SlideShare a Scribd company logo
1 of 50
Project Management Professional
PMP® Exam Prep – Week 4
Resource Management
Prof. Muzette Charles, PMP | mcharles2@pace.edu
Resource Management
Chapter 9
“… is the process that organize, manage & lead the project team.”
• Project Team is comprised of the people assigned roles & responsibilities to complete the project
• Project team members may have varied skill sets, FT or PT, added or removed from team
• Team members participating in Planning adds Expertise & Strengthens commitment to project
• Team members are also called the “Project Staff”
Process Process Group Key Deliverables
9.1 Plan Resource Management Planning Resource Management Plan
9.2 Estimate Activity Resources Planning Resource Requirements
9.3 Acquire Resources Executing Resource Calendars
9.4 Develop Team Executing Team performance assessments
9.5 Manage Team Executing Change Requests
9.6 Control Resources Monitoring & Controlling Work Performance Information
Resource management often intersects with other
project management processes.
Create WBS helps define
project staffing needs.
Estimate Activity Durations and Costs may
depend on the ability to acquire staff with
the right knowledge to complete the work.
Manage Stakeholder Engagement may
require resolving conflicts between
stakeholders and team members.
Control Quality may be affected by
team capabilities and motivation.
Resource Management
Chapter 9
Resource Management
Chapter 9
Plan Resource Management
Process 1 Key Points
 “… process of identifying & documenting project roles, responsibilities, required skills, reporting
rlnships & creating a staffing management plan.”
 Tools – Org Charts: Responsibility Assignment Matrix (RAM) - RACI Chart, OBS, RBS, Text
 Resource Mgmt Plan: Staffing Mgmt Plan – acquisition, resource calendars, release plan (roll off),
training needs, rewards, compliance, safety
Resource Management
Chapter 9
Plan Resource Management
Process 1
Resource Management
Chapter 9
Plan Resource Management
Process 1
Organizational Chart Examples
Organizational Breakdown Structure
(OBS) Chart
Key to understanding organizational reporting lines
and project manager’s authority
Resource Management
Chapter 9
Plan Resource Management
Process 1
Organizational Chart Examples
Resource Breakdown Structure
(RBS) Chart
Hierarchical depiction of resources,
including human resources
0. New Anti-Scarring Product
Project Resources
3. Equipment2. People1. Materials
2.1 Preclinical 2.2 Clinical 2.3 Formulation
2.4 Facility
Construction
2.5 Regulatory
Affairs
2.6 Marketing
2.4.1 Building Design 2.4.2 Mechanicals 2.4.3 Construction
2.4.2.1 Design
2.4.2.2 Mechanical
Engineering
2.4.2.3 Testing
2.4.2.2.1
Lead ME
2.4.2.2.2
Mech Specialist
2.4.2.2.3
Mech Asst
Resource Management
Chapter 9
Plan Resource Management
Process 1
Organizational Chart Examples
RACI Chart
• Only one individual can be accountable for each activity.
• In some organizations, it is not a good practice to have
the same person be both responsible and accountable.
R = Responsible for performing
A = Accountable; review and approve
C = Consult and advise
I = Inform of status
Resource Management
Chapter 9
Plan Resource Management
Process 1
Motivational Theories
McGregor’s Theory X & Y
 Theory X Managers
 Workers are not inherently motivated
 Coercion and direction
 Theory Y Managers
 Workers seek responsibility and power to solve problems
 Leadership, empowerment, and influence.
Resource Management
Chapter 9
Plan Resource Management
Process 1
Motivational Theories
Maslow’s Hierarchy of Needs
Self-actualization
Self-esteem and
respect for others
Belonging
Safety and security
Physical needsSet reasonable schedule and hours
Define expectations/rewards
Support membership in the team
Empower, train and reward
Delegate
A project manager relies heavily on team social events to
motivate members. One highly experienced member does not
enjoy the events. What should the project manager do?
A. Leave the member alone.
B. Talk to the member about his/her needs and wants.
C. Ask another team member to draw the reluctant member
into more enthusiastic participation.
D. Explain that lack of participation may negatively affect the
member’s career.
Discussion Question
Answer: B
The project manager should make an effort to find out what
types of rewards this team member values and then find a way
to deliver those rewards when appropriate.
Chapter 9, Topic 1
Resource Management
Chapter 9
Plan Resource Management
Process 1
Motivational Theories
McClelland’s Three Needs Theory
 Structure project work to reward each type through opportunities
to challenge oneself, share with others, or compete with others.
Achievement Affiliation Power
You cannot create motivation by ensuring job
satisfaction.
Motivation creates
satisfaction.
Work conditions
create
dissatisfaction.
Pay, security, schedule, work
relationships, supervisor style
Challenge, independence, creativity,
opportunities
Plan Resource Management
Process 1
Resource Management
Chapter 9
Motivational Theories
Herzberg’s Motivation-Hygiene Theory
 Legitimate Power: from position
 Reward Power: ability to control budget, career, pay
 Expert Power: knowledge and experience
 Referent Power: personality
 Coercive Power: demand and punish
How do project
managers lead?
Plan Resource Management
Process 1
Resource Management
Chapter 9
Management Skills
Project Manager Power
A project manager has formed a harmonious team
by cultivating comfortable, personal ties to each of
the team members. What type of power is this
project manager using?
A. Legitimate
B. Reward
C. Expert
D. Referent
Discussion Question
Answer: D
The project manager is relying on his or her personality to
create bonds. Over-reliance on one source of power may not be
sufficient over time and under stressful conditions.
Chapter 9, Topic 1
Roles and
responsibilities
• Function to be performed
• Authority
• Responsibility
• Required competencies
Project
organizational
charts
• Graphic visualization of reporting lines
Project team
resource
management
• Time-phased
• Staff acquisition, duration, and release
• Resource calendars
• Training needs for individuals
• Team-building and reward strategies
Resource Management
Chapter 9
Plan Resource Management
Process 1
Resource Management Plan
Resource Management
Chapter 9
Estimate Activity Resources
Process 2
Key Points
 “Estimates type & quantities of material, human resources, equipment or supplies required to perform each activity”
 Every activity has to have a resource assigned to it: Person, Equipment, Material
 Bottom-up estimating: estimate each activity, work package, control account rolled into overall project estimate
 Activity resource requirements: details which resources are assigned to each activity
 Closely coordinated with Estimate Costs in Cost Management
Resource Management
Chapter 9Acquire Resources
Process 3 Key Points
 “… process of confirming human resource availability & obtaining team necessary to complete project activities.”
 Resource Calendars - displays both 1) time resource is Assigned & 2) time resource is Available
 “Great PM will invite new team members to review their part of the project for changes before they start their work.
 Tools:
 Pre-Assignment (guaranteed resources not negotiated)
 Negotiation (for resources that don’t report to the PM)
 Acquisition - Going outside of the company to staff team
 Virtual Teams – Pro/Team mbrs can be the best worldwide, Con/Communication challenges
 Multi-criteria DM – Team mbrs selected by weighted scores on Cost, Experience, Location, Skill Set, Training, etc
 Halo Effect - Assigning a person to a position bc they’re an expert in their field, but not qualified in this position
Multi-Criteria Decision Analysis
 Decision matrix used as a rational, analytical staff selection tool
 Criteria are defined and weighted
 Candidates are scored against the criteria
Acquire Resources
Process 3
Resource Management
Chapter 9
Virtual Teams
 May be a reality in any
organization; likely to be a
reality in a global organization
 Potential for cost savings and
access to larger, high-quality
pool of talent
 Greater diversity
 More difficult to build a
smoothly functioning team
 Communication hurt by lack of
face-to-face contact
 Conflicts may be unrecognized
and unresolved
Acquire Resources
Process 3
Resource Management
Chapter 9
What are some techniques that project
managers can use to manage the potential
negatives of virtual teams and enhance their
benefits?
Discussion Question
Answers:
Could include finding budget for some face-to-face
meetings, including opportunities for getting to
know team members as individuals during virtual
meetings and opportunities to learn about other
cultures in the organization, and two techniques
that will be talked about in the next topic: ground
rules and colocation.Chapter 9, Topic 3
Resource Management
Chapter 9Develop Team
Process 4 Key Points
 “… process of improving competencies, team member interaction & overall team environment to enhance project performance.”
 Make sure team is motivated, well managed to reduce turnover & keep team moving toward goal of satisfactory project
completion
Tools
 Interpersonal (Soft) Skills: Leadership, Team Building, Motivation, Communication, Influencing, Political/Cultural Awareness,
Negotiation, Decision Making, Trust Building
 Team Building Activities: Forming, Storming, Norming, Performing, Adjourning
 Co-Location aka War Room: Improves communication when all team mbrs (especially Virtual Mbrs) can come together to review
project assignments
Create a Positive Work Environment
GroundRules
•Expectations regarding
acceptable behavior
•Shared values
•Clear procedures
Colocation
•Physically locating team
members in the same place
to improve communication
and productivity
•Creates tighter team
Develop Team
Process 4
Resource Management
Chapter 9
Tuckman Team Development Model
 Common stages of team formation
 Can be used to assess team state or anticipate issues
Forming
• Independence
• Little sharing
Storming
• More
conflict,
challenges to
authority
Norming
• Increased
acceptance
• Beginning of
cooperation
and trust
Performing
• Well organized
• Interdependence
Adjourning
• Lessons
learned
Develop Team
Process 4
Resource Management
Chapter 9
Team members perform their tasks independently
and are not interested in comparing approaches.
What stage of team formation does this behavior
illustrate?
A. Forming
B. Storming
C. Norming
D. Performing
Discussion Question
Answer: A
This type of guarded behavior is typical of forming,
which can be observed in newly formed teams or
established teams when new members are added.
Chapter 9, Topic 4
Recognition and Rewards
 Recognition—acknowledging the efforts of a group or individual, ideally in public
 Rewards—tangible or intangible gifts; if monetary, sufficient to motivate without being too
costly
These strategies are more effective when they are:
 Planned and thoughtful rather than “ad hoc.”
 Implemented throughout the project & not when they are needed most to motivate the team.
Ensure that all recognition and rewards align with
organizational policies and workplace cultures.
Develop Team
Process 4
Resource Management
Chapter 9
Resource Management
Chapter 9
Manage Team
Process 5 Key Points
 “… process of tracking team member performance, providing feedback, resolving issues & managing changes to
optimize project performance.”
 7 Conflict Sources: Schedules, Project priorities, Resources, Technical differences, Admin procedures, Cost, Personality
 Conflict Mgmt Tools:
 Collaborating (Problem Solving) – meetings to gain consensus on multiple difference of viewpoints … win-win situation
 Compromising (Reconciling) – find solutions to bring some degree of satisfaction … lose-lose situation
 Smoothing (Accommodating) – temporary solution, gives ppl space & time to step back
 Forcing (Directing) – pushing 1 viewpoint at the expense of another … win-lose situation
 Withdrawal (Avoidance) – counterproductive, problem is not resolved, project suffers, ppl are angry…. walk away
Leadership Skills
Interpersonal
skills
• Understand others and be respectful.
• Influence and persuade.
• Build trust and a supportive team
atmosphere.
Group
facilitation
skills
• Encourage team to engage in independent
problem solving.
Conflict
resolution
• Use when issues arise among team
members.
Manage Team
Process 5
Resource Management
Chapter 9
Resource Management
Chapter 9
Control Resources
Process 6
Key Points
 “…process to ensure that the physical resources planned assigned & allocated to the project are available as planned… to
the project at the right time & in the right place and are released when no longer needed.”
Management Skills
Explain
expectations.
Gather
performance
information.
Identify
performance gaps
and causes.
Implement
response and
monitor.
• In work context
• Through observation or conversation
• Lack of understanding of expectations?
• Lack of skills?
• Interference from work environment?
• Deliver training.
• Remove obstacles.
• Provide additional resources.
• Be sensitive to employees’ varying
needs for guidance.
Manage Team
Process 5
Resource Management
Chapter 9
A team member consistently misses project meetings when
the agenda does not include that team member’s work. The
organization uses a strong matrix structure. What should the
project manager do first?
A. Provide feedback to the team member’s functional head for
the performance review.
B. Ask if the team member understands the ground rules
about meeting attendance.
C. Ask colleagues for their opinion on how to handle this.
D. If this is a valued member and it is not hurting work, let it
go.
Discussion Question
Answer: B
The first step would be to understand the reason for the performance
gap and to correct possible causes. In this case, the individual may
not have understood the project manager’s expectations about
meeting attendance.
Chapter 9, Topic 5
Resource Management
Chapter 9
Communications Management
Chapter 10
“… is the process of monitoring and controlling communications throughout the entire project life
cycle to ensure the information needs of the project stakeholders are met. The key benefit of this
process is that it ensures an optimal information flow among all communication participants, at any
moment in time.
• Communication issues are the most frequent problem on a project
• Poor communication causes major problems & rework
• 90% of a PM time is spent communication
Process Process Group Key Deliverables
10.1 Plan Communications Management Planning Communications Management Plan
10.2 Manage Communications Executing Project communications
10.3 Monitor Communications Monitoring &
Control
Work performance information
Project Manager’s Role in Communications
Leader
Strong interpersonal
skills
Effective
writing and
presentation skills
Efficient
and effective
communicator
Administrative
skills
Sensitivity/respect
for others’
perspectives
Communications Management
Chapter 10
Plan Communications Management
Process 1
Key Points
 “… process how to store, maintain, distribute, retrieve & archive project information.”
 Flow of info: Internally, Externally, Vertically within org., Horizontally among peers & other projects
 Types of communications: Formal Written, Formal Verbal, Informal Written, Informal Verbal
Communications Management
Chapter 10
The Benefits of a Plan
Determining the who, what, when, why,
where, and how of communications can
avoid:
 Misinterpreted messages.
 Missed or delayed communications.
 Communications to the wrong audience.
 Sending irrelevant data.
Plan Communications Management
Process 1
Communications Management
Chapter 10
Plan Communications Management
Process 1
Key Tools
 Communications Requirement Analysis: know what stakeholders what communicated to them, when,
in what form & how often
 Communication Channels: PM needs to know how many lines of communication there are: N(N-1) / 2
 Communication Models: 1) Sender (Encoder) 2) The Message 3) The Receiver (Decoder)
 Noise/Factors of message interpretation: Receiver’s education, experience, language, culture
 Effective Communication: Nonverbal (body language), Paralingual (voice tone/sarcarsm), Words
 Effective Listening: Feedback (confirms listening, agreement/disagreement or ask for clarification)
 Communication Technology: face-to-face, phone, fax, mail, email, IM, intra/internet, security, etc
 Communication Methods: Interactive (reciprocal/2way), Push (1way/no fdbk), Pull (central/retrieve)
 Meetings: Pros/brings team mbrs/stakeholders together, Con/can be inefficient
Communications Management
Chapter 10
Communication Channels
The number of potential two-way interactions that can occur
between stakeholders.
 Indicate complexity of communication on a project
 More stakeholders = more lines of communication
n (n – 1)
2
Communication
Channels
=
Plan Communications Management
Process 1
Communications Management
Chapter 10
How many communication channels:
Example: 12 project stakeholders
n (n – 1)
2
Communication
Channels
=
12 ( 12 – 1) 12 × 11 132
2 2 2
= = = 66 channels
Communications Management
Chapter 10
Plan Communications Management
Process 1
A project manager has 15 stakeholders
assigned to his project. How many
communication channels would this project
have?
Discussion Question
Answer: 120 total communication channels.
Remember to include the project manager in
your count.
Chapter 10, Topic 1
16 ( 16 – 1) 16 × 15 240
2 2 2
= = = 120 channels
Communication Media
 Documents
 Worksheets (spreadsheets)
 Slide shows
 Emails
 Instant messaging/texting
 Phone calls/voice mails
 Conference calls
 Videoconferences
 Interactive virtual classrooms
 Websites
 Intranet upload/
download sites
 Meetings
Plan Communications Management
Process 1
Communications Management
Chapter 10
Communication Model
Transmit Message
Acknowledge Message
SENDER
RECEIVER
Feedback Message
Encode Decode
EncodeDecode
Noise
Noise
Noise
*Revise and Retransmit as Needed
Plan Communications Management
Process 1
Communications Management
Chapter 10
Communication Methods
• Pushed from the sender to the receiver(s)
• No acknowledgment or feedback stepsPush
• Pulls information in from other parties or sources
• Repositories of information accessed on demand
• Creator of information receives no feedback
Pull
• Two-way conversations that involve transmission,
acknowledgment, and feedback
• Promote common understanding
Interactive
Communications Management
Chapter 10
Plan Communications Management
Process 1
Communication Methods
• Project Management Plans, Charter, Reports, Minutes
• Legal document, contract, blueprints, specs
• Communication to your sponsor/customer/client
Formal Written
• Emails, Memos, Texts
• Communication to your team members/project staff
Informal Written
• Presentation, speeches or prepared talks ref. the project
• Team meetings, Team member conversations
Formal Verbal
Informal Verbal
Communications Management
Chapter 10
Plan Communications Management
Process 1
Manage Communications
Process 2
Key Points
 “… process gathers, provides & makes sure information is flowing back & forth as per the
Communications Plan.”
 PM sends information, ensures it’s received, effective & provides stakeholders ability to clarify and/or
request additional information
 Performance reporting: Status, Progress, Trend, Forecasting, Variance, Earned Value, Lessons Learned
Communications Management
Chapter 10
Project Reporting
 The project manager collects work performance data at regular intervals.
 The team analyzes the data against baselines. At this point, the data becomes
work performance information.
 The project manager ensures that the right people receive the right
information in the form of work performance reports.
“The act of collecting and distributing project information”;
can include status reports, progress measurements, and
forecasts.
Communications Management
Chapter 10
Manage Communications
Process 2
As project manager, every week you prepare a
report summarizing project progress and
forecasts. What type of communication is this?
A. Work performance information
B. Work performance data
C. Status report
D. Variance report
Discussion Questions
Answer: C
A status report is a regularly occurring snapshot of
project status at one point in time. Work performance
information is correct (since status reports are a type of
work performance information), but status report is a
better answer. Chapter 10, Topic 2
Monitor Communications
Process 3
Key Points
 “… process determines that communications are meeting the stakeholders needs, if not than identify the
break down and respond and adjust if necessary.”
 PM Soft Skills – ASK stakeholders for feedback
 Work performance data becomes information used for Status / Progress Reports
 Issue Log – tracks & communicates areas of confusion, disagreement, conflict & concern that require the
PM’s attention & ability to resolve issues proactively to prevent problems & change requests
Communications Management
Chapter 10
Communications Management
Chapter 10
CAPM Exam Prep
Group Exercise & Quiz 4

More Related Content

What's hot

A Day of the Life of a Project Manager
A Day of the Life of a Project ManagerA Day of the Life of a Project Manager
A Day of the Life of a Project Managerreeza fazily
 
Introduction to project management framework v2
Introduction to project management framework v2Introduction to project management framework v2
Introduction to project management framework v2Qussay Karam
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 
Risk management plan loren schwappach
Risk management plan   loren schwappachRisk management plan   loren schwappach
Risk management plan loren schwappachLoren Schwappach
 
Top Five Ideas for Project Management
Top Five Ideas for Project ManagementTop Five Ideas for Project Management
Top Five Ideas for Project ManagementJohn Goodpasture
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideasAhmad Hamid
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project ManagementRobbi Palacios
 
Why do projects fail - the project execution maturity model - basic collabor...
Why do projects fail  - the project execution maturity model - basic collabor...Why do projects fail  - the project execution maturity model - basic collabor...
Why do projects fail - the project execution maturity model - basic collabor...Pinnacle Strategies
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...GlobalSkillup
 
How to Start a Project
How to Start a ProjectHow to Start a Project
How to Start a ProjectCraig Brown
 
Project Management Silibus
Project Management SilibusProject Management Silibus
Project Management SilibusIzah Asmadi
 
Issue Management Plan
Issue Management PlanIssue Management Plan
Issue Management Plankudospower
 
Project Management 101 Briefing
Project Management 101 BriefingProject Management 101 Briefing
Project Management 101 BriefingBen Blanquera
 

What's hot (20)

Project management
Project managementProject management
Project management
 
A Day of the Life of a Project Manager
A Day of the Life of a Project ManagerA Day of the Life of a Project Manager
A Day of the Life of a Project Manager
 
Introduction to project management framework v2
Introduction to project management framework v2Introduction to project management framework v2
Introduction to project management framework v2
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Presentation on Project Risk Management
Presentation on Project Risk ManagementPresentation on Project Risk Management
Presentation on Project Risk Management
 
Risk management plan loren schwappach
Risk management plan   loren schwappachRisk management plan   loren schwappach
Risk management plan loren schwappach
 
CCP_SEC5_ Project Management
CCP_SEC5_ Project ManagementCCP_SEC5_ Project Management
CCP_SEC5_ Project Management
 
Top Five Ideas for Project Management
Top Five Ideas for Project ManagementTop Five Ideas for Project Management
Top Five Ideas for Project Management
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideas
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project Management
 
Why do projects fail - the project execution maturity model - basic collabor...
Why do projects fail  - the project execution maturity model - basic collabor...Why do projects fail  - the project execution maturity model - basic collabor...
Why do projects fail - the project execution maturity model - basic collabor...
 
PMP_Project Human Resources Management
PMP_Project Human Resources ManagementPMP_Project Human Resources Management
PMP_Project Human Resources Management
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...
 
How to Start a Project
How to Start a ProjectHow to Start a Project
How to Start a Project
 
Project Management Silibus
Project Management SilibusProject Management Silibus
Project Management Silibus
 
Issue Management Plan
Issue Management PlanIssue Management Plan
Issue Management Plan
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Project Management 101 Briefing
Project Management 101 BriefingProject Management 101 Briefing
Project Management 101 Briefing
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
 

Similar to PMP Chapter 9 Resource Management

HRM in PM (1).pptx
HRM in PM (1).pptxHRM in PM (1).pptx
HRM in PM (1).pptxumairshams6
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
2.09 hr management 1
2.09 hr management 12.09 hr management 1
2.09 hr management 1reddvise
 
Human resource managment.pptx
Human resource managment.pptxHuman resource managment.pptx
Human resource managment.pptxBetshaTizazu1
 
High_performance_team.pdf
High_performance_team.pdfHigh_performance_team.pdf
High_performance_team.pdfDeepikaTalawar
 
Project Human Resources Management.ppt
Project Human Resources Management.pptProject Human Resources Management.ppt
Project Human Resources Management.pptMUST
 
Pm0013 – managing human resources in projects
Pm0013 – managing human resources in projectsPm0013 – managing human resources in projects
Pm0013 – managing human resources in projectssmumbahelp
 
Chapter-5-implementation.pptx
Chapter-5-implementation.pptxChapter-5-implementation.pptx
Chapter-5-implementation.pptxdaniel627905
 
Module 2 - Employee Development.pptx
Module 2 - Employee Development.pptxModule 2 - Employee Development.pptx
Module 2 - Employee Development.pptxPadmasriMishra
 
Human Resource Management
Human Resource ManagementHuman Resource Management
Human Resource ManagementSanjay Rajpoot
 
InstructionsPart 6 Team Development PlanFor the project sel
InstructionsPart 6 Team Development PlanFor the project selInstructionsPart 6 Team Development PlanFor the project sel
InstructionsPart 6 Team Development PlanFor the project selTatianaMajor22
 
Project Human Resource Management.pptx
Project Human Resource Management.pptxProject Human Resource Management.pptx
Project Human Resource Management.pptxIkram192675
 
The 5 Critical Elements to Creating a Project Management Center of Excellence
The 5 Critical Elements to Creating a Project Management Center of ExcellenceThe 5 Critical Elements to Creating a Project Management Center of Excellence
The 5 Critical Elements to Creating a Project Management Center of ExcellenceFlevy.com Best Practices
 
project human resource managment
project human resource managmentproject human resource managment
project human resource managmentAroosa Chodhary
 

Similar to PMP Chapter 9 Resource Management (20)

CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 
HRM in PM (1).pptx
HRM in PM (1).pptxHRM in PM (1).pptx
HRM in PM (1).pptx
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
2.09 hr management 1
2.09 hr management 12.09 hr management 1
2.09 hr management 1
 
9 human resource PMBOK
9 human resource PMBOK9 human resource PMBOK
9 human resource PMBOK
 
Human resource managment.pptx
Human resource managment.pptxHuman resource managment.pptx
Human resource managment.pptx
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
High_performance_team.pdf
High_performance_team.pdfHigh_performance_team.pdf
High_performance_team.pdf
 
Project Human Resources Management.ppt
Project Human Resources Management.pptProject Human Resources Management.ppt
Project Human Resources Management.ppt
 
I, manager
I, manager I, manager
I, manager
 
Pm0013 – managing human resources in projects
Pm0013 – managing human resources in projectsPm0013 – managing human resources in projects
Pm0013 – managing human resources in projects
 
Chapter-5-implementation.pptx
Chapter-5-implementation.pptxChapter-5-implementation.pptx
Chapter-5-implementation.pptx
 
Module 2 - Employee Development.pptx
Module 2 - Employee Development.pptxModule 2 - Employee Development.pptx
Module 2 - Employee Development.pptx
 
Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp hr chapter 9
 
Human Resource Management
Human Resource ManagementHuman Resource Management
Human Resource Management
 
W frec04
W frec04W frec04
W frec04
 
InstructionsPart 6 Team Development PlanFor the project sel
InstructionsPart 6 Team Development PlanFor the project selInstructionsPart 6 Team Development PlanFor the project sel
InstructionsPart 6 Team Development PlanFor the project sel
 
Project Human Resource Management.pptx
Project Human Resource Management.pptxProject Human Resource Management.pptx
Project Human Resource Management.pptx
 
The 5 Critical Elements to Creating a Project Management Center of Excellence
The 5 Critical Elements to Creating a Project Management Center of ExcellenceThe 5 Critical Elements to Creating a Project Management Center of Excellence
The 5 Critical Elements to Creating a Project Management Center of Excellence
 
project human resource managment
project human resource managmentproject human resource managment
project human resource managment
 

More from Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

More from Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8
 
CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7
 
CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6
 

Recently uploaded

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Science lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonScience lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonJericReyAuditor
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 

Recently uploaded (20)

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Science lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonScience lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lesson
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 

PMP Chapter 9 Resource Management

  • 1. Project Management Professional PMP® Exam Prep – Week 4 Resource Management Prof. Muzette Charles, PMP | mcharles2@pace.edu
  • 2. Resource Management Chapter 9 “… is the process that organize, manage & lead the project team.” • Project Team is comprised of the people assigned roles & responsibilities to complete the project • Project team members may have varied skill sets, FT or PT, added or removed from team • Team members participating in Planning adds Expertise & Strengthens commitment to project • Team members are also called the “Project Staff” Process Process Group Key Deliverables 9.1 Plan Resource Management Planning Resource Management Plan 9.2 Estimate Activity Resources Planning Resource Requirements 9.3 Acquire Resources Executing Resource Calendars 9.4 Develop Team Executing Team performance assessments 9.5 Manage Team Executing Change Requests 9.6 Control Resources Monitoring & Controlling Work Performance Information
  • 3. Resource management often intersects with other project management processes. Create WBS helps define project staffing needs. Estimate Activity Durations and Costs may depend on the ability to acquire staff with the right knowledge to complete the work. Manage Stakeholder Engagement may require resolving conflicts between stakeholders and team members. Control Quality may be affected by team capabilities and motivation. Resource Management Chapter 9
  • 4. Resource Management Chapter 9 Plan Resource Management Process 1 Key Points  “… process of identifying & documenting project roles, responsibilities, required skills, reporting rlnships & creating a staffing management plan.”  Tools – Org Charts: Responsibility Assignment Matrix (RAM) - RACI Chart, OBS, RBS, Text  Resource Mgmt Plan: Staffing Mgmt Plan – acquisition, resource calendars, release plan (roll off), training needs, rewards, compliance, safety
  • 5. Resource Management Chapter 9 Plan Resource Management Process 1
  • 6. Resource Management Chapter 9 Plan Resource Management Process 1 Organizational Chart Examples Organizational Breakdown Structure (OBS) Chart Key to understanding organizational reporting lines and project manager’s authority
  • 7. Resource Management Chapter 9 Plan Resource Management Process 1 Organizational Chart Examples Resource Breakdown Structure (RBS) Chart Hierarchical depiction of resources, including human resources 0. New Anti-Scarring Product Project Resources 3. Equipment2. People1. Materials 2.1 Preclinical 2.2 Clinical 2.3 Formulation 2.4 Facility Construction 2.5 Regulatory Affairs 2.6 Marketing 2.4.1 Building Design 2.4.2 Mechanicals 2.4.3 Construction 2.4.2.1 Design 2.4.2.2 Mechanical Engineering 2.4.2.3 Testing 2.4.2.2.1 Lead ME 2.4.2.2.2 Mech Specialist 2.4.2.2.3 Mech Asst
  • 8. Resource Management Chapter 9 Plan Resource Management Process 1 Organizational Chart Examples RACI Chart • Only one individual can be accountable for each activity. • In some organizations, it is not a good practice to have the same person be both responsible and accountable. R = Responsible for performing A = Accountable; review and approve C = Consult and advise I = Inform of status
  • 9. Resource Management Chapter 9 Plan Resource Management Process 1 Motivational Theories McGregor’s Theory X & Y  Theory X Managers  Workers are not inherently motivated  Coercion and direction  Theory Y Managers  Workers seek responsibility and power to solve problems  Leadership, empowerment, and influence.
  • 10. Resource Management Chapter 9 Plan Resource Management Process 1 Motivational Theories Maslow’s Hierarchy of Needs Self-actualization Self-esteem and respect for others Belonging Safety and security Physical needsSet reasonable schedule and hours Define expectations/rewards Support membership in the team Empower, train and reward Delegate
  • 11. A project manager relies heavily on team social events to motivate members. One highly experienced member does not enjoy the events. What should the project manager do? A. Leave the member alone. B. Talk to the member about his/her needs and wants. C. Ask another team member to draw the reluctant member into more enthusiastic participation. D. Explain that lack of participation may negatively affect the member’s career. Discussion Question Answer: B The project manager should make an effort to find out what types of rewards this team member values and then find a way to deliver those rewards when appropriate. Chapter 9, Topic 1
  • 12. Resource Management Chapter 9 Plan Resource Management Process 1 Motivational Theories McClelland’s Three Needs Theory  Structure project work to reward each type through opportunities to challenge oneself, share with others, or compete with others. Achievement Affiliation Power
  • 13. You cannot create motivation by ensuring job satisfaction. Motivation creates satisfaction. Work conditions create dissatisfaction. Pay, security, schedule, work relationships, supervisor style Challenge, independence, creativity, opportunities Plan Resource Management Process 1 Resource Management Chapter 9 Motivational Theories Herzberg’s Motivation-Hygiene Theory
  • 14.  Legitimate Power: from position  Reward Power: ability to control budget, career, pay  Expert Power: knowledge and experience  Referent Power: personality  Coercive Power: demand and punish How do project managers lead? Plan Resource Management Process 1 Resource Management Chapter 9 Management Skills Project Manager Power
  • 15. A project manager has formed a harmonious team by cultivating comfortable, personal ties to each of the team members. What type of power is this project manager using? A. Legitimate B. Reward C. Expert D. Referent Discussion Question Answer: D The project manager is relying on his or her personality to create bonds. Over-reliance on one source of power may not be sufficient over time and under stressful conditions. Chapter 9, Topic 1
  • 16. Roles and responsibilities • Function to be performed • Authority • Responsibility • Required competencies Project organizational charts • Graphic visualization of reporting lines Project team resource management • Time-phased • Staff acquisition, duration, and release • Resource calendars • Training needs for individuals • Team-building and reward strategies Resource Management Chapter 9 Plan Resource Management Process 1 Resource Management Plan
  • 17. Resource Management Chapter 9 Estimate Activity Resources Process 2 Key Points  “Estimates type & quantities of material, human resources, equipment or supplies required to perform each activity”  Every activity has to have a resource assigned to it: Person, Equipment, Material  Bottom-up estimating: estimate each activity, work package, control account rolled into overall project estimate  Activity resource requirements: details which resources are assigned to each activity  Closely coordinated with Estimate Costs in Cost Management
  • 18. Resource Management Chapter 9Acquire Resources Process 3 Key Points  “… process of confirming human resource availability & obtaining team necessary to complete project activities.”  Resource Calendars - displays both 1) time resource is Assigned & 2) time resource is Available  “Great PM will invite new team members to review their part of the project for changes before they start their work.  Tools:  Pre-Assignment (guaranteed resources not negotiated)  Negotiation (for resources that don’t report to the PM)  Acquisition - Going outside of the company to staff team  Virtual Teams – Pro/Team mbrs can be the best worldwide, Con/Communication challenges  Multi-criteria DM – Team mbrs selected by weighted scores on Cost, Experience, Location, Skill Set, Training, etc  Halo Effect - Assigning a person to a position bc they’re an expert in their field, but not qualified in this position
  • 19. Multi-Criteria Decision Analysis  Decision matrix used as a rational, analytical staff selection tool  Criteria are defined and weighted  Candidates are scored against the criteria Acquire Resources Process 3 Resource Management Chapter 9
  • 20. Virtual Teams  May be a reality in any organization; likely to be a reality in a global organization  Potential for cost savings and access to larger, high-quality pool of talent  Greater diversity  More difficult to build a smoothly functioning team  Communication hurt by lack of face-to-face contact  Conflicts may be unrecognized and unresolved Acquire Resources Process 3 Resource Management Chapter 9
  • 21. What are some techniques that project managers can use to manage the potential negatives of virtual teams and enhance their benefits? Discussion Question Answers: Could include finding budget for some face-to-face meetings, including opportunities for getting to know team members as individuals during virtual meetings and opportunities to learn about other cultures in the organization, and two techniques that will be talked about in the next topic: ground rules and colocation.Chapter 9, Topic 3
  • 22. Resource Management Chapter 9Develop Team Process 4 Key Points  “… process of improving competencies, team member interaction & overall team environment to enhance project performance.”  Make sure team is motivated, well managed to reduce turnover & keep team moving toward goal of satisfactory project completion Tools  Interpersonal (Soft) Skills: Leadership, Team Building, Motivation, Communication, Influencing, Political/Cultural Awareness, Negotiation, Decision Making, Trust Building  Team Building Activities: Forming, Storming, Norming, Performing, Adjourning  Co-Location aka War Room: Improves communication when all team mbrs (especially Virtual Mbrs) can come together to review project assignments
  • 23. Create a Positive Work Environment GroundRules •Expectations regarding acceptable behavior •Shared values •Clear procedures Colocation •Physically locating team members in the same place to improve communication and productivity •Creates tighter team Develop Team Process 4 Resource Management Chapter 9
  • 24. Tuckman Team Development Model  Common stages of team formation  Can be used to assess team state or anticipate issues Forming • Independence • Little sharing Storming • More conflict, challenges to authority Norming • Increased acceptance • Beginning of cooperation and trust Performing • Well organized • Interdependence Adjourning • Lessons learned Develop Team Process 4 Resource Management Chapter 9
  • 25. Team members perform their tasks independently and are not interested in comparing approaches. What stage of team formation does this behavior illustrate? A. Forming B. Storming C. Norming D. Performing Discussion Question Answer: A This type of guarded behavior is typical of forming, which can be observed in newly formed teams or established teams when new members are added. Chapter 9, Topic 4
  • 26. Recognition and Rewards  Recognition—acknowledging the efforts of a group or individual, ideally in public  Rewards—tangible or intangible gifts; if monetary, sufficient to motivate without being too costly These strategies are more effective when they are:  Planned and thoughtful rather than “ad hoc.”  Implemented throughout the project & not when they are needed most to motivate the team. Ensure that all recognition and rewards align with organizational policies and workplace cultures. Develop Team Process 4 Resource Management Chapter 9
  • 27. Resource Management Chapter 9 Manage Team Process 5 Key Points  “… process of tracking team member performance, providing feedback, resolving issues & managing changes to optimize project performance.”  7 Conflict Sources: Schedules, Project priorities, Resources, Technical differences, Admin procedures, Cost, Personality  Conflict Mgmt Tools:  Collaborating (Problem Solving) – meetings to gain consensus on multiple difference of viewpoints … win-win situation  Compromising (Reconciling) – find solutions to bring some degree of satisfaction … lose-lose situation  Smoothing (Accommodating) – temporary solution, gives ppl space & time to step back  Forcing (Directing) – pushing 1 viewpoint at the expense of another … win-lose situation  Withdrawal (Avoidance) – counterproductive, problem is not resolved, project suffers, ppl are angry…. walk away
  • 28. Leadership Skills Interpersonal skills • Understand others and be respectful. • Influence and persuade. • Build trust and a supportive team atmosphere. Group facilitation skills • Encourage team to engage in independent problem solving. Conflict resolution • Use when issues arise among team members. Manage Team Process 5 Resource Management Chapter 9
  • 29. Resource Management Chapter 9 Control Resources Process 6 Key Points  “…process to ensure that the physical resources planned assigned & allocated to the project are available as planned… to the project at the right time & in the right place and are released when no longer needed.”
  • 30. Management Skills Explain expectations. Gather performance information. Identify performance gaps and causes. Implement response and monitor. • In work context • Through observation or conversation • Lack of understanding of expectations? • Lack of skills? • Interference from work environment? • Deliver training. • Remove obstacles. • Provide additional resources. • Be sensitive to employees’ varying needs for guidance. Manage Team Process 5 Resource Management Chapter 9
  • 31. A team member consistently misses project meetings when the agenda does not include that team member’s work. The organization uses a strong matrix structure. What should the project manager do first? A. Provide feedback to the team member’s functional head for the performance review. B. Ask if the team member understands the ground rules about meeting attendance. C. Ask colleagues for their opinion on how to handle this. D. If this is a valued member and it is not hurting work, let it go. Discussion Question Answer: B The first step would be to understand the reason for the performance gap and to correct possible causes. In this case, the individual may not have understood the project manager’s expectations about meeting attendance. Chapter 9, Topic 5
  • 33. Communications Management Chapter 10 “… is the process of monitoring and controlling communications throughout the entire project life cycle to ensure the information needs of the project stakeholders are met. The key benefit of this process is that it ensures an optimal information flow among all communication participants, at any moment in time. • Communication issues are the most frequent problem on a project • Poor communication causes major problems & rework • 90% of a PM time is spent communication Process Process Group Key Deliverables 10.1 Plan Communications Management Planning Communications Management Plan 10.2 Manage Communications Executing Project communications 10.3 Monitor Communications Monitoring & Control Work performance information
  • 34. Project Manager’s Role in Communications Leader Strong interpersonal skills Effective writing and presentation skills Efficient and effective communicator Administrative skills Sensitivity/respect for others’ perspectives Communications Management Chapter 10
  • 35. Plan Communications Management Process 1 Key Points  “… process how to store, maintain, distribute, retrieve & archive project information.”  Flow of info: Internally, Externally, Vertically within org., Horizontally among peers & other projects  Types of communications: Formal Written, Formal Verbal, Informal Written, Informal Verbal Communications Management Chapter 10
  • 36. The Benefits of a Plan Determining the who, what, when, why, where, and how of communications can avoid:  Misinterpreted messages.  Missed or delayed communications.  Communications to the wrong audience.  Sending irrelevant data. Plan Communications Management Process 1 Communications Management Chapter 10
  • 37. Plan Communications Management Process 1 Key Tools  Communications Requirement Analysis: know what stakeholders what communicated to them, when, in what form & how often  Communication Channels: PM needs to know how many lines of communication there are: N(N-1) / 2  Communication Models: 1) Sender (Encoder) 2) The Message 3) The Receiver (Decoder)  Noise/Factors of message interpretation: Receiver’s education, experience, language, culture  Effective Communication: Nonverbal (body language), Paralingual (voice tone/sarcarsm), Words  Effective Listening: Feedback (confirms listening, agreement/disagreement or ask for clarification)  Communication Technology: face-to-face, phone, fax, mail, email, IM, intra/internet, security, etc  Communication Methods: Interactive (reciprocal/2way), Push (1way/no fdbk), Pull (central/retrieve)  Meetings: Pros/brings team mbrs/stakeholders together, Con/can be inefficient Communications Management Chapter 10
  • 38. Communication Channels The number of potential two-way interactions that can occur between stakeholders.  Indicate complexity of communication on a project  More stakeholders = more lines of communication n (n – 1) 2 Communication Channels = Plan Communications Management Process 1 Communications Management Chapter 10
  • 39. How many communication channels: Example: 12 project stakeholders n (n – 1) 2 Communication Channels = 12 ( 12 – 1) 12 × 11 132 2 2 2 = = = 66 channels Communications Management Chapter 10 Plan Communications Management Process 1
  • 40. A project manager has 15 stakeholders assigned to his project. How many communication channels would this project have? Discussion Question Answer: 120 total communication channels. Remember to include the project manager in your count. Chapter 10, Topic 1 16 ( 16 – 1) 16 × 15 240 2 2 2 = = = 120 channels
  • 41. Communication Media  Documents  Worksheets (spreadsheets)  Slide shows  Emails  Instant messaging/texting  Phone calls/voice mails  Conference calls  Videoconferences  Interactive virtual classrooms  Websites  Intranet upload/ download sites  Meetings Plan Communications Management Process 1 Communications Management Chapter 10
  • 42. Communication Model Transmit Message Acknowledge Message SENDER RECEIVER Feedback Message Encode Decode EncodeDecode Noise Noise Noise *Revise and Retransmit as Needed Plan Communications Management Process 1 Communications Management Chapter 10
  • 43. Communication Methods • Pushed from the sender to the receiver(s) • No acknowledgment or feedback stepsPush • Pulls information in from other parties or sources • Repositories of information accessed on demand • Creator of information receives no feedback Pull • Two-way conversations that involve transmission, acknowledgment, and feedback • Promote common understanding Interactive Communications Management Chapter 10 Plan Communications Management Process 1
  • 44. Communication Methods • Project Management Plans, Charter, Reports, Minutes • Legal document, contract, blueprints, specs • Communication to your sponsor/customer/client Formal Written • Emails, Memos, Texts • Communication to your team members/project staff Informal Written • Presentation, speeches or prepared talks ref. the project • Team meetings, Team member conversations Formal Verbal Informal Verbal Communications Management Chapter 10 Plan Communications Management Process 1
  • 45. Manage Communications Process 2 Key Points  “… process gathers, provides & makes sure information is flowing back & forth as per the Communications Plan.”  PM sends information, ensures it’s received, effective & provides stakeholders ability to clarify and/or request additional information  Performance reporting: Status, Progress, Trend, Forecasting, Variance, Earned Value, Lessons Learned Communications Management Chapter 10
  • 46. Project Reporting  The project manager collects work performance data at regular intervals.  The team analyzes the data against baselines. At this point, the data becomes work performance information.  The project manager ensures that the right people receive the right information in the form of work performance reports. “The act of collecting and distributing project information”; can include status reports, progress measurements, and forecasts. Communications Management Chapter 10 Manage Communications Process 2
  • 47. As project manager, every week you prepare a report summarizing project progress and forecasts. What type of communication is this? A. Work performance information B. Work performance data C. Status report D. Variance report Discussion Questions Answer: C A status report is a regularly occurring snapshot of project status at one point in time. Work performance information is correct (since status reports are a type of work performance information), but status report is a better answer. Chapter 10, Topic 2
  • 48. Monitor Communications Process 3 Key Points  “… process determines that communications are meeting the stakeholders needs, if not than identify the break down and respond and adjust if necessary.”  PM Soft Skills – ASK stakeholders for feedback  Work performance data becomes information used for Status / Progress Reports  Issue Log – tracks & communicates areas of confusion, disagreement, conflict & concern that require the PM’s attention & ability to resolve issues proactively to prevent problems & change requests Communications Management Chapter 10
  • 50. CAPM Exam Prep Group Exercise & Quiz 4