lead)***
*** Contractually, the client has 5 days
to verify a ticket before it is delivered
to the production environment.
* Assumed that the design, the
functional and technical specification
are approved.
** Assumed that the UI Automation
Test is developed in a separate
codebase and is mandatory to have
before the production delivery.

More Related Content

What's hot

Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project Management 101 Primer
Project Management 101   PrimerProject Management 101   Primer
Project Management 101 PrimerGary Drumm
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Agus Suhanto
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder EngagementDavidMcLachlan1
 
Project management
Project managementProject management
Project managementNihal Ranjan
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
Project communications management
Project communications managementProject communications management
Project communications managementSanket Gandhi
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process GroupsBhuWan Khadka
 
2.project lifecycle
2.project lifecycle2.project lifecycle
2.project lifecyclerlabsza
 
Project time management
Project time managementProject time management
Project time managementImran Jamil
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project ManagementKevin Thomas
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-scheduleRaaz Karkee
 

What's hot (20)

Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project Management 101 Primer
Project Management 101   PrimerProject Management 101   Primer
Project Management 101 Primer
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement
 
Project management
Project managementProject management
Project management
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project communications management
Project communications managementProject communications management
Project communications management
 
6.3 Sequence Activities
6.3 Sequence Activities6.3 Sequence Activities
6.3 Sequence Activities
 
06 project time management
06  project time management06  project time management
06 project time management
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
2.project lifecycle
2.project lifecycle2.project lifecycle
2.project lifecycle
 
Project Management Methodologies
Project Management MethodologiesProject Management Methodologies
Project Management Methodologies
 
Project time management
Project time managementProject time management
Project time management
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project Management
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 

Similar to Project Schedule Management - Sequence Activities - PMP Workgroup

Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTSAJJAD KHUDHUR ABBAS
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615EqraBaig
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesSHAZEBALIKHAN1
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project ManagementMostafa Ewees
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptxWajihAnsari7
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4POOJA UDAYAN
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxMohanadRabea1
 

Similar to Project Schedule Management - Sequence Activities - PMP Workgroup (20)

Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 

More from Tùng Trần Thanh

Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTùng Trần Thanh
 
First time being a Team Leader or Technical Leader
First time being a Team Leader or Technical LeaderFirst time being a Team Leader or Technical Leader
First time being a Team Leader or Technical LeaderTùng Trần Thanh
 
Introduction to Project Management - PMP Workgroup
Introduction to Project Management - PMP WorkgroupIntroduction to Project Management - PMP Workgroup
Introduction to Project Management - PMP WorkgroupTùng Trần Thanh
 
Trobz - Odoo Demo - Sales Pricing Policy - Supply Chain - Multi-companies
Trobz - Odoo Demo - Sales Pricing Policy - Supply Chain - Multi-companiesTrobz - Odoo Demo - Sales Pricing Policy - Supply Chain - Multi-companies
Trobz - Odoo Demo - Sales Pricing Policy - Supply Chain - Multi-companiesTùng Trần Thanh
 
[OCV] OCA Introduction - 20170311
[OCV] OCA Introduction - 20170311[OCV] OCA Introduction - 20170311
[OCV] OCA Introduction - 20170311Tùng Trần Thanh
 
Trobz You? - Trobz Profile [dedicated for manufacturing projects]
Trobz   You?  - Trobz Profile [dedicated for manufacturing projects]Trobz   You?  - Trobz Profile [dedicated for manufacturing projects]
Trobz You? - Trobz Profile [dedicated for manufacturing projects]Tùng Trần Thanh
 
Trobz - UIT - System Analysis Process [Knowledge Sharing] - 2018-05-11
Trobz - UIT - System Analysis Process [Knowledge Sharing] - 2018-05-11Trobz - UIT - System Analysis Process [Knowledge Sharing] - 2018-05-11
Trobz - UIT - System Analysis Process [Knowledge Sharing] - 2018-05-11Tùng Trần Thanh
 
UIT - Trobz - Odoo Programming Overview
UIT - Trobz - Odoo Programming OverviewUIT - Trobz - Odoo Programming Overview
UIT - Trobz - Odoo Programming OverviewTùng Trần Thanh
 

More from Tùng Trần Thanh (8)

Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
First time being a Team Leader or Technical Leader
First time being a Team Leader or Technical LeaderFirst time being a Team Leader or Technical Leader
First time being a Team Leader or Technical Leader
 
Introduction to Project Management - PMP Workgroup
Introduction to Project Management - PMP WorkgroupIntroduction to Project Management - PMP Workgroup
Introduction to Project Management - PMP Workgroup
 
Trobz - Odoo Demo - Sales Pricing Policy - Supply Chain - Multi-companies
Trobz - Odoo Demo - Sales Pricing Policy - Supply Chain - Multi-companiesTrobz - Odoo Demo - Sales Pricing Policy - Supply Chain - Multi-companies
Trobz - Odoo Demo - Sales Pricing Policy - Supply Chain - Multi-companies
 
[OCV] OCA Introduction - 20170311
[OCV] OCA Introduction - 20170311[OCV] OCA Introduction - 20170311
[OCV] OCA Introduction - 20170311
 
Trobz You? - Trobz Profile [dedicated for manufacturing projects]
Trobz   You?  - Trobz Profile [dedicated for manufacturing projects]Trobz   You?  - Trobz Profile [dedicated for manufacturing projects]
Trobz You? - Trobz Profile [dedicated for manufacturing projects]
 
Trobz - UIT - System Analysis Process [Knowledge Sharing] - 2018-05-11
Trobz - UIT - System Analysis Process [Knowledge Sharing] - 2018-05-11Trobz - UIT - System Analysis Process [Knowledge Sharing] - 2018-05-11
Trobz - UIT - System Analysis Process [Knowledge Sharing] - 2018-05-11
 
UIT - Trobz - Odoo Programming Overview
UIT - Trobz - Odoo Programming OverviewUIT - Trobz - Odoo Programming Overview
UIT - Trobz - Odoo Programming Overview
 

Recently uploaded

What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxLigayaBacuel1
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 

Recently uploaded (20)

What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 

Project Schedule Management - Sequence Activities - PMP Workgroup

  • 2. Outline ● Project Schedule Knowledge Area ● ... ● Sequence Activities ● ...
  • 3. Project Schedule Management Processes Project Schedule Management includes the processes required to manage the timely completion of the project.
  • 4. Project scheduling provides a detailed plan that represents how and when the project will deliver the products, services, and results defined in the project scope and serves as a tool for communication, managing stakeholders’ expectations, and as a basis for performance reporting. The team selects a scheduling method (e.g., critical path/agile approach) to enter the project-specific data (e.g., activities, planned dates, durations, resources, dependencies & constraints) into the scheduling tool to create a schedule model for the project. When possible, the detailed project schedule should remain flexible throughout the project to adjust for knowledge gained, increased understanding of the risk, and value-added activities. Key Concepts
  • 6. Trends & Emerging Practices Adaptive planning defines a plan but acknowledges that once work starts, the priorities may change and the plan needs to reflect this new knowledge. ● Iterative scheduling (with a backlog): a form of rolling wave planning based on adaptive life cycles.The requirements are documented in user stories that are then prioritized and refined just prior to construction, and the product features are developed using time-boxed periods of work. ○ This approach is often used to deliver incremental value to the customer or when multiple teams can concurrently develop a large number of features that have few interconnected dependencies. ○ The benefit of this approach is that it welcomes changes throughout the development life cycle.
  • 7. Trends & Emerging Practices (cont.) ● On-demand scheduling: pulls work from a backlog or intermediate queue of work to be done immediately as resources become available. ○ This approach, typically used in a Kanban system, is based on the theory-of-constraints and pull-based scheduling concepts from lean manufacturing to limit a team’s work in progress in order to balance demand against the team’s delivery throughput. ○ On-demand scheduling is often used for projects that evolve the product incrementally in operational or sustainment environments, and where tasks may be made relatively similar in size and scope or can be bundled by size and scope.
  • 8. Tailoring Considerations ● Life cycle approach. What is the most appropriate life cycle approach that allows for a more detailed schedule? ● Resource availability. What are the factors influencing durations (such as the correlation between available resources and their productivity)? ● Project dimensions. How will the presence of project complexity, technological uncertainty, product novelty, pace, or progress tracking (such as earned value, percentage complete, red-yellow-green (stop light) indicators) impact the desired level of control? ● Technology support. Is technology used to develop, record, transmit, receive, and store project schedule model information and is it readily accessible?
  • 9. Considerations for Agile/Adaptive Environments Adaptive approaches use short cycles to undertake work, review the results, and adapt as necessary. These cycles generally manifest as iterative scheduling and on-demand, pull-based scheduling. In large organizations, it may require long-term roadmaps to manage the development of various programs using scaling factors (e.g., team size, geographical distribution, regulatory compliance, organizational complexity, and technical complexity). ● A range of techniques utilizing a predictive approach, adaptive approach, or a hybrid of both, may need to be adopted. ● The organization may need to combine practices from several core methods, or adopt a method that has already done so, and adopt a few principles and practices of more traditional techniques.
  • 11. Sequence Activities - IT&TO The process of identifying and documenting relationships among the project activities. ● Key Benefits: it defines the logical sequence of work to obtain the greatest efficiency given all project constraints. This process is performed throughout the project.
  • 12. 6.3 > Data Flow Diagram
  • 14. 6.3 > Outputs: Project Schedule Network Diagrams A graphical representation of the logical relationships, also referred to as dependencies, among the project schedule activities. A summary narrative can accompany the diagram and describe the basic approach used to sequence the activities. Activities that have multiple predecessor activities indicate a path convergence. Activities that have multiple successor activities indicate a path divergence. Activities with divergence and convergence are at greater risk as they are affected by multiple activities or can affect multiple activities.
  • 15. 6.3 > Outputs: Project Schedule Network Diagrams (2) A path convergence - has more than one predecessor. A path divergence - has more than one successor. Multiple relationships between the same activities are not recommended (so selecting the relationship with the highest impact). Closed loops are also not recommended in logical relationships.
  • 16. 6.3 > Outputs: Project Schedule Network Diagrams (3)
  • 17. 6.3 > Outputs: Project Documents Updates ● Activity attributes. Activity attributes may describe a necessary sequence of events or defined predecessor or successor relationships, as well as defined lead and lag and logical relationships between the activities. ● Activity list. The activity list may be impacted by the change in relationships among the project activities during the sequencing activities. ● Assumption log. Assumptions and constraints recorded in the assumption log may need to be updated based on the sequencing, relationship determination, and leads and lags, and may give rise to individual project risks that may impact the project schedule. ● Milestone list. The scheduled dates for specific milestones may be impacted by changes in relationships among the project activities during the sequencing activities.
  • 19. 6.3 > Tools & Techniques
  • 20. 6.3 > T&T: Precedence Diagramming Method (PDM) A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed. PDM includes four types of dependencies or logical relationships: Finish-to-start (FS), Finish-to-finish (FF), Start-to-start (SS) and Start-to-finish (SF). ● FS is the most commonly used type of precedence relationship while the SF relationship is very rarely used, ● Multiple relationships between the same activities are not recommended, so a decision has to be made to select the relationship with the highest impact. ● Closed loops are also not recommended in logical relationships.
  • 21. 6.3 > T&T: Dependency Determination and Integration Dependencies may be characterized by the following attributes: mandatory or discretionary, internal or external. Dependency has four attributes, but two can be applicable at the same time in the following ways: mandatory external dependencies, mandatory internal dependencies, discretionary external dependencies, or discretionary internal dependencies.
  • 22. 6.3 > T&T: Mandatory vs. Discretionary dependencies Mandatory dependencies Discretionary dependencies Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work. Discretionary dependencies are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. Mandatory dependencies are sometimes referred to as hard logic or hard dependencies. Discretionary dependencies are sometimes referred to as preferred logic, preferential logic, or soft logic. The project team determines which dependencies are mandatory during the process of sequencing the activities. The project team determines which dependencies are discretionary during the process of sequencing the activities. Mandatory dependencies should not be confused with assigning schedule constraints in the scheduling tool. Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. When fast tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal.
  • 23. 6.3 > T&T: Internal vs External dependencies External dependencies Internal dependencies External dependencies involve a relationship between project activities and non-project activities. Internal dependencies involve a precedence relationship between project activities. These dependencies are usually outside of the project team’s control. These dependencies are generally inside the project team’s control. The project management team determines which dependencies are external during the process of sequencing the activities. The project management team determines which dependencies are internal during the process of sequencing the activities.
  • 24. 6.3 > T&T: Leads & Lags A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity. Photoshoot (Est.: 4 days) Photo Editing (Est.: 6 days) FS (3 days lead) A lag is the amount of time a successor activity is required to be delayed with respect to a predecessor activity. 10 days 7 days Blaster Paint of Wall FS+1d Send the photos Photo Printing + Billing SS+14d Discretionary internal dependency Mandatory external dependency Mandatory internal dependency
  • 25. 6.3 > T&T: Lead vs. Lag Writing Document Reviewing Document FS-5d Writing Document Reviewing Document SS+5dvs. Lead Lag Discretionary dependency Mandatory dependency Lead is only found activities with FS relationships. Lag may be found in activities with all relationship types: FS, SS, FF, and SF. Lead time can also be used in conjunction with schedule compression techniques such as fast tracking. Notes ● The use of leads and lags should not replace schedule logic. ● Duration estimates do not include any leads or lags. ● Activities and their related assumptions should be documented.
  • 26. 6.3 > T&T: PMIS Project management information systems (PMIS) includes scheduling software that has the capability to help plan, organize, and adjust the sequence of the activities; insert the logical relationships, lead and lag values; and differentiate the different types of dependencies.
  • 27. 6.3 > Example Sequence the following activities (with dependencies) of developing the requirement below ● Requirement: Develop a login page from scratch*. ● Activities (not in the correct order) ○ Review (and merge) code (who: Technical Lead) ○ Develop the login API (Backend developer) ○ Write the UI automation test (QC engineer)** ○ Develop the login page (Frontend developer) ○ Write the test cases (QC engineer) ○ Test (manually) the login page (QC engineer) ○ Write API unit test (Backend developer) ○ Deploy the ticket to staging env. (Technical Lead) ○ Deploy the ticket to integration env. (Technical Lead) ○ Deploy the ticket to production env. (Technical Lead)*** *** Contractually, the client has 5 days to verify a ticket before it is delivered to the production environment. * Assumed that the design, the functional and technical specification are approved. ** Assumed that the UI Automation Test is developed in a separate codebase and is mandatory to have before the production delivery.

Editor's Notes

  1. The definitions are quoted from PMBOKⓇ Guide. P129 (165)
  2. P173 (209) 6.1 Plan Schedule Management—The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. 6.2 Define Activities—The process of identifying and documenting the specific actions to be performed to produce the project deliverables. 6.3 Sequence Activities—The process of identifying and documenting relationships among the project activities. 6.4 Estimate Activity Durations—The process of estimating the number of work periods needed to complete individual activities with the estimated resources. 6.5 Develop Schedule—The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling. 6.6 Control Schedule—The process of monitoring the status of the project to update the project schedule and manage changes to the schedule baseline.
  3. P175 (211) Some of the processes are presented more fully in the Practice Standard for Scheduling.
  4. P177 (213)
  5. P177 (213)
  6. P178 (214)
  7. P178 (214) The role of the project manager does not change based on managing projects using a predictive development life cycle or managing projects in adaptive environments. However, to be successful in using adaptive approaches, the project manager will need to be familiar with the tools and techniques to understand how to apply them effectively.
  8. The definitions are quoted from PMBOKⓇ Guide.
  9. P187 (223)
  10. P187 (223) Every activity except the first and last should be connected to at least one predecessor and at least one successor activity with an appropriate logical relationship. Logical relationships should be designed to create a realistic project schedule. It may be necessary to use lead or lag time between activities to support a realistic and achievable project schedule. Sequencing can be performed by using project management software or by using manual or automated techniques. The Sequence Activities process concentrates on converting the project activities from a list to a diagram to act as a first step to publish the schedule baseline.
  11. P185 (221)
  12. P194 (230)
  13. P193 (229)
  14. Each activity & milestone except the first & last should be connected to at least one predecessor with a finish-to-start or start-to-start logical relationship & at least one successor with a finish-to-start or finish-to-finish logical relationship.
  15. P194 (230)
  16. P185 (221)
  17. P185 (221)
  18. P189, 190 (225, 226)
  19. P191 (227)
  20. P191 (227) An example of discretionary dependency, generally accepted best practices recommend that during construction, the electrical work should start after finishing the plumbing work. This order is not mandatory and both activities may occur at the same time (in parallel), but performing the activities in sequential order reduces the overall project risk.
  21. P192 (228)
  22. P192 (228) Blaster: bôi bột matit (a substance made of lime, water and sand, that is put on walls and ceilings to give them a smooth hard surface)
  23. P192 (228)
  24. P193 (229) The PMIS provides access to information technology (IT) software tools, such as scheduling software tools, work authorization systems, configuration management systems, information collection and distribution systems, as well as interfaces to other online automated systems such as corporate knowledge base repositories. Automated gathering and reporting on key performance indicators (KPI) can be part of this system.