SlideShare a Scribd company logo
TAKING SAFETY MEASURES FORWARD
ZERO INCIDENTS
VERSION 1
APRIL 11, 2018
PRESENTED BY: GARETH ASHWORTH
GREEN FLAG COMPLIANCE
23 CORPORATE PLAZA DR, SUITE 150, NEWPORT BEACH CA
4/11/2018 Taking safety measures forward 1
TAKING SAFETY MEASURES FORWARD
SAFETY PROCCESS
Project process RISK
1 Communica�on ZERO
2 Ini�al ac�vity-physical LOW
3 Mobiliza�on-physical LOW
4 Project-Physical HIGH
5 De-Mobiliza�on-physical LOW
6 Comple�on/Customer feedback ZERO
INITIAL ASSESSMENT
Taking a typical project and assessing the ini�al risks for each individual ac�on, we can ascertain an
average risk factor for each. This enables a focus for each sec�on breaking down into different safety
categories.
COMMUNICATION
Ac�ons
1 Clear- The job brief should be direct and to the correct person. Often work scopes are passed down
through employees to management with confusing elements which could cause a variation of
requirements.
2 Concise- The information received must be focused on the job at hand and not to be confused or
included in additional projects if possible.
3 Accurate- Vague or incorrect instructions will cause issues. (Verify all scopes.)
4 Requirements-Make sure that the services required are necessary and available from your
company. Crews may not be suitably qualified or the job may not require the service (could be
done a safer way) & job may need additional personnel.
5 Schedule- Scheduling the project so it doesn’t conflict with other projects.
4/11/2018 Taking safety measures forward 2
INITIAL ACTIVITY (PHYSICAL)
Ac�ons
1 Informa�on collec�on- Visiting the site with an informed person to verify the initial scope and
understand better any physical risks.
2 Environmental risks- Rain, snow, ice, wind, sun, chemicals, physical matter (asbestos etc)
3 Physical risks- Analyzing the physical environment for dangers and review past incidents.
4 Opera�on guidelines- Review operational requirements that may conflict, increase time or
disallow certain procedures.
5 Rela�onships- Build healthy relationships with the customer so that communication flows
smoothly.
6 Prac�cal Solu�ons- Make sure the client is aware of the safest most efficient procedure for
performing the task. There may be a better alternative that he/she is not aware of.
3.MOBILIZATION
Ac�ons
1 Equipment- Making sure fully inspected & correct type of equipment is made available for the
project
2 Travel- Sending your technicians to the correct location via suitable transport
3 Employee selec�on- Selecting appropriate, available personnel that can fulfil the project
requirements.
4 Environmental- Geographical elements and weather may cause fatigue, extended travel times.
5 Training/Fitness for work- Send employees that are capable and fit enough to perform
mobilization and project in work scope. Avoid change outs if possible and allow time for site safety
training etc.
4. PROJECT EXECUTION
Ac�on
1 Site Orienta�on- Understanding the physical nature, processes, culture & safety history of the site.
2 Meet & Greet- Sharing knowledge, processes & site project conflicts as well as building
relationships.
4/11/2018 Taking safety measures forward 3
Ac�on
3 Project assessment- Verifying the project ties in with risk assessment and method statement and
that no new changes have happened. Reviewing all pertinent permits and that the work being
performed is understood by all.
4 Daily safety documenta�on- Analyzing local risk and mitigation. (Create dialog to discover risk.)
5 Pre-task equipment Inspec�on- Physical inspection of equipment prior to use to evaluate that its
in good working order and the correct type.
6 Execute project- Stick with the plan and if any changes occur, stop, review and mitigate.
7 Con�nuous risk review- Risks evolve and climates change so constant evaluation is required.
5. DE-MOBILIZATION
Ac�on
1 Equipment- Manifesting and inspection will show missing or damaged equipment allowing an
easier transition. Evaluation of the type of equipment used and its appropriateness for future
similar projects.
2 Travel- Timing and distance of travel arrangements can cause fatigue, especially after a long
project. Allow for rest and recuperation before sending crews on a long drive or plane trip.
6. COMPLETION
Ac�on
1 Lessons Learned- Project review from all the crew involved will maintain a higher standard for the
next time and can remove delays and speed up processes. (More hours at risk can create
additional safety issues.)
2 Communication/Follow up- Conversations with the customer can uncover unknown issues and
problems as well as learn how well the project went from their perspective. Some new customers
may have expected something different even if the project went well.
3 Equipment- Warehouse inspection to update database of any lost/broken or quarantined
equipment.
4 Project records- When a similar project is performed or redone there should be historical records.
This allows knowledge of technicians, equipment and safety measures used in order to continue
providing safe, quality work.
4/11/2018 Taking safety measures forward 4
SAFETY DOCUMENTATION & HOW IT WORKS:
With all projects that involve working at height there are processes we can u�lize to mi�gate safety
hazards.
Most safety incidents that occur are a culmina�on of several smaller issues. We call this a “Cascade of
Errors” and there is no “one” single process that can fully mi�gate this. These cascades can require
many assessments and processes to atempt to control.
These controls start before the project and con�nues well a�er comple�on. Our processes are not finite
or exhaus�ve but a good base to work from and learn. We start with our management of documents
right through to signing off and leaving site.
Control of Documents:
1. Master List:
This acts as a map to navigate what
document is required and when. It
tells us what is valid and when it was
created.
This allows consistency in document
submittal and distribution.
4/11/2018 Taking safety measures forward 5
2. Document Control Process:
These are lists of specific documents
that may be required for a project.eg
1. Risk assessment
2. Method statement
3. Work procedures
4. Tool box talk
5. Rescue & rigging
6. Job safety analysis
3. Job Scope:
This is initially created by the customer,
sometimes formally but often via email
or verbal. It is important to formalize
this internally/externally to avoid
confusion. It generally includes duties,
purpose, responsibilities, scope, and
working conditions of a job along with
the job's title, and the name or
designation of the person to whom the
employee reports.
4/11/2018 Taking safety measures forward 6
5. Method Statement:
This should be used before any
new project and sets out a
detailed plan of how the project or
task should be performed before
work commences. In most cases it
should be completed by a
senior/experienced supervisor or
manager in conjunction with a risk
assessment.
6. Risk Assessment:
This document allows risks to be
identified and mitigated prior to work
commencing and is normally completed
by a senior/experienced supervisor or
manager in conjunction with a method
statement.
These should be submitted to the
customer prior to start
4. Code of safe prac�ces:
This is designed to address the hazards common to our
industry and communicate safe work practices and
company expectations.
This is a mandatory document that shall be understood
and followed by all. Each crew should have this available
on site and in the office for reference. Supervisor training
is advisable in the use of this document.
4/11/2018 Taking safety measures forward 7
7. Rigging procedure:
As an addendum to code of safe
practices, this sets out common rigging
used in certain environments. In unusual
circumstances a specific procedure and
plan may be required. This document
shall be available and understood by all.
8. Rigging Plan:
This sets out prior to work on site, how the
rope systems will be rigged. This can be
used in conjunction with the rigging
procedure. If a long-term project has no
changes in rigging, then one initial plan
can be written. This should be witnessed
and understood by all.
A rigging plan should be completed in
conjunction with a rescue plan
4/11/2018 Taking safety measures forward 8
9. Rescue Procedure
As an addendum to the code of safe
practices, the rescue procedure sets out
some typical planned rescue scenarios and
shall be understood by all. In some unusual
circumstances a specific rescue procedure
may be required that may not be covered.
10. Rescue Plan
This sets out, prior to work onsite what
type of rescue should be performed for the
task at hand. In many cases the rigging
plan will also include a specific rescue
system. (releasable anchors to lower a
casualty etc.)
It must be understood by all as roles should
be identified for each technician.
A rescue plan should be completed in
conjunction with a rigging plan.
4/11/2018 Taking safety measures forward 9
11. Tool Box Talk
This is a daily, informal safety meeting that
focuses on safety topics related to the
specific job, such as workplace hazards and
safe work practices. Meetings are conducted
at the job site prior to the commencement of
a job or work shift.
A JSA can be performed at the tool box talk
12. Job Safety Analysis (JSA)
Daily safety document indica�ng local risks
and mi�ga�ons. This should be a live
document that is understood and signed
by all involved with the project. As
condi�ons change, updates should be
added.
4/11/2018 Taking safety measures forward 10
13. Quaran�ne
When equipment is damaged or not
working correctly, a procedure to remove
from the active equipment list is required.
This will stop damaged or broken
equipment being used in the future.
The site rope access lead will add to a
quarantine list and remove from service
until inspected. The equipment should be
marked clearly as “quarantined.”
Once officially inspected the equipment
can be repaired and put back into service
or destroyed and removed from the master
equipment list/log
14. Lessons Learned
An important review from the ac�ve work
crews and site operator to understand
how these processes worked and what
expecta�ons were met or missed. This
should be kept as a historical record and
reviewed again prior to any similar type
project.
4/11/2018 Taking safety measures forward 11
Conclusion:
Some of these documents you may already have, for example most companies will have a job safety
analysis JSA, JHA etc but using different safety documents for different sites will and can cause
confusion with rope access. Its good prac�ce to familiarize rope access crews with the same documents
for each project. For Audit purposes and compliance, (ISO, IRATA, Green Fag etc) all the rope access
documents need to be consistant throughout your rope access program. We recommend keeping your
dedicated rope access documents separate from your exis�ng sa�ey documents.
We believe that our safety documents and management system is fully inclusive and a solid founda�on
for new or exis�ng companies to help contol their rope access program safely and efficiently while they
grow.
TAKING SAFETY FORWARD.

More Related Content

What's hot

2007 Ergonomics society - What works in industry
2007 Ergonomics society - What works in industry2007 Ergonomics society - What works in industry
2007 Ergonomics society - What works in industry
Andy Brazier
 
Process Safety Management
Process Safety ManagementProcess Safety Management
Process Safety Management
Marcep Inc.
 
Internship report (Ikram Ali)
Internship report (Ikram Ali)Internship report (Ikram Ali)
Internship report (Ikram Ali)ikram ikram
 
2016 Irish Ergonomics Society - HFE in oil and gas
2016 Irish Ergonomics Society - HFE in oil and gas2016 Irish Ergonomics Society - HFE in oil and gas
2016 Irish Ergonomics Society - HFE in oil and gas
Andy Brazier
 
Process Safety
Process SafetyProcess Safety
Process Safety
Consultivo
 
PERUMIN 31: Bow-tie Risk Analysis
PERUMIN 31: Bow-tie Risk AnalysisPERUMIN 31: Bow-tie Risk Analysis
PERUMIN 31: Bow-tie Risk Analysis
PERUMIN - Convención Minera
 
Process safety management system
Process safety management systemProcess safety management system
Process safety management system
Muhammad Akram SAEED
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
Doruk Kimyasal Yönetim Sistemeri
 
Lesson 2 module 5 management
Lesson 2 module 5 managementLesson 2 module 5 management
Lesson 2 module 5 management
WellbeingChampion
 
Practical Safety Instrumentation & Emergency Shutdown Systems for Process Ind...
Practical Safety Instrumentation & Emergency Shutdown Systems for Process Ind...Practical Safety Instrumentation & Emergency Shutdown Systems for Process Ind...
Practical Safety Instrumentation & Emergency Shutdown Systems for Process Ind...
Living Online
 
Process Safety Life Cycle Management: Best Practices and Processes
Process Safety Life Cycle Management: Best Practices and ProcessesProcess Safety Life Cycle Management: Best Practices and Processes
Process Safety Life Cycle Management: Best Practices and Processes
Md Rahaman
 
PSM RM - Learn from experience
PSM RM - Learn from experiencePSM RM - Learn from experience
PSM RM - Learn from experience
Process Safety Culture
 
C.003 task based risk assessment
C.003 task based risk assessmentC.003 task based risk assessment
C.003 task based risk assessment
boris sukljan
 
2008 Hazards - Shift handover
2008 Hazards - Shift handover2008 Hazards - Shift handover
2008 Hazards - Shift handover
Andy Brazier
 
Enform oil and gas safety: Process safey vs. personal safety
Enform oil and gas safety: Process safey vs. personal safety Enform oil and gas safety: Process safey vs. personal safety
Enform oil and gas safety: Process safey vs. personal safety
Enform
 
2005 IBC - Managing risks of control room operations
2005 IBC - Managing risks of control room operations2005 IBC - Managing risks of control room operations
2005 IBC - Managing risks of control room operations
Andy Brazier
 
Maritime accident n incident investigation
Maritime accident n incident investigationMaritime accident n incident investigation
Maritime accident n incident investigation
Capt Ashok Menon
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety Management
Shirazeh arghami
 

What's hot (20)

2007 Ergonomics society - What works in industry
2007 Ergonomics society - What works in industry2007 Ergonomics society - What works in industry
2007 Ergonomics society - What works in industry
 
Process Safety Management
Process Safety ManagementProcess Safety Management
Process Safety Management
 
Internship report (Ikram Ali)
Internship report (Ikram Ali)Internship report (Ikram Ali)
Internship report (Ikram Ali)
 
2016 Irish Ergonomics Society - HFE in oil and gas
2016 Irish Ergonomics Society - HFE in oil and gas2016 Irish Ergonomics Society - HFE in oil and gas
2016 Irish Ergonomics Society - HFE in oil and gas
 
Process Safety
Process SafetyProcess Safety
Process Safety
 
PERUMIN 31: Bow-tie Risk Analysis
PERUMIN 31: Bow-tie Risk AnalysisPERUMIN 31: Bow-tie Risk Analysis
PERUMIN 31: Bow-tie Risk Analysis
 
Process safety management system
Process safety management systemProcess safety management system
Process safety management system
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
 
Lesson 2 module 5 management
Lesson 2 module 5 managementLesson 2 module 5 management
Lesson 2 module 5 management
 
Practical Safety Instrumentation & Emergency Shutdown Systems for Process Ind...
Practical Safety Instrumentation & Emergency Shutdown Systems for Process Ind...Practical Safety Instrumentation & Emergency Shutdown Systems for Process Ind...
Practical Safety Instrumentation & Emergency Shutdown Systems for Process Ind...
 
Process Safety Life Cycle Management: Best Practices and Processes
Process Safety Life Cycle Management: Best Practices and ProcessesProcess Safety Life Cycle Management: Best Practices and Processes
Process Safety Life Cycle Management: Best Practices and Processes
 
Internship Project - Bowtie
Internship Project - BowtieInternship Project - Bowtie
Internship Project - Bowtie
 
PSM RM - Learn from experience
PSM RM - Learn from experiencePSM RM - Learn from experience
PSM RM - Learn from experience
 
C.003 task based risk assessment
C.003 task based risk assessmentC.003 task based risk assessment
C.003 task based risk assessment
 
2008 Hazards - Shift handover
2008 Hazards - Shift handover2008 Hazards - Shift handover
2008 Hazards - Shift handover
 
Enform oil and gas safety: Process safey vs. personal safety
Enform oil and gas safety: Process safey vs. personal safety Enform oil and gas safety: Process safey vs. personal safety
Enform oil and gas safety: Process safey vs. personal safety
 
Safety (1)
Safety (1)Safety (1)
Safety (1)
 
2005 IBC - Managing risks of control room operations
2005 IBC - Managing risks of control room operations2005 IBC - Managing risks of control room operations
2005 IBC - Managing risks of control room operations
 
Maritime accident n incident investigation
Maritime accident n incident investigationMaritime accident n incident investigation
Maritime accident n incident investigation
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety Management
 

Similar to Taking safety measures forward: Zero Incidents

5 steps prior erecting a scaffold
5 steps prior erecting a scaffold5 steps prior erecting a scaffold
5 steps prior erecting a scaffold
ASK EHS Engineering & Consultants
 
Maintenance Management Process
Maintenance Management ProcessMaintenance Management Process
Maintenance Management Process
PIPINAZRIN
 
C.003 task based risk assessment
C.003 task based risk assessmentC.003 task based risk assessment
C.003 task based risk assessment
boris sukljan
 
Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...
Canberra Institute of technology
 
Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...Kayode Aremu
 
US5620 A3 2012002052 FS
US5620 A3 2012002052 FSUS5620 A3 2012002052 FS
US5620 A3 2012002052 FSPhillip Jonker
 
Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...
Canberra Institute of technology
 
4. Assessment Practical.docx
4. Assessment Practical.docx4. Assessment Practical.docx
4. Assessment Practical.docx
Canberra Institute of technology
 
Self Directed Research Proj
Self Directed Research ProjSelf Directed Research Proj
Self Directed Research ProjJames Morrow
 
23.plumbing method statement_gn23
23.plumbing method statement_gn2323.plumbing method statement_gn23
23.plumbing method statement_gn23bhattbhai
 
Twelve Things ... Use Procedures
Twelve Things ... Use ProceduresTwelve Things ... Use Procedures
Twelve Things ... Use Procedures
PMHaas
 
Seminar 141120202109-conversion-gate02
Seminar 141120202109-conversion-gate02Seminar 141120202109-conversion-gate02
Seminar 141120202109-conversion-gate02
Ashraf Rady
 
Construction safety management
Construction safety managementConstruction safety management
Construction safety management
GERServices
 
3. Assessment Practical.docx
3. Assessment Practical.docx3. Assessment Practical.docx
3. Assessment Practical.docx
Canberra Institute of technology
 
irfan cv
irfan cvirfan cv
irfan cv
irfan ullah
 
Applied Health and Safety_Basic Risk assessment
Applied Health and Safety_Basic Risk assessmentApplied Health and Safety_Basic Risk assessment
Applied Health and Safety_Basic Risk assessment
Charl Esau
 
SM Unit2.pptx
SM Unit2.pptxSM Unit2.pptx
SM Unit2.pptx
ABHINANDHKA1
 
Safe Operating Procudures
Safe Operating ProcuduresSafe Operating Procudures
Safe Operating Procudures
Light House Advertising
 
Module 4 pre construction
Module 4 pre constructionModule 4 pre construction
Module 4 pre constructionjohnbarsellona
 

Similar to Taking safety measures forward: Zero Incidents (20)

5 steps prior erecting a scaffold
5 steps prior erecting a scaffold5 steps prior erecting a scaffold
5 steps prior erecting a scaffold
 
Maintenance Management Process
Maintenance Management ProcessMaintenance Management Process
Maintenance Management Process
 
C.003 task based risk assessment
C.003 task based risk assessmentC.003 task based risk assessment
C.003 task based risk assessment
 
Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...
 
Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...
 
US5620 A3 2012002052 FS
US5620 A3 2012002052 FSUS5620 A3 2012002052 FS
US5620 A3 2012002052 FS
 
Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...
 
4. Assessment Practical.docx
4. Assessment Practical.docx4. Assessment Practical.docx
4. Assessment Practical.docx
 
Self Directed Research Proj
Self Directed Research ProjSelf Directed Research Proj
Self Directed Research Proj
 
23.plumbing method statement_gn23
23.plumbing method statement_gn2323.plumbing method statement_gn23
23.plumbing method statement_gn23
 
Twelve Things ... Use Procedures
Twelve Things ... Use ProceduresTwelve Things ... Use Procedures
Twelve Things ... Use Procedures
 
Seminar 141120202109-conversion-gate02
Seminar 141120202109-conversion-gate02Seminar 141120202109-conversion-gate02
Seminar 141120202109-conversion-gate02
 
Construction safety management
Construction safety managementConstruction safety management
Construction safety management
 
3. Assessment Practical.docx
3. Assessment Practical.docx3. Assessment Practical.docx
3. Assessment Practical.docx
 
irfan cv
irfan cvirfan cv
irfan cv
 
Hse inspection presentation
Hse inspection presentationHse inspection presentation
Hse inspection presentation
 
Applied Health and Safety_Basic Risk assessment
Applied Health and Safety_Basic Risk assessmentApplied Health and Safety_Basic Risk assessment
Applied Health and Safety_Basic Risk assessment
 
SM Unit2.pptx
SM Unit2.pptxSM Unit2.pptx
SM Unit2.pptx
 
Safe Operating Procudures
Safe Operating ProcuduresSafe Operating Procudures
Safe Operating Procudures
 
Module 4 pre construction
Module 4 pre constructionModule 4 pre construction
Module 4 pre construction
 

Recently uploaded

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

Taking safety measures forward: Zero Incidents

  • 1. TAKING SAFETY MEASURES FORWARD ZERO INCIDENTS VERSION 1 APRIL 11, 2018 PRESENTED BY: GARETH ASHWORTH GREEN FLAG COMPLIANCE 23 CORPORATE PLAZA DR, SUITE 150, NEWPORT BEACH CA
  • 2. 4/11/2018 Taking safety measures forward 1 TAKING SAFETY MEASURES FORWARD SAFETY PROCCESS Project process RISK 1 Communica�on ZERO 2 Ini�al ac�vity-physical LOW 3 Mobiliza�on-physical LOW 4 Project-Physical HIGH 5 De-Mobiliza�on-physical LOW 6 Comple�on/Customer feedback ZERO INITIAL ASSESSMENT Taking a typical project and assessing the ini�al risks for each individual ac�on, we can ascertain an average risk factor for each. This enables a focus for each sec�on breaking down into different safety categories. COMMUNICATION Ac�ons 1 Clear- The job brief should be direct and to the correct person. Often work scopes are passed down through employees to management with confusing elements which could cause a variation of requirements. 2 Concise- The information received must be focused on the job at hand and not to be confused or included in additional projects if possible. 3 Accurate- Vague or incorrect instructions will cause issues. (Verify all scopes.) 4 Requirements-Make sure that the services required are necessary and available from your company. Crews may not be suitably qualified or the job may not require the service (could be done a safer way) & job may need additional personnel. 5 Schedule- Scheduling the project so it doesn’t conflict with other projects.
  • 3. 4/11/2018 Taking safety measures forward 2 INITIAL ACTIVITY (PHYSICAL) Ac�ons 1 Informa�on collec�on- Visiting the site with an informed person to verify the initial scope and understand better any physical risks. 2 Environmental risks- Rain, snow, ice, wind, sun, chemicals, physical matter (asbestos etc) 3 Physical risks- Analyzing the physical environment for dangers and review past incidents. 4 Opera�on guidelines- Review operational requirements that may conflict, increase time or disallow certain procedures. 5 Rela�onships- Build healthy relationships with the customer so that communication flows smoothly. 6 Prac�cal Solu�ons- Make sure the client is aware of the safest most efficient procedure for performing the task. There may be a better alternative that he/she is not aware of. 3.MOBILIZATION Ac�ons 1 Equipment- Making sure fully inspected & correct type of equipment is made available for the project 2 Travel- Sending your technicians to the correct location via suitable transport 3 Employee selec�on- Selecting appropriate, available personnel that can fulfil the project requirements. 4 Environmental- Geographical elements and weather may cause fatigue, extended travel times. 5 Training/Fitness for work- Send employees that are capable and fit enough to perform mobilization and project in work scope. Avoid change outs if possible and allow time for site safety training etc. 4. PROJECT EXECUTION Ac�on 1 Site Orienta�on- Understanding the physical nature, processes, culture & safety history of the site. 2 Meet & Greet- Sharing knowledge, processes & site project conflicts as well as building relationships.
  • 4. 4/11/2018 Taking safety measures forward 3 Ac�on 3 Project assessment- Verifying the project ties in with risk assessment and method statement and that no new changes have happened. Reviewing all pertinent permits and that the work being performed is understood by all. 4 Daily safety documenta�on- Analyzing local risk and mitigation. (Create dialog to discover risk.) 5 Pre-task equipment Inspec�on- Physical inspection of equipment prior to use to evaluate that its in good working order and the correct type. 6 Execute project- Stick with the plan and if any changes occur, stop, review and mitigate. 7 Con�nuous risk review- Risks evolve and climates change so constant evaluation is required. 5. DE-MOBILIZATION Ac�on 1 Equipment- Manifesting and inspection will show missing or damaged equipment allowing an easier transition. Evaluation of the type of equipment used and its appropriateness for future similar projects. 2 Travel- Timing and distance of travel arrangements can cause fatigue, especially after a long project. Allow for rest and recuperation before sending crews on a long drive or plane trip. 6. COMPLETION Ac�on 1 Lessons Learned- Project review from all the crew involved will maintain a higher standard for the next time and can remove delays and speed up processes. (More hours at risk can create additional safety issues.) 2 Communication/Follow up- Conversations with the customer can uncover unknown issues and problems as well as learn how well the project went from their perspective. Some new customers may have expected something different even if the project went well. 3 Equipment- Warehouse inspection to update database of any lost/broken or quarantined equipment. 4 Project records- When a similar project is performed or redone there should be historical records. This allows knowledge of technicians, equipment and safety measures used in order to continue providing safe, quality work.
  • 5. 4/11/2018 Taking safety measures forward 4 SAFETY DOCUMENTATION & HOW IT WORKS: With all projects that involve working at height there are processes we can u�lize to mi�gate safety hazards. Most safety incidents that occur are a culmina�on of several smaller issues. We call this a “Cascade of Errors” and there is no “one” single process that can fully mi�gate this. These cascades can require many assessments and processes to atempt to control. These controls start before the project and con�nues well a�er comple�on. Our processes are not finite or exhaus�ve but a good base to work from and learn. We start with our management of documents right through to signing off and leaving site. Control of Documents: 1. Master List: This acts as a map to navigate what document is required and when. It tells us what is valid and when it was created. This allows consistency in document submittal and distribution.
  • 6. 4/11/2018 Taking safety measures forward 5 2. Document Control Process: These are lists of specific documents that may be required for a project.eg 1. Risk assessment 2. Method statement 3. Work procedures 4. Tool box talk 5. Rescue & rigging 6. Job safety analysis 3. Job Scope: This is initially created by the customer, sometimes formally but often via email or verbal. It is important to formalize this internally/externally to avoid confusion. It generally includes duties, purpose, responsibilities, scope, and working conditions of a job along with the job's title, and the name or designation of the person to whom the employee reports.
  • 7. 4/11/2018 Taking safety measures forward 6 5. Method Statement: This should be used before any new project and sets out a detailed plan of how the project or task should be performed before work commences. In most cases it should be completed by a senior/experienced supervisor or manager in conjunction with a risk assessment. 6. Risk Assessment: This document allows risks to be identified and mitigated prior to work commencing and is normally completed by a senior/experienced supervisor or manager in conjunction with a method statement. These should be submitted to the customer prior to start 4. Code of safe prac�ces: This is designed to address the hazards common to our industry and communicate safe work practices and company expectations. This is a mandatory document that shall be understood and followed by all. Each crew should have this available on site and in the office for reference. Supervisor training is advisable in the use of this document.
  • 8. 4/11/2018 Taking safety measures forward 7 7. Rigging procedure: As an addendum to code of safe practices, this sets out common rigging used in certain environments. In unusual circumstances a specific procedure and plan may be required. This document shall be available and understood by all. 8. Rigging Plan: This sets out prior to work on site, how the rope systems will be rigged. This can be used in conjunction with the rigging procedure. If a long-term project has no changes in rigging, then one initial plan can be written. This should be witnessed and understood by all. A rigging plan should be completed in conjunction with a rescue plan
  • 9. 4/11/2018 Taking safety measures forward 8 9. Rescue Procedure As an addendum to the code of safe practices, the rescue procedure sets out some typical planned rescue scenarios and shall be understood by all. In some unusual circumstances a specific rescue procedure may be required that may not be covered. 10. Rescue Plan This sets out, prior to work onsite what type of rescue should be performed for the task at hand. In many cases the rigging plan will also include a specific rescue system. (releasable anchors to lower a casualty etc.) It must be understood by all as roles should be identified for each technician. A rescue plan should be completed in conjunction with a rigging plan.
  • 10. 4/11/2018 Taking safety measures forward 9 11. Tool Box Talk This is a daily, informal safety meeting that focuses on safety topics related to the specific job, such as workplace hazards and safe work practices. Meetings are conducted at the job site prior to the commencement of a job or work shift. A JSA can be performed at the tool box talk 12. Job Safety Analysis (JSA) Daily safety document indica�ng local risks and mi�ga�ons. This should be a live document that is understood and signed by all involved with the project. As condi�ons change, updates should be added.
  • 11. 4/11/2018 Taking safety measures forward 10 13. Quaran�ne When equipment is damaged or not working correctly, a procedure to remove from the active equipment list is required. This will stop damaged or broken equipment being used in the future. The site rope access lead will add to a quarantine list and remove from service until inspected. The equipment should be marked clearly as “quarantined.” Once officially inspected the equipment can be repaired and put back into service or destroyed and removed from the master equipment list/log 14. Lessons Learned An important review from the ac�ve work crews and site operator to understand how these processes worked and what expecta�ons were met or missed. This should be kept as a historical record and reviewed again prior to any similar type project.
  • 12. 4/11/2018 Taking safety measures forward 11 Conclusion: Some of these documents you may already have, for example most companies will have a job safety analysis JSA, JHA etc but using different safety documents for different sites will and can cause confusion with rope access. Its good prac�ce to familiarize rope access crews with the same documents for each project. For Audit purposes and compliance, (ISO, IRATA, Green Fag etc) all the rope access documents need to be consistant throughout your rope access program. We recommend keeping your dedicated rope access documents separate from your exis�ng sa�ey documents. We believe that our safety documents and management system is fully inclusive and a solid founda�on for new or exis�ng companies to help contol their rope access program safely and efficiently while they grow. TAKING SAFETY FORWARD.