Goal
Introduce the Concept of BIM and applying it on a Project, from Schematic
design through Construction Documentation
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
Objectives of the Lecture
At the end of this Lecture, you will be able to:
 Define BIM
 Determine Origins of BIM
 Recognize the importance of BIM in Building Industry
 Being Aware of BIM Products and uses:
o Create 3D Intelligent Model
o Change Management
o Team Collaboration
o Building Simulation
o Clash Detection
o Interoperability ‘Integration’
o Remote Access
 Benefits of BIM to the Project Management Body of Knowledge
 Apply the BIM Concept on a Real Project (Case Studies)
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
Introduction
BIM Definition:
Building Information Modeling
BIM is a digital representation
of physical and functional
characteristics of a facility. BIM
is a shared knowledge resource
for information about a facility
forming a reliable basis for
decisions during its life-cycle;
defined as existing from earliest
conception to demolition.
(National BIM Standard - United States)
BUILDING
INFORMATION
MODELING
ARCHITECTS
STRUCTURAL
ENGINEERS
MEP SYSTEMS
ENGINEERS
BUILDERS &
FABRICATORS
OWNERS
CIVIL
ENGINEERS
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
Origins of BIM
 In 1963 Ivan Sutherland develops SketchPad
as a drawing assistant for part of his Ph.D
dissertation.
 In 1970 BIM concepts was born.
 In 1987 The first implementation of BIM product
by Graphisoft, ArchiCAD was released.
 In 2002 Autodesk acquire Revit Technology
Corporation.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
BIM is very much talked about in the Building
Industry
BUT
What is it really?
Why we use it?
How can we use it?
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
Some say BIM is a Process.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
Some say BIM is a type of Software.
Some say BIM is a Process.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
Some say BIM is the 3D Model of a building.
Some say BIM is a type of Software.
Some say BIM is a Process.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
And others say BIM is just an Organized Collection
of all Building Data.
Some say BIM is the 3D Model of a building.
Some say BIM is a Process.
Some say BIM is a type of Software.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
BIM is all the previous and more…
So we can say that BIM is the Process that we use a Software to Create
a 3D Model with an Organized Collection of all Building Data.
And others say BIM is just an Organized Collection
of all Building Data.
Some say BIM is the 3D Model of a building.
Some say BIM is a Process.
Some say BIM is a type of Software.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
BIM Product and its uses:
1- 3D Intelligent Model
It begins with a 3D digital model, this model is more than just a geometry and some
textures added to it for visualization.
A true BIM model consists of the virtual equivalents of the actual building sections
used to create a building.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
BIM Product and its uses:
1- 3D Intelligent Model
It begins with a 3D digital model, this model is more than just a geometry and some
textures added to it for visualization.
A true BIM model consists of the virtual equivalents of the actual building sections
used to create a building.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
BIM Product and its uses:
1- 3D Intelligent Model
It begins with a 3D digital model, this model is more than just a geometry and some
textures added to it for visualization.
A true BIM model consists of the virtual equivalents of the actual building sections
used to create a building.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
2- Change Management
Parametric relationships
Objects are defined as parameters and relations to other objects, so that if a related
object is modified, dependent ones will automatically change.
Door
Wall
Window
BIM Product and its uses:
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
2- Change Management
Parametric relationships
Objects are defined as parameters and relations to other objects, so that if a
related object is modified, dependent ones will automatically change.
BIM Product and its uses:
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
BIM Product and its uses:
2- Change Management
Bidirectional Associativity
Since data is stored in a central place in a BIM model, any modification to the building
design will be automatically replicated in each view, such as floor plans, sections,
elevations and also the schedules.
This not only helps in creating the documentation faster, but also provides automatic
coordination of different views.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
BIM Product and its uses:
2- Change Management
Bidirectional Associativity
Since data is stored in a central place in a BIM model, any modification to the building
design will be automatically replicated in each view, such as floor plans, sections,
elevations and also the schedules.
This not only helps in creating the documentation faster, but also provides automatic
coordination of different views.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
3- Team Collaboration
BIM Supports the team work concept and helps more than one member to work on the
same model, from early design through to completion, changes are automatically
coordinated across the project and information generated is therefore of high quality.
BIM Product and its uses:
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
4- Building Simulation
BIM model contains more than just Architectural data; information about the different
engineering disciplines (Arch, STR, and MEP), sustainability information, and other
characteristics can be easily simulated in advance of actual construction.
BIM Product and its uses:
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
5- Clash Detection
Through BIM process, Engineers are able to identify conflicts between model elements
and resolve interferences and other issues early in the design phase, enabling to make
design correction faster before the impact construction cost and schedules.
BIM Product and its uses:
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
6- Interoperability “Integration”
BIM process provides the ability of two separate systems or software programs to
communicate and exchange data with each other.
BIM Product and its uses:
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
7- Remote Access to Project Data
Making data easy to access for and from anywhere through the usable mobile devices,
viewing the latest models and comparing them with the actual work in the field, this
make it easier to identify the potential design issues.
BIM Product and its uses:
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
BIM Product and its uses:
7- Remote Access to Project Data
Making data easy to access for and from anywhere through the usable mobile devices,
viewing the latest models and comparing them with the actual work in the field, this
make it easier to identify the potential design issues.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
BIM Product and its uses:
7- Remote Access to Project Data
Making data easy to access for and from anywhere through the usable mobile devices,
viewing the latest models and comparing them with the actual work in the field, this
make it easier to identify the potential design issues.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
What are the benefits of BIM for the
Project Management Knowledge Areas?
The data put in the a BIM model
is not only useful during the
design and construction phase
of a building project but can be
used throughout the entire
building lifecycle, helping to
reduce the operation and
management cost of buildings,
which is significantly more than
the entire cost of construction.
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
 The result of all the previous benefits of working with BIM Technology:
 Preconstruction benefits to owner.
 Increase building performance.
 Reduce the financial risk.
 Accelerate Decision Making.
 Shorten the project schedule.
 Obtain reliable and accurate cost estimates.
 Assure program compliance.
 Optimize facility management and maintenance.
What are the benefits of BIM for the
Project Management Knowledge Areas?
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
Conclusion
You are now have the knowledge of creating Single Model Database.
With all the benefits BIM has to offer, don’t let
your competition get to BIM before you do!
Architecture Engineering and Technology (AET), Faculty of Engineering, Cairo University - November 2014
BIM Introduction
By: Mohamed Mohsen Kamel
Don’t Hesitate to contact me
E-mail: m_mohsen_k@hotmail.com
Cellular: +2 0100 294 2851
Fan Page: BIM Code
http://www.facebook.com/The.BIM.Code
Group: BIM Code (Revit ARCH, STR, MEP)
http://www.facebook.com/groups/BIM.Experts
THANK YOU!

BIM Introduction

  • 1.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIMIntroduction Prepared and Presented by: Mohamed Mohsen Kamel BIM Specialist ǀ Architect Autodesk Certified & Approved Instructor Revit Architecture Certified Professional
  • 2.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel Goal Introduce the Concept of BIM and applying it on a Project, from Schematic design through Construction Documentation
  • 3.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel Objectives of the Lecture At the end of this Lecture, you will be able to:  Define BIM  Determine Origins of BIM  Recognize the importance of BIM in Building Industry  Being Aware of BIM Products and uses: o Create 3D Intelligent Model o Change Management o Team Collaboration o Building Simulation o Clash Detection o Interoperability ‘Integration’ o Remote Access  Benefits of BIM to the Project Management Body of Knowledge  Apply the BIM Concept on a Real Project (Case Studies)
  • 4.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel Introduction BIM Definition: Building Information Modeling BIM is a digital representation of physical and functional characteristics of a facility. BIM is a shared knowledge resource for information about a facility forming a reliable basis for decisions during its life-cycle; defined as existing from earliest conception to demolition. (National BIM Standard - United States) BUILDING INFORMATION MODELING ARCHITECTS STRUCTURAL ENGINEERS MEP SYSTEMS ENGINEERS BUILDERS & FABRICATORS OWNERS CIVIL ENGINEERS
  • 5.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel Origins of BIM  In 1963 Ivan Sutherland develops SketchPad as a drawing assistant for part of his Ph.D dissertation.  In 1970 BIM concepts was born.  In 1987 The first implementation of BIM product by Graphisoft, ArchiCAD was released.  In 2002 Autodesk acquire Revit Technology Corporation.
  • 6.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIM is very much talked about in the Building Industry BUT What is it really? Why we use it? How can we use it?
  • 7.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel Some say BIM is a Process.
  • 8.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel Some say BIM is a type of Software. Some say BIM is a Process.
  • 9.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel Some say BIM is the 3D Model of a building. Some say BIM is a type of Software. Some say BIM is a Process.
  • 10.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel And others say BIM is just an Organized Collection of all Building Data. Some say BIM is the 3D Model of a building. Some say BIM is a Process. Some say BIM is a type of Software.
  • 11.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIM is all the previous and more… So we can say that BIM is the Process that we use a Software to Create a 3D Model with an Organized Collection of all Building Data. And others say BIM is just an Organized Collection of all Building Data. Some say BIM is the 3D Model of a building. Some say BIM is a Process. Some say BIM is a type of Software.
  • 12.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIM Product and its uses: 1- 3D Intelligent Model It begins with a 3D digital model, this model is more than just a geometry and some textures added to it for visualization. A true BIM model consists of the virtual equivalents of the actual building sections used to create a building.
  • 13.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIM Product and its uses: 1- 3D Intelligent Model It begins with a 3D digital model, this model is more than just a geometry and some textures added to it for visualization. A true BIM model consists of the virtual equivalents of the actual building sections used to create a building.
  • 14.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIM Product and its uses: 1- 3D Intelligent Model It begins with a 3D digital model, this model is more than just a geometry and some textures added to it for visualization. A true BIM model consists of the virtual equivalents of the actual building sections used to create a building.
  • 15.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel 2- Change Management Parametric relationships Objects are defined as parameters and relations to other objects, so that if a related object is modified, dependent ones will automatically change. Door Wall Window BIM Product and its uses:
  • 16.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel 2- Change Management Parametric relationships Objects are defined as parameters and relations to other objects, so that if a related object is modified, dependent ones will automatically change. BIM Product and its uses:
  • 17.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIM Product and its uses: 2- Change Management Bidirectional Associativity Since data is stored in a central place in a BIM model, any modification to the building design will be automatically replicated in each view, such as floor plans, sections, elevations and also the schedules. This not only helps in creating the documentation faster, but also provides automatic coordination of different views.
  • 18.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIM Product and its uses: 2- Change Management Bidirectional Associativity Since data is stored in a central place in a BIM model, any modification to the building design will be automatically replicated in each view, such as floor plans, sections, elevations and also the schedules. This not only helps in creating the documentation faster, but also provides automatic coordination of different views.
  • 19.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel 3- Team Collaboration BIM Supports the team work concept and helps more than one member to work on the same model, from early design through to completion, changes are automatically coordinated across the project and information generated is therefore of high quality. BIM Product and its uses:
  • 20.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel 4- Building Simulation BIM model contains more than just Architectural data; information about the different engineering disciplines (Arch, STR, and MEP), sustainability information, and other characteristics can be easily simulated in advance of actual construction. BIM Product and its uses:
  • 21.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel 5- Clash Detection Through BIM process, Engineers are able to identify conflicts between model elements and resolve interferences and other issues early in the design phase, enabling to make design correction faster before the impact construction cost and schedules. BIM Product and its uses:
  • 22.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel 6- Interoperability “Integration” BIM process provides the ability of two separate systems or software programs to communicate and exchange data with each other. BIM Product and its uses:
  • 23.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel 7- Remote Access to Project Data Making data easy to access for and from anywhere through the usable mobile devices, viewing the latest models and comparing them with the actual work in the field, this make it easier to identify the potential design issues. BIM Product and its uses:
  • 24.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIM Product and its uses: 7- Remote Access to Project Data Making data easy to access for and from anywhere through the usable mobile devices, viewing the latest models and comparing them with the actual work in the field, this make it easier to identify the potential design issues.
  • 25.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel BIM Product and its uses: 7- Remote Access to Project Data Making data easy to access for and from anywhere through the usable mobile devices, viewing the latest models and comparing them with the actual work in the field, this make it easier to identify the potential design issues.
  • 26.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel What are the benefits of BIM for the Project Management Knowledge Areas? The data put in the a BIM model is not only useful during the design and construction phase of a building project but can be used throughout the entire building lifecycle, helping to reduce the operation and management cost of buildings, which is significantly more than the entire cost of construction.
  • 27.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel  The result of all the previous benefits of working with BIM Technology:  Preconstruction benefits to owner.  Increase building performance.  Reduce the financial risk.  Accelerate Decision Making.  Shorten the project schedule.  Obtain reliable and accurate cost estimates.  Assure program compliance.  Optimize facility management and maintenance. What are the benefits of BIM for the Project Management Knowledge Areas?
  • 28.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel Conclusion You are now have the knowledge of creating Single Model Database. With all the benefits BIM has to offer, don’t let your competition get to BIM before you do!
  • 29.
    Architecture Engineering andTechnology (AET), Faculty of Engineering, Cairo University - November 2014 BIM Introduction By: Mohamed Mohsen Kamel Don’t Hesitate to contact me E-mail: m_mohsen_k@hotmail.com Cellular: +2 0100 294 2851 Fan Page: BIM Code http://www.facebook.com/The.BIM.Code Group: BIM Code (Revit ARCH, STR, MEP) http://www.facebook.com/groups/BIM.Experts THANK YOU!

Editor's Notes