SlideShare a Scribd company logo
1 of 20
Certified Associate Project Management
CAPM® Exam Prep – Week 4
Prof. Muzette Charles, PMP | mcharles2@pace.edu
Schedule Management
Chapter 6 - Review
Schedule Management
Chapter 6 - Review
Schedule Management
Chapter 6 - Review
Cost Management
Chapter 7
“… includes the processes involved in planning, estimating, budgeting, financing, funding,
managing & controlling costs so that the project can be completed within the approved
budget.”
Process Process Group Key Deliverables
7.1 Plan Cost Management Planning Cost Management Plan
7.2 Estimate Costs Planning Activity cost estimates
7.3 Determine Budget Planning Cost Baseline (budget)
7.4 Control Costs Monitoring & Controlling Change Requests
Cost Management
Chapter 7
Plan Cost Management
Process 1
Key Points
 Provides guidance on how costs aka budget, will be managed throughout the project
 Aligns with Schedule baseline estimates, units of measure, level of accuracy (+/- %)
 Funding decisions: existing funds, equity or debt
Cost Management
Chapter 7
Estimate Costs
Process 2
Key Points
 Developing the monetary cost each activity needed to complete the project
 Cost estimates are a prediction based on info known at a given point in time & is constantly reviewed
 Expected accuracy: initially ROM -25% to +75% , Budget -10% to +25%, Definitive -5% to +10%
 Usually expressed in currency: dollars, euros, yen, etc
Cost Management
Chapter 7
Determine Budget
Process 3
Key Points
 Budget: all the calculated funds authorized to execute the project, includes reserves
 Cost baseline: the approved version of the budget, less Management Reserves, used as a
benchmark for variance analysis to measure project’s success.
 Reserve Analysis: Contingency Reserve & Management Reserve
 Funding Limit Reconciliation: PM is responsible to not exceed funding limits
Cost Management
Chapter 7Control Costs
Process 4
Key Points
 Earned Value Mgmt (EVM):
 Tracks how is your project doing compared to plan
 Variances & forecast future performance, cost & completion date
 Performance Measurement Baseline: integrates cost, time & scope to predict variance, correct &
minimize risk
Cost Management
Chapter 7
Control Costs
Process 4
Project is on Track: .95 < CPI or SPI < 1.10 (Industry Rule)
Cost Management
Chapter 7
Quality Management
Chapter 8
“… works to ensure the project requirements, including product requirements are met & validated.”
• “Project is completed with no deviations from the project requirements.”
• Customer satisfaction – project meets the defined customer needs
• Continuous improvement: Plan-Do-Check-Act (PDCA) is the basis for quality improvement
• Prevention over inspection
• Management responsibility
Process Process Group Key Deliverables
8.1 Plan Quality Management Planning Quality Management Plan
8.2 Manage Quality Executing Change Requests
8.3 Control Quality Monitoring & Control Validated Changes
Quality Management
Chapter 8
Plan Quality Management
Process 1 Key Points
 “… identifying quality requirements and/or standards for the project & its deliverables & documenting how the
project will demonstrate compliance with quality requirements and/or standards.”
 Conformance to requirements: Customer Satisfaction & Fitness for use
 Quality vs Grade: It does what you NEED it to do vs people VALUE the product
 Baseline key inputs: Scope/WBS, deliverables, Acceptance Criteria, Cost/approving funding, budget per period,
Schedule/milestone dates
Quality Management
Chapter 8
Plan Quality Management
Process 1
Key Points
7 Basic Quality Tools:
 Fishbone aka Ishikawa (Cause & Effect Diagram): see all defect causes by categories or see all
requirements & the factors that may cause defects
 Pareto Diagram: sorts frequency of defects in descending order – 80/20 Rule
 Histogram: vertical bar chart of potential problems
 Control Cart: if a process is stable or has predictable performance with upper/lower limits, Heuristic 7
 Scatter Diagram (Correlation charts): compares 2 types of data
 Flowcharts (Process Map): visualize how tasks/phases are interrelated/depend on each other SIPOC
model (supplier, input, process, output, customer)
 Checksheet (Tally Sheet): gathers data of product being tested
Quality Management
Chapter 8
Plan Quality Management
Process 1
Quality Management
Chapter 8
Manage Quality
Process 2
Key Points
 “…. The process of auditing the quality requirements & the results from quality control measurements to ensure
appropriate quality standards are used.”
 Seeks confidence that a future output or unfinished output will be completed in a manner to meet requirements
 Unfinished Output = Work in progress
Quality Management
Chapter 8
Manage Quality
Process 2
Quality Management
Chapter 8
Control Quality
Process 3
Key Points
 “… identifying causes of poor process or product quality & recommending and/or taking action to eliminate them.”
 “Validating that project deliverables meet the stakeholder’s requirements necessary for final acceptance.”
 Defects: Prevention (monitor quality) is ALWAYS better than Inspection (checking deliverables for defects)
 Cost-Benefit Analysis: Decreased Rework vs. Increased Production, Efficiency & Satisfaction
Quality Management
Chapter 8
CAPM Exam Prep
Group Exercise & Quiz 4

More Related Content

What's hot

What i es do iie iab v2
What i es do iie iab v2What i es do iie iab v2
What i es do iie iab v2Jitesh Gaurav
 
Episode 24 : Project Quality Management
Episode 24 :  Project Quality ManagementEpisode 24 :  Project Quality Management
Episode 24 : Project Quality ManagementSAJJAD KHUDHUR ABBAS
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Managementmzedan
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management OverviewDavidMcLachlan1
 
Project Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation SlidesProject Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation SlidesSlideTeam
 
Quality in project management
Quality in project management Quality in project management
Quality in project management Zeeshan Azhar
 
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.iFour Institute - Sustainable Learning
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge AreaJoshua Render
 
Why we need to control scope
Why we need to control scope Why we need to control scope
Why we need to control scope Nooria Esmaelzade
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge AreaJoshua Render
 
Quality management procedures
Quality management proceduresQuality management procedures
Quality management proceduresselinasimpson1201
 
Project management kpi dashboard
Project management kpi dashboardProject management kpi dashboard
Project management kpi dashboardsamnopabisjones
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Management Foundation implementation introduction 2014 (public)
Management Foundation implementation introduction 2014 (public)Management Foundation implementation introduction 2014 (public)
Management Foundation implementation introduction 2014 (public)Richard den Dulk
 
Models of quality assessment
Models of quality assessmentModels of quality assessment
Models of quality assessmentAsila AL-harthi
 

What's hot (20)

What i es do iie iab v2
What i es do iie iab v2What i es do iie iab v2
What i es do iie iab v2
 
Episode 24 : Project Quality Management
Episode 24 :  Project Quality ManagementEpisode 24 :  Project Quality Management
Episode 24 : Project Quality Management
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management Overview
 
CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7
 
Project Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation SlidesProject Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation Slides
 
Project scope management 2
Project scope management 2Project scope management 2
Project scope management 2
 
Quality in project management
Quality in project management Quality in project management
Quality in project management
 
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
 
Why we need to control scope
Why we need to control scope Why we need to control scope
Why we need to control scope
 
Doc3
Doc3Doc3
Doc3
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge Area
 
Quality management procedures
Quality management proceduresQuality management procedures
Quality management procedures
 
Project management kpi dashboard
Project management kpi dashboardProject management kpi dashboard
Project management kpi dashboard
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Management Foundation implementation introduction 2014 (public)
Management Foundation implementation introduction 2014 (public)Management Foundation implementation introduction 2014 (public)
Management Foundation implementation introduction 2014 (public)
 
Models of quality assessment
Models of quality assessmentModels of quality assessment
Models of quality assessment
 
CMMI level 2 (MA & PPQA)
CMMI level 2 (MA & PPQA)CMMI level 2 (MA & PPQA)
CMMI level 2 (MA & PPQA)
 

Similar to CAPM Muzette Charles_Week4_Chapter7-8

PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
08 projectqualitymanagement
08 projectqualitymanagement08 projectqualitymanagement
08 projectqualitymanagementDhamo daran
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfHuyNguyen657394
 
PROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptPROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptAhtashamArshad4
 
projectqualitymanagement-140816235544-phpapp02.pptx
projectqualitymanagement-140816235544-phpapp02.pptxprojectqualitymanagement-140816235544-phpapp02.pptx
projectqualitymanagement-140816235544-phpapp02.pptxHamzaKhawar4
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 
Pmbok 5th planning process group part three
Pmbok 5th planning process group part threePmbok 5th planning process group part three
Pmbok 5th planning process group part threeHossam Maghrabi
 
Product quality management
Product quality managementProduct quality management
Product quality managementSunil Meena
 
Methodologies for quality management
Methodologies for quality managementMethodologies for quality management
Methodologies for quality managementAsamHussain3
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaGlobalSkillup
 
scribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdfscribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdfAbdullahSamy6
 
L07 quality management
L07 quality managementL07 quality management
L07 quality managementAsa Chan
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Roger H. Mandel
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 

Similar to CAPM Muzette Charles_Week4_Chapter7-8 (20)

Project quality management
Project quality managementProject quality management
Project quality management
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
Project quality management
Project quality managementProject quality management
Project quality management
 
08 projectqualitymanagement
08 projectqualitymanagement08 projectqualitymanagement
08 projectqualitymanagement
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdf
 
PROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptPROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.ppt
 
8.2 Manage Quality
8.2 Manage Quality8.2 Manage Quality
8.2 Manage Quality
 
Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
projectqualitymanagement-140816235544-phpapp02.pptx
projectqualitymanagement-140816235544-phpapp02.pptxprojectqualitymanagement-140816235544-phpapp02.pptx
projectqualitymanagement-140816235544-phpapp02.pptx
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
Pmbok 5th planning process group part three
Pmbok 5th planning process group part threePmbok 5th planning process group part three
Pmbok 5th planning process group part three
 
Product quality management
Product quality managementProduct quality management
Product quality management
 
Methodologies for quality management
Methodologies for quality managementMethodologies for quality management
Methodologies for quality management
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
 
scribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdfscribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdf
 
L07 quality management
L07 quality managementL07 quality management
L07 quality management
 
8 quality PMBOK
8 quality PMBOK8 quality PMBOK
8 quality PMBOK
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 

More from Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

More from Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 

Recently uploaded

Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxShobhayan Kirtania
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 

Recently uploaded (20)

Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptx
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 

CAPM Muzette Charles_Week4_Chapter7-8

  • 1. Certified Associate Project Management CAPM® Exam Prep – Week 4 Prof. Muzette Charles, PMP | mcharles2@pace.edu
  • 5. Cost Management Chapter 7 “… includes the processes involved in planning, estimating, budgeting, financing, funding, managing & controlling costs so that the project can be completed within the approved budget.” Process Process Group Key Deliverables 7.1 Plan Cost Management Planning Cost Management Plan 7.2 Estimate Costs Planning Activity cost estimates 7.3 Determine Budget Planning Cost Baseline (budget) 7.4 Control Costs Monitoring & Controlling Change Requests
  • 6. Cost Management Chapter 7 Plan Cost Management Process 1 Key Points  Provides guidance on how costs aka budget, will be managed throughout the project  Aligns with Schedule baseline estimates, units of measure, level of accuracy (+/- %)  Funding decisions: existing funds, equity or debt
  • 7. Cost Management Chapter 7 Estimate Costs Process 2 Key Points  Developing the monetary cost each activity needed to complete the project  Cost estimates are a prediction based on info known at a given point in time & is constantly reviewed  Expected accuracy: initially ROM -25% to +75% , Budget -10% to +25%, Definitive -5% to +10%  Usually expressed in currency: dollars, euros, yen, etc
  • 8. Cost Management Chapter 7 Determine Budget Process 3 Key Points  Budget: all the calculated funds authorized to execute the project, includes reserves  Cost baseline: the approved version of the budget, less Management Reserves, used as a benchmark for variance analysis to measure project’s success.  Reserve Analysis: Contingency Reserve & Management Reserve  Funding Limit Reconciliation: PM is responsible to not exceed funding limits
  • 9. Cost Management Chapter 7Control Costs Process 4 Key Points  Earned Value Mgmt (EVM):  Tracks how is your project doing compared to plan  Variances & forecast future performance, cost & completion date  Performance Measurement Baseline: integrates cost, time & scope to predict variance, correct & minimize risk
  • 10. Cost Management Chapter 7 Control Costs Process 4 Project is on Track: .95 < CPI or SPI < 1.10 (Industry Rule)
  • 12. Quality Management Chapter 8 “… works to ensure the project requirements, including product requirements are met & validated.” • “Project is completed with no deviations from the project requirements.” • Customer satisfaction – project meets the defined customer needs • Continuous improvement: Plan-Do-Check-Act (PDCA) is the basis for quality improvement • Prevention over inspection • Management responsibility Process Process Group Key Deliverables 8.1 Plan Quality Management Planning Quality Management Plan 8.2 Manage Quality Executing Change Requests 8.3 Control Quality Monitoring & Control Validated Changes
  • 13. Quality Management Chapter 8 Plan Quality Management Process 1 Key Points  “… identifying quality requirements and/or standards for the project & its deliverables & documenting how the project will demonstrate compliance with quality requirements and/or standards.”  Conformance to requirements: Customer Satisfaction & Fitness for use  Quality vs Grade: It does what you NEED it to do vs people VALUE the product  Baseline key inputs: Scope/WBS, deliverables, Acceptance Criteria, Cost/approving funding, budget per period, Schedule/milestone dates
  • 14. Quality Management Chapter 8 Plan Quality Management Process 1 Key Points 7 Basic Quality Tools:  Fishbone aka Ishikawa (Cause & Effect Diagram): see all defect causes by categories or see all requirements & the factors that may cause defects  Pareto Diagram: sorts frequency of defects in descending order – 80/20 Rule  Histogram: vertical bar chart of potential problems  Control Cart: if a process is stable or has predictable performance with upper/lower limits, Heuristic 7  Scatter Diagram (Correlation charts): compares 2 types of data  Flowcharts (Process Map): visualize how tasks/phases are interrelated/depend on each other SIPOC model (supplier, input, process, output, customer)  Checksheet (Tally Sheet): gathers data of product being tested
  • 15. Quality Management Chapter 8 Plan Quality Management Process 1
  • 16. Quality Management Chapter 8 Manage Quality Process 2 Key Points  “…. The process of auditing the quality requirements & the results from quality control measurements to ensure appropriate quality standards are used.”  Seeks confidence that a future output or unfinished output will be completed in a manner to meet requirements  Unfinished Output = Work in progress
  • 18. Quality Management Chapter 8 Control Quality Process 3 Key Points  “… identifying causes of poor process or product quality & recommending and/or taking action to eliminate them.”  “Validating that project deliverables meet the stakeholder’s requirements necessary for final acceptance.”  Defects: Prevention (monitor quality) is ALWAYS better than Inspection (checking deliverables for defects)  Cost-Benefit Analysis: Decreased Rework vs. Increased Production, Efficiency & Satisfaction
  • 20. CAPM Exam Prep Group Exercise & Quiz 4