Presentation on 
Ground improvement techniques 
Nilesh Bhosale 
M.Tech. 
Transportation Engg.
Introduction 
 Transportation contributes to the industrial, economic, social 
and cultural development of nation 
 Transportation by road or highways is the only mode 
which could give maximum service to one and all. 
 When the soil on a project site cannot support the loads, 
ground improvement to increase strength, reduce 
compressibility, and enhance performance under applied 
loadings may be required. 
 Various methods are discussed below:
METHODS FOR GROUND IMPROVEMENT 
1. VERTICAL DRAINS 
2. SOIL NAILING 
3. STONE COLUMNS 
4. VIBRO COMPACTION 
5. DYNAMIC COMPACTION
VERTICAL DRAINS 
 These consist of a column of pervious material placed in 
cylindrical vertical holes at sufficiently close spaces. 
 All drains should be connected at the ground surface to a 
drainage blanket. 
 Vertical drains accelerate consolidation by facilitating drainage 
of pore water. 
 Vertical drains are laid out in rows, staggered, or aligned to 
form patterns of equilateral triangles or squares. 
 Two types of drains are discussed below
SAND DRAINS 
A sand drain is a simple 
process, employing a column 
of at least 10 inches in width 
augered into ground to be 
surcharged & consolidated. 
The column is then filled with 
sand and connected to a 
free-draining blanket of 
granular soil.
WICK DRAIN 
• A wick drain is 
usually about, 4 
inches wide, 1/8-inch 
thick which acts as a 
high-permeability 
conduit for water to 
flow out of the soil 
and to the surface. 
• Most common 
application of wick 
drains is for 
accelerating the 
settlement rate of 
compressible soils.
SOIL NAILING 
• This ground reinforcement process uses steel tendons which 
are drilled and grouted into the soil to create a composite mass. 
• A shotcrete facing is typically applied. 
• Soil Nailing is an in situ technique for reinforcing, stabilizing and 
retaining excavations and deep cuts.
Shotcreteing
Holes are drilled though machine
Soil Nailing
Stone column 
 Also known as vibro-replacement or vibro-displacement, 
is a ground improvement process where vertical 
columns of compacted aggregate are formed through the 
soils to be improved. 
 The vibrator first penetrates to the required depth by 
vibration and air or water jetting or by vibration alone. 
 Gravel is then added at the tip of the vibrator and 
progressive raising and repenetration of the vibrator 
results in the gravel being pushed into the surrounding 
soil. 
 The soil-column matrix results in an overall mass having 
a high shear strength and a low compressibility.
Stone column
Vibro compaction 
• It is a ground improvement process for densifying loose 
sands to create stable foundation soils. 
• The action of the vibrator, usually accompanied by water 
jetting, reduces the inter-granular forces between the soil 
particles, allowing them to move into a denser 
configuration, typically achieving a relative density of 70 
to 85 percent. 
• Compaction is achieved above and below the water 
table.
Crane Mounted Vibrator
Process of vibro compaction
Dynamic compaction 
 Dynamic Compaction is the dropping of heavy weights on the 
ground surface to densify the soils at depth. 
 It involves the repeated dropping of large steel tampers by 
means of crawler cranes. 
 Tampers typically range from 6 to 20 tons and are dropped 
from heights of about 40 to 80 feet.
MACHINE WITH TAMPER COMPACTION BY TAMPER
Conclusion 
• Soil conditions can frequently be improved using soil 
improvement techniques. A variety of soil improvement 
techniques have been developed. However a suitable 
technique has to be adopt according to necessity of the 
structure and economy.
Thank you

More Related Content

What's hot

What is Ground Improvement Techniques?
What is Ground Improvement Techniques?What is Ground Improvement Techniques?
What is Ground Improvement Techniques?
roks99
 
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methods
Shivarajteggi
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
pjainrahul
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
jamali husain
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
Mohit Goyal
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement design
Rohit Ranjan
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
GARRE RAVI KUMAR
 
Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
Rushikesh Kolhe
 
Reinforced earth & its application
Reinforced earth & its applicationReinforced earth & its application
Reinforced earth & its application
Budarapu Venkat Pranay
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
Rakesh Reddy
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
Esri India
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
distress of concrete
distress of concretedistress of concrete
distress of concrete
kamariya keyur
 
GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES
harshitha alishetty
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
Seminar Links
 
Grouting
GroutingGrouting
Highway Materials Unit-III
Highway Materials  Unit-IIIHighway Materials  Unit-III
Highway Materials Unit-III
GAURAV. H .TANDON
 
Grouting in Soils
Grouting in SoilsGrouting in Soils
Grouting in Soils
Shoaib Wani
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
aditya choudhary
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
Imran Nawaz
 

What's hot (20)

What is Ground Improvement Techniques?
What is Ground Improvement Techniques?What is Ground Improvement Techniques?
What is Ground Improvement Techniques?
 
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methods
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement design
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
 
Reinforced earth & its application
Reinforced earth & its applicationReinforced earth & its application
Reinforced earth & its application
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
distress of concrete
distress of concretedistress of concrete
distress of concrete
 
GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
Grouting
GroutingGrouting
Grouting
 
Highway Materials Unit-III
Highway Materials  Unit-IIIHighway Materials  Unit-III
Highway Materials Unit-III
 
Grouting in Soils
Grouting in SoilsGrouting in Soils
Grouting in Soils
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
 

Similar to Ground Improvement Techniques

Vibration method for ground improvement technique
Vibration method for ground improvement techniqueVibration method for ground improvement technique
Vibration method for ground improvement technique
ABHISHEK THAKKAE
 
1206765 634528654292080000
1206765 6345286542920800001206765 634528654292080000
1206765 634528654292080000Civil Engineers
 
Chapter 6.0 modern foundation tech. & ground improvement
Chapter 6.0   modern foundation tech. & ground improvement Chapter 6.0   modern foundation tech. & ground improvement
Chapter 6.0 modern foundation tech. & ground improvement
DYPCET
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
Qasim Virk
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
NatarajaSaiCharan1
 
118039141-Soil-Improvement-Techniques.ppt
118039141-Soil-Improvement-Techniques.ppt118039141-Soil-Improvement-Techniques.ppt
118039141-Soil-Improvement-Techniques.ppt
FlittiAbdelhamid
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
Satish Kambaliya
 
ground improvement
ground improvementground improvement
ground improvement
INDRANIL BANERJEE
 
sand drain for consolidation settlement
sand drain for consolidation settlementsand drain for consolidation settlement
sand drain for consolidation settlement
subhamkabu123
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-DewateringMoe Abadla
 
5. Dewatering.pdf
5. Dewatering.pdf5. Dewatering.pdf
5. Dewatering.pdf
EmmanuelKiamaMutinda
 
Soil improvement Methods.pptx
Soil improvement Methods.pptxSoil improvement Methods.pptx
Soil improvement Methods.pptx
FlittiAbdelhamid
 
engineering practices for soil conservation
engineering practices for soil conservationengineering practices for soil conservation
engineering practices for soil conservation
Usman Khawaja
 
pdfslide.net_ppt-stone-columns.pptx
pdfslide.net_ppt-stone-columns.pptxpdfslide.net_ppt-stone-columns.pptx
pdfslide.net_ppt-stone-columns.pptx
SAYANSAHA963163
 
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITYBc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Sukhvinder Singh
 
5. Dewatering F1.pdf
5. Dewatering F1.pdf5. Dewatering F1.pdf
5. Dewatering F1.pdf
EmmanuelKiamaMutinda
 
Mechanical practices of soil conservation
Mechanical practices of soil conservation Mechanical practices of soil conservation
Mechanical practices of soil conservation
Usman Khawaja
 
mordern soil_improvement.ppt
mordern soil_improvement.pptmordern soil_improvement.ppt
mordern soil_improvement.ppt
HabibFatimi
 
Soil improvement
Soil improvementSoil improvement
Soil improvement
Mithra G
 

Similar to Ground Improvement Techniques (20)

Vibration method for ground improvement technique
Vibration method for ground improvement techniqueVibration method for ground improvement technique
Vibration method for ground improvement technique
 
1206765 634528654292080000
1206765 6345286542920800001206765 634528654292080000
1206765 634528654292080000
 
W16 ground improvement techniques-dycus
W16 ground improvement techniques-dycusW16 ground improvement techniques-dycus
W16 ground improvement techniques-dycus
 
Chapter 6.0 modern foundation tech. & ground improvement
Chapter 6.0   modern foundation tech. & ground improvement Chapter 6.0   modern foundation tech. & ground improvement
Chapter 6.0 modern foundation tech. & ground improvement
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
 
118039141-Soil-Improvement-Techniques.ppt
118039141-Soil-Improvement-Techniques.ppt118039141-Soil-Improvement-Techniques.ppt
118039141-Soil-Improvement-Techniques.ppt
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
ground improvement
ground improvementground improvement
ground improvement
 
sand drain for consolidation settlement
sand drain for consolidation settlementsand drain for consolidation settlement
sand drain for consolidation settlement
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-Dewatering
 
5. Dewatering.pdf
5. Dewatering.pdf5. Dewatering.pdf
5. Dewatering.pdf
 
Soil improvement Methods.pptx
Soil improvement Methods.pptxSoil improvement Methods.pptx
Soil improvement Methods.pptx
 
engineering practices for soil conservation
engineering practices for soil conservationengineering practices for soil conservation
engineering practices for soil conservation
 
pdfslide.net_ppt-stone-columns.pptx
pdfslide.net_ppt-stone-columns.pptxpdfslide.net_ppt-stone-columns.pptx
pdfslide.net_ppt-stone-columns.pptx
 
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITYBc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
 
5. Dewatering F1.pdf
5. Dewatering F1.pdf5. Dewatering F1.pdf
5. Dewatering F1.pdf
 
Mechanical practices of soil conservation
Mechanical practices of soil conservation Mechanical practices of soil conservation
Mechanical practices of soil conservation
 
mordern soil_improvement.ppt
mordern soil_improvement.pptmordern soil_improvement.ppt
mordern soil_improvement.ppt
 
Soil improvement
Soil improvementSoil improvement
Soil improvement
 

Recently uploaded

Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 

Recently uploaded (20)

Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 

Ground Improvement Techniques

  • 1. Presentation on Ground improvement techniques Nilesh Bhosale M.Tech. Transportation Engg.
  • 2. Introduction  Transportation contributes to the industrial, economic, social and cultural development of nation  Transportation by road or highways is the only mode which could give maximum service to one and all.  When the soil on a project site cannot support the loads, ground improvement to increase strength, reduce compressibility, and enhance performance under applied loadings may be required.  Various methods are discussed below:
  • 3. METHODS FOR GROUND IMPROVEMENT 1. VERTICAL DRAINS 2. SOIL NAILING 3. STONE COLUMNS 4. VIBRO COMPACTION 5. DYNAMIC COMPACTION
  • 4. VERTICAL DRAINS  These consist of a column of pervious material placed in cylindrical vertical holes at sufficiently close spaces.  All drains should be connected at the ground surface to a drainage blanket.  Vertical drains accelerate consolidation by facilitating drainage of pore water.  Vertical drains are laid out in rows, staggered, or aligned to form patterns of equilateral triangles or squares.  Two types of drains are discussed below
  • 5. SAND DRAINS A sand drain is a simple process, employing a column of at least 10 inches in width augered into ground to be surcharged & consolidated. The column is then filled with sand and connected to a free-draining blanket of granular soil.
  • 6. WICK DRAIN • A wick drain is usually about, 4 inches wide, 1/8-inch thick which acts as a high-permeability conduit for water to flow out of the soil and to the surface. • Most common application of wick drains is for accelerating the settlement rate of compressible soils.
  • 7. SOIL NAILING • This ground reinforcement process uses steel tendons which are drilled and grouted into the soil to create a composite mass. • A shotcrete facing is typically applied. • Soil Nailing is an in situ technique for reinforcing, stabilizing and retaining excavations and deep cuts.
  • 9. Holes are drilled though machine
  • 11. Stone column  Also known as vibro-replacement or vibro-displacement, is a ground improvement process where vertical columns of compacted aggregate are formed through the soils to be improved.  The vibrator first penetrates to the required depth by vibration and air or water jetting or by vibration alone.  Gravel is then added at the tip of the vibrator and progressive raising and repenetration of the vibrator results in the gravel being pushed into the surrounding soil.  The soil-column matrix results in an overall mass having a high shear strength and a low compressibility.
  • 13.
  • 14. Vibro compaction • It is a ground improvement process for densifying loose sands to create stable foundation soils. • The action of the vibrator, usually accompanied by water jetting, reduces the inter-granular forces between the soil particles, allowing them to move into a denser configuration, typically achieving a relative density of 70 to 85 percent. • Compaction is achieved above and below the water table.
  • 16. Process of vibro compaction
  • 17. Dynamic compaction  Dynamic Compaction is the dropping of heavy weights on the ground surface to densify the soils at depth.  It involves the repeated dropping of large steel tampers by means of crawler cranes.  Tampers typically range from 6 to 20 tons and are dropped from heights of about 40 to 80 feet.
  • 18. MACHINE WITH TAMPER COMPACTION BY TAMPER
  • 19. Conclusion • Soil conditions can frequently be improved using soil improvement techniques. A variety of soil improvement techniques have been developed. However a suitable technique has to be adopt according to necessity of the structure and economy.