SlideShare a Scribd company logo
1 of 9
Topic 9:
Project Scheduling
Topic 9 : Project Scheduling
 Project scheduling is a mechanism to communicate what tasks need to get done
and which organizational resources will be allocated to complete those tasks in
what timeframe.
 The following are the steps needed to schedule a project:
o Define Activities : Create Work Breakdown Structure (WBS) and a
deliverables diagram and organize them by mapping out the tasks .
o Do Estimates : Determine the time and effort it will take to complete them.
o Determine Dependencies : Place a bit of slack in your schedule to
accommodate these related tasks.
o Assign Resources : Finalize the planned schedule by deciding what
resources you are going to need to get those tasks done on time.
 Estimate Activity Duration Inputs
o This process has several tools and techniques ;-
-Expert Judgement, -Analogous Estimating, -Parametric Estimating
-Three-Point Estimating, -Group decision-making techniques, -Reserve Analysis
 3 Point Estimating
o Three-point estimating uses three estimates that when averaged come up with
final estimate.
• Most likely estimate – assumes there are no disaster and activity can be
completed as planned
• Optimistic estimate – fastest time frame in which your resource can
complete the activity
• Pessimistic – Assumes the worst happens and it takes much longer than
planned to get the activity completed
o Formula to calculate the expected duration : E = (O + P + M) / 3
o E=Expected, O = Optimistic, M = Most Likely
o The formula for standard deviation which helps to determine the confidence level
as below : E : (Pessimistic – Optimistic) / 6
 Expert Judgement - The staff members who will perform activities will most
accurately estimate them
 Analogous Estimating ( also called as top-down estimating, an expert
judgement) - Actual duration of a similar activity completed on previous project
will be used to determine the duration of current activity.
 Bottom Up Estimating – Is the most accurate approach to estimate cost and
duration. Setting the estimates of the amount of work, duration and cost at the
task level lets you combine them into estimates of higher-level deliverables and
the project as a whole
 Parametric Estimating - Quantitatively based estimating method that multiplies
the quantity of work by the rate or uses an algorithm in conjunction with historical
data to determine the cost, budget or duration estimates.
 Group decision-making techniques (brainstorming and the Delphi or nominal
group techniques)
o Brainstorming is an old-age technique where all participants have an
opportunity to speak up.
o Delphi technique is similar to brainstorming in that you involve subject matter
experts in determining estimates.
 Reserve Analysis
o Contingency reserve - a portion of time added to the schedule to account
for risk
o Management reserve - used for unknown events that have not been
previously identified
Resource Optimization Techniques
 Resource Leveling - also called as resource-based method is used when the
resources are overallocated and only available at certain times or when they are
assigned to more than one activity at a time. The purpose to use this technique is
to balance out the resource assignments to get tasks completed without
overloading the individual.
 Resource Smoothing - Resource smoothing accommodates resource availability
by modifying activities within their float times without changing the critical path or
project end date. More tasks are given to team members who are under allocated
.
 Reverse Resource - This technique requires the resources to be scheduled in
reverse order in order to assign this key resource at the correct time.
Modeling techniques
 Include the use of what-if scenario analysis and simulation
o What-If scenario : uses different sets of activity assumptions to produce
multiple project durations
o Simulation use a range of probable activity durations for each activity, and
those ranges are then used to calculate a range of probable duration results
for the project itself.
o Monte Carlo is a simulation technique that runs the possible activity durations
and schedule projections many many times to come up with the schedule
projections and their probability, critical path duration estimates and float
time.
Schedule Compression
 Mathematical analysis that’s used to shorten the project schedule duration without
changing the project scope in order to accomplish all activities sooner than
estimated.
o Crashing – accomplished by adding resources to the critical path.Crashing
the schedule can lead to increased risk and increased cost.
o Fast tracking – Performing 2 tasks or project phase in parallel that were
previously scheduled to start sequentially. It increases the project risk and
might cause the project team to re-work the tasks.
Project schedule can be presented in many forms ;
 Project schedule network diagram
 Gantt chart
 Milestone
Start
Activity
1
Activity
2
Activity
3 Activity
5
Activity
4 Activity
6
Task Name Jan Feb Mar Apr May
Planning
Design
Implementation
Milestone Scheduled date Actual Date Responsible
Testing completed 04/12/19 - Rachel
Acceptance and Signoff 07/12/19 15/12/19 Cindy
Project Closure 15/12/19 31/12/19 Carmen

More Related Content

What's hot

Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010B Sai Prasad
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSHafiz JUNAID
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1Ahmad Basim Hamza
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniquesNazish khalid
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yıldız
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Planproject management
 
Project scheduling
Project schedulingProject scheduling
Project schedulingJaafer Saeed
 
4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1pmb25
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTùng Trần Thanh
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Managementgrmkslideshare
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-scheduleRaaz Karkee
 
Project management technique PERT & CPM
Project management technique PERT & CPMProject management technique PERT & CPM
Project management technique PERT & CPMSyed Academic
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a projectSailish Cephas
 

What's hot (20)

Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniques
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Management
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
Project management technique PERT & CPM
Project management technique PERT & CPMProject management technique PERT & CPM
Project management technique PERT & CPM
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a project
 
Project time management
Project time managementProject time management
Project time management
 

Similar to Project Scheduling Techniques and Tools

Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)danieljohn810
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resouresMayank Kothawade
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimatingharwoodr
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Software Test Estimation
Software Test EstimationSoftware Test Estimation
Software Test EstimationJatin Kochhar
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 

Similar to Project Scheduling Techniques and Tools (20)

Agile planning
Agile planningAgile planning
Agile planning
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resoures
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Project planning
Project planningProject planning
Project planning
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Software Test Estimation
Software Test EstimationSoftware Test Estimation
Software Test Estimation
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 

More from Reema

CSS Basic Introduction
CSS Basic IntroductionCSS Basic Introduction
CSS Basic IntroductionReema
 
Google Analytics Course For Beginners
Google Analytics Course For BeginnersGoogle Analytics Course For Beginners
Google Analytics Course For BeginnersReema
 
Conclusion Of The Course
Conclusion Of The CourseConclusion Of The Course
Conclusion Of The CourseReema
 
Introduction
IntroductionIntroduction
IntroductionReema
 
Create A Texture Pattern:
Create A Texture Pattern:Create A Texture Pattern:
Create A Texture Pattern:Reema
 
Creating The Footer:
Creating The Footer:Creating The Footer:
Creating The Footer:Reema
 
Creating The Main Content Area
Creating The Main Content AreaCreating The Main Content Area
Creating The Main Content AreaReema
 
Create The Quick Quote Section:
Create The Quick Quote Section:Create The Quick Quote Section:
Create The Quick Quote Section:Reema
 
Create The Featured Project Section:
Create The Featured Project Section:Create The Featured Project Section:
Create The Featured Project Section:Reema
 
Creating The Navigation Bar:
Creating The Navigation Bar:Creating The Navigation Bar:
Creating The Navigation Bar:Reema
 
Creating The Logo:
Creating The Logo:Creating The Logo:
Creating The Logo:Reema
 
Prepare Your Photoshop Document:
Prepare Your Photoshop Document:Prepare Your Photoshop Document:
Prepare Your Photoshop Document:Reema
 
Conclusion Of The Course
Conclusion Of The CourseConclusion Of The Course
Conclusion Of The CourseReema
 
Adding A Dash In jQuery:
Adding A Dash In jQuery:Adding A Dash In jQuery:
Adding A Dash In jQuery:Reema
 
Introduction To jQuery:
Introduction To jQuery:Introduction To jQuery:
Introduction To jQuery:Reema
 
Introduction To JavaScript Ajax
Introduction To JavaScript AjaxIntroduction To JavaScript Ajax
Introduction To JavaScript AjaxReema
 
Introduction To JavaScript
Introduction To JavaScriptIntroduction To JavaScript
Introduction To JavaScriptReema
 
Responsive Web Development
Responsive Web DevelopmentResponsive Web Development
Responsive Web DevelopmentReema
 
How To Add CSS The Correct Way.
How To Add CSS The Correct Way.How To Add CSS The Correct Way.
How To Add CSS The Correct Way.Reema
 
CSS Basic Introduction, Rules, And Tips
CSS Basic Introduction, Rules, And TipsCSS Basic Introduction, Rules, And Tips
CSS Basic Introduction, Rules, And TipsReema
 

More from Reema (20)

CSS Basic Introduction
CSS Basic IntroductionCSS Basic Introduction
CSS Basic Introduction
 
Google Analytics Course For Beginners
Google Analytics Course For BeginnersGoogle Analytics Course For Beginners
Google Analytics Course For Beginners
 
Conclusion Of The Course
Conclusion Of The CourseConclusion Of The Course
Conclusion Of The Course
 
Introduction
IntroductionIntroduction
Introduction
 
Create A Texture Pattern:
Create A Texture Pattern:Create A Texture Pattern:
Create A Texture Pattern:
 
Creating The Footer:
Creating The Footer:Creating The Footer:
Creating The Footer:
 
Creating The Main Content Area
Creating The Main Content AreaCreating The Main Content Area
Creating The Main Content Area
 
Create The Quick Quote Section:
Create The Quick Quote Section:Create The Quick Quote Section:
Create The Quick Quote Section:
 
Create The Featured Project Section:
Create The Featured Project Section:Create The Featured Project Section:
Create The Featured Project Section:
 
Creating The Navigation Bar:
Creating The Navigation Bar:Creating The Navigation Bar:
Creating The Navigation Bar:
 
Creating The Logo:
Creating The Logo:Creating The Logo:
Creating The Logo:
 
Prepare Your Photoshop Document:
Prepare Your Photoshop Document:Prepare Your Photoshop Document:
Prepare Your Photoshop Document:
 
Conclusion Of The Course
Conclusion Of The CourseConclusion Of The Course
Conclusion Of The Course
 
Adding A Dash In jQuery:
Adding A Dash In jQuery:Adding A Dash In jQuery:
Adding A Dash In jQuery:
 
Introduction To jQuery:
Introduction To jQuery:Introduction To jQuery:
Introduction To jQuery:
 
Introduction To JavaScript Ajax
Introduction To JavaScript AjaxIntroduction To JavaScript Ajax
Introduction To JavaScript Ajax
 
Introduction To JavaScript
Introduction To JavaScriptIntroduction To JavaScript
Introduction To JavaScript
 
Responsive Web Development
Responsive Web DevelopmentResponsive Web Development
Responsive Web Development
 
How To Add CSS The Correct Way.
How To Add CSS The Correct Way.How To Add CSS The Correct Way.
How To Add CSS The Correct Way.
 
CSS Basic Introduction, Rules, And Tips
CSS Basic Introduction, Rules, And TipsCSS Basic Introduction, Rules, And Tips
CSS Basic Introduction, Rules, And Tips
 

Recently uploaded

Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 

Recently uploaded (20)

Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 

Project Scheduling Techniques and Tools

  • 2. Topic 9 : Project Scheduling  Project scheduling is a mechanism to communicate what tasks need to get done and which organizational resources will be allocated to complete those tasks in what timeframe.  The following are the steps needed to schedule a project: o Define Activities : Create Work Breakdown Structure (WBS) and a deliverables diagram and organize them by mapping out the tasks . o Do Estimates : Determine the time and effort it will take to complete them. o Determine Dependencies : Place a bit of slack in your schedule to accommodate these related tasks. o Assign Resources : Finalize the planned schedule by deciding what resources you are going to need to get those tasks done on time.
  • 3.  Estimate Activity Duration Inputs o This process has several tools and techniques ;- -Expert Judgement, -Analogous Estimating, -Parametric Estimating -Three-Point Estimating, -Group decision-making techniques, -Reserve Analysis  3 Point Estimating o Three-point estimating uses three estimates that when averaged come up with final estimate. • Most likely estimate – assumes there are no disaster and activity can be completed as planned • Optimistic estimate – fastest time frame in which your resource can complete the activity • Pessimistic – Assumes the worst happens and it takes much longer than planned to get the activity completed o Formula to calculate the expected duration : E = (O + P + M) / 3 o E=Expected, O = Optimistic, M = Most Likely o The formula for standard deviation which helps to determine the confidence level as below : E : (Pessimistic – Optimistic) / 6
  • 4.  Expert Judgement - The staff members who will perform activities will most accurately estimate them  Analogous Estimating ( also called as top-down estimating, an expert judgement) - Actual duration of a similar activity completed on previous project will be used to determine the duration of current activity.  Bottom Up Estimating – Is the most accurate approach to estimate cost and duration. Setting the estimates of the amount of work, duration and cost at the task level lets you combine them into estimates of higher-level deliverables and the project as a whole  Parametric Estimating - Quantitatively based estimating method that multiplies the quantity of work by the rate or uses an algorithm in conjunction with historical data to determine the cost, budget or duration estimates.
  • 5.  Group decision-making techniques (brainstorming and the Delphi or nominal group techniques) o Brainstorming is an old-age technique where all participants have an opportunity to speak up. o Delphi technique is similar to brainstorming in that you involve subject matter experts in determining estimates.  Reserve Analysis o Contingency reserve - a portion of time added to the schedule to account for risk o Management reserve - used for unknown events that have not been previously identified
  • 6. Resource Optimization Techniques  Resource Leveling - also called as resource-based method is used when the resources are overallocated and only available at certain times or when they are assigned to more than one activity at a time. The purpose to use this technique is to balance out the resource assignments to get tasks completed without overloading the individual.  Resource Smoothing - Resource smoothing accommodates resource availability by modifying activities within their float times without changing the critical path or project end date. More tasks are given to team members who are under allocated .  Reverse Resource - This technique requires the resources to be scheduled in reverse order in order to assign this key resource at the correct time.
  • 7. Modeling techniques  Include the use of what-if scenario analysis and simulation o What-If scenario : uses different sets of activity assumptions to produce multiple project durations o Simulation use a range of probable activity durations for each activity, and those ranges are then used to calculate a range of probable duration results for the project itself. o Monte Carlo is a simulation technique that runs the possible activity durations and schedule projections many many times to come up with the schedule projections and their probability, critical path duration estimates and float time.
  • 8. Schedule Compression  Mathematical analysis that’s used to shorten the project schedule duration without changing the project scope in order to accomplish all activities sooner than estimated. o Crashing – accomplished by adding resources to the critical path.Crashing the schedule can lead to increased risk and increased cost. o Fast tracking – Performing 2 tasks or project phase in parallel that were previously scheduled to start sequentially. It increases the project risk and might cause the project team to re-work the tasks.
  • 9. Project schedule can be presented in many forms ;  Project schedule network diagram  Gantt chart  Milestone Start Activity 1 Activity 2 Activity 3 Activity 5 Activity 4 Activity 6 Task Name Jan Feb Mar Apr May Planning Design Implementation Milestone Scheduled date Actual Date Responsible Testing completed 04/12/19 - Rachel Acceptance and Signoff 07/12/19 15/12/19 Cindy Project Closure 15/12/19 31/12/19 Carmen