SlideShare a Scribd company logo
1 of 21
TRANSFORMER ASSET MANAGEMENT
-AN OVERVIEW
Presented By:
S.M.G. MUZAFFAR HUSSAIN
SUBSTATION ENGINEER
Unrestricted
CONTENTS
 INTRODUCTION
 TAM
 TAMP
 TRANSFORMER AGING
 TRANSFORMER FAILURES
 CONDITION MONITORING / TESTING
 ASSET MANAGEMENT TOOLS
 FACTORS DECIDING PROCUREMENT OF SPARE
TRANSFORMER
 CONCLUSION
 REFERENCES AND ACKNOWLEDGEMENTS
INTRODUCTION
Asset Management is defined as an efficient way of
utilizing and maintaining a group of assets over their
entire life cycle assuring return on investments,
ensuring defined service, reliability and safety as per
standards.
An asset is the one which is,
 used in production and supply of goods and services.
 utilized maximum throughout its life cycle.
 A vital link in the network and has a specified life
period.
TRANSFORMER ASSET MANAGEMENT (TAM)
IN ELECTRICAL UTILITIES
A power transformer being a significant asset in the process of energy
transmission, Transformer Asset Management (TAM) becomes really
necessary that focuses on Plant reliability, Managing risks and
Optimizing life cycle costs.
In simple managing transformer assets for value and risk implies
 Balancing investors, customers and interested parties.
 Aiming uninterrupted long term service to customers.
 Cost effective quality energy supply to avoid customer conflict.
 Evaluating massive risk implications i.e. Cost of transformer Vs
Loss of revenue due to its failure at site
 Using management tools to calculate the life of a transformer to
avoid extending its use beyond planned to avoid windfall.
 Managing redundancy usually built in the network.
 Building teams and developing asset management cultures.
 Encouraging both internal and external interested parties to invest.
TRANSFORMER ASSET MANAGEMENT PLAN (TAMP)
A Transformer Asset Management Plan (TAMP) is made with the
business objective of providing a comprehensive
a) Qualitative assessment of condition.
i.e. Healthiness of the transformer
b) Risk Exposed to the business or extended usage of
transformers beyond its lifetime. (Power interruption due to
continued usage of defective transformers without
redundancy till the time it fails and not thinking of repair,
refurbishment or replacement).
c) Developing an effective inventory management
strategy to minimize the life cycle costs / Inventory costs.
a. QUALITATIVE ASSESSMENT OF CONDITION
Healthiness of the transformers is assessed during the
various stages of its life cycle through electrical
tests , dielectric tests on oil and insulation and
other diagnostics methods.
Preventive maintenance and Quality inspections are
carried out to detect faults and fix it in time to
ensure and acceptable level of transformer
reliability. However the spare parts and cost of
inventory should be mitigated.
b. RISK EXPOSED TO THE BUSINESS
A life extension beyond that planned is a significant
windfall for the utility. Any failure by the
transformer has massive risk implications.
Redundancy built in the network results in power
interruptions to customers and loss of revenue
which is many times its cost to the utility.
c. DEVELOPING AN EFFECTIVE INVENTORY MANAGEMENT STRATEGY
The components of the Power transformer are classified into
three categories.
i. Most Expensive Items (OLTC, Bushings Arrestors)
ii. Ordinary Items (Insulating Oil)
iii. Cheap Items (Nuts, Bolts and Gaskets)
The most expensive items that need close control and which
in cults usually high inventory cost are usually not kept in
huge numbers as stock due to capital investment
limitations. Hence the number of spare parts is based on
Minimum Safety Stock (MSS) with acceptable stock
availability.
Statistical distribution techniques such as Poisson and Normal
distribution is used to determine the optimum number of
spare parts after analyzing the failure rate on Power
transformer.
c. DEVELOPING AN EFFECTIVE INVENTORY MANAGEMENT STRATEGY
(Continued..)
The Ordinary items that need standard care,
the method of Economic Order Quantity
(EOQ) is proposed to minimize inventory cost.
The cheap items that need little care are
managed by KANBAN System.
With this effective inventory management the
electric utilities not only reduce the inventory
costs but also significantly reduce the hidden
capital costs due to power cuts.
4. TRANSFORMER AGING & END OF LIFE
Aging of a transformer refers to the thermal
degradation of the insulation system during its
normal life cycle. End-of-life refers to a point where it
can no longer withstand the stresses coming on to it
during fault conditions.
 The primary aging factors are temperature, time,
over loads and frequent faults.
 The environmental conditions such as corrosive
atmosphere, excessive vibration may affect actual
service life.
 Agents of deterioration like moisture and tracking
accelerates aging.
Degree of Polarization (DP test) on cellulose insulation
material sample taken from the hottest-spot region is
recommended as a supplementary test to determine
its correlation with transformer aging.
5. TRANSFORMER FAILURES
Failure is described as an insulation breakdown and
that a service outage would result if it occurs in the
field.
Main causes of transformer failure:
 Internal insulation breakdown caused by hot spots,
partial discharges and arcing.
 Oil Contamination caused by oil leaks.
 Voltage spikes caused by lightning surges.
 Movement of coils and weakening of cellulose caused
by external short circuits.
 Moisture content
 Internal flash over of tap changer
 External flash over of insulators
 Bursting out of tank due to enormous pressure
created during short circuits and failure of operation
of pressure relief vent.
 Operating an Off load tap changer without de-
energizing the transformer.
6. CONDITION MONITORING/TESTING
Since it is not possible to predict when a final failure
will occur, it is necessary that a number of
parameters such as dielectric strength,
thermal/mechanical strength and electrical strength
are to be monitored to avoid breakdown.
Maintenance Engineers are required to conduct
analysis, tests, and inspections and review previous
data to assess the condition (Healthiness) of the
power transformer.
INSULATION SYSTEM
Dissolved Gas Analysis (DGA)
Acidity
Water Content (ppm test)
Insulation power factor (Tan ∂ test)
Furan Analysis
Degree of Polymerization (DP test)
6. CONDITION MONITORING/TESTING
(Continued..)
ELECTRICAL SYSTEM
Ratio (TTR test)
DC measurement of Winding Resistance
MECHANICAL SYSTEM
Sweep Frequency Response Analysis
Tightness test for Oil leakage
Core to earth resistance
BENCH MARKING
Previous results
Signatures
Bench mark set by Electric utility companies
7. ASSET MANAGEMENT TOOLS
In practice as necessary tools are not available to determine the
end-of-life of a power transformer, the minimum life expectancy
(elapsed time) is calculated.
Minimum life expectancy calculation as per IEEE C57.100.1999
7. ASSET MANAGEMENT TOOLS (Continued..)
The elapsed time in actual for a transformer in service
will be very much greater than the life determined by
the continuous loading. Therefore it is indicative of
the fact that a transformer operated continuously at
rated hottest-spot temperature should give a
satisfactory life expectancy of 180 000 h
approximately 20.5yrs.
If a transformer fails before its life expectancy due to
material defect or poor workmanship the issue has to
be taken up with the manufacturer for immediate
replacement.
If the transformer fails in the end of life tests (series of
high voltage and high current tests), a service outage
occurs in the field and to refurbish with spare
transformer.
8. FACTORS DECIDING PROCUREMENT OF SPARE
TRANSFORMERS
Transformer is a costly equipment and incurs huge
investment and stock build up.
Even though its failure rate is low it plays an important
role in transmission network. Therefore a wise
decision has to be taken on the procurement of spare
transformers considering system reliability and risk
assessment.
Before procuring the spare transformers, the following
has to be evaluated
 Whether the aged transformers can be repaired.
 Value of the spare transformers V/s Repair cost
 Overloading of aged transformers or its Replacement.
8. FACTORS DECIDING PROCUREMENT OF SPARE
TRANSFORMERS (Continued..)
The other factors deciding on the procurement of
spare transformer are
 Total number of transformers available in the system.
 Load demand on the service transformers
 Condition of aged transformers
 Total years in service
 Risk Management Strategy
◦ Shifting aged transformers to under loaded
substations to minimize failures.
◦ Availability of identical spare transformers to
mitigate the risk of transformer failures and outage
at substation.
9. CONCLUSION
Since it is impracticable to determine the
condition of aged power transformers and its
end of life, the following are the conclusions.
◦ The aged transformers are to be identified in the
system to avoid overloading and failures at site
during its revenue earning period.
◦ Spare transformers to be procured as per the
inventory management strategy to prevent outage
and loss of revenue.
◦ Load demand and Load flow study to be done to
operate transformers in parallel.
◦ Mobile transformers identical to the existing ones
have many advantages in shifting and restoration.
◦ Avoid un-served customers and energy loss.
◦ Quality supply as per customer demand to avoid
customer conflict.
9. CONCLUSION (Continued..)
◦ Increasing transformer life through condition
monitoring and Preventive maintenance.
◦ Lessen Maintenance Costs.
◦ Depreciation on the value of the asset to be
calculated every year to decide on replacement.
◦ When the depreciated value of the asset becomes
equal to the maintenance cost it is the right time
for replacement.
◦ The Residual / Fair value of the asset at the end of
its service shall be an appreciable one.
◦ As such in the whole substation the asset value of
transformers are less compared to its cost of
failure. Hence avoid risk implications.
◦ Data Collection is a must for analysis
9. References and Acknowledgements
 Asset Management in Power Transformers by G. Kalinde
 Asset Management Plan of transformer & Factors affecting the decision on
procurement of spare transformer by Nahar S. Al Mutawah and Navin Rego
 Asset Management for Power transformer in High Voltage Substation by Thanapong
Suwanasri, Rattanakorn Phadungthin and Cattareeya Suwanasri
END OF PAPER
THANK YOU

More Related Content

What's hot

Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guideSlides Hub
 
Descarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia VirtualDescarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia VirtualTRANSEQUIPOS S.A.
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTCRohit Dave
 
Relay coordination
Relay coordinationRelay coordination
Relay coordinationD Målîk
 
Surge arrester ppt
Surge arrester pptSurge arrester ppt
Surge arrester pptIrinElsa
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgearAdnan Sayed
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protectionRakesh Joshi
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 
Unit-1 Power Semiconductor devices
Unit-1 Power Semiconductor devicesUnit-1 Power Semiconductor devices
Unit-1 Power Semiconductor devicesjohny renoald
 
Surge diverter
Surge diverterSurge diverter
Surge divertersarunkutti
 
Maintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of SubstationMaintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of SubstationSystem Protection
 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV SwitchgearSheikh Nazmul Islam
 
Vaccum Circuit Breaker
Vaccum Circuit BreakerVaccum Circuit Breaker
Vaccum Circuit BreakerRAHUL-GOPU
 
Basics of overcurrent protection
Basics of overcurrent protectionBasics of overcurrent protection
Basics of overcurrent protectionSalim Palayi
 
Power System Protection course - Part I
Power System Protection course - Part IPower System Protection course - Part I
Power System Protection course - Part ISlides Hub
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protectionSaifUrrehman183
 

What's hot (20)

Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Descarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia VirtualDescarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia Virtual
 
Vacuum circuit breaker
Vacuum circuit breakerVacuum circuit breaker
Vacuum circuit breaker
 
POWER-ELECTRONICS.ppt
POWER-ELECTRONICS.pptPOWER-ELECTRONICS.ppt
POWER-ELECTRONICS.ppt
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
 
Surge arrester ppt
Surge arrester pptSurge arrester ppt
Surge arrester ppt
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgear
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
Unit-1 Power Semiconductor devices
Unit-1 Power Semiconductor devicesUnit-1 Power Semiconductor devices
Unit-1 Power Semiconductor devices
 
Surge diverter
Surge diverterSurge diverter
Surge diverter
 
Maintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of SubstationMaintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of Substation
 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
 
Vaccum Circuit Breaker
Vaccum Circuit BreakerVaccum Circuit Breaker
Vaccum Circuit Breaker
 
Basics of overcurrent protection
Basics of overcurrent protectionBasics of overcurrent protection
Basics of overcurrent protection
 
Power System Protection course - Part I
Power System Protection course - Part IPower System Protection course - Part I
Power System Protection course - Part I
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protection
 

Similar to Transformer asset management

Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...
Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...
Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...Miracle Electronic Devices Private Limited
 
01 Overview of Power transformers - Remedial Measures.ppt
01 Overview of Power transformers - Remedial Measures.ppt01 Overview of Power transformers - Remedial Measures.ppt
01 Overview of Power transformers - Remedial Measures.pptvikram desai
 
Tahir Mahmood Butt
Tahir Mahmood ButtTahir Mahmood Butt
Tahir Mahmood ButtTahir Butt
 
Why transformers fail_final
Why transformers fail_finalWhy transformers fail_final
Why transformers fail_finalSnehangshu Ghosh
 
PES Wind Magazine - The development of a MV power converter for FC wind turbi...
PES Wind Magazine - The development of a MV power converter for FC wind turbi...PES Wind Magazine - The development of a MV power converter for FC wind turbi...
PES Wind Magazine - The development of a MV power converter for FC wind turbi...Ingeteam Wind Energy
 
IRJET- Systematic Steps in Overhauling of a Transformer
IRJET- Systematic Steps in Overhauling of a TransformerIRJET- Systematic Steps in Overhauling of a Transformer
IRJET- Systematic Steps in Overhauling of a TransformerIRJET Journal
 
Generator step-up and system intertie power transformers Securing high-qualit...
Generator step-up and system intertie power transformers Securing high-qualit...Generator step-up and system intertie power transformers Securing high-qualit...
Generator step-up and system intertie power transformers Securing high-qualit...Krishna P. Sharma
 
Transformer operation and maintenance cycle javid iqbal sodagar
Transformer operation and maintenance cycle javid iqbal sodagarTransformer operation and maintenance cycle javid iqbal sodagar
Transformer operation and maintenance cycle javid iqbal sodagarjavid iqbal sodagar
 
White paper - Extended validation and certification of Ingeteam's new-generat...
White paper - Extended validation and certification of Ingeteam's new-generat...White paper - Extended validation and certification of Ingeteam's new-generat...
White paper - Extended validation and certification of Ingeteam's new-generat...Ingeteam Wind Energy
 
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...Vecoin
 
transformerdesignandprotection-130408132534-phpapp02.ppt
transformerdesignandprotection-130408132534-phpapp02.ppttransformerdesignandprotection-130408132534-phpapp02.ppt
transformerdesignandprotection-130408132534-phpapp02.pptThien Phan Bản
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaUdhayakumar Venkataraman
 
Estimating Reliability of Power Factor Correction Circuits: A Comparative Study
Estimating Reliability of Power Factor Correction Circuits: A Comparative StudyEstimating Reliability of Power Factor Correction Circuits: A Comparative Study
Estimating Reliability of Power Factor Correction Circuits: A Comparative StudyIJERA Editor
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protectionashwin fcc
 
Mppkvv company ltd
Mppkvv company ltdMppkvv company ltd
Mppkvv company ltdDEEPAK PATEL
 

Similar to Transformer asset management (20)

Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...
Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...
Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...
 
01 Overview of Power transformers - Remedial Measures.ppt
01 Overview of Power transformers - Remedial Measures.ppt01 Overview of Power transformers - Remedial Measures.ppt
01 Overview of Power transformers - Remedial Measures.ppt
 
Tahir Mahmood Butt
Tahir Mahmood ButtTahir Mahmood Butt
Tahir Mahmood Butt
 
Why transformers fail_final
Why transformers fail_finalWhy transformers fail_final
Why transformers fail_final
 
PES Wind Magazine - The development of a MV power converter for FC wind turbi...
PES Wind Magazine - The development of a MV power converter for FC wind turbi...PES Wind Magazine - The development of a MV power converter for FC wind turbi...
PES Wind Magazine - The development of a MV power converter for FC wind turbi...
 
CHALLENGES AND STRATEGIES FOR IMPROVING TRANSFORMER EFFICIENCY.pdf
CHALLENGES AND STRATEGIES FOR IMPROVING TRANSFORMER EFFICIENCY.pdfCHALLENGES AND STRATEGIES FOR IMPROVING TRANSFORMER EFFICIENCY.pdf
CHALLENGES AND STRATEGIES FOR IMPROVING TRANSFORMER EFFICIENCY.pdf
 
IRJET- Systematic Steps in Overhauling of a Transformer
IRJET- Systematic Steps in Overhauling of a TransformerIRJET- Systematic Steps in Overhauling of a Transformer
IRJET- Systematic Steps in Overhauling of a Transformer
 
Turbina vapor
Turbina vaporTurbina vapor
Turbina vapor
 
Wgp4205 turbine
Wgp4205 turbineWgp4205 turbine
Wgp4205 turbine
 
Generator step-up and system intertie power transformers Securing high-qualit...
Generator step-up and system intertie power transformers Securing high-qualit...Generator step-up and system intertie power transformers Securing high-qualit...
Generator step-up and system intertie power transformers Securing high-qualit...
 
IOT PAPER.pdf
IOT PAPER.pdfIOT PAPER.pdf
IOT PAPER.pdf
 
Transformer operation and maintenance cycle javid iqbal sodagar
Transformer operation and maintenance cycle javid iqbal sodagarTransformer operation and maintenance cycle javid iqbal sodagar
Transformer operation and maintenance cycle javid iqbal sodagar
 
White paper - Extended validation and certification of Ingeteam's new-generat...
White paper - Extended validation and certification of Ingeteam's new-generat...White paper - Extended validation and certification of Ingeteam's new-generat...
White paper - Extended validation and certification of Ingeteam's new-generat...
 
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
 
transformerdesignandprotection-130408132534-phpapp02.ppt
transformerdesignandprotection-130408132534-phpapp02.ppttransformerdesignandprotection-130408132534-phpapp02.ppt
transformerdesignandprotection-130408132534-phpapp02.ppt
 
Power Generation: Coal-Fired
Power Generation: Coal-FiredPower Generation: Coal-Fired
Power Generation: Coal-Fired
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performa
 
Estimating Reliability of Power Factor Correction Circuits: A Comparative Study
Estimating Reliability of Power Factor Correction Circuits: A Comparative StudyEstimating Reliability of Power Factor Correction Circuits: A Comparative Study
Estimating Reliability of Power Factor Correction Circuits: A Comparative Study
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protection
 
Mppkvv company ltd
Mppkvv company ltdMppkvv company ltd
Mppkvv company ltd
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 

Transformer asset management

  • 1. TRANSFORMER ASSET MANAGEMENT -AN OVERVIEW Presented By: S.M.G. MUZAFFAR HUSSAIN SUBSTATION ENGINEER Unrestricted
  • 2. CONTENTS  INTRODUCTION  TAM  TAMP  TRANSFORMER AGING  TRANSFORMER FAILURES  CONDITION MONITORING / TESTING  ASSET MANAGEMENT TOOLS  FACTORS DECIDING PROCUREMENT OF SPARE TRANSFORMER  CONCLUSION  REFERENCES AND ACKNOWLEDGEMENTS
  • 3. INTRODUCTION Asset Management is defined as an efficient way of utilizing and maintaining a group of assets over their entire life cycle assuring return on investments, ensuring defined service, reliability and safety as per standards. An asset is the one which is,  used in production and supply of goods and services.  utilized maximum throughout its life cycle.  A vital link in the network and has a specified life period.
  • 4. TRANSFORMER ASSET MANAGEMENT (TAM) IN ELECTRICAL UTILITIES A power transformer being a significant asset in the process of energy transmission, Transformer Asset Management (TAM) becomes really necessary that focuses on Plant reliability, Managing risks and Optimizing life cycle costs. In simple managing transformer assets for value and risk implies  Balancing investors, customers and interested parties.  Aiming uninterrupted long term service to customers.  Cost effective quality energy supply to avoid customer conflict.  Evaluating massive risk implications i.e. Cost of transformer Vs Loss of revenue due to its failure at site  Using management tools to calculate the life of a transformer to avoid extending its use beyond planned to avoid windfall.  Managing redundancy usually built in the network.  Building teams and developing asset management cultures.  Encouraging both internal and external interested parties to invest.
  • 5. TRANSFORMER ASSET MANAGEMENT PLAN (TAMP) A Transformer Asset Management Plan (TAMP) is made with the business objective of providing a comprehensive a) Qualitative assessment of condition. i.e. Healthiness of the transformer b) Risk Exposed to the business or extended usage of transformers beyond its lifetime. (Power interruption due to continued usage of defective transformers without redundancy till the time it fails and not thinking of repair, refurbishment or replacement). c) Developing an effective inventory management strategy to minimize the life cycle costs / Inventory costs.
  • 6. a. QUALITATIVE ASSESSMENT OF CONDITION Healthiness of the transformers is assessed during the various stages of its life cycle through electrical tests , dielectric tests on oil and insulation and other diagnostics methods. Preventive maintenance and Quality inspections are carried out to detect faults and fix it in time to ensure and acceptable level of transformer reliability. However the spare parts and cost of inventory should be mitigated.
  • 7. b. RISK EXPOSED TO THE BUSINESS A life extension beyond that planned is a significant windfall for the utility. Any failure by the transformer has massive risk implications. Redundancy built in the network results in power interruptions to customers and loss of revenue which is many times its cost to the utility.
  • 8. c. DEVELOPING AN EFFECTIVE INVENTORY MANAGEMENT STRATEGY The components of the Power transformer are classified into three categories. i. Most Expensive Items (OLTC, Bushings Arrestors) ii. Ordinary Items (Insulating Oil) iii. Cheap Items (Nuts, Bolts and Gaskets) The most expensive items that need close control and which in cults usually high inventory cost are usually not kept in huge numbers as stock due to capital investment limitations. Hence the number of spare parts is based on Minimum Safety Stock (MSS) with acceptable stock availability. Statistical distribution techniques such as Poisson and Normal distribution is used to determine the optimum number of spare parts after analyzing the failure rate on Power transformer.
  • 9. c. DEVELOPING AN EFFECTIVE INVENTORY MANAGEMENT STRATEGY (Continued..) The Ordinary items that need standard care, the method of Economic Order Quantity (EOQ) is proposed to minimize inventory cost. The cheap items that need little care are managed by KANBAN System. With this effective inventory management the electric utilities not only reduce the inventory costs but also significantly reduce the hidden capital costs due to power cuts.
  • 10. 4. TRANSFORMER AGING & END OF LIFE Aging of a transformer refers to the thermal degradation of the insulation system during its normal life cycle. End-of-life refers to a point where it can no longer withstand the stresses coming on to it during fault conditions.  The primary aging factors are temperature, time, over loads and frequent faults.  The environmental conditions such as corrosive atmosphere, excessive vibration may affect actual service life.  Agents of deterioration like moisture and tracking accelerates aging. Degree of Polarization (DP test) on cellulose insulation material sample taken from the hottest-spot region is recommended as a supplementary test to determine its correlation with transformer aging.
  • 11. 5. TRANSFORMER FAILURES Failure is described as an insulation breakdown and that a service outage would result if it occurs in the field. Main causes of transformer failure:  Internal insulation breakdown caused by hot spots, partial discharges and arcing.  Oil Contamination caused by oil leaks.  Voltage spikes caused by lightning surges.  Movement of coils and weakening of cellulose caused by external short circuits.  Moisture content  Internal flash over of tap changer  External flash over of insulators  Bursting out of tank due to enormous pressure created during short circuits and failure of operation of pressure relief vent.  Operating an Off load tap changer without de- energizing the transformer.
  • 12. 6. CONDITION MONITORING/TESTING Since it is not possible to predict when a final failure will occur, it is necessary that a number of parameters such as dielectric strength, thermal/mechanical strength and electrical strength are to be monitored to avoid breakdown. Maintenance Engineers are required to conduct analysis, tests, and inspections and review previous data to assess the condition (Healthiness) of the power transformer. INSULATION SYSTEM Dissolved Gas Analysis (DGA) Acidity Water Content (ppm test) Insulation power factor (Tan ∂ test) Furan Analysis Degree of Polymerization (DP test)
  • 13. 6. CONDITION MONITORING/TESTING (Continued..) ELECTRICAL SYSTEM Ratio (TTR test) DC measurement of Winding Resistance MECHANICAL SYSTEM Sweep Frequency Response Analysis Tightness test for Oil leakage Core to earth resistance BENCH MARKING Previous results Signatures Bench mark set by Electric utility companies
  • 14. 7. ASSET MANAGEMENT TOOLS In practice as necessary tools are not available to determine the end-of-life of a power transformer, the minimum life expectancy (elapsed time) is calculated. Minimum life expectancy calculation as per IEEE C57.100.1999
  • 15. 7. ASSET MANAGEMENT TOOLS (Continued..) The elapsed time in actual for a transformer in service will be very much greater than the life determined by the continuous loading. Therefore it is indicative of the fact that a transformer operated continuously at rated hottest-spot temperature should give a satisfactory life expectancy of 180 000 h approximately 20.5yrs. If a transformer fails before its life expectancy due to material defect or poor workmanship the issue has to be taken up with the manufacturer for immediate replacement. If the transformer fails in the end of life tests (series of high voltage and high current tests), a service outage occurs in the field and to refurbish with spare transformer.
  • 16. 8. FACTORS DECIDING PROCUREMENT OF SPARE TRANSFORMERS Transformer is a costly equipment and incurs huge investment and stock build up. Even though its failure rate is low it plays an important role in transmission network. Therefore a wise decision has to be taken on the procurement of spare transformers considering system reliability and risk assessment. Before procuring the spare transformers, the following has to be evaluated  Whether the aged transformers can be repaired.  Value of the spare transformers V/s Repair cost  Overloading of aged transformers or its Replacement.
  • 17. 8. FACTORS DECIDING PROCUREMENT OF SPARE TRANSFORMERS (Continued..) The other factors deciding on the procurement of spare transformer are  Total number of transformers available in the system.  Load demand on the service transformers  Condition of aged transformers  Total years in service  Risk Management Strategy ◦ Shifting aged transformers to under loaded substations to minimize failures. ◦ Availability of identical spare transformers to mitigate the risk of transformer failures and outage at substation.
  • 18. 9. CONCLUSION Since it is impracticable to determine the condition of aged power transformers and its end of life, the following are the conclusions. ◦ The aged transformers are to be identified in the system to avoid overloading and failures at site during its revenue earning period. ◦ Spare transformers to be procured as per the inventory management strategy to prevent outage and loss of revenue. ◦ Load demand and Load flow study to be done to operate transformers in parallel. ◦ Mobile transformers identical to the existing ones have many advantages in shifting and restoration. ◦ Avoid un-served customers and energy loss. ◦ Quality supply as per customer demand to avoid customer conflict.
  • 19. 9. CONCLUSION (Continued..) ◦ Increasing transformer life through condition monitoring and Preventive maintenance. ◦ Lessen Maintenance Costs. ◦ Depreciation on the value of the asset to be calculated every year to decide on replacement. ◦ When the depreciated value of the asset becomes equal to the maintenance cost it is the right time for replacement. ◦ The Residual / Fair value of the asset at the end of its service shall be an appreciable one. ◦ As such in the whole substation the asset value of transformers are less compared to its cost of failure. Hence avoid risk implications. ◦ Data Collection is a must for analysis
  • 20. 9. References and Acknowledgements  Asset Management in Power Transformers by G. Kalinde  Asset Management Plan of transformer & Factors affecting the decision on procurement of spare transformer by Nahar S. Al Mutawah and Navin Rego  Asset Management for Power transformer in High Voltage Substation by Thanapong Suwanasri, Rattanakorn Phadungthin and Cattareeya Suwanasri