SlideShare a Scribd company logo
ARCHITECTURAL
WORKING DRAWINGS
ARCHITECT SANJIB SENGUPTA
What is Architectural Working Drawing.
Is a organized technical drawing of a building (or
building project) having all required information and
instruction in graphical form to enable us to erect the
building/ building project on site/ground. It is called
construction documents(CD). Traditionally, working
drawings consist of 2 dimensional orthogonal projections
of the building or component they are describing, such as
plans, sections, elevations, details, schedules and
specification etc. It is a tool of communication. It is legal
foundation for the project.
Purpose of Architectural Working Drawing.
1. To develop a design idea into a coherent proposal.
2. To communicate technical information among design and construction
teams.
3. To provide information for preparation of structural design and
drawings for foundation, columns, beams, floor slabs , staircase and
any other structural component of a building.
4. To provide information for preparation of Acoustic Design, Electrical,
HVAC, mechanical, Fire Fighting, Plumbing, Sanitary, external &
internal finish and interior furnishing etc. drawings.
5. To provide information for preparation of specifications and detailed
estimates for civil, acoustic design, electrical, plumbing, horticulture,
landscape, site development etc. works.
6. To provide information for preparation of Bill of Quantities of various
items and materials to be used in construction of the building.
7. To guide the contractor & construction team.
8. To obtain approval of Local Self Government, Fire Department, Urban
Art Commission and other Statutory Authorities.
Purpose of Architectural Working Drawing.
(Cont----)
9. To provide information for preparation of tender document.
10. To show how the design is to be materialized.
11. To serve as reference for supervision of construction works at site.
12. To start and complete the execution of the construction of building
on the basis of the information given in the drawing.
13. To convey the design intent to the contractor for bidding and
construction
14. To prepare the shop drawing, to fabricate components of the works
or to assemble or install components
15. To make a record of existing building/structure and completed
works.
16. Act as a basis for ordering materials and components .
17. Assist in the measurement of construction progress
18. Records of completed works and building that
already exists.
How Architectural Working Drawing is prepared
Is made according to a set of conventions, which include particular views (floor
plan, section , elevations, specifications and details etc.), sheet sizes, units of
measurement and scales, annotation and cross referencing, for maintaining the
uniformity of drawing in terms of scale , line weight/thickness, line type , size of
sheet and symbols etc.
Working Drawing may be very simple or very complex depending upon the
project. The complexity of the drawing is a factor in determining the size of sheet.
Is made to show how the design is to be implemented , therefore should give the
contractor exactly the information he needs and relevant data.
Traditionally, consist of 2 dimensional orthogonal projections of the building or
component they are describing, such as plans, sections , elevations and details etc.
Includes title block, dimensions, notation, notes & symbols consistent with
industry standards so that their precise meaning is clear & can be understood.
Specification information can be included on working drawings or in a separate
specification sheet, but information should not be duplicated as this can become
contradictory and may cause confusion.
Criteria of good Architectural Working Drawing.
1. Accurately Drawn with appropriate symbols, notations, conventions,
graphical representation and all relevant information.
2. Information should not be duplicated as this can become contradictory
and may cause confusion.
3. Structured and dimensioned well carefully so that they convey
necessary information to carry out particular parts of the works.
4. The Layout of the drawing and text on the drawing shall be such as to
facilitate the reading of drawing and make it possible for essential
references to be located easily.
5. Drawn in appropriate scale logically and neatly arranged and properly
titled.
6. Standard abbreviations, Schedule formats, Material designations.
7. Required information for preparation of tender document.
8. Serve as reference for supervision of construction works at site.
9. The scale at which drawings are prepared should reflect the level of
detail of the information they are required to convey. Different line
thicknesses should be used to provide greater clarity for certain
elements.
Layout of Drawings.
1. The layout of drawings shall be such as to facilitate
the reading of drawings and make it possible for
essential references to be located easily.
2. The Standard arrangements shall include all
relevant information and sufficient margins shall
be left from the edges of finished drawings to
facilitate filing and binding where necessary.
3. Margins, the provision of blank border will enable
prints to be trimmed, if necessary, without incurring
the use of uneconomical sizes of sensitized material
to allow for trimming.
4. There should be marked with zones.
Basic contents of
Architectural Working
Drawings
1. Title Block
2. Site Layout Plan
3. Column Layout Plan in case of frame
structure building.
4. Foundation layout Plan in case of load
bearing structure.
5. Foundation details
6. Excavation Plans
7. Floor Plans including basement floor if
any
8. Roof Plan
9. Elevations
10. Sections
11. Services Layout plan
12. Door window Details
13. Electrical Layout & HVAC Plan
14. Plumbing layout plan
15. Structural details plan of Footings,
Columns, Beams, Slabs, Staircase etc.
16. Toilet Details
nosing, risers & tread
18. Kitchen details.
19. Iron mongaries
20. Reflected Ceiling plan
21. Typical Details of various components
& elements, like cupboard, flooring
pattern etc.
22. Specification of various finishes and
building materials
23. Shop drawings wherever required.
24. Beam- column layout
25. Brickwork layout
26. PHE drawing
27. Fire Fighting drawing.
28. Drainage system
29. Landscape, Horticulture, Circulation &
Site Development.
30. Furniture Layout
31. Acoustic Design
32. Area Calculation
33. Internal & External Colour Scheme
34. Schedules.
Size of Drawing Sheet.
Sl. No. Designation Trimmed Size
In mm
Untrimmed
Size in mm
1. A0 841 x 1189 880 x 1230
2. A1 594 x 841 625 x 880
3. A2 420 x 594 450 x 625
4. A3 297 x 420 330 x 450
5. A4 210 x 297 240 x 330
6. A5 148 x 210 165 x 240
The trimmed sizes are on the following basic principles
1. Two successive sizes of the series are obtained by halving or doubling. Consequently,
the surface areas of two successive sizes are in the ratio of 1:2 appx.
2. The formats or forms are geometrically similar to one another , the sides of each size
being in the ratio of 1:√2.
3. The surface area of the basic size A0 is one square metre
Title Block
1.The title block is an important
feature in a drawing , since it
facilitates obtaining uniformity and
presents in definite manner the
details like title of drawing, Job
Title, Name of Organization or
Firm, Name of Architect, Name of
Structural Engineer, Drawing
Number, Scale, Date of Drawing,
North Direction , Dated initials of
Technical Staff preparing checking
the drawing, Revision Panels, Key
Plan, Notes, List of Reference
Drawings, Schedules etc.
2. The width of title block shall be
150 mm.
Title Block ( contd.---)
Standard Notes in Title Block:
1. This Drawing has been prepared on the basis of preliminary architectural drawings
bearing number_____________.
2. All dimensions are in “mm” unless otherwise specified.
3. Drawing not to be measured only written dimensions to be followed.
4. This drawing should be read in conjunction with relevant Architectural/structural
drawing .
5. The sizes of Columns and Beams in this drawing are in accordance with Structural
Drawing number __________.
6. Any discrepancies between this drawing and correspondence/ related structural
drawing should immediately be brought to the notice of the Architect before execution
and work should not be carried out at site till the discrepancies are not removed.
7. All external walls are _____mm thick and all internal walls are _____mm thick Brick/
RCC walls unless otherwise specified.
8. The building shall be constructed in full compliance with all applicable codes,
ordinances and regulations as well as the drawings and specifications. Any code
deficiencies in the drawings recognized by the contractor should be brought to the
attention of the architect for clarification.
9. Any other notes as deemed fit by the Architect and relevant to the drawing.
Title Block ( contd.---)
CONSTRUCTION DOCUMENT SHEET NUMBERS AND SHEET ORDER
United States National CAD Standard:
Components of the Sheet Number:-
• There are three components that make up sheet numbers in a set of construction
documents. The first two letters, the discipline designators, identify the construction
discipline that the sheet covers - architectural sheets, plumbing sheets, structural sheets,
etc. The third digit, the sheet type, is a number that represents the type of drawings that
are on the sheet - plans, sections, details, schedules, etc. The final two digits, the
sequence numbers, are numbers that simply place the sheets in order.
• The Discipline Designator can be a single letter or a double-letter. Very large or complex
projects will want to make use of the double-letter designations to help sub-divide each
discipline further.
• The Sheet Types Designator takes the drawings of a single discipline and organizes
them. Drawings are always organized from most general to most specific or specialized.
Since plans are most helpful to see the overall design of the project, they come first.
Elevations and sections are a bit more specific and come next followed by details and
schedules, which are the most specific type of drawings.
• Sequence Number, which is two-digit between 01 and 99. The sequence numbers do not
have to be sequential so that space may be left within the set for future additions.
Title Block ( contd.---)
CONSTRUCTION DOCUMENT SHEET NUMBERS AND SHEET ORDER
The following table indicates the primary (single) letter designations that may be used and the order that the
disciplines should take. In this case, a hyphen shall be inserted in place of the secondary discipline designator so that
the format remains.
Designator Name Additional Description
Cover Sheet
G General Sheet list, symbols, code summary, etc.
H Hazardous Materials Abatement, handling, etc.
V Survey / Mapping
B Geotechnical
C Civil
L Landscape
S Structural
A Architectural
I Interiors
Q Equipment
F Fire Protection
P Plumbing
D Process
Title Block ( contd.---)
CONSTRUCTION DOCUMENT SHEET NUMBERS AND SHEET ORDER
Designator Name Additional Description
M Mechanical
E Electrical
T Telecommunications
R Resource Existing Condition/ Building
X Other Disciplines
Z Contractor / Shop Drawings
O Operations
The Sheet Types designator takes the drawings of a single discipline and organizes
them. Drawings are always organized from most general to most specific or specialized.
Since plans are most helpful to see the overall design of the project, they come first.
Elevations and sections are a bit more specific and come next followed by details and
schedules, which are the most specific type of drawings.
Site Layout plans
Site plans usually show the extent of the site but no surrounding detail.
Recommended scales are:
1 : 500, 1 : 200
The function of the site plan is to show:
1. The location of the proposed building or buildings with reference to a bench
mark and in relation to surroundings of the plot.
2. The topography of the site, with both existing and finished levels.
3. Existing Buildings to be demolished or removed or retained.
4. The extent of earthworks, included, cutting and filling, and the provision of
bank and retaining walls.
5. Roads, footpaths, hard standings and paved areas.
6. Planting.
7. The layout of external service runs, including drainage, water, gas,
electricity, telephone, etc.
8. The layout of external lighting.
9. Fencing, walls and gates.
10. The location of miscellaneous external components – bollards, litter bins,
etc.
Column Layout Plan in Case of Framed
Structured Building
Thumb rules to be followed for column layout plan are:-
1. Always Plan a Column layout on a planning grid.
2. Column Spacing, i.e. Distances between columns in X
& Y Directions.
3. Show Column numbers.
4. Show Sizes of Columns
5. Show Alignment of Columns
Foundation Layout Plan in Case of
Framed Load Bearing Building
Site plans usually show the extent of the site but no surrounding detail.
Recommended scales are:
1 : 500
1 : 200
The function of the site plan is to show:
1. The location of the building or buildings in relation to their surroundings.
2. The topography of the site, with both existing and finished levels.
3. Buildings to be demolished or removed.
4. The extent of earthworks, included, cutting and filling, and the provision of
bank and retaining walls.
5. Roads, footpaths, hard standings and paved areas.
6. Planting.
7. The layout of external service runs, including drainage, water, gas,
electricity, telephone, etc.
8. The layout of external lighting.
9. Fencing, walls and gates.
10. The location of miscellaneous external components – bollards, litter bins,
etc.
Foundation Layout
Elevation
Staircase Details
Floor and Parapet details
Electrical drawing.
Architectural working drawing

More Related Content

What's hot

Toilet and Bath Working Drawing
Toilet and Bath Working DrawingToilet and Bath Working Drawing
Toilet and Bath Working Drawing
Geeva Chandana
 
Architectural Design Process for Beginners/Students
Architectural Design Process for Beginners/StudentsArchitectural Design Process for Beginners/Students
Architectural Design Process for Beginners/Students
Gary Gilson
 
Time-Saver Standards for Architectural Design Data (Malestrom).pdf
Time-Saver Standards for Architectural Design Data (Malestrom).pdfTime-Saver Standards for Architectural Design Data (Malestrom).pdf
Time-Saver Standards for Architectural Design Data (Malestrom).pdf
aigle3
 
Architectural Drawing
Architectural DrawingArchitectural Drawing
Architectural Drawing
Lea Alberto
 
Geodesic Dome - History and Construction
Geodesic Dome - History and ConstructionGeodesic Dome - History and Construction
Geodesic Dome - History and Construction
Azra Maliha
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture II
Ar. Mukunda K.S
 
Architectural competitions
Architectural  competitionsArchitectural  competitions
Architectural competitions
zehbamp
 
Section Working Drawing
Section Working DrawingSection Working Drawing
Section Working Drawing
Weam Adam
 
case study of residential buildings
case study of residential buildingscase study of residential buildings
case study of residential buildings
abhisubedi
 
Architectural drawing pdf
Architectural drawing pdfArchitectural drawing pdf
Architectural drawing pdf
AbhishekChavan63
 
Concepts in Architecture
Concepts in ArchitectureConcepts in Architecture
Concepts in Architecture
Piloo Mody College of Architecture
 
Architects professional liability
Architects professional liabilityArchitects professional liability
Architects professional liability
Aditi Garg
 
Architectural case study of Apartments
Architectural case study of ApartmentsArchitectural case study of Apartments
Architectural case study of Apartments
Tanzil Faraz
 
Case study on Apartment
Case study on ApartmentCase study on Apartment
Case study on Apartment
Asmit Kiran Bhattarai
 
Architecture in Hot and humid climate
Architecture in Hot and humid climateArchitecture in Hot and humid climate
Architecture in Hot and humid climateMaitreyi Yellapragada
 
architectural working drawings
architectural working drawings  architectural working drawings
architectural working drawings
Aditya Sanyal
 
Space frames
Space framesSpace frames
Space frames
Bnv Aditya
 
Nbc ppt
Nbc pptNbc ppt
Group housing case study
Group housing case studyGroup housing case study
Group housing case study
Vishwas Sahni
 
Architectural drafting-Ar.Archana Sreedharan
Architectural drafting-Ar.Archana SreedharanArchitectural drafting-Ar.Archana Sreedharan
Architectural drafting-Ar.Archana Sreedharan
archsree
 

What's hot (20)

Toilet and Bath Working Drawing
Toilet and Bath Working DrawingToilet and Bath Working Drawing
Toilet and Bath Working Drawing
 
Architectural Design Process for Beginners/Students
Architectural Design Process for Beginners/StudentsArchitectural Design Process for Beginners/Students
Architectural Design Process for Beginners/Students
 
Time-Saver Standards for Architectural Design Data (Malestrom).pdf
Time-Saver Standards for Architectural Design Data (Malestrom).pdfTime-Saver Standards for Architectural Design Data (Malestrom).pdf
Time-Saver Standards for Architectural Design Data (Malestrom).pdf
 
Architectural Drawing
Architectural DrawingArchitectural Drawing
Architectural Drawing
 
Geodesic Dome - History and Construction
Geodesic Dome - History and ConstructionGeodesic Dome - History and Construction
Geodesic Dome - History and Construction
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture II
 
Architectural competitions
Architectural  competitionsArchitectural  competitions
Architectural competitions
 
Section Working Drawing
Section Working DrawingSection Working Drawing
Section Working Drawing
 
case study of residential buildings
case study of residential buildingscase study of residential buildings
case study of residential buildings
 
Architectural drawing pdf
Architectural drawing pdfArchitectural drawing pdf
Architectural drawing pdf
 
Concepts in Architecture
Concepts in ArchitectureConcepts in Architecture
Concepts in Architecture
 
Architects professional liability
Architects professional liabilityArchitects professional liability
Architects professional liability
 
Architectural case study of Apartments
Architectural case study of ApartmentsArchitectural case study of Apartments
Architectural case study of Apartments
 
Case study on Apartment
Case study on ApartmentCase study on Apartment
Case study on Apartment
 
Architecture in Hot and humid climate
Architecture in Hot and humid climateArchitecture in Hot and humid climate
Architecture in Hot and humid climate
 
architectural working drawings
architectural working drawings  architectural working drawings
architectural working drawings
 
Space frames
Space framesSpace frames
Space frames
 
Nbc ppt
Nbc pptNbc ppt
Nbc ppt
 
Group housing case study
Group housing case studyGroup housing case study
Group housing case study
 
Architectural drafting-Ar.Archana Sreedharan
Architectural drafting-Ar.Archana SreedharanArchitectural drafting-Ar.Archana Sreedharan
Architectural drafting-Ar.Archana Sreedharan
 

Similar to Architectural working drawing

Wk3 cd1 site-f-plan1
Wk3 cd1 site-f-plan1Wk3 cd1 site-f-plan1
Wk3 cd1 site-f-plan1
VARDTDS123
 
Asu history and theory lecture 5-design development 18-11-2017
Asu history and theory lecture 5-design development 18-11-2017Asu history and theory lecture 5-design development 18-11-2017
Asu history and theory lecture 5-design development 18-11-2017
Galala University
 
Asu history and theory lecture 5-design development 18-11-2017
Asu history and theory lecture 5-design development 18-11-2017Asu history and theory lecture 5-design development 18-11-2017
Asu history and theory lecture 5-design development 18-11-2017
Galala University
 
Construction Documents Guide: Types and Significance in 2024
Construction Documents Guide: Types and Significance in 2024Construction Documents Guide: Types and Significance in 2024
Construction Documents Guide: Types and Significance in 2024
Chandresh Chudasama
 
Building Drawing(CE3G)- Introduction.ppt
Building Drawing(CE3G)-  Introduction.pptBuilding Drawing(CE3G)-  Introduction.ppt
Building Drawing(CE3G)- Introduction.ppt
RameshMahato19
 
SEM 6 : BTECH 2 PROJECT 2
SEM 6 : BTECH 2 PROJECT 2SEM 6 : BTECH 2 PROJECT 2
SEM 6 : BTECH 2 PROJECT 2
Darshiini Vig
 
1. What two major components make up the contract documents 2. .docx
1. What two major components make up the contract documents 2. .docx1. What two major components make up the contract documents 2. .docx
1. What two major components make up the contract documents 2. .docx
jeremylockett77
 
Building con 1 (arc 1523) project 2 brief aug 2014
Building con 1 (arc 1523) project 2 brief aug 2014Building con 1 (arc 1523) project 2 brief aug 2014
Building con 1 (arc 1523) project 2 brief aug 2014Preston Liew
 
Building con 1 (arc 1523) project 2 brief aug 2014 (1)
Building con 1 (arc 1523) project 2 brief aug 2014 (1)Building con 1 (arc 1523) project 2 brief aug 2014 (1)
Building con 1 (arc 1523) project 2 brief aug 2014 (1)Anthony Chew
 
Technical Specification MEP Works
Technical Specification MEP WorksTechnical Specification MEP Works
Technical Specification MEP Works
zahid qayum
 
Building con 1 (arc1523) project 2 brief august 2015
Building con 1 (arc1523) project 2 brief   august 2015Building con 1 (arc1523) project 2 brief   august 2015
Building con 1 (arc1523) project 2 brief august 2015
Chow Hong Da
 
Building con 1 (arc1523) project 2 brief
Building con 1 (arc1523) project 2 brief   Building con 1 (arc1523) project 2 brief
Building con 1 (arc1523) project 2 brief
Darshiini Vig
 
SEM 6 : BTECH 2 PROJECT 1
SEM 6 : BTECH 2 PROJECT 1SEM 6 : BTECH 2 PROJECT 1
SEM 6 : BTECH 2 PROJECT 1
Darshiini Vig
 
stuDYING
stuDYINGstuDYING
stuDYING
bruhsocool
 
Slide using and communicating technical information
Slide using and communicating technical informationSlide using and communicating technical information
Slide using and communicating technical information
Reece Hancock
 
Types of drawings
Types of drawingsTypes of drawings
Types of drawings
kevin porter
 
Technical drawing slide
Technical drawing slideTechnical drawing slide
Technical drawing slide
OBIABUCHI NNANNA
 
Graphics Within Industry
Graphics Within IndustryGraphics Within Industry
Graphics Within Industrys2francetrip
 
Presentation on Architectural Drawing
Presentation on Architectural DrawingPresentation on Architectural Drawing
Presentation on Architectural Drawing
AbhishekChavan63
 
CE Lec Slides, Plans.pdf
CE Lec Slides, Plans.pdfCE Lec Slides, Plans.pdf
CE Lec Slides, Plans.pdf
JunaidMughal34
 

Similar to Architectural working drawing (20)

Wk3 cd1 site-f-plan1
Wk3 cd1 site-f-plan1Wk3 cd1 site-f-plan1
Wk3 cd1 site-f-plan1
 
Asu history and theory lecture 5-design development 18-11-2017
Asu history and theory lecture 5-design development 18-11-2017Asu history and theory lecture 5-design development 18-11-2017
Asu history and theory lecture 5-design development 18-11-2017
 
Asu history and theory lecture 5-design development 18-11-2017
Asu history and theory lecture 5-design development 18-11-2017Asu history and theory lecture 5-design development 18-11-2017
Asu history and theory lecture 5-design development 18-11-2017
 
Construction Documents Guide: Types and Significance in 2024
Construction Documents Guide: Types and Significance in 2024Construction Documents Guide: Types and Significance in 2024
Construction Documents Guide: Types and Significance in 2024
 
Building Drawing(CE3G)- Introduction.ppt
Building Drawing(CE3G)-  Introduction.pptBuilding Drawing(CE3G)-  Introduction.ppt
Building Drawing(CE3G)- Introduction.ppt
 
SEM 6 : BTECH 2 PROJECT 2
SEM 6 : BTECH 2 PROJECT 2SEM 6 : BTECH 2 PROJECT 2
SEM 6 : BTECH 2 PROJECT 2
 
1. What two major components make up the contract documents 2. .docx
1. What two major components make up the contract documents 2. .docx1. What two major components make up the contract documents 2. .docx
1. What two major components make up the contract documents 2. .docx
 
Building con 1 (arc 1523) project 2 brief aug 2014
Building con 1 (arc 1523) project 2 brief aug 2014Building con 1 (arc 1523) project 2 brief aug 2014
Building con 1 (arc 1523) project 2 brief aug 2014
 
Building con 1 (arc 1523) project 2 brief aug 2014 (1)
Building con 1 (arc 1523) project 2 brief aug 2014 (1)Building con 1 (arc 1523) project 2 brief aug 2014 (1)
Building con 1 (arc 1523) project 2 brief aug 2014 (1)
 
Technical Specification MEP Works
Technical Specification MEP WorksTechnical Specification MEP Works
Technical Specification MEP Works
 
Building con 1 (arc1523) project 2 brief august 2015
Building con 1 (arc1523) project 2 brief   august 2015Building con 1 (arc1523) project 2 brief   august 2015
Building con 1 (arc1523) project 2 brief august 2015
 
Building con 1 (arc1523) project 2 brief
Building con 1 (arc1523) project 2 brief   Building con 1 (arc1523) project 2 brief
Building con 1 (arc1523) project 2 brief
 
SEM 6 : BTECH 2 PROJECT 1
SEM 6 : BTECH 2 PROJECT 1SEM 6 : BTECH 2 PROJECT 1
SEM 6 : BTECH 2 PROJECT 1
 
stuDYING
stuDYINGstuDYING
stuDYING
 
Slide using and communicating technical information
Slide using and communicating technical informationSlide using and communicating technical information
Slide using and communicating technical information
 
Types of drawings
Types of drawingsTypes of drawings
Types of drawings
 
Technical drawing slide
Technical drawing slideTechnical drawing slide
Technical drawing slide
 
Graphics Within Industry
Graphics Within IndustryGraphics Within Industry
Graphics Within Industry
 
Presentation on Architectural Drawing
Presentation on Architectural DrawingPresentation on Architectural Drawing
Presentation on Architectural Drawing
 
CE Lec Slides, Plans.pdf
CE Lec Slides, Plans.pdfCE Lec Slides, Plans.pdf
CE Lec Slides, Plans.pdf
 

Recently uploaded

The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
PedroFerreira53928
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 

Recently uploaded (20)

The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 

Architectural working drawing

  • 2. What is Architectural Working Drawing. Is a organized technical drawing of a building (or building project) having all required information and instruction in graphical form to enable us to erect the building/ building project on site/ground. It is called construction documents(CD). Traditionally, working drawings consist of 2 dimensional orthogonal projections of the building or component they are describing, such as plans, sections, elevations, details, schedules and specification etc. It is a tool of communication. It is legal foundation for the project.
  • 3. Purpose of Architectural Working Drawing. 1. To develop a design idea into a coherent proposal. 2. To communicate technical information among design and construction teams. 3. To provide information for preparation of structural design and drawings for foundation, columns, beams, floor slabs , staircase and any other structural component of a building. 4. To provide information for preparation of Acoustic Design, Electrical, HVAC, mechanical, Fire Fighting, Plumbing, Sanitary, external & internal finish and interior furnishing etc. drawings. 5. To provide information for preparation of specifications and detailed estimates for civil, acoustic design, electrical, plumbing, horticulture, landscape, site development etc. works. 6. To provide information for preparation of Bill of Quantities of various items and materials to be used in construction of the building. 7. To guide the contractor & construction team. 8. To obtain approval of Local Self Government, Fire Department, Urban Art Commission and other Statutory Authorities.
  • 4. Purpose of Architectural Working Drawing. (Cont----) 9. To provide information for preparation of tender document. 10. To show how the design is to be materialized. 11. To serve as reference for supervision of construction works at site. 12. To start and complete the execution of the construction of building on the basis of the information given in the drawing. 13. To convey the design intent to the contractor for bidding and construction 14. To prepare the shop drawing, to fabricate components of the works or to assemble or install components 15. To make a record of existing building/structure and completed works. 16. Act as a basis for ordering materials and components . 17. Assist in the measurement of construction progress 18. Records of completed works and building that already exists.
  • 5. How Architectural Working Drawing is prepared Is made according to a set of conventions, which include particular views (floor plan, section , elevations, specifications and details etc.), sheet sizes, units of measurement and scales, annotation and cross referencing, for maintaining the uniformity of drawing in terms of scale , line weight/thickness, line type , size of sheet and symbols etc. Working Drawing may be very simple or very complex depending upon the project. The complexity of the drawing is a factor in determining the size of sheet. Is made to show how the design is to be implemented , therefore should give the contractor exactly the information he needs and relevant data. Traditionally, consist of 2 dimensional orthogonal projections of the building or component they are describing, such as plans, sections , elevations and details etc. Includes title block, dimensions, notation, notes & symbols consistent with industry standards so that their precise meaning is clear & can be understood. Specification information can be included on working drawings or in a separate specification sheet, but information should not be duplicated as this can become contradictory and may cause confusion.
  • 6. Criteria of good Architectural Working Drawing. 1. Accurately Drawn with appropriate symbols, notations, conventions, graphical representation and all relevant information. 2. Information should not be duplicated as this can become contradictory and may cause confusion. 3. Structured and dimensioned well carefully so that they convey necessary information to carry out particular parts of the works. 4. The Layout of the drawing and text on the drawing shall be such as to facilitate the reading of drawing and make it possible for essential references to be located easily. 5. Drawn in appropriate scale logically and neatly arranged and properly titled. 6. Standard abbreviations, Schedule formats, Material designations. 7. Required information for preparation of tender document. 8. Serve as reference for supervision of construction works at site. 9. The scale at which drawings are prepared should reflect the level of detail of the information they are required to convey. Different line thicknesses should be used to provide greater clarity for certain elements.
  • 7. Layout of Drawings. 1. The layout of drawings shall be such as to facilitate the reading of drawings and make it possible for essential references to be located easily. 2. The Standard arrangements shall include all relevant information and sufficient margins shall be left from the edges of finished drawings to facilitate filing and binding where necessary. 3. Margins, the provision of blank border will enable prints to be trimmed, if necessary, without incurring the use of uneconomical sizes of sensitized material to allow for trimming. 4. There should be marked with zones.
  • 8. Basic contents of Architectural Working Drawings 1. Title Block 2. Site Layout Plan 3. Column Layout Plan in case of frame structure building. 4. Foundation layout Plan in case of load bearing structure. 5. Foundation details 6. Excavation Plans 7. Floor Plans including basement floor if any 8. Roof Plan 9. Elevations 10. Sections 11. Services Layout plan 12. Door window Details 13. Electrical Layout & HVAC Plan 14. Plumbing layout plan 15. Structural details plan of Footings, Columns, Beams, Slabs, Staircase etc. 16. Toilet Details nosing, risers & tread 18. Kitchen details. 19. Iron mongaries 20. Reflected Ceiling plan 21. Typical Details of various components & elements, like cupboard, flooring pattern etc. 22. Specification of various finishes and building materials 23. Shop drawings wherever required. 24. Beam- column layout 25. Brickwork layout 26. PHE drawing 27. Fire Fighting drawing. 28. Drainage system 29. Landscape, Horticulture, Circulation & Site Development. 30. Furniture Layout 31. Acoustic Design 32. Area Calculation 33. Internal & External Colour Scheme 34. Schedules.
  • 9. Size of Drawing Sheet. Sl. No. Designation Trimmed Size In mm Untrimmed Size in mm 1. A0 841 x 1189 880 x 1230 2. A1 594 x 841 625 x 880 3. A2 420 x 594 450 x 625 4. A3 297 x 420 330 x 450 5. A4 210 x 297 240 x 330 6. A5 148 x 210 165 x 240 The trimmed sizes are on the following basic principles 1. Two successive sizes of the series are obtained by halving or doubling. Consequently, the surface areas of two successive sizes are in the ratio of 1:2 appx. 2. The formats or forms are geometrically similar to one another , the sides of each size being in the ratio of 1:√2. 3. The surface area of the basic size A0 is one square metre
  • 10. Title Block 1.The title block is an important feature in a drawing , since it facilitates obtaining uniformity and presents in definite manner the details like title of drawing, Job Title, Name of Organization or Firm, Name of Architect, Name of Structural Engineer, Drawing Number, Scale, Date of Drawing, North Direction , Dated initials of Technical Staff preparing checking the drawing, Revision Panels, Key Plan, Notes, List of Reference Drawings, Schedules etc. 2. The width of title block shall be 150 mm.
  • 11. Title Block ( contd.---) Standard Notes in Title Block: 1. This Drawing has been prepared on the basis of preliminary architectural drawings bearing number_____________. 2. All dimensions are in “mm” unless otherwise specified. 3. Drawing not to be measured only written dimensions to be followed. 4. This drawing should be read in conjunction with relevant Architectural/structural drawing . 5. The sizes of Columns and Beams in this drawing are in accordance with Structural Drawing number __________. 6. Any discrepancies between this drawing and correspondence/ related structural drawing should immediately be brought to the notice of the Architect before execution and work should not be carried out at site till the discrepancies are not removed. 7. All external walls are _____mm thick and all internal walls are _____mm thick Brick/ RCC walls unless otherwise specified. 8. The building shall be constructed in full compliance with all applicable codes, ordinances and regulations as well as the drawings and specifications. Any code deficiencies in the drawings recognized by the contractor should be brought to the attention of the architect for clarification. 9. Any other notes as deemed fit by the Architect and relevant to the drawing.
  • 12. Title Block ( contd.---) CONSTRUCTION DOCUMENT SHEET NUMBERS AND SHEET ORDER United States National CAD Standard: Components of the Sheet Number:- • There are three components that make up sheet numbers in a set of construction documents. The first two letters, the discipline designators, identify the construction discipline that the sheet covers - architectural sheets, plumbing sheets, structural sheets, etc. The third digit, the sheet type, is a number that represents the type of drawings that are on the sheet - plans, sections, details, schedules, etc. The final two digits, the sequence numbers, are numbers that simply place the sheets in order. • The Discipline Designator can be a single letter or a double-letter. Very large or complex projects will want to make use of the double-letter designations to help sub-divide each discipline further. • The Sheet Types Designator takes the drawings of a single discipline and organizes them. Drawings are always organized from most general to most specific or specialized. Since plans are most helpful to see the overall design of the project, they come first. Elevations and sections are a bit more specific and come next followed by details and schedules, which are the most specific type of drawings. • Sequence Number, which is two-digit between 01 and 99. The sequence numbers do not have to be sequential so that space may be left within the set for future additions.
  • 13. Title Block ( contd.---) CONSTRUCTION DOCUMENT SHEET NUMBERS AND SHEET ORDER The following table indicates the primary (single) letter designations that may be used and the order that the disciplines should take. In this case, a hyphen shall be inserted in place of the secondary discipline designator so that the format remains. Designator Name Additional Description Cover Sheet G General Sheet list, symbols, code summary, etc. H Hazardous Materials Abatement, handling, etc. V Survey / Mapping B Geotechnical C Civil L Landscape S Structural A Architectural I Interiors Q Equipment F Fire Protection P Plumbing D Process
  • 14. Title Block ( contd.---) CONSTRUCTION DOCUMENT SHEET NUMBERS AND SHEET ORDER Designator Name Additional Description M Mechanical E Electrical T Telecommunications R Resource Existing Condition/ Building X Other Disciplines Z Contractor / Shop Drawings O Operations The Sheet Types designator takes the drawings of a single discipline and organizes them. Drawings are always organized from most general to most specific or specialized. Since plans are most helpful to see the overall design of the project, they come first. Elevations and sections are a bit more specific and come next followed by details and schedules, which are the most specific type of drawings.
  • 15. Site Layout plans Site plans usually show the extent of the site but no surrounding detail. Recommended scales are: 1 : 500, 1 : 200 The function of the site plan is to show: 1. The location of the proposed building or buildings with reference to a bench mark and in relation to surroundings of the plot. 2. The topography of the site, with both existing and finished levels. 3. Existing Buildings to be demolished or removed or retained. 4. The extent of earthworks, included, cutting and filling, and the provision of bank and retaining walls. 5. Roads, footpaths, hard standings and paved areas. 6. Planting. 7. The layout of external service runs, including drainage, water, gas, electricity, telephone, etc. 8. The layout of external lighting. 9. Fencing, walls and gates. 10. The location of miscellaneous external components – bollards, litter bins, etc.
  • 16. Column Layout Plan in Case of Framed Structured Building Thumb rules to be followed for column layout plan are:- 1. Always Plan a Column layout on a planning grid. 2. Column Spacing, i.e. Distances between columns in X & Y Directions. 3. Show Column numbers. 4. Show Sizes of Columns 5. Show Alignment of Columns
  • 17. Foundation Layout Plan in Case of Framed Load Bearing Building Site plans usually show the extent of the site but no surrounding detail. Recommended scales are: 1 : 500 1 : 200 The function of the site plan is to show: 1. The location of the building or buildings in relation to their surroundings. 2. The topography of the site, with both existing and finished levels. 3. Buildings to be demolished or removed. 4. The extent of earthworks, included, cutting and filling, and the provision of bank and retaining walls. 5. Roads, footpaths, hard standings and paved areas. 6. Planting. 7. The layout of external service runs, including drainage, water, gas, electricity, telephone, etc. 8. The layout of external lighting. 9. Fencing, walls and gates. 10. The location of miscellaneous external components – bollards, litter bins, etc.
  • 18.
  • 19.
  • 21.
  • 22.
  • 25. Floor and Parapet details