This document provides a tutorial on transformer maintenance best practices. It outlines a maintenance strategy, process, and considerations for component selection and maintenance. The maintenance strategy discusses factors that influence maintenance practices such as transformer characteristics, duty, and environment. It also presents results from a survey on current maintenance practices. The maintenance process covers planning, organization, execution, recording, and optimization. Levels of competence for maintenance tasks and safety aspects are discussed. Component selection impacts maintenance effort, and considerations for various transformer components are provided.
Unit I: Introduction to Protection System:
Introduction to protection system and its elements, functions of protective relaying, protective zones, primary and backup protection, desirable qualities of protective relaying, basic terminology.
Relays:
Electromagnetic, attracted and induction type relays, thermal relay, gas actuated relay, design considerations of electromagnetic relay.
Unit-II: Relay Application and Characteristics:
Amplitude and phase comparators, over current relays, directional relays, distance relays, differential relay.
Static Relays: Comparison with electromagnetic relay, classification and their description, over current relays, directional relay, distance relays, differential relay.
Unit-III Protection of Transmission Line:
Over current protection, distance protection, pilot wire protection, carrier current protection, protection of bus, auto re-closing,
Unit-IV: Circuit Breaking:
Properties of arc, arc extinction theories, re-striking voltage transient, current chopping, resistance switching, capacitive current interruption, short line interruption, circuit breaker ratings.
Testing Of Circuit Breaker: Classification, testing station and equipments, testing procedure, direct and indirect testing.
Unit-V Apparatus Protection:
Protection of Transformer, generator and motor.
Circuit Breaker: Operating modes, selection of circuit breakers, constructional features and operation of Bulk Oil, Minimum Oil, Air Blast, SF6, Vacuum and d. c. circuit breakers.
Test done on Power transformers.
Insulation Resistance test, Winding Resistance test, Ratio Measurements, Magnetic balance test, Tan delta test, DIssolved gas analysis for transformer, Sweep frequency response analysis.
To sense/detect the fault occurrence and other abnormal conditions at the protected equipment/area/section.
To operate the correct circuit breakers so as to disconnect only the faulty equipment/area/section as quickly as possible, thus minimizing the damage caused by the faults.
To operate the correct circuit breakers to isolate the faulty equipment/area/section from the healthy system in the case of abnormalities like overloads, unbalance, undervoltage, etc.
To clear the fault before the system becomes unstable.
To identify distinctly where the fault has occurred.
Unit I: Introduction to Protection System:
Introduction to protection system and its elements, functions of protective relaying, protective zones, primary and backup protection, desirable qualities of protective relaying, basic terminology.
Relays:
Electromagnetic, attracted and induction type relays, thermal relay, gas actuated relay, design considerations of electromagnetic relay.
Unit-II: Relay Application and Characteristics:
Amplitude and phase comparators, over current relays, directional relays, distance relays, differential relay.
Static Relays: Comparison with electromagnetic relay, classification and their description, over current relays, directional relay, distance relays, differential relay.
Unit-III Protection of Transmission Line:
Over current protection, distance protection, pilot wire protection, carrier current protection, protection of bus, auto re-closing,
Unit-IV: Circuit Breaking:
Properties of arc, arc extinction theories, re-striking voltage transient, current chopping, resistance switching, capacitive current interruption, short line interruption, circuit breaker ratings.
Testing Of Circuit Breaker: Classification, testing station and equipments, testing procedure, direct and indirect testing.
Unit-V Apparatus Protection:
Protection of Transformer, generator and motor.
Circuit Breaker: Operating modes, selection of circuit breakers, constructional features and operation of Bulk Oil, Minimum Oil, Air Blast, SF6, Vacuum and d. c. circuit breakers.
Test done on Power transformers.
Insulation Resistance test, Winding Resistance test, Ratio Measurements, Magnetic balance test, Tan delta test, DIssolved gas analysis for transformer, Sweep frequency response analysis.
To sense/detect the fault occurrence and other abnormal conditions at the protected equipment/area/section.
To operate the correct circuit breakers so as to disconnect only the faulty equipment/area/section as quickly as possible, thus minimizing the damage caused by the faults.
To operate the correct circuit breakers to isolate the faulty equipment/area/section from the healthy system in the case of abnormalities like overloads, unbalance, undervoltage, etc.
To clear the fault before the system becomes unstable.
To identify distinctly where the fault has occurred.
Random switching of power system equipment may lead to high-frequency overvoltage transient and inrush current.
This, in turn, may stress the equipment, leading to rapid aging or dielectric failure.
What is ?
Point on Wave Controller/ Switch?
Point on Wave Switch (PoW), often called Point on Wave Controller is a high speed microprocessor based relay used for the controlled switching of circuit breaker of HVAC system. Controlled switching refers to open or close a breaker at a pre-determined point on the voltage waveform.
Electrical Substation and Switchyard DesignLiving Online
Electrical substations form important nodal points in all power networks. Substations can be of various capacities, voltages, configurations and types depending on what is the application for which the substation is being designed. Location and layout of a substation present a number of challenges to the designer due to a large variety of options available to a designer. There are ever so many constraints too that need to be kept in mind; technical, environmental and naturally financial. Arriving at an optimum design within these constraints is as much an art as it is a science. Designing a substation which will operate with utmost reliability for at the least three or four decades involves a thorough knowledge of the current state-of-the art equipment, emerging technologies, the tools for presenting and evaluating all available options and a good appreciation of power system operation and maintenance. This course will present a comprehensive capsule of all the knowledge essential for a substation designer and walk the participants through the substation design process using a set of interlinked case studies.
FOR MORE INFORMATION: http://www.idc-online.com/content/electrical-substation-and-switchyard-design-25
Random switching of power system equipment may lead to high-frequency overvoltage transient and inrush current.
This, in turn, may stress the equipment, leading to rapid aging or dielectric failure.
What is ?
Point on Wave Controller/ Switch?
Point on Wave Switch (PoW), often called Point on Wave Controller is a high speed microprocessor based relay used for the controlled switching of circuit breaker of HVAC system. Controlled switching refers to open or close a breaker at a pre-determined point on the voltage waveform.
Electrical Substation and Switchyard DesignLiving Online
Electrical substations form important nodal points in all power networks. Substations can be of various capacities, voltages, configurations and types depending on what is the application for which the substation is being designed. Location and layout of a substation present a number of challenges to the designer due to a large variety of options available to a designer. There are ever so many constraints too that need to be kept in mind; technical, environmental and naturally financial. Arriving at an optimum design within these constraints is as much an art as it is a science. Designing a substation which will operate with utmost reliability for at the least three or four decades involves a thorough knowledge of the current state-of-the art equipment, emerging technologies, the tools for presenting and evaluating all available options and a good appreciation of power system operation and maintenance. This course will present a comprehensive capsule of all the knowledge essential for a substation designer and walk the participants through the substation design process using a set of interlinked case studies.
FOR MORE INFORMATION: http://www.idc-online.com/content/electrical-substation-and-switchyard-design-25
Qualitrol has tons of products to help you properly monitor your Vault Transformers. Dissolved Gas Analyzers, Intelligent Monitors, and Temperature Gauges are some of the ways to maintain your assets.
You can learn more about Vault Monitoring with Qualitrol by clicking this link, https://www.qualitrolcorp.com/assets/vault-transformers/
Transformer Asset Management is an activity in transmission department and a team of engineers maintaining transformers at site through condition monitoring and preventive maintenance to avoid failures at site during the revenue earning period and loss of revenue to the utility.
The following slides present the basis of Guided Wave Theory and Technology and how this portable system maximizes the efficiency of a corrosion management program.
Here my project theme is to monitor and control Transformer health using Arduino, as we all know there are both internal and external faults occur in the transformer, for internal faults we use Buchholz relay and Differential protection relay for external but it is not efficient with time. so,we use Arduino for real time protection, here we fix some values to the Arduino in the program itself according to the rating of the transformer by that we monitor and control whenever the faults occur
This presentation will discuss how the use and need for voltage transformers has changed over the last twenty years. With the introduction of auto-ranging electric meters, meter technicians need to be prepared, use the appropriate tools and PPE for high capacity circuits (without VT's), as this method has become increasingly popular.
Industrial monitoring and control systems using andriod applicationAvinash Vemula
Automation takes the complete control of total plants few authentication and manual actions are needed from user side for completing action .Hence there is a must situation for users presence at all times in the control for taking some timely needed control actions. The proposed system provides a good solution to this problem. The whole control room environment is additionally implemented in the arm-android platform and the same is communicated to the process through Bluetooth. Now the user in control can use mobile at anytime, anywhere to monitor and control the whole plant.8051 is used here for acquiring process control parameters from the sensors like temperature, gas etc and transmitting it via a Bluetooth module to an android device. Hence the parameter values can be monitored and stored simultaneously.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
3. • Prepared to help transformer users define and apply
best practices to transformer maintenance
• Includes transformers rated 69 kV and above, and
larger than 25 MVA
• Subjects covered - best practice, checking and
testing to evaluate transformer condition, intervals for
the various actions, advanced maintenance activities,
human and material factors
Guide for Transformer
Maintenance
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 3
4. Commissioning
T ransformer
Operation
TBMTB CM
Corrective
Maintenance
Major W ork
On-site or in
W orkshop
OK Interpretation
Apply Special T ests and/or Intensive
M onitoring (if needed)
Normal?
Y ES
NO
Major work Minor work
Technical &
Economic
Evaluation
Refurbish
or Repair
Scrap &
Replace
E nd of Life
OLCM
Condition A ssessment
Maintenance Strategy (TBM, CBM, RCM)
Tests & Checks
C BM
Transformer
Operation and
Maintenance Cycle
Time Based
Condition
Monitoring
Condition
Based
Maintenance
On-line
Condition
Monitoring
Time Based
Maintenance
TBCM
CBM
OLCM
TBM
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 4
6. Maintenance Strategy
Importance of Transformer Maintenance
Life
Used Possible Impacts of Lack of Maintenance
- Baseline data not recorded, commissioning errors missed
- Failure to detect early life problems within warranty period
- Oil oxidation begins
- OLTC contacts wear (medium and heavy loads)
- Weathering and UV takes affect
- Trends in condition not observed
- Corrosion in severe environments
- Visible affects of weathering and UV
- Transducers go out of calibration
- Fan and pump bearing wear
- Trends in condition not observed
- Gaskets and seals lose resilience, oil leaks manifest
- Oil decay products affect paper insulation
- Weathered paint, edge and spot corrosion
- Miss opportunity to intercept accelerated ageing
- Miss benefits of implementing a mid-life intervention
- Uncertainty on remnant life
- Oxidation and hydrolysis enters accelerated ageing stage
- Paper DP drops, sometimes prematurely
- OLTC and bushing failure rates increase
- Paint system protection fails
NEW
20%
40%
60%
80%
100%
- Expect sludge if oil has been in poor condition
- Exposure causes device malfunctions
- Wiring and cable insulation en-brittle
- Bad oil leaks need regular topping up
- Dielectric withstand diminishes (moisture)
- Expensive failure (often bushing or OLTC)
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 6
7. The condition begins
to deteriorate
Y
Z
The condition change
becomes detectable
Good Condition
X
The condition has
deteriorated to the
point of failure
Time
Failure
Maintenance Strategy
Theoretical Transformer Condition Degradation
- detect initial changes in condition that are relatively small compared
to the deterioration necessary for failure to occur
- have measurement or inspection intervals that are smaller than
∆T[XY]+∆T[YZ] to allow detection before failure occurs
- have a period of time ∆T[YZ] that is long enough to be able to take
the preventive action (ex: transformer outage)
To be technically feasible, a condition assessment task should have the ability to:
∆T[XY] ∆T[YZ]
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 7
8. Maintenance Strategy
Survey on Maintenance Practices
• There were significant differences on the task intervals for "visits“
• Oil test task intervals were generally in accordance with IEC 60422
• A majority of respondents used Electrical tests on a "Conditional
based" criterion only - CBM
• For "Accessories verification", task intervals varied significantly (from 1
to 12 years)
• OLTC task intervals varied between 4 and 12 years
• Bushing maintenance practices varied significantly between utilities
KEY FINDINGS
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 8
9. • Generally, the intervals between visits were longer than for GSU
users and also varied greatly
• Continuous DGA monitoring was used intensively by 50% of the
respondents, particularly on their critical units
• Electrical tests were performed by two thirds of the respondents
For GSU transformers, it was observed that:
• Visits were made at significantly shorter intervals
• Periodic sampling for dissolved gas analysis (DGA), by the majority,
were at intervals of one year or less
• Continuous DGA monitoring was not often applied, probably due to
the proximity of a maintenance crew
• A minority of respondents were performing electrical tests
periodically
For Transmission transformers, it was observed that:
Maintenance Strategy
Survey on Maintenance Practices
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 9
10. • Transformer characteristics and specifications
• The quality of the components installed on the transformer
• The required duty of the transformer (load, OLTC operation)
• The transformer environment (temperature, humidity)
• Historical transformer failure rate and failure types
• The level of transformer redundancy and the consequences of
unavailability
• The failure mode and its effects on substation safety
• Company culture and focus based on maintenance
• The availability and costs of labour
• The degree of implementation of modern technologies
• The presence of a maintenance optimization program
The survey showed that maintenance practices varied significantly
between transformer users.
Factors that can influence maintenance practice and effort:
Maintenance Strategy
Survey on Maintenance Practices
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 10
11. Maintenance Strategy
TBM and TBCM Maintenance Intervals
Action Task Interval Remark
Light Regular Intensive
Visit 6 m 1 m 1 d In service
Detailed visual
inspection
1 y 3 m 2 w In service
DGA 2 y 1 y 3 m Task interval may differ with monitoring
Oil tests 6 y 2 y 1 y
Cooling system cleaning Conditional Conditional Any Interval Outage may be required
Accessories verification 12 y or Cond. 6-8 y 1-2 y Outage required
Electrical basic tests Conditional Conditional Any Interval Outage required
Insulation tests (DF or
PF)
Conditional 6-8 y 2-4 y Outage required
OLTC internal inspection 12 y 6-8 y 4 y Consider number of operation,
technology and manufacturer
recommendations
Survey showed many tasks were performed conditionally - CBM
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 11
12. Regular
The intensity of these maintenance task intervals:
Light
• Transformer equipped with components known to be very reliable
• Low load and low number of tap-changer operations
• Transformer does not operate in a harsh environment
• Advanced technology that requires less maintenance
• Low consequences from unexpected failure
Intensive
• Components that are known to require frequent attention
• High load, high number of OLTC operations
• Transformer operates in a harsh environment
• Older transformer technologies
• High consequences from unexpected failure
Maintenance Strategy
TBM and TBCM Maintenance Intervals
• Any situation between these two
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 12
14. Maintenance Strategy
Monitoring
On-line Monitoring
Data, measurements or samples (oil) are collected while the transformer is
energized and in service. If these are performed at discrete intervals (in
‘visits’) then they provide only ‘snapshots’ of the transformer’s condition.
Continuous On-line Monitoring
Data, measurements or samples are collected in a continuum by
transducers, sometimes at discrete sampling rates, while the transformer is
energized and in service. This captures real time data to provide trends in
transformer condition.
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 14
15. Maintenance Strategy
Continuous On-line Monitoring
Modern continuous on-line monitoring adds an intelligent electronic device
(IED) to the monitoring transducer(s). These devices have a measurement
mechanism, that together with internal signal and data processing
capabilities, can be described as ‘smart sensors’ or ‘smart systems’
capable of providing multiple measurement and control functions.
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 15
16. Maintenance Strategy
Continuous DGA On-Line Monitoring
• This is the most commonly used on-line monitoring technology for
transformers because:
- It is a very good indicator for most transformer incipient faults
- Early detection of incipient faults often avoids major failure
• DGA sensor technologies include fuel cell, chromatography,
semiconductor, photo-acoustic spectroscopy, thermal conductivity
• Depending on the technology chosen, these systems can provide:
- A single measurement of one specific gas
- A single measurement of a composition of several gases with
specific proportions and sensitivities
- Multiple measurements of different gases
• Gas-in-oil monitors often include a built-in moisture sensor
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 16
17. • Systems with models or algorithms that calculate
winding hot spot temperatures, rate of ageing of
paper insulation, moisture content in paper or
barriers, and effectiveness of cooling systems
• Monitors condenser bushings by measuring
leakage current through their capacitance taps
• OLTC monitoring including mechanical conditions
of the drive system, contact wear, temperature
differential, dissolved gas analysis, tap position
tracking/counting
• Partial discharge detection using electrical,
acoustical, or UHF signals
Maintenance Strategy
Other On-Line Monitoring Technologies
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 17
19. Planning Organization Execution Recording
Optimization
Maintenance Process
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 19
20. • General information about the transformer (type, power, voltage)
• Types of maintenance work to be done with relevant triggering points
(time interval, event, condition, result of diagnostics) and operational
status (energized, de-energized, or both de-energized and disconnected)
• Qualifications and skills required to perform individual maintenance works
• List of tasks related to individual maintenance works and the associated
time required
• Excerpt from, or reference to manufacturer’s manual giving detailed
information (work steps, sequence, tools, material, safety aspects)
• Maintenance report forms
• Source of information for maintenance data collection and reporting –
based on standard report forms
A guideline would include:
Maintenance Process
Maintenance Planning– Maintenance Guidelines
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 20
21. • Equipment Inventory
• Computerized Maintenance Guidelines
• Task lists and Operations
• Maintenance plan
• Maintenance schedules
• Work orders
• Outage Planning
• Maintenance task tracking
Maintenance Planning – Computer Aided
Maintenance Management Systems (MMS)
There are different computer aided tools for maintenance planning used
by different utilities. All have this similar structure:
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 21
22. Planning Organization Execution Recording
Optimization
Maintenance Process
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 22
23. Level 1:
Actions to be taken on certain transformer components, and generally
described in a maintenance manual issued by the manufacturer.
Examples: control operations, check of oil levels, exchange of
consumable materials
Maintenance Organization
5 Levels of Competence
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 23
24. Level 2:
Actions performed with basic written procedures and/or supporting
equipment or devices, which are simple to use or to assemble, being part
of the transformer or external to it.
Examples: replacement / exchange of accessories or parts, routine
checks.
Maintenance Organization
5 Levels of Competence
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 24
25. Level 3:
Actions performed with complex written procedures or the use of special
supporting equipment. Personnel are trained in using complex tools or
processes.
Examples: exchange of an original part or component, complex setting or
re-setting
Maintenance Organization
5 Levels of Competence
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 25
26. Level 4:
Actions performed requiring personnel trained in special techniques or
technologies and utilization of special tools, and/or supporting equipment.
Examples: modifications and upgrading activities, changes in functions,
changes in the way of operation and use.
Maintenance Organization
5 Levels of Competence
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 26
27. Level 5:
Actions needing specialist technical knowledge and with the support of
industrial processes, industrial equipment or devices.
Examples: complete inspections or revisions which require detailed
dismantling of the equipment, its reconstruction, replacement of obsolete
or worn parts or components.
Maintenance Organization
5 Levels of Competence
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 27
28. Planning Organization Execution Recording
Optimization
Maintenance Process
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 28
29. • ground all bushings to avoid induction
• use working at height safety measures
• beware all bushings and leads when testing
• beware opening pressurized access covers
• identify and isolate cubicle auxiliary supplies
• deactivate springs whilst working on OLTC
• treat all tanks as confined spaces
• beware of nitrogen gas filling
• vent explosive gases accumulated by OLTCs or faults
• perform a risk assessment on the need to deactivate the fire
extinguishing system
Maintenance Execution
Safety
Some safety aspects that have to be considered when working on a
transformer:
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 29
30. Planning Organization Execution Recording
Optimization
Maintenance Process
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 30
31. Maintenance Recording
Corrective Maintenance Tracking
Data recorded for corrective maintenance should contain:
• Unique identification of the transformer and its properties and location
• Transformer location details
• Time of maintenance action
• Environmental conditions on site during maintenance action:
Temperature, wind, rain, storm, humidity
• Components, parts and material used and the parts replaced
• Photographs: The ‘as found’ and ‘return to service’ condition, providing a
reference for future work
• Tests results taken before a return to service
• Problem description: Failure, symptoms and circumstances
• Problem cause: Data on what was causal to the failure or malfunction (in
some cases the root-cause may not be obvious and requires more
detailed diagnosis and investigation)
• Remedy / Action: A report of the remedial action taken
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 31
32. Planning Organization Execution Recording
Optimization
Maintenance Process
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 32
33. Maintenance Optimization
Reliability Centred Maintenance
A combination of TBM, TBCM, CBM and OLCM is often used to maintain
large complex assets such as power transformers.
Reliability Centred Maintenance: The extent of maintenance to be
performed is proportional to the level of risk associated with the
transformer
Risk = likelihood of failure * failure consequence
The likelihood of failure can be represented by the "Health Index" of the
unit (obsolescence, service history, technical condition)
Failure consequence can also be mitigated by various control measures
(protection upgrade, contingency plan, fire wall, oil containment)
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 33
35. Component Selection and Maintenance
Transformer maintenance effort is strongly related to component selection.
- Bushings
- Oil preservation systems
- Cooling systems
- Gaskets
- Gauges, indicators and relays
- Control cabinets
- Current transformers
- On-load tap changers
- De-energized tap changers
- Surge arresters
- Transformer active part
- Sensing and monitoring devices
This is because transformer components vary in quality, initial cost,
maintainability, technology, reliability, life expectancy and potential for its
failure and the consequences.
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 35
36. Component Selection and Maintenance
Bushings
Oil Impregnated Paper (OIP) Bushings
Advantages Disadvantages
- Very long history with relatively good
performances
- Very low partial discharge – can be used at
any voltage level
- Relatively low cost
- Minimal handling and storage requirements
- DGA diagnostics are possible
- Vulnerable to insulating oil leaks and water
ingress if the gasket/sealing system is
compromised
- Higher risk of bushing explosion and
resultant transformer fire
- Positioning angle during transportation,
handling and storage
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 36
37. Component Selection and Maintenance
Bushings
Resin Impregnated Paper (RIP) Bushings
Advantages Disadvantages
-Non-flammable core
-Bushing failure is less likely to release main
tank oil
-The core is less likely to be affected by
water ingress
-Very low partial discharge levels – can be
used at any voltage level
- No constraints on the attitude of the bushing
during transportation, handling and storage
-Relatively higher costs
-Constraints on handling and storage
-The oil end of the body must be protected
from moisture during storage
- Oil end of the bushing is susceptible to
transport damage
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 37
38. Porcelain Insulators
Composite Insulators
Component Selection and Maintenance
Bushings
Advantages Disadvantages
-No ageing
- Long history of good reliability
-Could create exploding projectiles if the
bushing fails
-Relatively fragile in the event of shock or
heavy force
- Makes the bushing relatively heavy
Advantages Disadvantages
-Relatively lightweight
-Lower risk of projectiles in the event of a
bushing failure
-High seismic withstand capability
- Better hydrophobicity in polluted conditions
-Less field experience compare to porcelain
- Long term reliability is not known, early
examples have suffered from surface
deterioration
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 38
39. Component Selection and Maintenance
Bushings
Types of Bushing Connections
Draw Solid Bottom Draw
Lead Conductor Connected Rod
Black denotes the current path
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 39
41. Maintenance Action Catalogue
Electrical Tests and DGA Diagnostic Matrix
Frequency Response Analysis
Dissolved Gas Analysis
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 41
42. Maintenance Action Catalogue
Electrical Test Example – Winding Resistance
Detectable
failures
Contact problems on the tap selector, contact problems on the diverter switch, broken
conductors, broken parallel strands, shorted winding disks, shorted winding layers, poor
bushing connections
Indication High internal temperatures, normally indicated by the DGA
Test method A constant current source is used to feed a DC current into the winding. The test current and
the voltage across the winding are measured and the resistance value is calculated. The
accuracy of the equipment should guarantee that differences of 1% or even lower can be
detected. Since the winding resistances are small, the test set should be connected in 4-wire
technology. A relatively high no-load voltage enables a quick saturation of the core and a fast
reaching of the stationary final value. It is recommended to measure the resistance for all taps of
the OLTC. The resistance values should be corrected to 75°C according to IEC 60076 Part 1
Reference Test report of the manufacturer, fingerprint measurements
Interpretation The measured winding resistance should not differ more than about 1% compared to the
factory test report, if the winding temperature at measurement conditions is corrected to the
factory conditions. Difference between phases usually less than 2-3%; Comparison between
HV and LV resistance is usually in the order of the square of the winding ratio, when losses are
balanced between HV and LV
Comments In comparison to the LV winding, the resistance of the HV winding is much higher. Therefore
identification of contact problems can be less sensitive on the HV side than the LV side. If the LV
windings have very low resistance values, in the order of a few mΩ, it can be helpful to use the HV
winding of the same limb in serial connection to get faster stabilization of the measurement current. The
time needed to get stable readings can be in the order of tens of minutes for very low resistance values
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 42
43. Maintenance Action Catalogue
Dissolved Gas Analysis
• One of the most useful and widely applied diagnostic tools
• Gases commonly measured: Hydrogen (H2), Methane (CH4), Ethane
(C2H6), Ethylene (C2H4), Acetylene (C2H2), Carbon Monoxide (CO),
Carbon Dioxide (CO2), Oxygen (O2) and Nitrogen (N2)
• No consensus about the absolute maximum level acceptable for each gas
• Considers both gassing rates and absolute values of the different gases
• Algorithms are used to:
- Identify significant gases because they exceed a limit value
- Evaluate gassing rates by comparing with previous gas
concentrations
- Assign weightings to each gas (because each gas is not produced by
the same amount of energy)
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 43
44. There are several methods used to interpret DGA results. Commonly, gas
ratios are used to match the DGA gas profile to the generation source in the
transformer (incipient faults), and identify the level of energy (temperature)
required to produce them.
Depending on the DGA profile (ratios), the gassing may be associated with:
- Thermal faults of low temperature
- Thermal faults of medium temperature
- Thermal faults of high temperature
- Discharges of low energy
- Discharges of high energy
- Partial discharge activity
Maintenance Action Catalogue
Dissolved Gas Analysis
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 44
45. Tests for in-service oils:
• GROUP 1: Minimum monitoring to ensure the oil is suitable for
continued use - colour, water content, breakdown voltage, interfacial
tension, acidity, dissipation/power factor and resistivity
• GROUP 2: Additional tests that obtain specific information about the
quality of the oil and also used to assist in the evaluation of the oil for
continued use – particle count, oxidation stability, sediment and sludge
• GROUP 3: Tests used to determine the suitability of the oil for use in
the transformer and the oil’s environmental compliance – corrosive
sulphur and PCB
Maintenance Action Catalogue
Oil Tests
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 45
46. Maintenance Action Catalogue
Relation between Transformer Problems and
Main Parameters of the Oil
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 46
48. Maintenance Action Catalogue
Maintenance Inspection Tasks
• Thermography
• Main tank and conservator
• Cooling system
• Accessories
• Transformer cabinets
• On-Load Tapchanger
• Buchholz relay operation
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 48
49. Maintenance Action Catalogue
Insulation Drying
• Remaining moisture in insulation during manufacturing
• Humid air from outside during transportation and/or assembling in
substation
• Humid air from outside through the breather (non sealed)
• Moisture ingress through gaskets
• Chemical decomposition of cellulose
• Moisture absorption due to exposure during maintenance
• Topping-up of oil level made with humid oil (non dried)
The moisture in a transformer is generated by several sources:
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 49
50. A 1% increase in the moisture content of paper has the same effect as
an increase in operating temperature of 8°C (doubling the rate of
depolymerisation)
- Accelerated ageing of the transformer insulation
- Moisture in the oil combined with particles reduces the breakdown voltage
of the oil and increases the risk of static electrification, partial discharge
activity and tracking
- High water content in cellulose
increases the risk of bubbling
during sudden overload or
thermal stress, and the risk of
dielectric breakdown
Reference: CIGRE Brochure #349 Moisture Equilibrium and
Moisture Migration within Transformer Insulation System
Maintenance Action Catalogue
Risks of Not Drying Insulation
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 50
51. • On-line oil dryers - molecular sieve
• Hot oil circulation
• Hot oil + vacuum / hot oil + vacuum + hot oil spray / hot oil + vacuum
‘+ cold trap
• Low frequency heating (LFH) / LFH + hot oil spray
• Vapour phase
Transformer Hot oil + Vacuum
(24 h / day)
LFH + Oil Spray
110 MVA / 70 kV 8 days 4 days
400 MVA / 400 kV 20-30 days 9 days
The typical time needed to dry a transformer from initial moisture
in the solid insulation of 3% to remaining moisture of 1%:
Maintenance Action Catalogue
Drying Techniques
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 51
52. Maintenance Action Catalogue
Physical and Chemical Oil Treatments
• Reclamation is defined by the IEC as “a
process that eliminates or reduces soluble
and insoluble polar contaminants from the oil
by chemical and physical processing”.
• The contaminants in question are mostly
oxidation products predominately in the oil but
also on the solid insulation.
• Chemical and physical processing is typically
a combination of treatment with a sorbent
material and filtering.
• Oil reclamation scenarios: on-site on-line, on
site off-line, tank to tank, large scale
reclaiming
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 52
53. Oil reclamation treatment is recommended because:
• An increase in oil acidity accelerates paper ageing
• Timely treatment, before advanced degradation, is important if the oil
quality is to be maintained.
Maintenance Action Catalogue
Importance of Oil Treatments
3 oil treatments used for corrosive sulphur problems:
• Adding metal passivator
• Removal of corrosive sulphur
• Oil exchange
Reference: CIGRE Brochure #378
Copper Sulphide in Transformer Insulation
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 53
54. Maintenance Action Catalogue
Precautions for Invasive Work
Work that requires oil to be partially or completely removed
from the transformer may be regarded as invasive.
Invasive work requires certain precautions to be taken
because the transformer insulation is very sensitive to
moisture, trapped air or gas bubbles, and particulate
contaminants.
Contaminants may easily be introduced either from airborne
dust and humidity, or directly from people, tools and
materials entering the transformer.
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 54
55. Maintenance Action Catalogue
Precautions for Invasive Work - Examples
Planning the Work
Evaluation of the amount of oil required to carry out, if the work required to access into
the tank, proper confined space training, plans and permit, plan to reduce the
exposure time to minimum, evaluate the ability of the tank to withstand vacuum
Draining the Transformer
Use of dry air to during oil draining, apply a positive pressure if the tank is left empty,
avoid any loss of oil into the environment
Access to the Transformer
Extreme cleanliness, continuous flow of dry air entering the tank, suitable safety
precautions need to be taken, gaskets replacement, cleaning cloths and boots, be
aware of the compatibility of solvents, paints, glues and other chemicals, tools should
be tethered and an inventory be kept
Refilling the Transformer
Vacuum filled (if the transformer was originally vacuum filled), air leaks elimination,
remove any free water on the tank, use dry oil and use a reconditioning plan, limit the
oil flow velocity, winding connected to earth, apply a standing time following oil filling
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 55
57. Major Work – Transformer Repair
Definition
On-site repair is invasive work, performed in-situ, where it is necessary to
partly or completely drain oil and remove the main covers in order to
repair or upgrade the transformer .
The level of expertise and the need for high voltage tests may vary,
depending on the complexity of the work.
Repairs are categorized as follows:
- Minor repairs such as replacement
of bushings or tap changers, repair
of connections
- Major repairs such as exchange of
windings, repair of the core,
modifications or upgrades
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 57
58. Major Work – Transformer Repair
Advantages of On-site Repair
• Transportation difficult or impossible:
disused railway, axle load limits,
changed road alignment, bridges,
roundabouts
• High transportation costs
• High transportation risks: poor road
conditions, heavily aged insulation
• Reduced down-time by avoiding
transportation: avoid higher losses in
the network due to changes in
optimum power flow, loss of energy
sales, loss of water in a hydro plant,
penalty in case of non delivery of
energy; time saving 1 - 3 months
On-site repair might have advantages over factory repair:
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 58
59. Major Work – Transformer Repair
Process
• The process of on-site major repair can with appropriate resources and
planning effectively emulate a workshop repair. Some adaptations are
needed due to site conditions.
• A detailed plan for each activity will allow adequate time for the
equipment and material to arrive at the proper phase of the repair.
Planning should be updated daily by the site supervisor and reviewed
periodically. Site personnel require regular contact with their service
centre or factory for logistical, administrative and technical support.
• On-site repair requires excellent logistics, competent planning as well as
the flexibility to adapt to the unforeseen (inherent to most repair
situations) in order to minimize delays to the schedule.
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 59
60. Major Work – Transformer Repair
Testing
Site testing extends the repair time and represents significant costs.
However, these tests will reduce future risk of unexpected failure.
In defining the scope of site testing, the following aspects should be
considered:
• Type of repair and scope of work (replacing
bushings, winding replacement)
• Possible consequences of a failure
• Stress from the network (lightning, short-circuit,
overload)
• Urgency and loss of production due to down-
time
• Repair/refurbishment versus replacement
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 60
61. Suggested categories of on-site testing:
Transformer
Category
Characteristics
Category 1 - Nominal Voltage < 72.5 kV
- Units with no critical loss of production in case of failure, or with good redundancy or a
‘’’spare unit
- Limited risk of fire in case of failure (collateral damages)
- Repair of connections, replacement of bushing or OLTC
- No expected overload. Good protection system. Low risk of short-circuit on the network
- Urgency to put the units back in service to meet operation constraints
- No availability of testing equipment
Category 2 - Nominal Voltage >=72.5kV and < 170 kV
- Repair involving work on the active part
Category 3 - Nominal Voltage >=170kV and <= 300 kV
- Transformers with severe consequences in case of failure and/or significant loss of ’’
production - generation or industrial applications
- Transformer with no spare unit
Category 4 - Nominal Voltage > 300 kV
- Repair that incorporates a new winding design
- Upgrade with new design to reach higher MVA / Voltage.
- Transformers with high lightning exposure
Major Work – Transformer Repair
Testing
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 61
62. Category Recommended tests
Category 1 - Low voltage tests: winding resistance, ratio, insulation resistance of windings & core, power factor
- Functional tests and checks on indicators, control circuits, relays and OLTC
- Dielectric Response (DR) and Frequency Response Analysis (FRA) as a fingerprint
- Continuous increase of voltage whenever possible (GSU) without any load: 20%–100% Un
- Connection to the network with no load at 100% Un for 12 hours with monitoring of gas (preferably
on-line or off-line after one hour and then every 3 hours). In any case, the results of DGA should be
analyzed before putting the transformer back under load
- Incremental load rise (whenever possible)
- Monthly follow-up of DGA over a 6 month period
Category 2 - Same tests as for Category 1
- Induced voltage tests with partial discharge (PD) measurement according to IEC 60076-3 or IEEE
‘’C57.12.00 standard
Category 3 - Same tests as for Category 2
- In case of delta connected HV windings, separate source AC withstand voltage test (applied voltage
‘’test) at 80% of the nominal voltage test according to IEC 60076-3 or IEEE C57.12.00 standard
Category 4 - Same tests as for Category 3
- Lightning impulse test, switching impulse test and chopped impulse test may be performed;
‘’nevertheless, the added value of these has to be evaluated (costs involved, availability of test
‘’equipments)
Major Work – Transformer Repair
Testing
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 62
63. Major Work – Transformer Repair
Economics
Case Examples:
- Problematic transportation
- Problematic outage time
- Repair of a faulted unit with core repair and windings replacement
Factors to consider:
- Costs of material and labour
- Core and winding losses
- Transportation
- Outage time
- Reliability and Tests
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 63
64. Major Work – Transformer Repair
Environmental Considerations
Guide for Transformer maintenance – Tutorial of Cigre WG A2.34 64