SlideShare a Scribd company logo
1 of 2
Project Schedule Management (A high-level
snapshot)
Every resource on the project needs to know what to do and when. Without an agreed and realistic
schedule, time may be wasted. The Project Schedule Management knowledge Area deals with the
Activities, their durations and eventually the Schedule.
Project Schedule Management Processes
Plan Schedule Management (Planning)
 Guidance and direction on how the project schedule will be managed throughout the project
 The process of establishing the policies, procedures, and documentation for planning, developing,
managing, executing, and controlling the project schedule.
 Performed once or at predefined points in the project
Define Activities (Planning)
 Decomposed Schedule Activities provide a basis for estimating, scheduling, executing, monitoring,
and controlling the project work
 The process of identifying and documenting the specific actions to be performed to produce the
project deliverables.
 Performed throughout the project.
Sequence Activities (Planning)
 Defines the logical sequence of work to obtain the greatest efficiency given all project constraints
 The process of identifying and documenting relationships among the project activities
 Performed throughout the project
Estimate Activity Duration (Planning)
 It provides the amount of time each activity will take to complete
 The process of estimating the number of work periods needed to complete individual activities with
estimated resources
 Performed throughout the project
Develop Schedule (Planning)
 It generates a schedule model with planned dates for completing project activities
 The process of analyzing activity sequences, durations, resource requirements, and schedule
constraints to create a schedule model for project execution and monitoring and controlling
 Performed throughout the project
Control Schedule (Monitoring and Controlling)
 The schedule baseline is maintained throughout the project
 The process of monitoring the status of the project to update the project schedule and managing
changes to the schedule baseline
 It is performed throughout the project
Further Information on Project Schedule Management

More Related Content

What's hot

Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
project time management
 project time management project time management
project time managementHira Atiq
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Project scheduling
Project schedulingProject scheduling
Project schedulingJaafer Saeed
 
L05 time management
L05 time managementL05 time management
L05 time managementAsa Chan
 
Project time management
Project time managementProject time management
Project time managementJivan Nepali
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheederKarin Rheeder
 
Project control wps office
Project control wps officeProject control wps office
Project control wps officekaransingh1064
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
Project Time Management
Project Time Management Project Time Management
Project Time Management Waqar Ali
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling Reema
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management UploadBhuWan Khadka
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTùng Trần Thanh
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a projectSailish Cephas
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and trackingComputer_ at_home
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Managementgrmkslideshare
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planningJeanette C. Patindol
 

What's hot (19)

Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
project time management
 project time management project time management
project time management
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
L05 time management
L05 time managementL05 time management
L05 time management
 
Project time management
Project time managementProject time management
Project time management
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
Project control wps office
Project control wps officeProject control wps office
Project control wps office
 
06 project time management
06  project time management06  project time management
06 project time management
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a project
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and tracking
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Management
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
 

Similar to Project schedule Management - PMP/CAPM

Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
1.1b Construction (Project) Planning.ppt
1.1b Construction (Project) Planning.ppt1.1b Construction (Project) Planning.ppt
1.1b Construction (Project) Planning.pptravi590686
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
Project time management
Project time managementProject time management
Project time managementImran Jamil
 
Summary of key project manager actions & results
Summary of key project manager actions & resultsSummary of key project manager actions & results
Summary of key project manager actions & resultsTut Andrei-Eugen
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptxWajihAnsari7
 
Projectplanningandprojectworkplan Amit Payal
Projectplanningandprojectworkplan Amit PayalProjectplanningandprojectworkplan Amit Payal
Projectplanningandprojectworkplan Amit PayalAMIT PAYAL
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4Qussay Karam
 
Advanced program management resource, content and knowledge management
Advanced program management   resource, content and knowledge managementAdvanced program management   resource, content and knowledge management
Advanced program management resource, content and knowledge managementMarcus Vannini
 
5 phases of project management service in Virginia
5 phases of project management service in Virginia5 phases of project management service in Virginia
5 phases of project management service in VirginiaSingTone Technologies
 
1.1c Construction Planning.ppt
1.1c Construction Planning.ppt1.1c Construction Planning.ppt
1.1c Construction Planning.pptravi590686
 
integration management
 integration management integration management
integration managementsaiftahlawi1
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
Definition presentation
Definition presentationDefinition presentation
Definition presentationPrem Kumar
 

Similar to Project schedule Management - PMP/CAPM (20)

Project management
Project managementProject management
Project management
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
1.1b Construction (Project) Planning.ppt
1.1b Construction (Project) Planning.ppt1.1b Construction (Project) Planning.ppt
1.1b Construction (Project) Planning.ppt
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Project time management
Project time managementProject time management
Project time management
 
Summary of key project manager actions & results
Summary of key project manager actions & resultsSummary of key project manager actions & results
Summary of key project manager actions & results
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
 
Projectplanningandprojectworkplan Amit Payal
Projectplanningandprojectworkplan Amit PayalProjectplanningandprojectworkplan Amit Payal
Projectplanningandprojectworkplan Amit Payal
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4
 
Advanced program management resource, content and knowledge management
Advanced program management   resource, content and knowledge managementAdvanced program management   resource, content and knowledge management
Advanced program management resource, content and knowledge management
 
5 phases of project management service in Virginia
5 phases of project management service in Virginia5 phases of project management service in Virginia
5 phases of project management service in Virginia
 
Project Management
Project ManagementProject Management
Project Management
 
1.1c Construction Planning.ppt
1.1c Construction Planning.ppt1.1c Construction Planning.ppt
1.1c Construction Planning.ppt
 
integration management
 integration management integration management
integration management
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
Definition presentation
Definition presentationDefinition presentation
Definition presentation
 

More from Mudassir Iqbal

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIMudassir Iqbal
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIMudassir Iqbal
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIMudassir Iqbal
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMIMudassir Iqbal
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIMudassir Iqbal
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIMudassir Iqbal
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIMudassir Iqbal
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPMMudassir Iqbal
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMMudassir Iqbal
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPMMudassir Iqbal
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
Executing process group
Executing process groupExecuting process group
Executing process groupMudassir Iqbal
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone scheduleMudassir Iqbal
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budgetMudassir Iqbal
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko Mudassir Iqbal
 

More from Mudassir Iqbal (17)

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMI
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMI
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMI
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMI
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMI
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMI
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPM
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPM
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPM
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
Executing process group
Executing process groupExecuting process group
Executing process group
 
Closing process group
Closing process groupClosing process group
Closing process group
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone schedule
 
Quality and Grade
Quality and GradeQuality and Grade
Quality and Grade
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budget
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko
 

Recently uploaded

(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 

Recently uploaded (20)

(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 

Project schedule Management - PMP/CAPM

  • 1. Project Schedule Management (A high-level snapshot) Every resource on the project needs to know what to do and when. Without an agreed and realistic schedule, time may be wasted. The Project Schedule Management knowledge Area deals with the Activities, their durations and eventually the Schedule. Project Schedule Management Processes Plan Schedule Management (Planning)  Guidance and direction on how the project schedule will be managed throughout the project  The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.  Performed once or at predefined points in the project Define Activities (Planning)  Decomposed Schedule Activities provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work  The process of identifying and documenting the specific actions to be performed to produce the project deliverables.  Performed throughout the project. Sequence Activities (Planning)  Defines the logical sequence of work to obtain the greatest efficiency given all project constraints  The process of identifying and documenting relationships among the project activities  Performed throughout the project Estimate Activity Duration (Planning)  It provides the amount of time each activity will take to complete
  • 2.  The process of estimating the number of work periods needed to complete individual activities with estimated resources  Performed throughout the project Develop Schedule (Planning)  It generates a schedule model with planned dates for completing project activities  The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule model for project execution and monitoring and controlling  Performed throughout the project Control Schedule (Monitoring and Controlling)  The schedule baseline is maintained throughout the project  The process of monitoring the status of the project to update the project schedule and managing changes to the schedule baseline  It is performed throughout the project Further Information on Project Schedule Management