BIM-Enabled IPD Laura Handler Sarah Vekasy, AIA Virtual Construction Manager Associate
Our Three Steps 1 2 3 Building  Information  Model Virtual  Design &  Construction Integrated Project Delivery
IPD is like…
IPD is like…
IPD  IS…
We Won’t Focus On IPD Contract Principles, But… Profit Pooling & Shared Risk Shared Success Criteria Rated by an Independent Judge Partners Covenant - Zero Litigation
The Integrated Team
Here’s Our Focus: Modeling Goals Shared Revit Model = Shared Revit File s NavisWorks Manage BIM Management Direct From Model Fabrication LEED/Sustainability Analysis Quantities Extracted from the Model Schedule “Infused” in the Model
It All Starts With the BEP
Selecting BIM Leads
Autodesk BIM Portfolio: Revit Architecture 2009 Revit MEP 2009 Navisworks Manage Quantity Takeoff (QTO) Design Review (DWF) Inventor Buzzsaw Software Selection 3 rd  Party Software: CAD Duct CAD Pipe Hydro CAD Wood WAP Document Locator
Revit Standards: File Nomenclature
Revit Standards: Phases
Revit Standards: Worksets
Revit Standards: Parameters
Revit Standards: Materials
Model Location & Access Design Construction: Architecture Engineering Construction Architecture Engineering Construction Subcontractors FTP VPN Live VPN Live VPN Live
Enough planning, let’s start design…
Design: Options
Design : Costing
Design: Communicating
Design: Co-Locating
Design: Advanced Bill of Materials
Programming Wall-Splitting Design Layout KlingStubbins Tocci KlingStubbins Tocci Design: Model Collaboration
Design: Documentation
Design: Communicating
Design: Communicating
Design Documentation Fabrication Installation MEP: (Lack of?) Model Collaboration
MEP: Design
MEP: Model Transfers
Architect Builder Mechanical Engineer HVAC Sub Electrical Engineer MEP: Co-Locating
MEP: Co-Locating
MEP: Costing
Coordination: Clash Detection
Coordination: Clash Detection
Coordination: Documentation
Coordination: Documentation
Millwork: Design
Millwork: Costing
Millwork: Fabrication Model
Millwork: Fabrication Model
Millwork: Fabrication Model
Millwork: Fabrication
Millwork: Co-Locating
Millwork: Co-Locating
Millwork: Co-Locating
Execution: Communicating Design
Execution: Communicating Detail
Execution: Visualization
Execution: Visualization
Execution: Visualization
Execution: Visualization
Execution: Co-Locating
Execution: Co-Locating
Barriers to IPD .  Letting lawyers lead
Barriers to IPD .  Caged thinking
Barriers .  Drawings are the deliverable
Barriers .  Failure to engage means & methods
Barriers .  Lack of sensitivity
Barriers .  Failed Handoffs
Barriers .  Patience is (not) a virtue
Barriers .  Indecision Kills
MasterBuilder 2.0
Laura Handler Sarah Vekasy, AIA [email_address] [email_address]

Bim Enabled Ipd