SlideShare a Scribd company logo
GN23
Plumbing Method Statement
Guidance Note
December 2012
Guidance Note SC GN 23 (V3) Dec 20122
Method Statements – A basic guide to preparation
Introduction
This Guidance Note gives practical information about creating a method statement.
A completed sample template has been included in Appendix 1 and a blank template in
Appendix 2. If you wish to use the template in Appendix 2 to construct your own
documents, you must ensure that all references to safecontractor have been removed and
the final documents are clearly incorporated into your existing safety management system.
A method statement is an ideal way of recording the hazards involved in a specific work
activity and communicating the risk and precautions required to all those involved in the
work, including those undertaking the work and their immediate managers.
A method statement should be developed in conjunction with a risk assessment and
together these demonstrate a safe system of work. The method statement needs be clear,
no longer than necessary, and not over complicated. The document should avoid
ambiguities or generalisations, which could lead to confusion and layout a step-by-step
sequence of work to describe how the activity is to be carried out safely.
Format
The actual format is dependent on the work being undertaken and the organisational
arrangements in place but generally the following headings should be present:
1. Organisation/company in control of the operation
2. Named individual responsible for the activity and its safety
3. Name of method statement originator and authorisation date
4. Arrangements for changing/deviating from method statement
5. General description of activity
6. Location of activity including access and restrictions
7. General working environment considerations, e.g. temperature and wind speed
8. Protection of others, e.g. members of the public
9. Emergency procedures, including location of emergency equipment
10. Identity of operatives (and any specific training or certification required)
11. Requirements for Personal Protective Equipment
12. Plant and equipment used, including safety precautions and restrictions
13. Materials information e.g. hazard information and storage/transport requirements
14. Work sequence, including associated risks and required control measures for each
stage
15. Safety checks/clearances at specific stages
16. Final clearance that activity is completed to specification
17. Any other additional information that may be relevant.
The list above is not exhaustive and a method statement may or may not include each and
every item. However as a minimum it must achieve the following objectives:-
 It should be up to date, identifiable and its source accountable
 It should contain the sequence of works
 It should identify the associated risks and control measures
 It should state actions/authorisation required to deviate from method statement.
Appendix 1 is a sample method statement for plumbing activities. It can be as simple or as
detailed as the job/risk requires, so long as it meets the four main objectives.
Guidance Note SC GN 23 (V3) Dec 20123
Appendix 1
Plumbing Method Statement
Contract Manager: Joe Bloggs Site supervisor: David Jones
Originator: Joe Bloggs Position: David Jones Date: 01/12/2012
This method statement is critical to the health and safety of the activity(ies) it
relates to. It is to be strictly adhered to. Any deviation must first be authorised by
the Site Supervisor.
Planned Task/Activity Description:
Replace Ball Valve to Water Tank.
Location and Access: (attached plan as appropriate)
Located on flat roof through access door into plant room.
Working Environment & Restrictions:
Flat roof accessed through locked door. Mandatory use of Mansafe system required.
Protection of others:
Men at work sign attached to roof access door, additional signage displayed at work
area
Emergency Procedures:
Normal site emergency procedures will apply.
Operatives/Competence:
1 city and guilds trained Plumber with safe use of harness training.
Personal Protective Equipment:
Overalls, Safety Harness, Gloves, Goggles, Safety Footwear
Plant & Equipment:
Isolation lock and general hand tools
Materials Handling/Storage & Safety Information:
All material in manageable individual lengths
Critical Stages: (must be undertaken in correct sequence)
1. Attend Induction, sign for permit and obtain access door key
2. If no information is available on the site water treatment regime/water quality
checks, contact office for further clearance to work
3. Access to roof through locked door
4. Once on roof attach harness to fixed safety restraint system
5. Follow set walkway to plant room
6. Isolate supply to Water Tank using Isolation Lock
7. Drain tank
8. Remove defective Ball Valve and replace
9. Remove Isolation
10. Re-Fill Water Tank and test new Ball Valve
11. Return to access door via set walkway
12. Return key and sign off permit.
Final Clearance: (Work/Activity completed to satisfaction).
Name Position: Date:
Guidance Note SC GN 23 (V3) Dec 20124
Appendix 2
Blank Method Statement Template
Contract Manager: Site Supervisor:
Originator: Position: Date:
This method statement is critical to the health and safety of the activity(ies) it
relates to. It is to be strictly adhered to. Any deviation must first be authorised by
the Site Supervisor.
Planned Task/Activity Description:
Location and Access: (attached plan as appropriate)
Working Environment & Restrictions:
Protection of others:
Emergency Procedures:
Operatives/Competence:
Personal Protective Equipment:
Plant & Equipment:
Materials Handling/Storage & Safety Information:
Critical Stages: (must be undertaken in correct sequence)
Final Clearance: (Work/Activity completed to satisfaction).
Name Position: Date:

More Related Content

What's hot

Electrical standard symbols
Electrical standard symbolsElectrical standard symbols
Electrical standard symbols
asifsalafy
 
Piping and instrumentation diagram (p&id)
Piping and instrumentation diagram (p&id)Piping and instrumentation diagram (p&id)
Piping and instrumentation diagram (p&id)
Karnav Rana
 
Control system
Control systemControl system
Control system
abhishek ambhore
 
Relays book.pdf
Relays book.pdfRelays book.pdf
Relays book.pdf
YesidFigueroa3
 
How-to read P&ID Reference Guide .pdf
How-to read P&ID Reference Guide .pdfHow-to read P&ID Reference Guide .pdf
How-to read P&ID Reference Guide .pdf
GHANSHYAMDASS11
 
RTCC & AVR
RTCC & AVRRTCC & AVR
RTCC & AVR
Indiran K
 
Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a Substation
Md. Atiqur Rahman
 
Process Plant design fundementals
Process Plant design fundementalsProcess Plant design fundementals
Process Plant design fundementals
Greg Pajak - P. Tech (Eng.), ISA84 SIS Expert
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,Bonding
Ko Winnwe
 
Breaker Operation & Maintenance
Breaker Operation & MaintenanceBreaker Operation & Maintenance
Breaker Operation & Maintenance
Sheikh Nazmul Islam
 
igbt and its characteristics
igbt and its characteristicsigbt and its characteristics
igbt and its characteristics
dharmendrawaghjipur007
 
Basics Of Instrumentation
Basics Of InstrumentationBasics Of Instrumentation
Basics Of Instrumentation
Vinoth Ganesh
 
Block reduction technique
Block reduction techniqueBlock reduction technique
Block reduction technique
rajkumar ch
 
Controller ppt
Controller pptController ppt
Controller ppt
gourav0077
 
Introduction to Industrial Instrumentation
Introduction to Industrial InstrumentationIntroduction to Industrial Instrumentation
Introduction to Industrial Instrumentation
Maria Romina Angustia
 
Industrial process control
Industrial process controlIndustrial process control
Industrial process control
Mohamed A Hakim
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
Sheikh Nazmul Islam
 
Control valves
Control valvesControl valves
Control valves
Syed Waqas Haider
 
Controllers ppt
Controllers pptControllers ppt
Controllers ppt
KevalSavsviya
 
Cascade control presentation
Cascade control presentationCascade control presentation
Cascade control presentation
Inara Ahmadova
 

What's hot (20)

Electrical standard symbols
Electrical standard symbolsElectrical standard symbols
Electrical standard symbols
 
Piping and instrumentation diagram (p&id)
Piping and instrumentation diagram (p&id)Piping and instrumentation diagram (p&id)
Piping and instrumentation diagram (p&id)
 
Control system
Control systemControl system
Control system
 
Relays book.pdf
Relays book.pdfRelays book.pdf
Relays book.pdf
 
How-to read P&ID Reference Guide .pdf
How-to read P&ID Reference Guide .pdfHow-to read P&ID Reference Guide .pdf
How-to read P&ID Reference Guide .pdf
 
RTCC & AVR
RTCC & AVRRTCC & AVR
RTCC & AVR
 
Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a Substation
 
Process Plant design fundementals
Process Plant design fundementalsProcess Plant design fundementals
Process Plant design fundementals
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,Bonding
 
Breaker Operation & Maintenance
Breaker Operation & MaintenanceBreaker Operation & Maintenance
Breaker Operation & Maintenance
 
igbt and its characteristics
igbt and its characteristicsigbt and its characteristics
igbt and its characteristics
 
Basics Of Instrumentation
Basics Of InstrumentationBasics Of Instrumentation
Basics Of Instrumentation
 
Block reduction technique
Block reduction techniqueBlock reduction technique
Block reduction technique
 
Controller ppt
Controller pptController ppt
Controller ppt
 
Introduction to Industrial Instrumentation
Introduction to Industrial InstrumentationIntroduction to Industrial Instrumentation
Introduction to Industrial Instrumentation
 
Industrial process control
Industrial process controlIndustrial process control
Industrial process control
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
 
Control valves
Control valvesControl valves
Control valves
 
Controllers ppt
Controllers pptControllers ppt
Controllers ppt
 
Cascade control presentation
Cascade control presentationCascade control presentation
Cascade control presentation
 

Similar to 23.plumbing method statement_gn23

Taking safety measures forward: Zero Incidents
Taking safety measures forward: Zero IncidentsTaking safety measures forward: Zero Incidents
Taking safety measures forward: Zero Incidents
Gareth Ashworth
 
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
AHU.pdf
AHU.pdfAHU.pdf
Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...
Canberra Institute of technology
 
3. Assessment Practical.docx
3. Assessment Practical.docx3. Assessment Practical.docx
3. Assessment Practical.docx
Canberra Institute of technology
 
27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates
Dwarika Bhushan Sharma
 
Notre Dame Lockout/Tagout Policy
Notre Dame Lockout/Tagout PolicyNotre Dame Lockout/Tagout Policy
Notre Dame Lockout/Tagout Policy
Jeremy Riddle
 
072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
Dr Fereidoun Dejahang
 
Hazard Identification & Control
Hazard Identification & ControlHazard Identification & Control
Hazard Identification & Control
Hasnizam Md Saad
 
Loto.ppt
Loto.pptLoto.ppt
Loto.ppt
hdiana818
 
4. Assessment Practical.docx
4. Assessment Practical.docx4. Assessment Practical.docx
4. Assessment Practical.docx
Canberra Institute of technology
 
Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...
Canberra Institute of technology
 
Lock Out - Tag Out - Try Out Safety Course 2014
Lock Out - Tag Out - Try Out Safety Course 2014Lock Out - Tag Out - Try Out Safety Course 2014
Lock Out - Tag Out - Try Out Safety Course 2014
H&K Equipment Group
 
Identify Construction Hazards and Select Risk Control Strategies Part 4.pptx
Identify Construction Hazards and Select Risk Control Strategies Part 4.pptxIdentify Construction Hazards and Select Risk Control Strategies Part 4.pptx
Identify Construction Hazards and Select Risk Control Strategies Part 4.pptx
Canberra Institute of technology
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
Atif767782
 
Student Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docxStudent Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docx
florriezhamphrey3065
 
078 switchgear install 1.0
078 switchgear install 1.0078 switchgear install 1.0
078 switchgear install 1.0
Invest Northern Ireland
 
Trailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearTrailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation Switchgear
Marty Stevenson
 
4_Fire Prevention Elements.ppt
4_Fire Prevention Elements.ppt4_Fire Prevention Elements.ppt
4_Fire Prevention Elements.ppt
OktomiWijaya1
 
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AhmadNadzir4
 

Similar to 23.plumbing method statement_gn23 (20)

Taking safety measures forward: Zero Incidents
Taking safety measures forward: Zero IncidentsTaking safety measures forward: Zero Incidents
Taking safety measures forward: Zero Incidents
 
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
 
AHU.pdf
AHU.pdfAHU.pdf
AHU.pdf
 
Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...
 
3. Assessment Practical.docx
3. Assessment Practical.docx3. Assessment Practical.docx
3. Assessment Practical.docx
 
27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates
 
Notre Dame Lockout/Tagout Policy
Notre Dame Lockout/Tagout PolicyNotre Dame Lockout/Tagout Policy
Notre Dame Lockout/Tagout Policy
 
072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
 
Hazard Identification & Control
Hazard Identification & ControlHazard Identification & Control
Hazard Identification & Control
 
Loto.ppt
Loto.pptLoto.ppt
Loto.ppt
 
4. Assessment Practical.docx
4. Assessment Practical.docx4. Assessment Practical.docx
4. Assessment Practical.docx
 
Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...
 
Lock Out - Tag Out - Try Out Safety Course 2014
Lock Out - Tag Out - Try Out Safety Course 2014Lock Out - Tag Out - Try Out Safety Course 2014
Lock Out - Tag Out - Try Out Safety Course 2014
 
Identify Construction Hazards and Select Risk Control Strategies Part 4.pptx
Identify Construction Hazards and Select Risk Control Strategies Part 4.pptxIdentify Construction Hazards and Select Risk Control Strategies Part 4.pptx
Identify Construction Hazards and Select Risk Control Strategies Part 4.pptx
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
Student Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docxStudent Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docx
 
078 switchgear install 1.0
078 switchgear install 1.0078 switchgear install 1.0
078 switchgear install 1.0
 
Trailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearTrailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation Switchgear
 
4_Fire Prevention Elements.ppt
4_Fire Prevention Elements.ppt4_Fire Prevention Elements.ppt
4_Fire Prevention Elements.ppt
 
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
 

More from bhattbhai

Dm p lhosp(1)
Dm p lhosp(1)Dm p lhosp(1)
Dm p lhosp(1)
bhattbhai
 
100957233 19228966-plumbing-calculation
100957233 19228966-plumbing-calculation100957233 19228966-plumbing-calculation
100957233 19228966-plumbing-calculation
bhattbhai
 
2006 plumbing dc
2006 plumbing dc2006 plumbing dc
2006 plumbing dc
bhattbhai
 
0018 p 1.3 plumbing notes details and schedule(1)
0018 p 1.3 plumbing notes details and schedule(1)0018 p 1.3 plumbing notes details and schedule(1)
0018 p 1.3 plumbing notes details and schedule(1)bhattbhai
 
59446885 hvac
59446885 hvac59446885 hvac
59446885 hvac
bhattbhai
 
7200 rev1 plumbing
7200 rev1 plumbing7200 rev1 plumbing
7200 rev1 plumbing
bhattbhai
 
3 cf ch-006_hvac_systems
3 cf ch-006_hvac_systems3 cf ch-006_hvac_systems
3 cf ch-006_hvac_systems
bhattbhai
 
21 hvac design manual
21 hvac design manual21 hvac design manual
21 hvac design manual
bhattbhai
 
158742585 packaged-type-ac-units
158742585 packaged-type-ac-units158742585 packaged-type-ac-units
158742585 packaged-type-ac-units
bhattbhai
 

More from bhattbhai (9)

Dm p lhosp(1)
Dm p lhosp(1)Dm p lhosp(1)
Dm p lhosp(1)
 
100957233 19228966-plumbing-calculation
100957233 19228966-plumbing-calculation100957233 19228966-plumbing-calculation
100957233 19228966-plumbing-calculation
 
2006 plumbing dc
2006 plumbing dc2006 plumbing dc
2006 plumbing dc
 
0018 p 1.3 plumbing notes details and schedule(1)
0018 p 1.3 plumbing notes details and schedule(1)0018 p 1.3 plumbing notes details and schedule(1)
0018 p 1.3 plumbing notes details and schedule(1)
 
59446885 hvac
59446885 hvac59446885 hvac
59446885 hvac
 
7200 rev1 plumbing
7200 rev1 plumbing7200 rev1 plumbing
7200 rev1 plumbing
 
3 cf ch-006_hvac_systems
3 cf ch-006_hvac_systems3 cf ch-006_hvac_systems
3 cf ch-006_hvac_systems
 
21 hvac design manual
21 hvac design manual21 hvac design manual
21 hvac design manual
 
158742585 packaged-type-ac-units
158742585 packaged-type-ac-units158742585 packaged-type-ac-units
158742585 packaged-type-ac-units
 

23.plumbing method statement_gn23

  • 2. Guidance Note SC GN 23 (V3) Dec 20122 Method Statements – A basic guide to preparation Introduction This Guidance Note gives practical information about creating a method statement. A completed sample template has been included in Appendix 1 and a blank template in Appendix 2. If you wish to use the template in Appendix 2 to construct your own documents, you must ensure that all references to safecontractor have been removed and the final documents are clearly incorporated into your existing safety management system. A method statement is an ideal way of recording the hazards involved in a specific work activity and communicating the risk and precautions required to all those involved in the work, including those undertaking the work and their immediate managers. A method statement should be developed in conjunction with a risk assessment and together these demonstrate a safe system of work. The method statement needs be clear, no longer than necessary, and not over complicated. The document should avoid ambiguities or generalisations, which could lead to confusion and layout a step-by-step sequence of work to describe how the activity is to be carried out safely. Format The actual format is dependent on the work being undertaken and the organisational arrangements in place but generally the following headings should be present: 1. Organisation/company in control of the operation 2. Named individual responsible for the activity and its safety 3. Name of method statement originator and authorisation date 4. Arrangements for changing/deviating from method statement 5. General description of activity 6. Location of activity including access and restrictions 7. General working environment considerations, e.g. temperature and wind speed 8. Protection of others, e.g. members of the public 9. Emergency procedures, including location of emergency equipment 10. Identity of operatives (and any specific training or certification required) 11. Requirements for Personal Protective Equipment 12. Plant and equipment used, including safety precautions and restrictions 13. Materials information e.g. hazard information and storage/transport requirements 14. Work sequence, including associated risks and required control measures for each stage 15. Safety checks/clearances at specific stages 16. Final clearance that activity is completed to specification 17. Any other additional information that may be relevant. The list above is not exhaustive and a method statement may or may not include each and every item. However as a minimum it must achieve the following objectives:-  It should be up to date, identifiable and its source accountable  It should contain the sequence of works  It should identify the associated risks and control measures  It should state actions/authorisation required to deviate from method statement. Appendix 1 is a sample method statement for plumbing activities. It can be as simple or as detailed as the job/risk requires, so long as it meets the four main objectives.
  • 3. Guidance Note SC GN 23 (V3) Dec 20123 Appendix 1 Plumbing Method Statement Contract Manager: Joe Bloggs Site supervisor: David Jones Originator: Joe Bloggs Position: David Jones Date: 01/12/2012 This method statement is critical to the health and safety of the activity(ies) it relates to. It is to be strictly adhered to. Any deviation must first be authorised by the Site Supervisor. Planned Task/Activity Description: Replace Ball Valve to Water Tank. Location and Access: (attached plan as appropriate) Located on flat roof through access door into plant room. Working Environment & Restrictions: Flat roof accessed through locked door. Mandatory use of Mansafe system required. Protection of others: Men at work sign attached to roof access door, additional signage displayed at work area Emergency Procedures: Normal site emergency procedures will apply. Operatives/Competence: 1 city and guilds trained Plumber with safe use of harness training. Personal Protective Equipment: Overalls, Safety Harness, Gloves, Goggles, Safety Footwear Plant & Equipment: Isolation lock and general hand tools Materials Handling/Storage & Safety Information: All material in manageable individual lengths Critical Stages: (must be undertaken in correct sequence) 1. Attend Induction, sign for permit and obtain access door key 2. If no information is available on the site water treatment regime/water quality checks, contact office for further clearance to work 3. Access to roof through locked door 4. Once on roof attach harness to fixed safety restraint system 5. Follow set walkway to plant room 6. Isolate supply to Water Tank using Isolation Lock 7. Drain tank 8. Remove defective Ball Valve and replace 9. Remove Isolation 10. Re-Fill Water Tank and test new Ball Valve 11. Return to access door via set walkway 12. Return key and sign off permit. Final Clearance: (Work/Activity completed to satisfaction). Name Position: Date:
  • 4. Guidance Note SC GN 23 (V3) Dec 20124 Appendix 2 Blank Method Statement Template Contract Manager: Site Supervisor: Originator: Position: Date: This method statement is critical to the health and safety of the activity(ies) it relates to. It is to be strictly adhered to. Any deviation must first be authorised by the Site Supervisor. Planned Task/Activity Description: Location and Access: (attached plan as appropriate) Working Environment & Restrictions: Protection of others: Emergency Procedures: Operatives/Competence: Personal Protective Equipment: Plant & Equipment: Materials Handling/Storage & Safety Information: Critical Stages: (must be undertaken in correct sequence) Final Clearance: (Work/Activity completed to satisfaction). Name Position: Date: