SlideShare a Scribd company logo
1 of 7
Download to read offline
Chapter 6 – TIME Management
GSN Notes- 6 Time Page 1 of 7
Project Time Management - processes required to ensure timely completion of the project
Activity Definition – defines activities that must take place to produce project deliverables
Activity – consumes time (eg testing)
Events – specified accomplishment / does not consume time (eg tested)
Time Management – In small projects Activity Definition, Sequencing, Resource Estimation,
Duration Estimation and Schedule development are so tightly linked that they are viewed as
single process.
Schedule Management Plan – Development of Schedule Management Plan is part of Develop
Project Management Plan Process. SMP is a subsidiary plan of PMP and may formal or informal,
highly detailed or broadly framed depending on the project.
Decomposition (TT used in Activity Definition)
Involves sub dividing the Work Packages into smaller components called activities.
Activity Definition output is schedule activities not Deliverables (Create WBS output is
Deliverables)
Activity list, WBS and WBS dictionary can be developed either sequentially or concurrently.
Performed by team members responsible for the work package.
Planning Component (TT used in Activity Definition)
Control Account – From management Perspective a control line is drawn in the WBS Hierarchy
levels. All the Planning components above this line belong to what is called the Control
Account. All efforts performed within a control account are documented in a control account
plan.
Planning Package – It is a WBS Component below the control account but above the work
package.
Activity List
Does not include any schedule activity that is not required as part of the project scope
It includes a activity identifier and scope of work description for each schedule activity in
sufficient detail.
It is used in schedule model and is part of PMP(Project Management Plan)
Discrete components of Project Schedule but are not components of the WBS.
Activity Attributes – Contain Activity identifier, activity Code, Activity Description, Predecessor
Activities, Successor activities, logical relationships, leads and lags, resource requirements,
imposed dates, constraints and assumptions.
Milestone – Can be mandatory or optional, it a component of PMP, included in SS and WBSD
and used in schedule model. PM can impose additional milestones.
Chapter 6 – TIME Management
GSN Notes- 6 Time Page 2 of 7
Fragment Network – Portions of project schedule network diagram are often referred to as a Sub
network or Fragment Network. Sub Network templates are useful when project has several
identical or nearly identical deliverables.
Lead and Lag – Lead allows acceleration of the successor activity, A lag direct a delay in
Successor activity.
Bottom Up Estimation (TT of Resource Estimation) – Estimation is done for lower level items and
then aggregated.
Activity Resource Estimation – Identifies type and quantities of resources required for a schedule
activity. These are aggregated to determine the estimated resources for each work package.
RBS (Resource Break Down Structure) – Output of Activity Resource Estimation process, it is a
hierarchical structure of resources by category & type.
Activity Duration Estimate – Some indication of range of possible values (2Weeks + or – 2 days)
TT for Activity Duration Estimation
1. Analogous Estimation – Using actual duration of previous similar schedule activity. It is
project level, given to PM from Management or Sponsor; it is a form of Expert Judgment.
2. Parametric Estimation – Quantity of Work * Productivity Rate - 1.Regression Analysis
(Scatter Diagram) 2.Learning Curve. Results of Parametric Estimation can become
heuristics.
3. Three Point Estimates – Most Likely, Optimistic, Pessimistic.
4. Reserve Analysis
5. Expert Judgment
Imposed Dates – Imposed dates in Scope Statement (I/P to Schedule Development Process)
restrict the start or finish date.
Schedule Network Analysis (TT for Schedule Development)
1. Critical Path Method – Calculate Project Duration, Critical path length and Float. Critical
path can have 0 or negative total float.
2. Schedule Compression – Crashing (Additional Resources) and Fast Tracking (Parallel)
3. What if Scenario – Monte Carlo Analysis
4. Resource Leveling – Applied after Critical Path Method, Keep resource usage at
constant level
5. Critical Chain Method – Uses Pessimistic resource availability, Adds duration buffers that
are non work schedule activities.
Monte Carlo Analysis – 1. Probability of Completion 2. Probability of Completion in amount of
Cost 3.Probability of activity in critical path 4. Risk
Project Schedule – Should at least include planned start date and finish date for each schedule
activity, project schedule is preliminary till resource allocations are done, which usually happens
Chapter 6 – TIME Management
GSN Notes- 6 Time Page 3 of 7
before completion of PMP. Project schedule is when presented in summary form is called as
master schedule or milestone schedule.
Time Estimate – Non-Calendar Schedule – Calendar Based
Hammock Activity – O/p of Schedule Development -> Bar Charts -> For Control and
management communication, the broader more comprehensive summary activity called
Hammock Activity is used between milestones or across multiple interdependent work
packages.
Project network diagrams. Project network diagrams are schematic displays of the project’s
activities and the logical relationships (dependencies) among them.
Coding structure. – Activities must have different attributes (as responsibility, geographic area ,…
- Used for sorting)
Critical Path Method (CPM) (ML) —calculates start and finish date for each activity & float
Graphical Evaluation and Review Technique (GERT)—allows for probabilistic treatment of both
network logic and activity duration estimates. It is a form of ADM (A Network Drawing Method)
that allows loops between activities. The easiest example is when you have an activity to design
a component and then test it.
Program Evaluation and Review Technique (PERT) (O+4ML+P/6)—uses a weighted average
duration estimate to calculate activity durations.
Project Time Management
Arrow Diagramming
Method (ADM):
PERT and CPM focuses on float duration, to determine which
activities have the least scheduling flexibility. Activity on Arrow.
Only Show finish-to-start relationship
PERT Program Evaluation and Review Technique
Emphasis on meeting schedules with flexibility on cost
Three time estimates per activity: pessimistic, most likely, and
optimistic
The probability of completing a project at or later than its
expected time is 50%
Event oriented; uses dummy; activity on arrow (AOA)
Finish-to-Start logical relationship
Time estimates appear on arrow
Critical Path Method
(CPM)
Emphasis on controlling cost and leaving the schedule flexible
One time estimate per activity
Activity oriented; uses dummy; activity on arrow
Time estimates appear on arrow
Precedence Diagram
Method (PDM)
Represents improvement to PERT and CPM by adding lag
relationships to activities
[Start to Start; Start to Finish; Finish to Start; Finish to Finish]
Work is done during activity. Arrow indicates dependancy
Activity on node; no dummy
finish-to-start is the most commonly used type of logical
relationship. Start-to-finish relationships are rarely used
GERT A network diagram drawing method that allows loops between
tasks. It is a method of sequencing (e.g. a project requires redesign
after completion of testing)
Chapter 6 – TIME Management
GSN Notes- 6 Time Page 4 of 7
Dependencies
Mandatory or Hard Often involve physical or technological limitations (based on the
nature of work being done)
Discretionary may also be called preferred logic, preferential logic, or soft logic.
Soft: desirable and customary (based on experience)
Preferential: preferred or mandated by a customer (also, need of
the project sponsor)
Defined by PM Team
External Input needed from another project or source
Critical chain is a technique that modifies the project schedule to account for limited resources.
PERT Weighted Average = (O + 4M + P)/6 standard deviation = (P - O)/6 variance = standard
deviation2 (To add standard deviations: convert to variance then add; take the square root of
the sum). Best method when you have no historical data for a similar task. Results is the 50% point
(mean).
Monte Carlo Analysis - computer simulation of project outcomes using PERT estimates; result
represented in S curve. Provides the ability to compute the probability of completing a project
on a specific day. Can also be used to assess feasibility of schedule under adverse conditions
(eg when a schedule constraint is identified)
Heuristics - rules of thumb
Critical Path – longest path (almost always have no float)
Near Critical Path – Path is close in duration to critical path, the close it is the more RISK project
has.
Variance - Plan minus Actual
Float / Slack – 1.Free 2. Total 3. Project Float. Time an activity may be delayed from its early start
without delaying the project finish date. Difference between the required end date and the
expected project completion date. A negative slack on the critical path means that the project
is behind schedule.
Free Float – Amount of time a task can be delayed without delaying the early start of its
successor
Total Float – amount of time that an activity may be delayed from early start without delaying
the project finish date
Lag – waiting time between two tasks (negative lead)
Schedule Baseline - the original, approved project schedule; should never be changed without
proper review and approval. Any approved change should be documented in writing. Should
be created at the beginning of the project and used during the project to gauge (measure)
overall project performance, not just schedule.
Chapter 6 – TIME Management
GSN Notes- 6 Time Page 5 of 7
The project Performance Measurement Baseline should generally change only in response to a
scope or deliverable change. The project performance measurement baselines should generally
change only in response to a scope or deliverable change.
Corrective action - in project time management primarily concerns expediting to ensure that
activities remain on schedule. Is anything done to bring expected future schedule performance
in line with the project plan.
Revisions are changes to the scheduled start and finish dates in the approved project schedule;
generally revised only in response to scope changes. Rebaselining may be needed to provide
realistic data to measure performance.
Scheduling and allocating resources to multiple projects may affect schedule slippage and in-
process inventory.
The most important element necessary for project control is clear requirements.
Duration Compression Methods – occurs after activity duration estimating and before finalizing
the schedule. Include crashing, fast track,
Crashing – when you are worried about time, not so much about costs.
Fast Track – resources in parallel, involve increase rework. Should fast track tasks on the critical
path (float = 0) in order to save time.
Resource Leveling – often results in a project duration that is longer than the preliminary
schedule.
Resource reallocation from non-critical to critical path activities is a common way to bring the
schedule back, or as close as possible, to the originally intended overall duration. So 1. Schedule
Can Slip 2. Cost increase
Finish to Finish - activities must finish on a specific sequence
“Start no earlier than” & “Finish no later than” – Respectively #1 and #2 most popular date
constraint in project management software.
Root Cause Analysis – used to identify the cause of the variation
Variance analysis – key element to time control. Float variance is an essential planning
component for evaluating project time performance.
Revision – category of schedule update that result in change to the project’s scheduled start or
finish dates. New target schedule should be the usual mode of schedule revision.
Schedule Management Plan – defines how schedule changes will be managed; may be formal
or informal.
Schedule Change Control System – defines procedures for changing the project schedule and
includes the documentation, tracking systems, and approval levels required for authorizing
schedule changes.
Chapter 6 – TIME Management
GSN Notes- 6 Time Page 6 of 7
Resource Planning
Tools
Responsibility Matrix Identify who does what at what time/phase of the project
Resource
Spreadsheet
Quantifies how much work is needed from each resource during each time period
Resource Gantt
Chart
Identify the periods of time (e.g. calendar date) when a particular resource is
working on a particular task
Resource Histogram
(Resource Loading
Chart)
Vertical bar chart showing the total number of resources needed during each time
period
Scheduling Tools
Networks (PERT, CPM,
PDM)
Interdependencies; how related
Barchart (Gantt) Effective progress reporting tool; no logical relationships shown between
activities
Milestone Chart Significant events; good for communicating status (used to track success)
Bar Chart (Grant Chart) – 1. Weak Planning Tools 2. Good reporting tools 3. No Dependency
Shown 4. No Resources shown
Progress Report – 50/50, 20/80, 0/100 – An Activity is considered X percent complete when it
begins and gets credit of the last 100-X percent only when it is completed.
Chapter 6 – TIME Management
GSN Notes- 6 Time Page 7 of 7
Time Questions
What is the critical path? The longest path through the network which represents the
shortest amount of time in which the project can be
completed.
What is crashing? Taking action to determine how to obtain the greatest amount
of duration compression for the least incremental cost;
generally increases cost.
What is fast tracking? Compressing the schedule by overlapping activities that would
normally be done in sequence; may result in rework and
increased risk; logical relationships are modified
How does resource leveling work? By using positive float available on non-critical paths, schedule
by smoothing or leveling peaks and valleys of resource
utilization
What is activity duration estimating? Assessing the number of work periods likely to be needed to
complete each activity
What is a dummy activity? One that consumes no time or resources; it shows only
dependency
What is slack or float? Free float? Amount of time that an activity can be delayed without
delaying project. Free float is the amount of time an activity
can be delayed without delaying the early start of the next
activity
What is lag? Required waiting time between activities

More Related Content

What's hot

Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryMichael Pink
 
Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)Anupam Kumar
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingHariasha
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1Ahmad Basim Hamza
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTùng Trần Thanh
 
PERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKINGPERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKINGAlam Nuzhathalam
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET Journal
 
4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1pmb25
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1Chris Carson
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010B Sai Prasad
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisLisa Dehner
 

What's hot (20)

Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)
 
105 project time management
105 project time management105 project time management
105 project time management
 
PERT
PERTPERT
PERT
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
SanDiegoPresentation
SanDiegoPresentationSanDiegoPresentation
SanDiegoPresentation
 
PERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKINGPERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKING
 
construction project planing
 construction project planing construction project planing
construction project planing
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project Schedule
 
4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1
 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHART
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact Analysis
 

Similar to 6 time PMBOK

TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4POOJA UDAYAN
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTùng Trần Thanh
 
L05 time management
L05 time managementL05 time management
L05 time managementAsa Chan
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 

Similar to 6 time PMBOK (20)

TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
3. project time management
3. project time management3. project time management
3. project time management
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
L05 time management
L05 time managementL05 time management
L05 time management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 

More from Waseem Siddique (11)

Waseem siddique cv
Waseem siddique cvWaseem siddique cv
Waseem siddique cv
 
5 scope
5 scope5 scope
5 scope
 
8 quality PMBOK
8 quality PMBOK8 quality PMBOK
8 quality PMBOK
 
9 human resource PMBOK
9 human resource PMBOK9 human resource PMBOK
9 human resource PMBOK
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
 
4 integration
4 integration4 integration
4 integration
 
12 procurement
12 procurement12 procurement
12 procurement
 
10 communication
10 communication10 communication
10 communication
 
11 risk management
11 risk management11 risk management
11 risk management
 
Waseem siddique Resume
Waseem siddique ResumeWaseem siddique Resume
Waseem siddique Resume
 
Waseem siddique (li)
Waseem siddique (li)Waseem siddique (li)
Waseem siddique (li)
 

Recently uploaded

Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 

Recently uploaded (17)

Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 

6 time PMBOK

  • 1. Chapter 6 – TIME Management GSN Notes- 6 Time Page 1 of 7 Project Time Management - processes required to ensure timely completion of the project Activity Definition – defines activities that must take place to produce project deliverables Activity – consumes time (eg testing) Events – specified accomplishment / does not consume time (eg tested) Time Management – In small projects Activity Definition, Sequencing, Resource Estimation, Duration Estimation and Schedule development are so tightly linked that they are viewed as single process. Schedule Management Plan – Development of Schedule Management Plan is part of Develop Project Management Plan Process. SMP is a subsidiary plan of PMP and may formal or informal, highly detailed or broadly framed depending on the project. Decomposition (TT used in Activity Definition) Involves sub dividing the Work Packages into smaller components called activities. Activity Definition output is schedule activities not Deliverables (Create WBS output is Deliverables) Activity list, WBS and WBS dictionary can be developed either sequentially or concurrently. Performed by team members responsible for the work package. Planning Component (TT used in Activity Definition) Control Account – From management Perspective a control line is drawn in the WBS Hierarchy levels. All the Planning components above this line belong to what is called the Control Account. All efforts performed within a control account are documented in a control account plan. Planning Package – It is a WBS Component below the control account but above the work package. Activity List Does not include any schedule activity that is not required as part of the project scope It includes a activity identifier and scope of work description for each schedule activity in sufficient detail. It is used in schedule model and is part of PMP(Project Management Plan) Discrete components of Project Schedule but are not components of the WBS. Activity Attributes – Contain Activity identifier, activity Code, Activity Description, Predecessor Activities, Successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints and assumptions. Milestone – Can be mandatory or optional, it a component of PMP, included in SS and WBSD and used in schedule model. PM can impose additional milestones.
  • 2. Chapter 6 – TIME Management GSN Notes- 6 Time Page 2 of 7 Fragment Network – Portions of project schedule network diagram are often referred to as a Sub network or Fragment Network. Sub Network templates are useful when project has several identical or nearly identical deliverables. Lead and Lag – Lead allows acceleration of the successor activity, A lag direct a delay in Successor activity. Bottom Up Estimation (TT of Resource Estimation) – Estimation is done for lower level items and then aggregated. Activity Resource Estimation – Identifies type and quantities of resources required for a schedule activity. These are aggregated to determine the estimated resources for each work package. RBS (Resource Break Down Structure) – Output of Activity Resource Estimation process, it is a hierarchical structure of resources by category & type. Activity Duration Estimate – Some indication of range of possible values (2Weeks + or – 2 days) TT for Activity Duration Estimation 1. Analogous Estimation – Using actual duration of previous similar schedule activity. It is project level, given to PM from Management or Sponsor; it is a form of Expert Judgment. 2. Parametric Estimation – Quantity of Work * Productivity Rate - 1.Regression Analysis (Scatter Diagram) 2.Learning Curve. Results of Parametric Estimation can become heuristics. 3. Three Point Estimates – Most Likely, Optimistic, Pessimistic. 4. Reserve Analysis 5. Expert Judgment Imposed Dates – Imposed dates in Scope Statement (I/P to Schedule Development Process) restrict the start or finish date. Schedule Network Analysis (TT for Schedule Development) 1. Critical Path Method – Calculate Project Duration, Critical path length and Float. Critical path can have 0 or negative total float. 2. Schedule Compression – Crashing (Additional Resources) and Fast Tracking (Parallel) 3. What if Scenario – Monte Carlo Analysis 4. Resource Leveling – Applied after Critical Path Method, Keep resource usage at constant level 5. Critical Chain Method – Uses Pessimistic resource availability, Adds duration buffers that are non work schedule activities. Monte Carlo Analysis – 1. Probability of Completion 2. Probability of Completion in amount of Cost 3.Probability of activity in critical path 4. Risk Project Schedule – Should at least include planned start date and finish date for each schedule activity, project schedule is preliminary till resource allocations are done, which usually happens
  • 3. Chapter 6 – TIME Management GSN Notes- 6 Time Page 3 of 7 before completion of PMP. Project schedule is when presented in summary form is called as master schedule or milestone schedule. Time Estimate – Non-Calendar Schedule – Calendar Based Hammock Activity – O/p of Schedule Development -> Bar Charts -> For Control and management communication, the broader more comprehensive summary activity called Hammock Activity is used between milestones or across multiple interdependent work packages. Project network diagrams. Project network diagrams are schematic displays of the project’s activities and the logical relationships (dependencies) among them. Coding structure. – Activities must have different attributes (as responsibility, geographic area ,… - Used for sorting) Critical Path Method (CPM) (ML) —calculates start and finish date for each activity & float Graphical Evaluation and Review Technique (GERT)—allows for probabilistic treatment of both network logic and activity duration estimates. It is a form of ADM (A Network Drawing Method) that allows loops between activities. The easiest example is when you have an activity to design a component and then test it. Program Evaluation and Review Technique (PERT) (O+4ML+P/6)—uses a weighted average duration estimate to calculate activity durations. Project Time Management Arrow Diagramming Method (ADM): PERT and CPM focuses on float duration, to determine which activities have the least scheduling flexibility. Activity on Arrow. Only Show finish-to-start relationship PERT Program Evaluation and Review Technique Emphasis on meeting schedules with flexibility on cost Three time estimates per activity: pessimistic, most likely, and optimistic The probability of completing a project at or later than its expected time is 50% Event oriented; uses dummy; activity on arrow (AOA) Finish-to-Start logical relationship Time estimates appear on arrow Critical Path Method (CPM) Emphasis on controlling cost and leaving the schedule flexible One time estimate per activity Activity oriented; uses dummy; activity on arrow Time estimates appear on arrow Precedence Diagram Method (PDM) Represents improvement to PERT and CPM by adding lag relationships to activities [Start to Start; Start to Finish; Finish to Start; Finish to Finish] Work is done during activity. Arrow indicates dependancy Activity on node; no dummy finish-to-start is the most commonly used type of logical relationship. Start-to-finish relationships are rarely used GERT A network diagram drawing method that allows loops between tasks. It is a method of sequencing (e.g. a project requires redesign after completion of testing)
  • 4. Chapter 6 – TIME Management GSN Notes- 6 Time Page 4 of 7 Dependencies Mandatory or Hard Often involve physical or technological limitations (based on the nature of work being done) Discretionary may also be called preferred logic, preferential logic, or soft logic. Soft: desirable and customary (based on experience) Preferential: preferred or mandated by a customer (also, need of the project sponsor) Defined by PM Team External Input needed from another project or source Critical chain is a technique that modifies the project schedule to account for limited resources. PERT Weighted Average = (O + 4M + P)/6 standard deviation = (P - O)/6 variance = standard deviation2 (To add standard deviations: convert to variance then add; take the square root of the sum). Best method when you have no historical data for a similar task. Results is the 50% point (mean). Monte Carlo Analysis - computer simulation of project outcomes using PERT estimates; result represented in S curve. Provides the ability to compute the probability of completing a project on a specific day. Can also be used to assess feasibility of schedule under adverse conditions (eg when a schedule constraint is identified) Heuristics - rules of thumb Critical Path – longest path (almost always have no float) Near Critical Path – Path is close in duration to critical path, the close it is the more RISK project has. Variance - Plan minus Actual Float / Slack – 1.Free 2. Total 3. Project Float. Time an activity may be delayed from its early start without delaying the project finish date. Difference between the required end date and the expected project completion date. A negative slack on the critical path means that the project is behind schedule. Free Float – Amount of time a task can be delayed without delaying the early start of its successor Total Float – amount of time that an activity may be delayed from early start without delaying the project finish date Lag – waiting time between two tasks (negative lead) Schedule Baseline - the original, approved project schedule; should never be changed without proper review and approval. Any approved change should be documented in writing. Should be created at the beginning of the project and used during the project to gauge (measure) overall project performance, not just schedule.
  • 5. Chapter 6 – TIME Management GSN Notes- 6 Time Page 5 of 7 The project Performance Measurement Baseline should generally change only in response to a scope or deliverable change. The project performance measurement baselines should generally change only in response to a scope or deliverable change. Corrective action - in project time management primarily concerns expediting to ensure that activities remain on schedule. Is anything done to bring expected future schedule performance in line with the project plan. Revisions are changes to the scheduled start and finish dates in the approved project schedule; generally revised only in response to scope changes. Rebaselining may be needed to provide realistic data to measure performance. Scheduling and allocating resources to multiple projects may affect schedule slippage and in- process inventory. The most important element necessary for project control is clear requirements. Duration Compression Methods – occurs after activity duration estimating and before finalizing the schedule. Include crashing, fast track, Crashing – when you are worried about time, not so much about costs. Fast Track – resources in parallel, involve increase rework. Should fast track tasks on the critical path (float = 0) in order to save time. Resource Leveling – often results in a project duration that is longer than the preliminary schedule. Resource reallocation from non-critical to critical path activities is a common way to bring the schedule back, or as close as possible, to the originally intended overall duration. So 1. Schedule Can Slip 2. Cost increase Finish to Finish - activities must finish on a specific sequence “Start no earlier than” & “Finish no later than” – Respectively #1 and #2 most popular date constraint in project management software. Root Cause Analysis – used to identify the cause of the variation Variance analysis – key element to time control. Float variance is an essential planning component for evaluating project time performance. Revision – category of schedule update that result in change to the project’s scheduled start or finish dates. New target schedule should be the usual mode of schedule revision. Schedule Management Plan – defines how schedule changes will be managed; may be formal or informal. Schedule Change Control System – defines procedures for changing the project schedule and includes the documentation, tracking systems, and approval levels required for authorizing schedule changes.
  • 6. Chapter 6 – TIME Management GSN Notes- 6 Time Page 6 of 7 Resource Planning Tools Responsibility Matrix Identify who does what at what time/phase of the project Resource Spreadsheet Quantifies how much work is needed from each resource during each time period Resource Gantt Chart Identify the periods of time (e.g. calendar date) when a particular resource is working on a particular task Resource Histogram (Resource Loading Chart) Vertical bar chart showing the total number of resources needed during each time period Scheduling Tools Networks (PERT, CPM, PDM) Interdependencies; how related Barchart (Gantt) Effective progress reporting tool; no logical relationships shown between activities Milestone Chart Significant events; good for communicating status (used to track success) Bar Chart (Grant Chart) – 1. Weak Planning Tools 2. Good reporting tools 3. No Dependency Shown 4. No Resources shown Progress Report – 50/50, 20/80, 0/100 – An Activity is considered X percent complete when it begins and gets credit of the last 100-X percent only when it is completed.
  • 7. Chapter 6 – TIME Management GSN Notes- 6 Time Page 7 of 7 Time Questions What is the critical path? The longest path through the network which represents the shortest amount of time in which the project can be completed. What is crashing? Taking action to determine how to obtain the greatest amount of duration compression for the least incremental cost; generally increases cost. What is fast tracking? Compressing the schedule by overlapping activities that would normally be done in sequence; may result in rework and increased risk; logical relationships are modified How does resource leveling work? By using positive float available on non-critical paths, schedule by smoothing or leveling peaks and valleys of resource utilization What is activity duration estimating? Assessing the number of work periods likely to be needed to complete each activity What is a dummy activity? One that consumes no time or resources; it shows only dependency What is slack or float? Free float? Amount of time that an activity can be delayed without delaying project. Free float is the amount of time an activity can be delayed without delaying the early start of the next activity What is lag? Required waiting time between activities