The document summarizes the construction of new football practice fields at Oregon State University from April to July 2003. Key details include excavating and grading the existing field, installing a head-head irrigation system and subsurface drains, adding a sand and organic topsoil mixture, laying sod, and completing the project on schedule by early July. The summary concludes by noting that concentrated wear occurred near the fixed goals but that the turf recovered well overall once the football season started regularly rotating drills to different areas of the fields.