SlideShare a Scribd company logo
Genaro Contreras
Geotechnical Master Plan
Company Sponsor: CVL
Group 7
3/20/2015
Spring2015
JOY RANCH HOUSING
COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
1
JOY RANCH HOUSING COMMUNITY
Table of Contents
1.0 EXECUTIVE SUMMARY.................................................................................................................2
2.0 INTRODUCTION ...........................................................................................................................2
2.1 Proposed Project.......................................................................................................................2
2.2 Site Conditions..........................................................................................................................2
3.0 SITE EXPLORATION ......................................................................................................................3
3.1 Exploratory Borings ..................................................................................................................3
32 Groundwater Table....................................................................................................................3
4.0 SOIL CHARACTERISTICS.................................................................................................................4
4.1 Test Results ..............................................................................................................................4
4.2 Strength and Capacity...............................................................................................................6
5.0 SOIL ISSUES ..................................................................................................................................7
5.1 Collapse....................................................................................................................................8
5.2 Subsidence ...............................................................................................................................8
5.3 Fissures....................................................................................................................................8
5.4 Sulfate......................................................................................................................................8
6.0 DESIGN RECOMMENDATIONS......................................................................................................8
6.1 Footings ...................................................................................................................................8
6.2 Earth Retaining Walls ...............................................................................................................8
6.3 Earthwork ................................................................................................................................8
7.0 SUSTAINABILITY ...........................................................................................................................8
8.0 CONCLUSION................................................................................................................................9
APPENDIX A: SCHMERTMANN ANALYSIS..................................................................................... 10-12
APPENDIX B: RETAINING WALL CALCULATIONS............................................................................ 13-15
APPENDIX C: BORING LOG DATA .................................................................................................16-37
APPENDIX D: PROJECT VALIDATION FORM .......................................................................................38
TEAM 7: GEOTECHNICAL MASTER PLAN
2
JOY RANCH HOUSING COMMUNITY
Figure 1: Land Use Plan
1.0 Executive Summary
An apparently square, undeveloped area is proposed as the site for a small residential
community, titled Joy Ranch Housing. This land is intended to be divided into 5 main uses:
housing, recreational, commercial, water treatment and educational. Shown below in figure 1 are
the types of land use each parcel in this site is devoted to. Due to the scarcity of information
available concerning the earth conditions thereof, a geotechnical investigation was performed to
properly analyze and evaluate the challenges that could potentially arise from land development
on this site. General site topography and groundwater depth were provided by site visitation and
the Groundwater Site Inventory of the Arizona Department of Water Resources.
Exploratory borings were performed to obtain at least 1 soil sample from each of the 14
parcels. The soil characteristics determined or extrapolated from these samplings were used to
assign or affirm effective use of each subdivision. The incorporation of numerous assumptions
became necessary, as some crucial factors would require further laboratory testing for total
accuracy. Design recommendations for structure footings and earth retaining walls were
provided according to the soil properties and the loads of the planned structures (3,101,400 lb.
for an elementary school building and 157,784 lb. for a pedestrian bridge).
2.0 Introduction:
2.1 Proposed Project: Joy Ranch Housing is a small residential community, spanning
approximately 622.86 acres and divided into 14 parcels of land. The majority of these parcels are
devoted to housing, with both high and low dwelling unit densities, with the remaining ones set
aside for the purposes of wastewater treatment, education, recreation and commercial activity.
Two collector roads intersect at a roundabout towards the northeastern quadrant of the site,
providing access to the rest of the parcels.
The performance of a geotechnical investigation fulfills the requirement of ascertaining
the suitability of the soil concerning land development.
2.2 Site Conditions: The site for Joy Ranch Housing is bound by North 7th Avenue, North
7th Street, West Joy Ranch Road and West Cloud Road, all of which are arterials. No previous
development is evident or recorded. Surrounding establishments include, located to the south,
TEAM 7: GEOTECHNICAL MASTER PLAN
3
JOY RANCH HOUSING COMMUNITY
Deer Mountain Elementary and Dove Valley Ranch, approximately two miles to the East. A
smaller fraction of the land surrounding the planned site is developed, with one story homes
lining the roads.
The topography is flat in general, with no apparent hills or earth depreciations, nor
apparent evidence of boulders or cobbles. Elevation slowly decreases from the northern to
southern half, which dictates the flow of the washes. Two major ones flow directly through the
site, one of which is the West Fork Desert Lake Wash and traverses the eastern half of the site.
Surface indicators of the location of these washes include clear lines of trees, which will
necessitate clearing and possible grubbing to make further use of the washes. Other vegetation
includes abundant shrubbery in the southwestern corner. The surrounding area is mountainous.
3.0 Site Exploration:
3.1 Borings: For the purpose of exploring various subsurface conditions throughout the
site, exploratory borings were performed by use of a 6 5/8” hollow stem auger. The locations for
these borings were selected according to the planned parcels. One boring was performed in each
smaller parcel, with two performed in larger ones, such as parcels 5 and 10, to obtain more
reliable averages for the soil characteristics pertaining to a given area. Because the depths of the
logs are approximately 6 feet, they are preliminary. Deeper ones that fall within the range of 10-
15 feet will be required to make reliable foundation recommendations for larger loads.
4.2 Groundwater: Though some moisture was present in the majority of the samples, the
groundwater table is evidently located far below the depth of any exploratory boring for the
pertinent project. Researching of the records kept by the Arizona Department of Water
4 2 1
5
7
6
10
3
11
9
14
8
13
12
Legend
= Boring Location
= ParcelNumber
Figure 2: Boring Map
TEAM 7: GEOTECHNICAL MASTER PLAN
4
JOY RANCH HOUSING COMMUNITY
Resources revealed no existing data specifically regarding the pertinent land, affirming that no
previous development has been completed nor attempted. Data from wells at various adjacent
points, monitored as recent as 2010, indicates the depth of the groundwater table to be far below
the range of the infrastructure for Joy Ranch Housing, ranging from 301.2 to 511.6 feet.
Considering this, it is highly unlikely that the groundwater table will pose any difficulties that
need to be figured into the calculations.
4.0 Soil Characteristics
4.1 Test Results: In accordance with the standards of ASTM D2937, the drive-cylinder
test was performed on samples from the boring sites. The simple measurement of sample
cylindrical masses before and after drying enabled the computation of the dry unit weights and
water contents. On the field, visual classification was performed by ASTM D2487 and ASTM
D2488 specifics, producing the descriptions included in the boring logs. Weak cementation was
an abundant characteristic, noted from most of the samples. ASTM C136 standards were
followed for the sieve analysis, showing a predominance of clayey sands, particularly within the
surface strata.
Plasticity was required to determine the quality of strength for each boring location.
ASTM D4318 procedure was followed in identifying the liquid and plastic limits, both of which
are required for the plasticity indices. The results to these are shown in tables 1 and 2. The
separation into 2 tables of data was necessitated by the availability of data for the multiple depths
at which exploratory borings were performed.
Figure 3: Map of Sample Wells
Legend
= Site Border
= Well Location
Top Number = Well Elevation
Bottom Number = Date of Data
Collection
TEAM 7: GEOTECHNICAL MASTER PLAN
5
JOY RANCH HOUSING COMMUNITY
Table 1: Laboratory Test Results
Table 2: Soil Classification and Consistency
TEAM 7: GEOTECHNICAL MASTER PLAN
6
JOY RANCH HOUSING COMMUNITY
4.2 Strength and Bearing Capacity: In determining strength and capacity characteristics
for the soils within the site, it must be acknowledged that insufficient data has been gathered
from laboratory tests to produce truly accurate quantities. This necessitates assumptions
regarding certain vital factors, based on previously established correlations and standards.
Laboratory results for soil classification were utilized when available, with visual classification
accepted as reasonable approximation for all other cases. The angle of internal friction required
already established value ranges assigned to each soil type. The value used for calculation was
selected in relation to the dry density of the soil. Cohesion was also determined using previous
data based on soil types. The bearing capacity factors were obtained from a chart constructed for
use in conjunction with two common methods for ultimate bearing pressure, and are listed below
in table 3. Furthermore, due to the extensive depth of the groundwater table and the presence of
moisture within the soil samples from the exploratory borings, soil conditions were assumed to
be unsaturated, drained and normally consolidated. The latter two conditions are acceptable for
this preliminary analysis, partially due to the lack of previous land development.
Terzhagi’s method for computing soil bearing capacity was utilized with the footing
dimensions for the different planned structures, applying the standard factor of safety of 2.5. The
results are shown in table 4.
Table 3: Bearing Capacity Factors
TEAM 7: GEOTECHNICAL MASTER PLAN
7
JOY RANCH HOUSING COMMUNITY
5.0 Soil Issues
5.1 Subsidence: While data from the site itself is currently unavailable, studies on the
greater Maricopa area from the Hydrology Division of the ADWR reveal that the site does not
fall within the areas of major subsidence, which are outlined below in figure 3.
Table 4: Bearing Capacity
Legend
= Subsidence Zone
= Major Highway
Figure 3: Subsidence Map
TEAM 7: GEOTECHNICAL MASTER PLAN
8
JOY RANCH HOUSING COMMUNITY
Because the majority of the area is composed of clayey sands, a considerable amount of
immediate settlement is expected, but consolidation is not anticipated due to the depth of the
groundwater table and overall scarcity of clays.
5.2 Collapse: Parcels 6 and 8, which are intended to serve as the locations for low density
housing and a grocery store respectably, were shown to have collapsible soil. In addition to
potentially exacerbating differential settlement, this issue may be compounded be compounded
by the area’s comparatively high flood rate, as an influx of water is one of the triggers for soil
collapse. Methods for combating this problem are explained under the design recommendations
for footings.
5.3 Fissures: Fissuring is often the result of subsidence. Because the site is not located
within any of the major subsidence zones in Maricopa County, fissuring is not a major concern.
Furthermore, data maps from the ADWR did not identify any nearby areas with a high risk of
fissuring. Though this geological hazard does not pose a problem for this particular case, it is a
common concern for geotechnical engineers. Thus, the reasons for disregarding it are
noteworthy.
5.4 Sulfate: The soil of parcel 2 was shown to have a significantly high sulfate
concentration, at 299 ppm. According to the standards from the Portland Cement Association,
this level of soluble sulfates constitutes a moderate hazard, capable of causing cracks and
disintegration on concrete constructs, including footings.
6.0 DesignRecommendations
6.1 Footings: The spread footings for the homes in both low and high density
housing developments will be square and 3 feet in width, although the soil conditions of parcel 2
necessitate a width of 4 feet to meet, or exceed, an acceptable bearing capacity of 5,000 𝑙𝑏/𝑓𝑑2
.
For parcel 6, the high concentration of soluble sulfates necessitates that any concrete slab
footings be composed of type II concrete, which is resistant to sulfate attack. A 3 foot width is
sufficient for most of the other land use types, except for the two story elementary school
building and the bridges.
A 10 foot wide continuous footing was assumed for the pedestrian bridge, which passes
the design criteria for this type of foundation, including the bearing capacity. The predicted
immediate settlement following construction is well below the allowable total settlement for
bridges, according to table 2.1 of Coduto’s text on foundations. The building from the
elementary school requires 16 spread footings, each 5 feet in width.
6.2 Earth Retaining Walls: Concrete cut-off walls will be constructed below the
pedestrian bridge along the wash between the housing development in parcel 12 and the
recreational park in parcel 10. This is primarily to prevent the issue of scour on the bridge
footings, which could prove severe in the long run, and without a deep foundation. At the least in
the short term, the level of flooding in this wash is not predicted to be high enough to pose an
issue for the adjacent housing development. Parcels 6 and 8 will also require cut-off walls along
the adjacent wash, primarily to prevent soil collapse. These walls will also be composed of type
II concrete to combat damage from soluble sulfates. The other walls will be composed of type I
concrete.
TEAM 7: GEOTECHNICAL MASTER PLAN
9
JOY RANCH HOUSING COMMUNITY
The walls themselves will be a total of 16 feet in height, with a toe of 3 feet, a stem of 1.5
feet and a heel of 7 feet. These dimensions are acceptable for the soil conditions of all the walls
due to the common backfill, which will be high quality granular soil. The soil properties will
include a unit weight of 120 𝑙𝑏/𝑓𝑑2
, a friction angle of 30 degrees and no cohesion.
6.3 Earthwork: In addition to the excavation required for the footings of the residential,
commercial and educational structures, the soil at the edge of the washes adjacent to parcels 12,
10, 6 and 8 will be removed as part of the construction of the retaining walls. This will be done
with typical excavators. Scrapers will be used to transport the removed soil, as a different
backfill will be placed behind the walls. Prior to any compaction, the soils will be moisture
conditioned to within 3% of the optimum moisture content, identified during the Proctor tests.
Compaction will increase the density of the soil to approximately 95% of the proctor test results.
7.0 Sustainability
Cells are installed underground, designed to provide additional nutrients to the surrounding soil
to sustain the health of the vegetation. These are located near the pedestrian and vehicle bridges,
and can be particularly beneficial to the recreational park and the washes, which may eventually
develop vegetation that can be maintained and increase the aesthetic appeal of the area. The cells
are provided power, at least in part, by specialized batteries that convert the vibrations of the
bridges, from passing pedestrians and vehicles, to electricity.
8.0 Conclusion
Due to a number of assumptions, limitations to this preliminary analysis include a lack of
conclusive shear strength values, the margin of error for bearing capacity and the preliminary
nature of the exploratory borings. The depth of the borings is of particular note, as it only
increases the uncertainty of the conditions under which substructures are constructed. However,
the error for the ultimate bearing capacity calculations is not significant because of the adherence
to typical soil factor values, making the computed bearing capacities reasonably accurate for the
purposes of this report. Earth conditions for the site of the proposed Joy Ranch Housing
community are concluded to be manageable for the purposes of land development, although
further testing is still required to refine the design recommendations and improve safety.
TEAM 7: GEOTECHNICAL MASTER PLAN
10
JOY RANCH HOUSING COMMUNITY
Appendix A: Schmertmann Analysis
ο‚· Footings (Elementary School Building)
o π‘ž = 8000
𝑙𝑏
𝑓𝑑2 , 𝐡 = 5 𝑓𝑑, 𝐻 = 1.5 𝑓𝑑, 𝐷 = 3.5 𝑓𝑑, 𝑃 = 194,375 𝑙𝑏
o Important Geostatic Stresses
 πœŽπ‘§π·
β€²
= (114.38
𝑙𝑏
𝑓𝑑3 ) (3.5 𝑓𝑑) = 400.33
𝑙𝑏
𝑓𝑑2
 πœŽπ‘§π‘
β€²
= (114.38
𝑙𝑏
𝑓𝑑3 )(3.5𝑓𝑑 +
5
2
𝑓𝑑) = 686.28
𝑙𝑏
𝑓 𝑑2
o Equivalent Modulus: 𝐸𝑠 = (50,000
𝑙𝑏
𝑓𝑑2 )√1 + 12,000(25
𝑙𝑏
𝑓𝑑2 ) = 350,000
𝑙𝑏
𝑓𝑑2
o Peak Influence Factor: πΌπœ–π‘ = 0.5 + 0.1√
(8,000
𝑙𝑏
𝑓𝑑2βˆ’343.14
𝑙𝑏
𝑓𝑑2)
629 .09
𝑙𝑏
𝑓𝑑2
= 0.849
o Depth, Creep and Shape Factors
 𝐢1 = 1 βˆ’ 0.5 (
(343 .14
𝑙𝑏
𝑓𝑑2 )
8,000
𝑙𝑏
𝑓𝑑2βˆ’343.14
𝑙𝑏
𝑓𝑑2
) = 0.974
 𝐢2 = 1 + log(
0.1
0.1
) = 1
 𝐢3 = 1 (value for square footings)
o Settlement: 𝛿 =
((0.978)(1)(1)(8,000
𝑙𝑏
𝑓𝑑2βˆ’343.14
𝑙𝑏
𝑓𝑑2)(0.849 +0.025)(5 𝑓𝑑))
350,000
𝑙𝑏
𝑓𝑑2
= 0.091 𝑓𝑑 =
1.09 𝑖𝑛
o Immediate settlement falls within the acceptable range of 0.5 to 2 inches.
ο‚· Footing (Pedestrian Bridge, Parcel 10)
o π‘ž = 1,014
𝑙𝑏
𝑓𝑑2 , 𝐡 = 10 𝑓𝑑, 𝐻 = 1.5 𝑓𝑑, 𝐷 = 3.5 𝑓𝑑, 𝑃 = 78,892 𝑙𝑏
5’
3.5’
2.5’
P
2’
TEAM 7: GEOTECHNICAL MASTER PLAN
11
JOY RANCH HOUSING COMMUNITY
o Important Geostatic Stresses
 πœŽπ‘§π·
β€²
= (108.4
𝑙𝑏
𝑓𝑑3 ) (3.5 𝑓𝑑) = 379.4
𝑙𝑏
𝑓𝑑2
 πœŽπ‘§π‘
β€²
= (108.4
𝑙𝑏
𝑓𝑑3 ) (3.5 𝑓𝑑) = 1,463.4
𝑙𝑏
𝑓𝑑2
o Equivalent Modulus: 𝐸𝑠 = (50,000
𝑙𝑏
𝑓𝑑2 )√1 + (12,000
𝑙𝑏
𝑓𝑑2 )(33) = 446,000
𝑙𝑏
𝑓𝑑2
o Peak Influence Factor: πΌπœ–π‘ = 0.5 + 0.1√
(1,255
𝑙𝑏
𝑓𝑑2βˆ’379.4
𝑙𝑏
𝑓𝑑2)
1,463 .4
𝑙𝑏
𝑓𝑑2
= 0.566
o Depth, Creep and Shape Factors
 𝐢1 = 1 βˆ’ 0.5 (
(379 .4
𝑙𝑏
𝑓𝑑2 )
1,255
𝑙𝑏
𝑓𝑑2βˆ’379.4
𝑙𝑏
𝑓𝑑2
) = 0.783
 𝐢2 = 1
 𝐢3 = 1.03 βˆ’ 0.3(10) = 0.73
o Settlement: 𝛿 =
(0.783)(1)(0.73)(1,255
𝑙𝑏
𝑓𝑑2 βˆ’379.4
𝑙𝑏
𝑓𝑑2)(2βˆ—0.566+0.1)(10)
446 ,000
𝑙𝑏
𝑓𝑑2
= 0.012 𝑓𝑑 =
0.15 𝑖𝑛
o Immediate settlement falls below the acceptable limit of 2 inches for bridges.
ο‚· Footing( Pedestrian Bridge, Parcel 12)
o π‘ž = 1,014
𝑙𝑏
𝑓𝑑2 , 𝐡 = 10 𝑓𝑑, 𝐻 = 1.5 𝑓𝑑, 𝐷 = 3.5 𝑓𝑑, 𝑃 = 78,892 𝑙𝑏
o Though the top soil stratum of this area is has different properties, the bottom of
the footing extends below this layer, making the simplified Schmertmann’s
analysis appropriate.
o Important Geostatic Stresses
 πœŽπ‘§π·
β€²
= (132.24
𝑙𝑏
𝑓𝑑3 ) (3.5 𝑓𝑑) = 462.84
𝑙𝑏
𝑓𝑑2
 πœŽπ‘§π‘
β€²
= (132.24
𝑙𝑏
𝑓𝑑3 )(3.5𝑓𝑑 + 10𝑓𝑑) = 1,785.24
𝑙𝑏
𝑓𝑑2
o Equivalent Modulus: 𝐸𝑠 = (50,000
𝑙𝑏
𝑓𝑑2 )√1 + (12,000
𝑙𝑏
𝑓𝑑2 )(53) = 686,000
𝑙𝑏
𝑓𝑑2
o Peak Influence Factor: πΌπœ–π‘ = 0.5 + 0.1√
(1,014
𝑙𝑏
𝑓𝑑2βˆ’462.84
𝑙𝑏
𝑓𝑑2)
1,785.24
𝑙𝑏
𝑓𝑑2
= 0.556
o Depth, Creep and Shape Factors
 𝐢1 = 1 βˆ’ 0.5 (
(462 .84
𝑙𝑏
𝑓𝑑2 )
1,014
𝑙𝑏
𝑓𝑑2βˆ’462.84
𝑙𝑏
𝑓𝑑2
) = 0.580
 𝐢2 = 1
 𝐢3 = 1.03 βˆ’ 0.3(10) = 0.73
TEAM 7: GEOTECHNICAL MASTER PLAN
12
JOY RANCH HOUSING COMMUNITY
o Settlement: 𝛿 =
(0.580)(1)(0.73)(1,014
𝑙𝑏
𝑓𝑑2 βˆ’462 .84
𝑙𝑏
𝑓𝑑2)(2βˆ—0.556+0.1)(10 𝑓𝑑)
686,000
𝑙𝑏
𝑓𝑑2
= 0.006 𝑓𝑑 =
0.068 𝑖𝑛
o Immediate settlement falls below the acceptable limit of 2 inches for bridges.
TEAM 7: GEOTECHNICAL MASTER PLAN
13
JOY RANCH HOUSING COMMUNITY
Appendix B: Retaining Wall Calculations
ο‚· Cantilever Cut-Off Wall
o The following calculations are applicable to all of the planned retaining walls.
o 𝐻 𝑀 = 14 𝑓𝑑, π΅β„Žπ‘’π‘’π‘™ = 7 𝑓𝑑, π΅π‘‘π‘œπ‘’ = 3 𝑓𝑑, π΅π‘ π‘‘π‘’π‘š = 1.5 𝑓𝑑, π‘’π‘šπ‘π‘’π‘‘π‘šπ‘’π‘›π‘‘ =
0.5 𝑓𝑑, 𝐻 = 16 𝑓𝑑, 𝛾 = 120
𝑙𝑏
𝑓𝑑3 , 𝑐 = 0
𝑙𝑏
𝑓𝑑2 , πœ™ = 30Β°, 𝛽 = 3Β°, πœ‡ = 0.45
o Sliding
 Coefficient of Lateral Earth Pressure: πΎπ‘Ž =
(cos(3)βˆ’βˆšcos2(3)βˆ’cos2(32))
cos(3)+√cos2(3)βˆ’cos2(32)
=
0.322
 Soil Load on Wall (per unit length):
𝑃 π‘Ž
𝑏
=
(
(132 .24
𝑙𝑏
𝑓𝑑3 )(17𝑓𝑑)2(0.322)
2
)cos(3) = 5,141
𝑙𝑏
𝑓𝑑
 Soil Load (per unit length):
𝑃
𝑏
= 0.5 βˆ— (6𝑓𝑑)(1𝑓𝑑 + 2 βˆ— 14𝑓𝑑 +
6 tan(3) 𝑓𝑑) (120
𝑙𝑏
𝑓𝑑3 ) = 12,334
𝑙𝑏
𝑓𝑑2
 Load from Wall Weight (per unit length):
π‘Š 𝑓
𝑏
= (6𝑓𝑑 + 3𝑓𝑑 +
1.5𝑓𝑑)(1.5𝑓𝑑) (150
𝑙𝑏
𝑓𝑑3 ) + (1.5𝑓𝑑)(14𝑓𝑑 + 0.5𝑓𝑑) (150
𝑙𝑏
𝑓𝑑3 ) = 5,850
𝑙𝑏
𝑓𝑑
 Factor of Safety: 𝐹 =
((12 ,334
𝑙𝑏
𝑓𝑑2+5,850
𝑙𝑏
𝑓𝑑2)(0.45))
4,295
𝑙𝑏
𝑓𝑑2
= 1.59
ο‚· This is an acceptable factor of safety, as it falls within the range of
1.5 to 2.
7’3’
14’
1.5’
π‘ƒπ‘Ž
𝑏
1.5’
TEAM 7: GEOTECHNICAL MASTER PLAN
14
JOY RANCH HOUSING COMMUNITY
o Overturning
 πœ™ 𝑀 =
2
3
(30Β°) = 20Β°
 Loads Contributing to Turning Moments (per unit length) and Arm
Lengths
ο‚·
𝑃 π‘Žsin(πœ™ 𝑀)
𝑏
= 1,758
𝑙𝑏
𝑓𝑑
, 𝑏 = π΅π‘‘π‘œπ‘’ + π΅π‘ π‘‘π‘’π‘š = 4.5 𝑓𝑑
ο‚·
𝑃 π‘Ž cos( πœ™ 𝑀)
𝑏
= 4,830
𝑙𝑏
𝑓𝑑
, 𝑐 =
(0.5𝑓𝑑+15𝑓𝑑+6 tan(3Β°))
3
= 4.96 𝑓𝑑
ο‚·
π‘Š 𝑓
𝑏
= 2,588
𝑙𝑏
𝑓𝑑
, π‘Ž =
6𝑓𝑑+1.5𝑓𝑑+3𝑓𝑑
2
= 5.75 𝑓𝑑
ο‚·
𝑃
𝑏
= 12,334
𝑙𝑏
𝑓𝑑
, 𝑒 = (3𝑓𝑑 + 1.5𝑓𝑑 +
6𝑓𝑑
2
) = 8 𝑓𝑑
ο‚·
π‘Šπ‘ π‘‘π‘’π‘š
𝑏
= 3,263
𝑙𝑏
𝑓𝑑
, 𝑑 = (3𝑓𝑑 +
1.5𝑓𝑑
2
) = 3.75 𝑓𝑑
 Factor of Safety: 𝐹 =
((1,758 𝑙𝑏)(4.5𝑓𝑑)+(2,588 𝑙𝑏)(5.75 𝑓𝑑)+(12,334 𝑙𝑏)(8 𝑓𝑑)+(3,263 𝑙𝑏)(3.75𝑓𝑑))
(4,830 𝑙𝑏)(4.96𝑓𝑑)
= 5.58
ο‚· This factor of safety is acceptable, well above the required value of
1.5.
 Eccentricity
π‘ƒπ‘Ž
𝑏
c
π‘Šπ‘ π‘‘π‘’π‘š
𝑏
π‘Šπ‘“
𝑏
𝑃
𝑏
a
d
b
e
πœ™ 𝑀
Moment
Reference Point
TEAM 7: GEOTECHNICAL MASTER PLAN
15
JOY RANCH HOUSING COMMUNITY
ο‚·
(((1,758 𝑙𝑏)(4.5𝑓𝑑)+(2,588 𝑙𝑏)(5.75 𝑓𝑑)+(12,334 𝑙𝑏)(8 𝑓𝑑)+(3,263 𝑙𝑏)(3.75𝑓𝑑))βˆ’(4,830 𝑙𝑏)(4.96𝑓𝑑))
1,758
𝑙𝑏
𝑓𝑑
+2,588
𝑙𝑏
𝑓𝑑
+12,334
𝑙𝑏
𝑓𝑑
+3,263
𝑙𝑏
𝑓𝑑
=
4.77 𝑓𝑑 = π‘₯
ο‚· π‘’π‘π‘π‘’π‘›π‘‘π‘Ÿπ‘–π‘π‘–π‘‘π‘¦ =
11.5 𝑓𝑑
2
βˆ’ 4.77 𝑓𝑑 = 0.981
ο‚·
𝐡
6
= 1.92
𝐡
6
> π‘’π‘π‘π‘’π‘›π‘‘π‘Ÿπ‘–π‘π‘–π‘‘π‘¦ => π‘Žπ‘π‘π‘’π‘π‘‘π‘Žπ‘π‘™π‘’
TEAM 7: GEOTECHNICAL MASTER PLAN
16
JOY RANCH HOUSING COMMUNITY
Appendix C: Boring Logs
TEAM 7: GEOTECHNICAL MASTER PLAN
17
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
18
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
19
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
20
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
21
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
22
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
23
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
24
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
25
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
26
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
27
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
28
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
29
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
30
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
31
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
32
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
33
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
34
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
35
JOY RANCH HOUSING COMMUNITY
TEAM 7: GEOTECHNICAL MASTER PLAN
36
JOY RANCH HOUSING COMMUNITY

More Related Content

What's hot

site investigation
 site investigation site investigation
site investigation
Sanzidah Islam
Β 
1892 soil investigation for foundations
1892 soil investigation for foundations1892 soil investigation for foundations
1892 soil investigation for foundations
Chandra Mouli
Β 
The advantages and disadvantages of site investigation tools and exploratory ...
The advantages and disadvantages of site investigation tools and exploratory ...The advantages and disadvantages of site investigation tools and exploratory ...
The advantages and disadvantages of site investigation tools and exploratory ...
George Majunting
Β 
Groundwater improvement techniques
Groundwater improvement techniques Groundwater improvement techniques
Groundwater improvement techniques
my-will
Β 
Site investigation
Site investigationSite investigation
Site investigation
Shah Naseer
Β 
1442 site investigation 325
1442 site investigation 3251442 site investigation 325
1442 site investigation 325
Abhilash Chandra Dey
Β 
Subsurface Investigation and Geotechnical Evaluation
Subsurface Investigation and Geotechnical EvaluationSubsurface Investigation and Geotechnical Evaluation
Subsurface Investigation and Geotechnical Evaluationmecocca5
Β 
Dewatering
DewateringDewatering
Dewatering
Madhusudhan Reddy
Β 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
IEI GSC
Β 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point systemAnshuman Tyagi
Β 
B05820514
B05820514B05820514
B05820514
IOSR-JEN
Β 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
Umar Faruk
Β 
Engineering Site investigation
 Engineering Site investigation Engineering Site investigation
Engineering Site investigation
Vasu Goel
Β 
Subsoil exploiration
Subsoil exploirationSubsoil exploiration
Subsoil exploiration
dhara dattani
Β 
Site investigation 2nd clayton etc
Site investigation 2nd clayton etcSite investigation 2nd clayton etc
Site investigation 2nd clayton etc
Fungky King
Β 
Introduction to underground mine planning
Introduction to underground mine planningIntroduction to underground mine planning
Introduction to underground mine planning
IndranathSinha3
Β 

What's hot (19)

site investigation
 site investigation site investigation
site investigation
Β 
1892 soil investigation for foundations
1892 soil investigation for foundations1892 soil investigation for foundations
1892 soil investigation for foundations
Β 
H063771
H063771H063771
H063771
Β 
The advantages and disadvantages of site investigation tools and exploratory ...
The advantages and disadvantages of site investigation tools and exploratory ...The advantages and disadvantages of site investigation tools and exploratory ...
The advantages and disadvantages of site investigation tools and exploratory ...
Β 
Groundwater improvement techniques
Groundwater improvement techniques Groundwater improvement techniques
Groundwater improvement techniques
Β 
Site investigation
Site investigationSite investigation
Site investigation
Β 
1442 site investigation 325
1442 site investigation 3251442 site investigation 325
1442 site investigation 325
Β 
Subsurface Investigation and Geotechnical Evaluation
Subsurface Investigation and Geotechnical EvaluationSubsurface Investigation and Geotechnical Evaluation
Subsurface Investigation and Geotechnical Evaluation
Β 
V1 s3 raw materials evaluation
V1 s3   raw materials evaluationV1 s3   raw materials evaluation
V1 s3 raw materials evaluation
Β 
Dewatering
DewateringDewatering
Dewatering
Β 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
Β 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point system
Β 
B05820514
B05820514B05820514
B05820514
Β 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
Β 
Engineering Site investigation
 Engineering Site investigation Engineering Site investigation
Engineering Site investigation
Β 
Field Compaction
Field CompactionField Compaction
Field Compaction
Β 
Subsoil exploiration
Subsoil exploirationSubsoil exploiration
Subsoil exploiration
Β 
Site investigation 2nd clayton etc
Site investigation 2nd clayton etcSite investigation 2nd clayton etc
Site investigation 2nd clayton etc
Β 
Introduction to underground mine planning
Introduction to underground mine planningIntroduction to underground mine planning
Introduction to underground mine planning
Β 

Similar to Team #7 Geotechnical Report (2)

Soil exploration by abhishek sharma
Soil exploration by abhishek sharmaSoil exploration by abhishek sharma
Soil exploration by abhishek sharma
ABHISHEK SHARMA
Β 
IRJET- Soil Water Retention Curve of an Unsaturated Sand Under Square Footing...
IRJET- Soil Water Retention Curve of an Unsaturated Sand Under Square Footing...IRJET- Soil Water Retention Curve of an Unsaturated Sand Under Square Footing...
IRJET- Soil Water Retention Curve of an Unsaturated Sand Under Square Footing...
IRJET Journal
Β 
Geotechnical-Engineering (1).pdf
Geotechnical-Engineering (1).pdfGeotechnical-Engineering (1).pdf
Geotechnical-Engineering (1).pdf
Xise1
Β 
Geological Site Investigation Methods
Geological Site Investigation MethodsGeological Site Investigation Methods
Geological Site Investigation Methods
!SYOU co-designed sneakers
Β 
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATIONSOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
IRJET Journal
Β 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis Smith
Β 
Bhadhla report geotechnical layout contour survey
Bhadhla report geotechnical layout contour surveyBhadhla report geotechnical layout contour survey
Bhadhla report geotechnical layout contour surveySanman Rajput
Β 
report.docx
report.docxreport.docx
report.docx
SudipBalLama
Β 
Geological site investigation for Civil Engineering Foundations
Geological site investigation for Civil Engineering FoundationsGeological site investigation for Civil Engineering Foundations
Geological site investigation for Civil Engineering Foundations
Dr.Anil Deshpande
Β 
PROJECT WORK( CNS LAYER)-1.pptx
PROJECT WORK( CNS LAYER)-1.pptxPROJECT WORK( CNS LAYER)-1.pptx
PROJECT WORK( CNS LAYER)-1.pptx
JayaprakashRH
Β 
GT Lab Manual
GT Lab ManualGT Lab Manual
GT Lab Manual
Malla Reddy University
Β 
11CCEE_23Jul2015_Final
11CCEE_23Jul2015_Final11CCEE_23Jul2015_Final
11CCEE_23Jul2015_FinalUpul Atukorala
Β 
Date.docx
Date.docxDate.docx
Date.docx
SudipBalLama
Β 
Site Investigation.ppt
Site Investigation.pptSite Investigation.ppt
Site Investigation.ppt
Saravanan367781
Β 
Siteinvestigation
SiteinvestigationSiteinvestigation
SiteinvestigationAbhishek sagar
Β 
NATCL Biopile Management Plan Dec 2014 - IFU
NATCL  Biopile Management Plan Dec 2014 - IFUNATCL  Biopile Management Plan Dec 2014 - IFU
NATCL Biopile Management Plan Dec 2014 - IFUStacey O'Sullivan
Β 
Soil stabilization methods_and_materials
Soil stabilization methods_and_materialsSoil stabilization methods_and_materials
Soil stabilization methods_and_materials
priyank 59
Β 
Sub soil exploration
Sub soil explorationSub soil exploration
Sub soil exploration
Surpal Zala
Β 
FEIS H-Revised Stormwater Management Plan
FEIS H-Revised Stormwater Management Plan FEIS H-Revised Stormwater Management Plan
FEIS H-Revised Stormwater Management Plan
WSP_SELLS
Β 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewateringajinkya gaikwad
Β 

Similar to Team #7 Geotechnical Report (2) (20)

Soil exploration by abhishek sharma
Soil exploration by abhishek sharmaSoil exploration by abhishek sharma
Soil exploration by abhishek sharma
Β 
IRJET- Soil Water Retention Curve of an Unsaturated Sand Under Square Footing...
IRJET- Soil Water Retention Curve of an Unsaturated Sand Under Square Footing...IRJET- Soil Water Retention Curve of an Unsaturated Sand Under Square Footing...
IRJET- Soil Water Retention Curve of an Unsaturated Sand Under Square Footing...
Β 
Geotechnical-Engineering (1).pdf
Geotechnical-Engineering (1).pdfGeotechnical-Engineering (1).pdf
Geotechnical-Engineering (1).pdf
Β 
Geological Site Investigation Methods
Geological Site Investigation MethodsGeological Site Investigation Methods
Geological Site Investigation Methods
Β 
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATIONSOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
Β 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016
Β 
Bhadhla report geotechnical layout contour survey
Bhadhla report geotechnical layout contour surveyBhadhla report geotechnical layout contour survey
Bhadhla report geotechnical layout contour survey
Β 
report.docx
report.docxreport.docx
report.docx
Β 
Geological site investigation for Civil Engineering Foundations
Geological site investigation for Civil Engineering FoundationsGeological site investigation for Civil Engineering Foundations
Geological site investigation for Civil Engineering Foundations
Β 
PROJECT WORK( CNS LAYER)-1.pptx
PROJECT WORK( CNS LAYER)-1.pptxPROJECT WORK( CNS LAYER)-1.pptx
PROJECT WORK( CNS LAYER)-1.pptx
Β 
GT Lab Manual
GT Lab ManualGT Lab Manual
GT Lab Manual
Β 
11CCEE_23Jul2015_Final
11CCEE_23Jul2015_Final11CCEE_23Jul2015_Final
11CCEE_23Jul2015_Final
Β 
Date.docx
Date.docxDate.docx
Date.docx
Β 
Site Investigation.ppt
Site Investigation.pptSite Investigation.ppt
Site Investigation.ppt
Β 
Siteinvestigation
SiteinvestigationSiteinvestigation
Siteinvestigation
Β 
NATCL Biopile Management Plan Dec 2014 - IFU
NATCL  Biopile Management Plan Dec 2014 - IFUNATCL  Biopile Management Plan Dec 2014 - IFU
NATCL Biopile Management Plan Dec 2014 - IFU
Β 
Soil stabilization methods_and_materials
Soil stabilization methods_and_materialsSoil stabilization methods_and_materials
Soil stabilization methods_and_materials
Β 
Sub soil exploration
Sub soil explorationSub soil exploration
Sub soil exploration
Β 
FEIS H-Revised Stormwater Management Plan
FEIS H-Revised Stormwater Management Plan FEIS H-Revised Stormwater Management Plan
FEIS H-Revised Stormwater Management Plan
Β 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
Β 

Team #7 Geotechnical Report (2)

  • 1. Genaro Contreras Geotechnical Master Plan Company Sponsor: CVL Group 7 3/20/2015 Spring2015 JOY RANCH HOUSING COMMUNITY
  • 2. TEAM 7: GEOTECHNICAL MASTER PLAN 1 JOY RANCH HOUSING COMMUNITY Table of Contents 1.0 EXECUTIVE SUMMARY.................................................................................................................2 2.0 INTRODUCTION ...........................................................................................................................2 2.1 Proposed Project.......................................................................................................................2 2.2 Site Conditions..........................................................................................................................2 3.0 SITE EXPLORATION ......................................................................................................................3 3.1 Exploratory Borings ..................................................................................................................3 32 Groundwater Table....................................................................................................................3 4.0 SOIL CHARACTERISTICS.................................................................................................................4 4.1 Test Results ..............................................................................................................................4 4.2 Strength and Capacity...............................................................................................................6 5.0 SOIL ISSUES ..................................................................................................................................7 5.1 Collapse....................................................................................................................................8 5.2 Subsidence ...............................................................................................................................8 5.3 Fissures....................................................................................................................................8 5.4 Sulfate......................................................................................................................................8 6.0 DESIGN RECOMMENDATIONS......................................................................................................8 6.1 Footings ...................................................................................................................................8 6.2 Earth Retaining Walls ...............................................................................................................8 6.3 Earthwork ................................................................................................................................8 7.0 SUSTAINABILITY ...........................................................................................................................8 8.0 CONCLUSION................................................................................................................................9 APPENDIX A: SCHMERTMANN ANALYSIS..................................................................................... 10-12 APPENDIX B: RETAINING WALL CALCULATIONS............................................................................ 13-15 APPENDIX C: BORING LOG DATA .................................................................................................16-37 APPENDIX D: PROJECT VALIDATION FORM .......................................................................................38
  • 3. TEAM 7: GEOTECHNICAL MASTER PLAN 2 JOY RANCH HOUSING COMMUNITY Figure 1: Land Use Plan 1.0 Executive Summary An apparently square, undeveloped area is proposed as the site for a small residential community, titled Joy Ranch Housing. This land is intended to be divided into 5 main uses: housing, recreational, commercial, water treatment and educational. Shown below in figure 1 are the types of land use each parcel in this site is devoted to. Due to the scarcity of information available concerning the earth conditions thereof, a geotechnical investigation was performed to properly analyze and evaluate the challenges that could potentially arise from land development on this site. General site topography and groundwater depth were provided by site visitation and the Groundwater Site Inventory of the Arizona Department of Water Resources. Exploratory borings were performed to obtain at least 1 soil sample from each of the 14 parcels. The soil characteristics determined or extrapolated from these samplings were used to assign or affirm effective use of each subdivision. The incorporation of numerous assumptions became necessary, as some crucial factors would require further laboratory testing for total accuracy. Design recommendations for structure footings and earth retaining walls were provided according to the soil properties and the loads of the planned structures (3,101,400 lb. for an elementary school building and 157,784 lb. for a pedestrian bridge). 2.0 Introduction: 2.1 Proposed Project: Joy Ranch Housing is a small residential community, spanning approximately 622.86 acres and divided into 14 parcels of land. The majority of these parcels are devoted to housing, with both high and low dwelling unit densities, with the remaining ones set aside for the purposes of wastewater treatment, education, recreation and commercial activity. Two collector roads intersect at a roundabout towards the northeastern quadrant of the site, providing access to the rest of the parcels. The performance of a geotechnical investigation fulfills the requirement of ascertaining the suitability of the soil concerning land development. 2.2 Site Conditions: The site for Joy Ranch Housing is bound by North 7th Avenue, North 7th Street, West Joy Ranch Road and West Cloud Road, all of which are arterials. No previous development is evident or recorded. Surrounding establishments include, located to the south,
  • 4. TEAM 7: GEOTECHNICAL MASTER PLAN 3 JOY RANCH HOUSING COMMUNITY Deer Mountain Elementary and Dove Valley Ranch, approximately two miles to the East. A smaller fraction of the land surrounding the planned site is developed, with one story homes lining the roads. The topography is flat in general, with no apparent hills or earth depreciations, nor apparent evidence of boulders or cobbles. Elevation slowly decreases from the northern to southern half, which dictates the flow of the washes. Two major ones flow directly through the site, one of which is the West Fork Desert Lake Wash and traverses the eastern half of the site. Surface indicators of the location of these washes include clear lines of trees, which will necessitate clearing and possible grubbing to make further use of the washes. Other vegetation includes abundant shrubbery in the southwestern corner. The surrounding area is mountainous. 3.0 Site Exploration: 3.1 Borings: For the purpose of exploring various subsurface conditions throughout the site, exploratory borings were performed by use of a 6 5/8” hollow stem auger. The locations for these borings were selected according to the planned parcels. One boring was performed in each smaller parcel, with two performed in larger ones, such as parcels 5 and 10, to obtain more reliable averages for the soil characteristics pertaining to a given area. Because the depths of the logs are approximately 6 feet, they are preliminary. Deeper ones that fall within the range of 10- 15 feet will be required to make reliable foundation recommendations for larger loads. 4.2 Groundwater: Though some moisture was present in the majority of the samples, the groundwater table is evidently located far below the depth of any exploratory boring for the pertinent project. Researching of the records kept by the Arizona Department of Water 4 2 1 5 7 6 10 3 11 9 14 8 13 12 Legend = Boring Location = ParcelNumber Figure 2: Boring Map
  • 5. TEAM 7: GEOTECHNICAL MASTER PLAN 4 JOY RANCH HOUSING COMMUNITY Resources revealed no existing data specifically regarding the pertinent land, affirming that no previous development has been completed nor attempted. Data from wells at various adjacent points, monitored as recent as 2010, indicates the depth of the groundwater table to be far below the range of the infrastructure for Joy Ranch Housing, ranging from 301.2 to 511.6 feet. Considering this, it is highly unlikely that the groundwater table will pose any difficulties that need to be figured into the calculations. 4.0 Soil Characteristics 4.1 Test Results: In accordance with the standards of ASTM D2937, the drive-cylinder test was performed on samples from the boring sites. The simple measurement of sample cylindrical masses before and after drying enabled the computation of the dry unit weights and water contents. On the field, visual classification was performed by ASTM D2487 and ASTM D2488 specifics, producing the descriptions included in the boring logs. Weak cementation was an abundant characteristic, noted from most of the samples. ASTM C136 standards were followed for the sieve analysis, showing a predominance of clayey sands, particularly within the surface strata. Plasticity was required to determine the quality of strength for each boring location. ASTM D4318 procedure was followed in identifying the liquid and plastic limits, both of which are required for the plasticity indices. The results to these are shown in tables 1 and 2. The separation into 2 tables of data was necessitated by the availability of data for the multiple depths at which exploratory borings were performed. Figure 3: Map of Sample Wells Legend = Site Border = Well Location Top Number = Well Elevation Bottom Number = Date of Data Collection
  • 6. TEAM 7: GEOTECHNICAL MASTER PLAN 5 JOY RANCH HOUSING COMMUNITY Table 1: Laboratory Test Results Table 2: Soil Classification and Consistency
  • 7. TEAM 7: GEOTECHNICAL MASTER PLAN 6 JOY RANCH HOUSING COMMUNITY 4.2 Strength and Bearing Capacity: In determining strength and capacity characteristics for the soils within the site, it must be acknowledged that insufficient data has been gathered from laboratory tests to produce truly accurate quantities. This necessitates assumptions regarding certain vital factors, based on previously established correlations and standards. Laboratory results for soil classification were utilized when available, with visual classification accepted as reasonable approximation for all other cases. The angle of internal friction required already established value ranges assigned to each soil type. The value used for calculation was selected in relation to the dry density of the soil. Cohesion was also determined using previous data based on soil types. The bearing capacity factors were obtained from a chart constructed for use in conjunction with two common methods for ultimate bearing pressure, and are listed below in table 3. Furthermore, due to the extensive depth of the groundwater table and the presence of moisture within the soil samples from the exploratory borings, soil conditions were assumed to be unsaturated, drained and normally consolidated. The latter two conditions are acceptable for this preliminary analysis, partially due to the lack of previous land development. Terzhagi’s method for computing soil bearing capacity was utilized with the footing dimensions for the different planned structures, applying the standard factor of safety of 2.5. The results are shown in table 4. Table 3: Bearing Capacity Factors
  • 8. TEAM 7: GEOTECHNICAL MASTER PLAN 7 JOY RANCH HOUSING COMMUNITY 5.0 Soil Issues 5.1 Subsidence: While data from the site itself is currently unavailable, studies on the greater Maricopa area from the Hydrology Division of the ADWR reveal that the site does not fall within the areas of major subsidence, which are outlined below in figure 3. Table 4: Bearing Capacity Legend = Subsidence Zone = Major Highway Figure 3: Subsidence Map
  • 9. TEAM 7: GEOTECHNICAL MASTER PLAN 8 JOY RANCH HOUSING COMMUNITY Because the majority of the area is composed of clayey sands, a considerable amount of immediate settlement is expected, but consolidation is not anticipated due to the depth of the groundwater table and overall scarcity of clays. 5.2 Collapse: Parcels 6 and 8, which are intended to serve as the locations for low density housing and a grocery store respectably, were shown to have collapsible soil. In addition to potentially exacerbating differential settlement, this issue may be compounded be compounded by the area’s comparatively high flood rate, as an influx of water is one of the triggers for soil collapse. Methods for combating this problem are explained under the design recommendations for footings. 5.3 Fissures: Fissuring is often the result of subsidence. Because the site is not located within any of the major subsidence zones in Maricopa County, fissuring is not a major concern. Furthermore, data maps from the ADWR did not identify any nearby areas with a high risk of fissuring. Though this geological hazard does not pose a problem for this particular case, it is a common concern for geotechnical engineers. Thus, the reasons for disregarding it are noteworthy. 5.4 Sulfate: The soil of parcel 2 was shown to have a significantly high sulfate concentration, at 299 ppm. According to the standards from the Portland Cement Association, this level of soluble sulfates constitutes a moderate hazard, capable of causing cracks and disintegration on concrete constructs, including footings. 6.0 DesignRecommendations 6.1 Footings: The spread footings for the homes in both low and high density housing developments will be square and 3 feet in width, although the soil conditions of parcel 2 necessitate a width of 4 feet to meet, or exceed, an acceptable bearing capacity of 5,000 𝑙𝑏/𝑓𝑑2 . For parcel 6, the high concentration of soluble sulfates necessitates that any concrete slab footings be composed of type II concrete, which is resistant to sulfate attack. A 3 foot width is sufficient for most of the other land use types, except for the two story elementary school building and the bridges. A 10 foot wide continuous footing was assumed for the pedestrian bridge, which passes the design criteria for this type of foundation, including the bearing capacity. The predicted immediate settlement following construction is well below the allowable total settlement for bridges, according to table 2.1 of Coduto’s text on foundations. The building from the elementary school requires 16 spread footings, each 5 feet in width. 6.2 Earth Retaining Walls: Concrete cut-off walls will be constructed below the pedestrian bridge along the wash between the housing development in parcel 12 and the recreational park in parcel 10. This is primarily to prevent the issue of scour on the bridge footings, which could prove severe in the long run, and without a deep foundation. At the least in the short term, the level of flooding in this wash is not predicted to be high enough to pose an issue for the adjacent housing development. Parcels 6 and 8 will also require cut-off walls along the adjacent wash, primarily to prevent soil collapse. These walls will also be composed of type II concrete to combat damage from soluble sulfates. The other walls will be composed of type I concrete.
  • 10. TEAM 7: GEOTECHNICAL MASTER PLAN 9 JOY RANCH HOUSING COMMUNITY The walls themselves will be a total of 16 feet in height, with a toe of 3 feet, a stem of 1.5 feet and a heel of 7 feet. These dimensions are acceptable for the soil conditions of all the walls due to the common backfill, which will be high quality granular soil. The soil properties will include a unit weight of 120 𝑙𝑏/𝑓𝑑2 , a friction angle of 30 degrees and no cohesion. 6.3 Earthwork: In addition to the excavation required for the footings of the residential, commercial and educational structures, the soil at the edge of the washes adjacent to parcels 12, 10, 6 and 8 will be removed as part of the construction of the retaining walls. This will be done with typical excavators. Scrapers will be used to transport the removed soil, as a different backfill will be placed behind the walls. Prior to any compaction, the soils will be moisture conditioned to within 3% of the optimum moisture content, identified during the Proctor tests. Compaction will increase the density of the soil to approximately 95% of the proctor test results. 7.0 Sustainability Cells are installed underground, designed to provide additional nutrients to the surrounding soil to sustain the health of the vegetation. These are located near the pedestrian and vehicle bridges, and can be particularly beneficial to the recreational park and the washes, which may eventually develop vegetation that can be maintained and increase the aesthetic appeal of the area. The cells are provided power, at least in part, by specialized batteries that convert the vibrations of the bridges, from passing pedestrians and vehicles, to electricity. 8.0 Conclusion Due to a number of assumptions, limitations to this preliminary analysis include a lack of conclusive shear strength values, the margin of error for bearing capacity and the preliminary nature of the exploratory borings. The depth of the borings is of particular note, as it only increases the uncertainty of the conditions under which substructures are constructed. However, the error for the ultimate bearing capacity calculations is not significant because of the adherence to typical soil factor values, making the computed bearing capacities reasonably accurate for the purposes of this report. Earth conditions for the site of the proposed Joy Ranch Housing community are concluded to be manageable for the purposes of land development, although further testing is still required to refine the design recommendations and improve safety.
  • 11. TEAM 7: GEOTECHNICAL MASTER PLAN 10 JOY RANCH HOUSING COMMUNITY Appendix A: Schmertmann Analysis ο‚· Footings (Elementary School Building) o π‘ž = 8000 𝑙𝑏 𝑓𝑑2 , 𝐡 = 5 𝑓𝑑, 𝐻 = 1.5 𝑓𝑑, 𝐷 = 3.5 𝑓𝑑, 𝑃 = 194,375 𝑙𝑏 o Important Geostatic Stresses  πœŽπ‘§π· β€² = (114.38 𝑙𝑏 𝑓𝑑3 ) (3.5 𝑓𝑑) = 400.33 𝑙𝑏 𝑓𝑑2  πœŽπ‘§π‘ β€² = (114.38 𝑙𝑏 𝑓𝑑3 )(3.5𝑓𝑑 + 5 2 𝑓𝑑) = 686.28 𝑙𝑏 𝑓 𝑑2 o Equivalent Modulus: 𝐸𝑠 = (50,000 𝑙𝑏 𝑓𝑑2 )√1 + 12,000(25 𝑙𝑏 𝑓𝑑2 ) = 350,000 𝑙𝑏 𝑓𝑑2 o Peak Influence Factor: πΌπœ–π‘ = 0.5 + 0.1√ (8,000 𝑙𝑏 𝑓𝑑2βˆ’343.14 𝑙𝑏 𝑓𝑑2) 629 .09 𝑙𝑏 𝑓𝑑2 = 0.849 o Depth, Creep and Shape Factors  𝐢1 = 1 βˆ’ 0.5 ( (343 .14 𝑙𝑏 𝑓𝑑2 ) 8,000 𝑙𝑏 𝑓𝑑2βˆ’343.14 𝑙𝑏 𝑓𝑑2 ) = 0.974  𝐢2 = 1 + log( 0.1 0.1 ) = 1  𝐢3 = 1 (value for square footings) o Settlement: 𝛿 = ((0.978)(1)(1)(8,000 𝑙𝑏 𝑓𝑑2βˆ’343.14 𝑙𝑏 𝑓𝑑2)(0.849 +0.025)(5 𝑓𝑑)) 350,000 𝑙𝑏 𝑓𝑑2 = 0.091 𝑓𝑑 = 1.09 𝑖𝑛 o Immediate settlement falls within the acceptable range of 0.5 to 2 inches. ο‚· Footing (Pedestrian Bridge, Parcel 10) o π‘ž = 1,014 𝑙𝑏 𝑓𝑑2 , 𝐡 = 10 𝑓𝑑, 𝐻 = 1.5 𝑓𝑑, 𝐷 = 3.5 𝑓𝑑, 𝑃 = 78,892 𝑙𝑏 5’ 3.5’ 2.5’ P 2’
  • 12. TEAM 7: GEOTECHNICAL MASTER PLAN 11 JOY RANCH HOUSING COMMUNITY o Important Geostatic Stresses  πœŽπ‘§π· β€² = (108.4 𝑙𝑏 𝑓𝑑3 ) (3.5 𝑓𝑑) = 379.4 𝑙𝑏 𝑓𝑑2  πœŽπ‘§π‘ β€² = (108.4 𝑙𝑏 𝑓𝑑3 ) (3.5 𝑓𝑑) = 1,463.4 𝑙𝑏 𝑓𝑑2 o Equivalent Modulus: 𝐸𝑠 = (50,000 𝑙𝑏 𝑓𝑑2 )√1 + (12,000 𝑙𝑏 𝑓𝑑2 )(33) = 446,000 𝑙𝑏 𝑓𝑑2 o Peak Influence Factor: πΌπœ–π‘ = 0.5 + 0.1√ (1,255 𝑙𝑏 𝑓𝑑2βˆ’379.4 𝑙𝑏 𝑓𝑑2) 1,463 .4 𝑙𝑏 𝑓𝑑2 = 0.566 o Depth, Creep and Shape Factors  𝐢1 = 1 βˆ’ 0.5 ( (379 .4 𝑙𝑏 𝑓𝑑2 ) 1,255 𝑙𝑏 𝑓𝑑2βˆ’379.4 𝑙𝑏 𝑓𝑑2 ) = 0.783  𝐢2 = 1  𝐢3 = 1.03 βˆ’ 0.3(10) = 0.73 o Settlement: 𝛿 = (0.783)(1)(0.73)(1,255 𝑙𝑏 𝑓𝑑2 βˆ’379.4 𝑙𝑏 𝑓𝑑2)(2βˆ—0.566+0.1)(10) 446 ,000 𝑙𝑏 𝑓𝑑2 = 0.012 𝑓𝑑 = 0.15 𝑖𝑛 o Immediate settlement falls below the acceptable limit of 2 inches for bridges. ο‚· Footing( Pedestrian Bridge, Parcel 12) o π‘ž = 1,014 𝑙𝑏 𝑓𝑑2 , 𝐡 = 10 𝑓𝑑, 𝐻 = 1.5 𝑓𝑑, 𝐷 = 3.5 𝑓𝑑, 𝑃 = 78,892 𝑙𝑏 o Though the top soil stratum of this area is has different properties, the bottom of the footing extends below this layer, making the simplified Schmertmann’s analysis appropriate. o Important Geostatic Stresses  πœŽπ‘§π· β€² = (132.24 𝑙𝑏 𝑓𝑑3 ) (3.5 𝑓𝑑) = 462.84 𝑙𝑏 𝑓𝑑2  πœŽπ‘§π‘ β€² = (132.24 𝑙𝑏 𝑓𝑑3 )(3.5𝑓𝑑 + 10𝑓𝑑) = 1,785.24 𝑙𝑏 𝑓𝑑2 o Equivalent Modulus: 𝐸𝑠 = (50,000 𝑙𝑏 𝑓𝑑2 )√1 + (12,000 𝑙𝑏 𝑓𝑑2 )(53) = 686,000 𝑙𝑏 𝑓𝑑2 o Peak Influence Factor: πΌπœ–π‘ = 0.5 + 0.1√ (1,014 𝑙𝑏 𝑓𝑑2βˆ’462.84 𝑙𝑏 𝑓𝑑2) 1,785.24 𝑙𝑏 𝑓𝑑2 = 0.556 o Depth, Creep and Shape Factors  𝐢1 = 1 βˆ’ 0.5 ( (462 .84 𝑙𝑏 𝑓𝑑2 ) 1,014 𝑙𝑏 𝑓𝑑2βˆ’462.84 𝑙𝑏 𝑓𝑑2 ) = 0.580  𝐢2 = 1  𝐢3 = 1.03 βˆ’ 0.3(10) = 0.73
  • 13. TEAM 7: GEOTECHNICAL MASTER PLAN 12 JOY RANCH HOUSING COMMUNITY o Settlement: 𝛿 = (0.580)(1)(0.73)(1,014 𝑙𝑏 𝑓𝑑2 βˆ’462 .84 𝑙𝑏 𝑓𝑑2)(2βˆ—0.556+0.1)(10 𝑓𝑑) 686,000 𝑙𝑏 𝑓𝑑2 = 0.006 𝑓𝑑 = 0.068 𝑖𝑛 o Immediate settlement falls below the acceptable limit of 2 inches for bridges.
  • 14. TEAM 7: GEOTECHNICAL MASTER PLAN 13 JOY RANCH HOUSING COMMUNITY Appendix B: Retaining Wall Calculations ο‚· Cantilever Cut-Off Wall o The following calculations are applicable to all of the planned retaining walls. o 𝐻 𝑀 = 14 𝑓𝑑, π΅β„Žπ‘’π‘’π‘™ = 7 𝑓𝑑, π΅π‘‘π‘œπ‘’ = 3 𝑓𝑑, π΅π‘ π‘‘π‘’π‘š = 1.5 𝑓𝑑, π‘’π‘šπ‘π‘’π‘‘π‘šπ‘’π‘›π‘‘ = 0.5 𝑓𝑑, 𝐻 = 16 𝑓𝑑, 𝛾 = 120 𝑙𝑏 𝑓𝑑3 , 𝑐 = 0 𝑙𝑏 𝑓𝑑2 , πœ™ = 30Β°, 𝛽 = 3Β°, πœ‡ = 0.45 o Sliding  Coefficient of Lateral Earth Pressure: πΎπ‘Ž = (cos(3)βˆ’βˆšcos2(3)βˆ’cos2(32)) cos(3)+√cos2(3)βˆ’cos2(32) = 0.322  Soil Load on Wall (per unit length): 𝑃 π‘Ž 𝑏 = ( (132 .24 𝑙𝑏 𝑓𝑑3 )(17𝑓𝑑)2(0.322) 2 )cos(3) = 5,141 𝑙𝑏 𝑓𝑑  Soil Load (per unit length): 𝑃 𝑏 = 0.5 βˆ— (6𝑓𝑑)(1𝑓𝑑 + 2 βˆ— 14𝑓𝑑 + 6 tan(3) 𝑓𝑑) (120 𝑙𝑏 𝑓𝑑3 ) = 12,334 𝑙𝑏 𝑓𝑑2  Load from Wall Weight (per unit length): π‘Š 𝑓 𝑏 = (6𝑓𝑑 + 3𝑓𝑑 + 1.5𝑓𝑑)(1.5𝑓𝑑) (150 𝑙𝑏 𝑓𝑑3 ) + (1.5𝑓𝑑)(14𝑓𝑑 + 0.5𝑓𝑑) (150 𝑙𝑏 𝑓𝑑3 ) = 5,850 𝑙𝑏 𝑓𝑑  Factor of Safety: 𝐹 = ((12 ,334 𝑙𝑏 𝑓𝑑2+5,850 𝑙𝑏 𝑓𝑑2)(0.45)) 4,295 𝑙𝑏 𝑓𝑑2 = 1.59 ο‚· This is an acceptable factor of safety, as it falls within the range of 1.5 to 2. 7’3’ 14’ 1.5’ π‘ƒπ‘Ž 𝑏 1.5’
  • 15. TEAM 7: GEOTECHNICAL MASTER PLAN 14 JOY RANCH HOUSING COMMUNITY o Overturning  πœ™ 𝑀 = 2 3 (30Β°) = 20Β°  Loads Contributing to Turning Moments (per unit length) and Arm Lengths ο‚· 𝑃 π‘Žsin(πœ™ 𝑀) 𝑏 = 1,758 𝑙𝑏 𝑓𝑑 , 𝑏 = π΅π‘‘π‘œπ‘’ + π΅π‘ π‘‘π‘’π‘š = 4.5 𝑓𝑑 ο‚· 𝑃 π‘Ž cos( πœ™ 𝑀) 𝑏 = 4,830 𝑙𝑏 𝑓𝑑 , 𝑐 = (0.5𝑓𝑑+15𝑓𝑑+6 tan(3Β°)) 3 = 4.96 𝑓𝑑 ο‚· π‘Š 𝑓 𝑏 = 2,588 𝑙𝑏 𝑓𝑑 , π‘Ž = 6𝑓𝑑+1.5𝑓𝑑+3𝑓𝑑 2 = 5.75 𝑓𝑑 ο‚· 𝑃 𝑏 = 12,334 𝑙𝑏 𝑓𝑑 , 𝑒 = (3𝑓𝑑 + 1.5𝑓𝑑 + 6𝑓𝑑 2 ) = 8 𝑓𝑑 ο‚· π‘Šπ‘ π‘‘π‘’π‘š 𝑏 = 3,263 𝑙𝑏 𝑓𝑑 , 𝑑 = (3𝑓𝑑 + 1.5𝑓𝑑 2 ) = 3.75 𝑓𝑑  Factor of Safety: 𝐹 = ((1,758 𝑙𝑏)(4.5𝑓𝑑)+(2,588 𝑙𝑏)(5.75 𝑓𝑑)+(12,334 𝑙𝑏)(8 𝑓𝑑)+(3,263 𝑙𝑏)(3.75𝑓𝑑)) (4,830 𝑙𝑏)(4.96𝑓𝑑) = 5.58 ο‚· This factor of safety is acceptable, well above the required value of 1.5.  Eccentricity π‘ƒπ‘Ž 𝑏 c π‘Šπ‘ π‘‘π‘’π‘š 𝑏 π‘Šπ‘“ 𝑏 𝑃 𝑏 a d b e πœ™ 𝑀 Moment Reference Point
  • 16. TEAM 7: GEOTECHNICAL MASTER PLAN 15 JOY RANCH HOUSING COMMUNITY ο‚· (((1,758 𝑙𝑏)(4.5𝑓𝑑)+(2,588 𝑙𝑏)(5.75 𝑓𝑑)+(12,334 𝑙𝑏)(8 𝑓𝑑)+(3,263 𝑙𝑏)(3.75𝑓𝑑))βˆ’(4,830 𝑙𝑏)(4.96𝑓𝑑)) 1,758 𝑙𝑏 𝑓𝑑 +2,588 𝑙𝑏 𝑓𝑑 +12,334 𝑙𝑏 𝑓𝑑 +3,263 𝑙𝑏 𝑓𝑑 = 4.77 𝑓𝑑 = π‘₯ ο‚· π‘’π‘π‘π‘’π‘›π‘‘π‘Ÿπ‘–π‘π‘–π‘‘π‘¦ = 11.5 𝑓𝑑 2 βˆ’ 4.77 𝑓𝑑 = 0.981 ο‚· 𝐡 6 = 1.92 𝐡 6 > π‘’π‘π‘π‘’π‘›π‘‘π‘Ÿπ‘–π‘π‘–π‘‘π‘¦ => π‘Žπ‘π‘π‘’π‘π‘‘π‘Žπ‘π‘™π‘’
  • 17. TEAM 7: GEOTECHNICAL MASTER PLAN 16 JOY RANCH HOUSING COMMUNITY Appendix C: Boring Logs
  • 18. TEAM 7: GEOTECHNICAL MASTER PLAN 17 JOY RANCH HOUSING COMMUNITY
  • 19. TEAM 7: GEOTECHNICAL MASTER PLAN 18 JOY RANCH HOUSING COMMUNITY
  • 20. TEAM 7: GEOTECHNICAL MASTER PLAN 19 JOY RANCH HOUSING COMMUNITY
  • 21. TEAM 7: GEOTECHNICAL MASTER PLAN 20 JOY RANCH HOUSING COMMUNITY
  • 22. TEAM 7: GEOTECHNICAL MASTER PLAN 21 JOY RANCH HOUSING COMMUNITY
  • 23. TEAM 7: GEOTECHNICAL MASTER PLAN 22 JOY RANCH HOUSING COMMUNITY
  • 24. TEAM 7: GEOTECHNICAL MASTER PLAN 23 JOY RANCH HOUSING COMMUNITY
  • 25. TEAM 7: GEOTECHNICAL MASTER PLAN 24 JOY RANCH HOUSING COMMUNITY
  • 26. TEAM 7: GEOTECHNICAL MASTER PLAN 25 JOY RANCH HOUSING COMMUNITY
  • 27. TEAM 7: GEOTECHNICAL MASTER PLAN 26 JOY RANCH HOUSING COMMUNITY
  • 28. TEAM 7: GEOTECHNICAL MASTER PLAN 27 JOY RANCH HOUSING COMMUNITY
  • 29. TEAM 7: GEOTECHNICAL MASTER PLAN 28 JOY RANCH HOUSING COMMUNITY
  • 30. TEAM 7: GEOTECHNICAL MASTER PLAN 29 JOY RANCH HOUSING COMMUNITY
  • 31. TEAM 7: GEOTECHNICAL MASTER PLAN 30 JOY RANCH HOUSING COMMUNITY
  • 32. TEAM 7: GEOTECHNICAL MASTER PLAN 31 JOY RANCH HOUSING COMMUNITY
  • 33. TEAM 7: GEOTECHNICAL MASTER PLAN 32 JOY RANCH HOUSING COMMUNITY
  • 34. TEAM 7: GEOTECHNICAL MASTER PLAN 33 JOY RANCH HOUSING COMMUNITY
  • 35. TEAM 7: GEOTECHNICAL MASTER PLAN 34 JOY RANCH HOUSING COMMUNITY
  • 36. TEAM 7: GEOTECHNICAL MASTER PLAN 35 JOY RANCH HOUSING COMMUNITY
  • 37. TEAM 7: GEOTECHNICAL MASTER PLAN 36 JOY RANCH HOUSING COMMUNITY