SlideShare a Scribd company logo
1 of 52
LECTURER:
ENG.HISHAM ALI, PMP
Project Management Processes (47)
 PROCESSES GROUP
Project Management Processes
 KNOWLEDGE AREA
• Time Management
 Plan Schedule management
 Define Activities
 Sequence Activities
 Estimate Activity Resources
 Estimate Activity Durations
 Develop Schedule
 Control Schedule
• 6.1 Plan Schedule Management
 the process of establishing the policies, procedures,
and documentation for planning, developing,
managing, executing, and controlling the project
schedule.
 it provides guidance and direction on how the project
schedule will be managed throughout the project
• Schedule Management Plan
 Project schedule model development
The scheduling methodology and the scheduling tool to be used
 Units of measure.
Each unit used in measurements (such as staff hours, staff days...)
 Level of accuracy.
The acceptable range used in determining realistic activity duration
 Control thresholds.
variation to be allowed before some action needs to be taken
 Rules of performance measurement
 Reporting formats.
The formats and frequency for the various schedule reports are
defined.
6.1 Plan Schedule Management
1. Project
management plan
1. Expert judgment
1. Schedule
Management Plan
2. Project Charter
2. Analytical
Technique
3. E.E.F
3. Meetings
4. O.P.A
• 6.2 Define Activities
 the process of identifying and documenting the specific
actions to be performed to produce the project deliverables
 to break down work packages into activities that provide
a basis for estimating, scheduling, executing, monitoring,
and controlling the project work
WBS Packages
Product Analysis
Product
Deliverables
WBS WBS WBS
Activity Activity
Deliverables
WBS
Activity Activity
• 6.2 Define Activities
 Activity List
The activity list is a comprehensive list that includes all
schedule activities required on the project.
 Activity Attributes
Activity attributes extend the description of the activity by
identifying the multiple components associated with each
activity.
 Milestone List
A milestone is a significant point or
event in a project
6.2 Define Activities
1. Schedule
management plan
1. Expert judgment
1. Activity List
2. Scope Baseline 2. Decomposition
2. Activity
Attributes
3. E.E.F
3. Rolling Wave
Planning 3. Milestone List
4. O.P.A
• 6.3 Sequence Activities
 the process of identifying and documenting relationships
among the project activities.
 it defines the logical sequence of work to obtain the
greatest efficiency given all project constraints.
How to make the sequence ??
 Precedence Diagramming Method (PDM)
 Finish-to-Start (FS)
 Finish-to-Finish (FF)
 Start-to-Start (SS)
 Start-to-Finish(SF)
 Types of Dependencies
 Mandatory Dependency(Hard Logic)
 Discretionary Dependency(Preferred-Soft Logic)
 External Dependency
 Internal Dependency
 Leads & Lags
 Lead : overlapping between activities
 Lags : waiting time between activities
Project Schedule Network Diagram
6.3 Sequence Activities
1. Schedule
management plan
1. Precedence
diagramming
method (PDM)
1. Project Schedule
Network Diagrams
2. Activity List
2. Dependency
Determination
2. Project
Documents Updates
3. Activity
Attributes
3. Leads & Lags
4. Milestone List
5. Project Scope
Statement
6. E.E.F
7. O.P.A
• 6.4 Estimate Activity Resources
 the process of estimating the type and quantities of
material, human resources, equipment, or supplies
required to perform each activity
 It identifies the type, quantity, and characteristics of
resources required to complete the activity
• Actions:
 Understand activities and their needs of resources.
 Review historical information and organization polices.
 Check availability of resources.
 Identify skills needed in resources.
 Review cost estimates and make alternative analysis.
 Review resources calendar.
 Quantify resources requirements for each activity.
 Create a resource breakdown structure (RBS).
Resource Breakdown Structure
6.4 Estimate Activity Resources
1. Schedule management
plan
1. Expert Judgment
1. Activity Resource
Requirements
2. Activity List 2. Alternative Analysis
2. Resource
Breakdown Structure
3. Activity Attributes
3. Published
Estimating Data
3. Project Documents
Updates
4. Resources Calendar
4. Bottom up
Estimating
5. Risk Register
5. Project Management
Software
6. Activity Cost
Estimates
6. E.E.F
7. O.P.A
• 6.5 Estimate Activity Durations
 the process of estimating the number of work periods
needed to complete individual activities with estimated
resources.
 it provides the amount of time each activity will take to
complete.
•Tools:
 One point estimating
coming from one source depending on expert or
historical information.
 Analogous Estimating
using historical data from a similar activity or project
to forecast for estimating our activities and used for
limited amount of information.
•Tools:
 Parametric Estimating
uses a statistical relationship between historical data
and other variables to calculate activity duration.
1) Regression Analysis (Scatter Diagram)
2) Learning Curve
depend on improvement of performance
3) Heuristics
depend on accepted rules or best practice
•Tools:
• Three Point Estimating (optimistic, pessimistic, most likely)
 Triangular Distribution
( simple Average )
 Beta Distribution
( weighted Average )
Tools Advantages & Disadvantages
6.5 Estimate Activity Durations
1. Schedule management plan 1. Expert Judgment
1. Activity Duration
Estimates
2. Activity List 2. Analogous Estimating
2. Project Documents
Updates
3. Activity Attributes 3. Parametric Estimating
4. Activity Resource
Requirements
4. Three Point Estimating
5. Resource Calendar
5.Group Decision Making
Technique
6. Project Scope Statement 6.Reserve Analysis
7. Risk Register
8.Resource Breakdown
Structure
9. E.E.F
10. O.P.A
• 6.6 Develop Schedule
 the process of analyzing activity sequences, durations,
resource requirements, and schedule constraints to
create the project schedule model.
 We entering schedule activities, durations, resources,
resource availabilities, and logical relationships into the
scheduling tool
Schedule Techniques
Critical Path Method (CPM)
 method used to estimate the minimum project
duration and determine the amount of scheduling
flexibility on the schedule model.
 Critical Path
the sequence of activities that represents the longest
path through a project, which determines the shortest
possible project duration.
Critical Path Method (CPM)
Critical path Benefits:
 Determine how long the project will take
 Helps the PM to focus his effort on critical activities
 Helps the PM to assign the best resources to critical path
 Shows the activities which have float to help PM
whenever have change.
 Helps to manage resources throughout the project
Float (slack):
 Free Float:
the time an activity can be delayed without delaying
Early start of Successor.
 Total Float:
the time an activity can be delayed without delaying
project end date.
 Project Float:
the time the project can be delayed without delaying
another project.
Critical Path Method (CPM)
Critical Path Method (CPM)
Schedule Compression
 Fast Tracking
By making activities on critical path in parallel not in
sequence. (discretionary dependency)
this technique will increase Risk
 Crashing
by adding or adjusting resources to activities to
compress the schedule.
this technique will increase costs and may increase risk
Critical Path Method (CPM)
Critical Chain Method
 method that allows the project team to place buffers
on any project schedule path to account for limited
resources and project uncertainties
Resource Leveling
 when a resource has been assigned to two or more
activities during the same time period we reallocate
this resources to be at constant level.
Modeling Techniques
 What if Scenario
the process of evaluating scenarios in order to predict
their effect, positively or negatively, on project objectives.
 Simulation
calculating multiple project durations with different sets
of activity assumptions, usually using probability
distributions (Monte Carlo analysis)
Project Schedule
 Network diagram.
showing dependencies
between activities each others.
 Milestone Chart
to show a summary status
to top management or key stakeholders.
 Bar chart (Gant chart)
to show progress between
project team
6.6 Develop Schedule
1. Schedule management
plan
1. Schedule Network
Analysis
1. Schedule baseline
2. Activity List 2. Critical Path Method 2. Project schedule
3. Activity Attributes 3. Critical chain method 3. Schedule data
4. Project schedule Network
Diagram
4. Resource optimization
techniques
4. Project calendars
5. Activity Resource
Requirements
5. Modeling techniques
5. Project management
plan Updates
6. Resource Calendar 6. Leads and lags
6. Project documents
updates
6.6 Develop Schedule
7. Activity Resource
Estimate
7. Schedule compression
8. Project Scope Statement 8. Scheduling tool
9. Risk Register
10. Project staff Assignment
11.Resource Breakdown
Structure
12. E.E.F
13. O.P.A
• 6.7 Control Schedule
 the process of monitoring the status of project activities
to update project progress and manage changes to the
schedule baseline to achieve the plan.
 it provides the means to recognize deviation from the
plan and take corrective and preventive actions.
Actions:
 Determining the current status of the project schedule,
 Influencing the factors that create schedule changes,
 Determining if the project schedule has changed,
 Managing the actual changes as they occur.
 Reprioritizing the remaining work plan
 Take a preventive or corrective action by creating change
requests.
6.7 Control Schedule
1. Project management plan 1. Performance reviews
1. Work performance
information
2. Project schedule
2. Project management
software
2. Schedule forecasts
3. Work performance data
3. Resource optimization
techniques
3. Change requests
4. Project calendars 4. Modeling techniques
4. Project management
plan
updates
5. Schedule data 5. Leads and lags
5. Project documents
updates
6. O.P.A 6. Schedule compression 6. O.P.A. Updates
7. Scheduling tool
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5

More Related Content

What's hot

Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Managementguest90bddb
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010Abdul Ghaffar, PMP
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management MethodologyMohammed Al-Taee
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sAbhik Tushar Das
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 
Project & Project managment
Project & Project managmentProject & Project managment
Project & Project managmentPramod Sharma
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)PM Majik
 
Confluence for the Evolving Project Management Office (PMO)
Confluence for the Evolving Project Management Office (PMO)Confluence for the Evolving Project Management Office (PMO)
Confluence for the Evolving Project Management Office (PMO)Atlassian
 

What's hot (20)

Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management Methodology
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Project management
Project managementProject management
Project management
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
MS Project
MS Project MS Project
MS Project
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
PMO Strategic Planning
PMO Strategic Planning PMO Strategic Planning
PMO Strategic Planning
 
Project Management Basics
Project Management BasicsProject Management Basics
Project Management Basics
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Project & Project managment
Project & Project managmentProject & Project managment
Project & Project managment
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
 
Confluence for the Evolving Project Management Office (PMO)
Confluence for the Evolving Project Management Office (PMO)Confluence for the Evolving Project Management Office (PMO)
Confluence for the Evolving Project Management Office (PMO)
 

Viewers also liked

PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryYudha Pratama, PMP
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Editionpankajsh10
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementHisham Ali,PMP
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
PMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENTPMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENTHisham Ali,PMP
 
PMBOK 5th edition Project Stakeholder Management
PMBOK 5th edition Project Stakeholder ManagementPMBOK 5th edition Project Stakeholder Management
PMBOK 5th edition Project Stakeholder ManagementSudhanshu Singh MBA,PMP
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaOnline PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaGlobalSkillup
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaGlobalSkillup
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...GlobalSkillup
 
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...GlobalSkillup
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaGlobalSkillup
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaGlobalSkillup
 
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamEasy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamGlobalSkillup
 

Viewers also liked (20)

PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Pmp 3 chapter
Pmp  3 chapterPmp  3 chapter
Pmp 3 chapter
 
PMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENTPMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENT
 
Chap06 project time management
Chap06 project time managementChap06 project time management
Chap06 project time management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
PMBOK 5th edition Project Stakeholder Management
PMBOK 5th edition Project Stakeholder ManagementPMBOK 5th edition Project Stakeholder Management
PMBOK 5th edition Project Stakeholder Management
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaOnline PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...
 
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
 
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamEasy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
 

Similar to TIME MANAGEMENT chapter(6), PMBOK5

Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.pptMohamadAGhareb
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615EqraBaig
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
L05 time management
L05 time managementL05 time management
L05 time managementAsa Chan
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTùng Trần Thanh
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 

Similar to TIME MANAGEMENT chapter(6), PMBOK5 (20)

Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
Time management
Time managementTime management
Time management
 
CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.ppt
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
08 ch06
08 ch0608 ch06
08 ch06
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
L05 time management
L05 time managementL05 time management
L05 time management
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 

Recently uploaded

Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectivesmintusiprd
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentationthomas851723
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentationthomas851723
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxSaujanya Jung Pandey
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 

Recently uploaded (20)

sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectives
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentation
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentation
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptx
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 

TIME MANAGEMENT chapter(6), PMBOK5

  • 2. Project Management Processes (47)  PROCESSES GROUP
  • 4. • Time Management  Plan Schedule management  Define Activities  Sequence Activities  Estimate Activity Resources  Estimate Activity Durations  Develop Schedule  Control Schedule
  • 5. • 6.1 Plan Schedule Management  the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.  it provides guidance and direction on how the project schedule will be managed throughout the project
  • 6. • Schedule Management Plan  Project schedule model development The scheduling methodology and the scheduling tool to be used  Units of measure. Each unit used in measurements (such as staff hours, staff days...)  Level of accuracy. The acceptable range used in determining realistic activity duration  Control thresholds. variation to be allowed before some action needs to be taken  Rules of performance measurement  Reporting formats. The formats and frequency for the various schedule reports are defined.
  • 7. 6.1 Plan Schedule Management 1. Project management plan 1. Expert judgment 1. Schedule Management Plan 2. Project Charter 2. Analytical Technique 3. E.E.F 3. Meetings 4. O.P.A
  • 8. • 6.2 Define Activities  the process of identifying and documenting the specific actions to be performed to produce the project deliverables  to break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work
  • 9. WBS Packages Product Analysis Product Deliverables WBS WBS WBS Activity Activity Deliverables WBS Activity Activity
  • 10.
  • 11.
  • 12. • 6.2 Define Activities  Activity List The activity list is a comprehensive list that includes all schedule activities required on the project.  Activity Attributes Activity attributes extend the description of the activity by identifying the multiple components associated with each activity.  Milestone List A milestone is a significant point or event in a project
  • 13. 6.2 Define Activities 1. Schedule management plan 1. Expert judgment 1. Activity List 2. Scope Baseline 2. Decomposition 2. Activity Attributes 3. E.E.F 3. Rolling Wave Planning 3. Milestone List 4. O.P.A
  • 14. • 6.3 Sequence Activities  the process of identifying and documenting relationships among the project activities.  it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
  • 15. How to make the sequence ??  Precedence Diagramming Method (PDM)  Finish-to-Start (FS)  Finish-to-Finish (FF)  Start-to-Start (SS)  Start-to-Finish(SF)
  • 16.  Types of Dependencies  Mandatory Dependency(Hard Logic)  Discretionary Dependency(Preferred-Soft Logic)  External Dependency  Internal Dependency  Leads & Lags  Lead : overlapping between activities  Lags : waiting time between activities
  • 18. 6.3 Sequence Activities 1. Schedule management plan 1. Precedence diagramming method (PDM) 1. Project Schedule Network Diagrams 2. Activity List 2. Dependency Determination 2. Project Documents Updates 3. Activity Attributes 3. Leads & Lags 4. Milestone List 5. Project Scope Statement 6. E.E.F 7. O.P.A
  • 19. • 6.4 Estimate Activity Resources  the process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity  It identifies the type, quantity, and characteristics of resources required to complete the activity
  • 20. • Actions:  Understand activities and their needs of resources.  Review historical information and organization polices.  Check availability of resources.  Identify skills needed in resources.  Review cost estimates and make alternative analysis.  Review resources calendar.  Quantify resources requirements for each activity.  Create a resource breakdown structure (RBS).
  • 22. 6.4 Estimate Activity Resources 1. Schedule management plan 1. Expert Judgment 1. Activity Resource Requirements 2. Activity List 2. Alternative Analysis 2. Resource Breakdown Structure 3. Activity Attributes 3. Published Estimating Data 3. Project Documents Updates 4. Resources Calendar 4. Bottom up Estimating 5. Risk Register 5. Project Management Software 6. Activity Cost Estimates 6. E.E.F 7. O.P.A
  • 23. • 6.5 Estimate Activity Durations  the process of estimating the number of work periods needed to complete individual activities with estimated resources.  it provides the amount of time each activity will take to complete.
  • 24. •Tools:  One point estimating coming from one source depending on expert or historical information.  Analogous Estimating using historical data from a similar activity or project to forecast for estimating our activities and used for limited amount of information.
  • 25. •Tools:  Parametric Estimating uses a statistical relationship between historical data and other variables to calculate activity duration. 1) Regression Analysis (Scatter Diagram) 2) Learning Curve depend on improvement of performance 3) Heuristics depend on accepted rules or best practice
  • 26. •Tools: • Three Point Estimating (optimistic, pessimistic, most likely)  Triangular Distribution ( simple Average )  Beta Distribution ( weighted Average )
  • 27. Tools Advantages & Disadvantages
  • 28. 6.5 Estimate Activity Durations 1. Schedule management plan 1. Expert Judgment 1. Activity Duration Estimates 2. Activity List 2. Analogous Estimating 2. Project Documents Updates 3. Activity Attributes 3. Parametric Estimating 4. Activity Resource Requirements 4. Three Point Estimating 5. Resource Calendar 5.Group Decision Making Technique 6. Project Scope Statement 6.Reserve Analysis 7. Risk Register 8.Resource Breakdown Structure 9. E.E.F 10. O.P.A
  • 29. • 6.6 Develop Schedule  the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.  We entering schedule activities, durations, resources, resource availabilities, and logical relationships into the scheduling tool
  • 31. Critical Path Method (CPM)  method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the schedule model.  Critical Path the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration.
  • 33. Critical path Benefits:  Determine how long the project will take  Helps the PM to focus his effort on critical activities  Helps the PM to assign the best resources to critical path  Shows the activities which have float to help PM whenever have change.  Helps to manage resources throughout the project
  • 34. Float (slack):  Free Float: the time an activity can be delayed without delaying Early start of Successor.  Total Float: the time an activity can be delayed without delaying project end date.  Project Float: the time the project can be delayed without delaying another project.
  • 37. Schedule Compression  Fast Tracking By making activities on critical path in parallel not in sequence. (discretionary dependency) this technique will increase Risk  Crashing by adding or adjusting resources to activities to compress the schedule. this technique will increase costs and may increase risk
  • 39. Critical Chain Method  method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties
  • 40. Resource Leveling  when a resource has been assigned to two or more activities during the same time period we reallocate this resources to be at constant level.
  • 41. Modeling Techniques  What if Scenario the process of evaluating scenarios in order to predict their effect, positively or negatively, on project objectives.  Simulation calculating multiple project durations with different sets of activity assumptions, usually using probability distributions (Monte Carlo analysis)
  • 42. Project Schedule  Network diagram. showing dependencies between activities each others.  Milestone Chart to show a summary status to top management or key stakeholders.  Bar chart (Gant chart) to show progress between project team
  • 43. 6.6 Develop Schedule 1. Schedule management plan 1. Schedule Network Analysis 1. Schedule baseline 2. Activity List 2. Critical Path Method 2. Project schedule 3. Activity Attributes 3. Critical chain method 3. Schedule data 4. Project schedule Network Diagram 4. Resource optimization techniques 4. Project calendars 5. Activity Resource Requirements 5. Modeling techniques 5. Project management plan Updates 6. Resource Calendar 6. Leads and lags 6. Project documents updates
  • 44. 6.6 Develop Schedule 7. Activity Resource Estimate 7. Schedule compression 8. Project Scope Statement 8. Scheduling tool 9. Risk Register 10. Project staff Assignment 11.Resource Breakdown Structure 12. E.E.F 13. O.P.A
  • 45. • 6.7 Control Schedule  the process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.  it provides the means to recognize deviation from the plan and take corrective and preventive actions.
  • 46. Actions:  Determining the current status of the project schedule,  Influencing the factors that create schedule changes,  Determining if the project schedule has changed,  Managing the actual changes as they occur.  Reprioritizing the remaining work plan  Take a preventive or corrective action by creating change requests.
  • 47. 6.7 Control Schedule 1. Project management plan 1. Performance reviews 1. Work performance information 2. Project schedule 2. Project management software 2. Schedule forecasts 3. Work performance data 3. Resource optimization techniques 3. Change requests 4. Project calendars 4. Modeling techniques 4. Project management plan updates 5. Schedule data 5. Leads and lags 5. Project documents updates 6. O.P.A 6. Schedule compression 6. O.P.A. Updates 7. Scheduling tool