SlideShare a Scribd company logo
Project Risk
Management
Project Risk Management
Coincides with PMBOK 11.0
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group
Monitoring and Controlling Process
Group
Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project
Management Plan
4.3 Direct and Manage Project
Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or
Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost
Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project
Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk
Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement
Management
12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders
13.2 Plan Stakeholder
Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
Project Risk Management
Coincides with PMBOK 11.0
The Project Risk Management Processes are:
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses
11.7 Monitor Risks
Planning
Monitoring and
Controlling
Executing
Initiating
Closing
Project Risk Management Overview
Project Risk Management
Coincides with PMBOK 11.0
Plan Risk Management Identify Risks
Perform Qualitative
Risk Analysis
Perform Quantitative
Risk Analysis
1. Project charter
2. Project management plan
3. Project documents
4. Enterprise environmental
factors
5. Organizational process assets
1. Project management plan
2. Project documents
3. Agreements
4. Procurement documentation
5. Enterprise environmental
factors
6. Organizational process assets
1. Project management plan
2. Project documents
3. Enterprise environmental
factors
4. Organizational process assets
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets
1. Expert judgment
2. Data analysis
3. Meetings
1. Expert judgment
2. Data gathering
3. Data analysis
4. Interpersonal and team skills
5. Prompt lists
6. . Meetings
1. Expert judgment
2. Data gathering
3. Data analysis
4. Interpersonal and team skills
5. Risk categorization
6. Data representation
7. Meetings
1. Expert judgment
2. Data gathering
3. Interpersonal and team skills
4. Representations of uncertainty
5. Data analysis
1. Risk management plan
1. Risk register
2. Risk report
3. Project documents updates
1. Project documents updates 1. Project documents updates
Inputs
Tools &
Techniques
Outputs
Project Risk Management Overview
Project Risk Management
Coincides with PMBOK 11.0
Plan Risk Responses Implement Risk Responses Monitor Risks
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets
1. Project management plan
2. Project documents
3. Organizational process assets
1. Project management plan
2. Project documents
3. Work performance data
4. Work performance reports
1. Expert judgment
2. Data gathering
3. Interpersonal and team skills
4. Strategies for threats
5. Strategies for opportunities
6. Contingent response strategies
7. Strategies for overall project risk
8. Data analysis
9. Decision making
1. Expert judgment
2. Interpersonal and team skills
3. Project management information system
1. Data analysis
2. Audits
3. Meetings
1. Change requests
2. Project management plan updates
3. Project documents updates
1. Change requests
2. Project documents updates
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates
Inputs
Tools &
Techniques
Outputs
Key Concepts
Project Risk Management
Coincides with PMBOK 11.0
All projects have risk, since they are delivering a change from one state to
another.
Risk exists at two levels within every project. Risks that affect the
achievement of project objectives, and risks upon delivery of the change.
• Individual project risk is an uncertain event or condition that, if it occurs,
has a positive or negative effect on one or more project objectives.
• Overall project risk is the effect of uncertainty on the project as a whole
- the exposure of stakeholders to the implications of variations in project
outcome, both positive and negative.
Key Concepts
Project Risk Management
Coincides with PMBOK 11.0
Risks can have a positive or negative effect if they occur. Project Risk Management aims
to exploit or enhance positive risks (opportunities) while avoiding or mitigating negative
risks (threats).
• Unmanaged threats may result in issues or problems such as delay, cost overruns,
performance shortfall, or loss of reputation.
• Opportunities that are captured can lead to benefits such as reduced time and cost,
improved performance, or reputation.
Trends and Emerging Practices
Project Risk Management
Coincides with PMBOK 11.0
The focus of project risk management is broadening to ensure that risks are understood
in a wider context.
Trends and emerging practices for Project Risk Management include but are not limited
to:
1. Non-event risks
• Variability risk
• Ambiguity risk
2. Project resilience (against unknowable unknowns)
3. Integrated risk management
Project Risk Management
Coincides with PMBOK 11.0
Because each project is unique, it is necessary to tailor the way Project Risk
Management processes are applied.
Considerations for tailoring include but are not limited to:
1. Project size
2. Project complexity
3. Project importance
4. Development approach
Tailoring Considerations
Considerations for Agile or Adaptive Environments
Project Risk Management
Coincides with PMBOK 11.0
High-variability environments, by definition, incur more uncertainty and risk.
To address this, projects can use various Agile approaches to managing Risk.
Demonstrations and Reviews: Customer and Risk reviews of incremental
work products help ensure the project is on track and that risk is
understood.
Backlog of work and the Product Owner role: The requirements are kept as
a living document that is updated regularly, and work may be reprioritized as
the project progresses, based on an improved understanding of current risk
exposure.
Risk is considered when selecting the content of each iteration, and risks will
also be identified, analysed, and managed during each iteration.

More Related Content

What's hot

Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
Amr Miqdadi
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1reddvise
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - Processes
Andrew Mikityuk
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
Amr Miqdadi
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
DavidMcLachlan1
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
Andersson Lujan Ojeda
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
DavidMcLachlan1
 
Planning process group
Planning process groupPlanning process group
Planning process group
Mudassir Iqbal
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
Mohamed Salah Eldien Mohamed Ali
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management area
Zaur Ahmadov, PMP
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
Amit Gupta
 
Project Integration Management - PMP Preparation
Project Integration Management - PMP PreparationProject Integration Management - PMP Preparation
Project Integration Management - PMP Preparation
Vladimir Vujovic
 
PM FrameWork: Module 2
PM FrameWork: Module 2PM FrameWork: Module 2
PM FrameWork: Module 2
Mohammad Ashraf Khan, PMP
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
GlobalSkillup
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration Management
Andrew Mikityuk
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
DavidMcLachlan1
 
Project integration management
Project  integration managementProject  integration management
Project integration management
deep sharma
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
pankajsh10
 

What's hot (20)

Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - Processes
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management area
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
Project Integration Management - PMP Preparation
Project Integration Management - PMP PreparationProject Integration Management - PMP Preparation
Project Integration Management - PMP Preparation
 
PM FrameWork: Module 2
PM FrameWork: Module 2PM FrameWork: Module 2
PM FrameWork: Module 2
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration Management
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 

Similar to 11.0 Project Risk Management Overview

13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview
DavidMcLachlan1
 
11.1 Plan Risk Management
11.1 Plan Risk Management11.1 Plan Risk Management
11.1 Plan Risk Management
DavidMcLachlan1
 
11.6 Implement Risk Responses
11.6 Implement Risk Responses11.6 Implement Risk Responses
11.6 Implement Risk Responses
DavidMcLachlan1
 
11.5 Plan Risk Responses
11.5 Plan Risk Responses11.5 Plan Risk Responses
11.5 Plan Risk Responses
DavidMcLachlan1
 
11.2 Identify Risks
11.2 Identify Risks11.2 Identify Risks
11.2 Identify Risks
DavidMcLachlan1
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
DavidMcLachlan1
 
11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
DavidMcLachlan1
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
hatemk
 
11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
DavidMcLachlan1
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overview
Oleksiy Rudenko
 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
umairzubairallnaats
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
Ahmed Elgazzar
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
Nawzad Bilal
 
Project Management Methodologies
Project Management MethodologiesProject Management Methodologies
Project Management Methodologies
Monief Eid,Prince2,Prosci, Lean Six Sigma &ITIL
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
Ahmed Abdelaziz
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
Ahmed Yousry Abdelaziz
 
Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...
Simplilearn
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
Abdullah Ahmed, PMP, RMP
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
DavidMcLachlan1
 

Similar to 11.0 Project Risk Management Overview (20)

13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview
 
11.1 Plan Risk Management
11.1 Plan Risk Management11.1 Plan Risk Management
11.1 Plan Risk Management
 
11.6 Implement Risk Responses
11.6 Implement Risk Responses11.6 Implement Risk Responses
11.6 Implement Risk Responses
 
11.5 Plan Risk Responses
11.5 Plan Risk Responses11.5 Plan Risk Responses
11.5 Plan Risk Responses
 
11.2 Identify Risks
11.2 Identify Risks11.2 Identify Risks
11.2 Identify Risks
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
 
11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overview
 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
Project Management Methodologies
Project Management MethodologiesProject Management Methodologies
Project Management Methodologies
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...
 
Project managment 10
Project managment  10Project managment  10
Project managment 10
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 

More from DavidMcLachlan1

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
DavidMcLachlan1
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
DavidMcLachlan1
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
DavidMcLachlan1
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
DavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
DavidMcLachlan1
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
DavidMcLachlan1
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
DavidMcLachlan1
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
DavidMcLachlan1
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
DavidMcLachlan1
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
DavidMcLachlan1
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
DavidMcLachlan1
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
DavidMcLachlan1
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
DavidMcLachlan1
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
DavidMcLachlan1
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
DavidMcLachlan1
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
DavidMcLachlan1
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
DavidMcLachlan1
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
DavidMcLachlan1
 
7.0 Project Cost Management Overview
7.0 Project Cost Management Overview7.0 Project Cost Management Overview
7.0 Project Cost Management Overview
DavidMcLachlan1
 

More from DavidMcLachlan1 (19)

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
 
7.0 Project Cost Management Overview
7.0 Project Cost Management Overview7.0 Project Cost Management Overview
7.0 Project Cost Management Overview
 

Recently uploaded

Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 

Recently uploaded (20)

Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 

11.0 Project Risk Management Overview

  • 2. Project Risk Management Coincides with PMBOK 11.0 Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement
  • 3. Project Risk Management Coincides with PMBOK 11.0 The Project Risk Management Processes are: 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks Planning Monitoring and Controlling Executing Initiating Closing
  • 4. Project Risk Management Overview Project Risk Management Coincides with PMBOK 11.0 Plan Risk Management Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis 1. Project charter 2. Project management plan 3. Project documents 4. Enterprise environmental factors 5. Organizational process assets 1. Project management plan 2. Project documents 3. Agreements 4. Procurement documentation 5. Enterprise environmental factors 6. Organizational process assets 1. Project management plan 2. Project documents 3. Enterprise environmental factors 4. Organizational process assets 1. Project management plan 2. Project documents 3. Enterprise environmental factors 4. Organizational process assets 1. Expert judgment 2. Data analysis 3. Meetings 1. Expert judgment 2. Data gathering 3. Data analysis 4. Interpersonal and team skills 5. Prompt lists 6. . Meetings 1. Expert judgment 2. Data gathering 3. Data analysis 4. Interpersonal and team skills 5. Risk categorization 6. Data representation 7. Meetings 1. Expert judgment 2. Data gathering 3. Interpersonal and team skills 4. Representations of uncertainty 5. Data analysis 1. Risk management plan 1. Risk register 2. Risk report 3. Project documents updates 1. Project documents updates 1. Project documents updates Inputs Tools & Techniques Outputs
  • 5. Project Risk Management Overview Project Risk Management Coincides with PMBOK 11.0 Plan Risk Responses Implement Risk Responses Monitor Risks 1. Project management plan 2. Project documents 3. Enterprise environmental factors 4. Organizational process assets 1. Project management plan 2. Project documents 3. Organizational process assets 1. Project management plan 2. Project documents 3. Work performance data 4. Work performance reports 1. Expert judgment 2. Data gathering 3. Interpersonal and team skills 4. Strategies for threats 5. Strategies for opportunities 6. Contingent response strategies 7. Strategies for overall project risk 8. Data analysis 9. Decision making 1. Expert judgment 2. Interpersonal and team skills 3. Project management information system 1. Data analysis 2. Audits 3. Meetings 1. Change requests 2. Project management plan updates 3. Project documents updates 1. Change requests 2. Project documents updates 1. Work performance information 2. Change requests 3. Project management plan updates 4. Project documents updates 5. Organizational process assets updates Inputs Tools & Techniques Outputs
  • 6. Key Concepts Project Risk Management Coincides with PMBOK 11.0 All projects have risk, since they are delivering a change from one state to another. Risk exists at two levels within every project. Risks that affect the achievement of project objectives, and risks upon delivery of the change. • Individual project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives. • Overall project risk is the effect of uncertainty on the project as a whole - the exposure of stakeholders to the implications of variations in project outcome, both positive and negative.
  • 7. Key Concepts Project Risk Management Coincides with PMBOK 11.0 Risks can have a positive or negative effect if they occur. Project Risk Management aims to exploit or enhance positive risks (opportunities) while avoiding or mitigating negative risks (threats). • Unmanaged threats may result in issues or problems such as delay, cost overruns, performance shortfall, or loss of reputation. • Opportunities that are captured can lead to benefits such as reduced time and cost, improved performance, or reputation.
  • 8. Trends and Emerging Practices Project Risk Management Coincides with PMBOK 11.0 The focus of project risk management is broadening to ensure that risks are understood in a wider context. Trends and emerging practices for Project Risk Management include but are not limited to: 1. Non-event risks • Variability risk • Ambiguity risk 2. Project resilience (against unknowable unknowns) 3. Integrated risk management
  • 9. Project Risk Management Coincides with PMBOK 11.0 Because each project is unique, it is necessary to tailor the way Project Risk Management processes are applied. Considerations for tailoring include but are not limited to: 1. Project size 2. Project complexity 3. Project importance 4. Development approach Tailoring Considerations
  • 10. Considerations for Agile or Adaptive Environments Project Risk Management Coincides with PMBOK 11.0 High-variability environments, by definition, incur more uncertainty and risk. To address this, projects can use various Agile approaches to managing Risk. Demonstrations and Reviews: Customer and Risk reviews of incremental work products help ensure the project is on track and that risk is understood. Backlog of work and the Product Owner role: The requirements are kept as a living document that is updated regularly, and work may be reprioritized as the project progresses, based on an improved understanding of current risk exposure. Risk is considered when selecting the content of each iteration, and risks will also be identified, analysed, and managed during each iteration.

Editor's Notes

  1. The process of defining how to conduct risk management activities for a project. The process of identifying individual project risks as well as sources of overall project risk, and documenting their characteristics. The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics. The process of numerically analysing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives. The process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks. The process of implementing agreed-upon risk response plans. The process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analysing new risks, and evaluating risk process effectiveness throughout the project.
  2. Variability: productivity may be above or below target, the number of errors found during testing may be higher or lower than expected, or unseasonal weather conditions may occur during the construction phase. Ambiguity: elements of the requirement or technical solution, future developments in regulatory frameworks, or inherent systemic complexity in the project. Against black swan events, the unknowable unknowns. Emergent risks can be tackled through developing project resilience. Right level of budget and schedule contingency for emergent risks, in addition to a specific risk budget for known risks; Flexible project processes that can cope with emergent risk, strong change management; Empowered project team that has clear objectives Frequent review of early warning signs to identify Clear input from stakeholders to clarify areas where the project scope or strategy can be adjusted in response to emergent risks. Between Projects, Programs and Portfolios.
  3. Does the project’s size in terms of budget, duration, scope, or team size require a more detailed approach to risk management? Or is it small enough to justify a simplified risk process? Is a robust risk approach demanded by high levels of innovation, new technology, commercial arrangements, interfaces, or external dependencies that increase project complexity? Or is the project simple enough that a reduced risk process will suffice? How strategically important is the project? Is the level of risk increased for this project because it aims to produce breakthrough opportunities, addresses significant blocks to organizational performance, or involves major product innovation? Is this a waterfall project, where risk processes can be followed sequentially and iteratively, or does the project follow an agile approach where risk is addressed at the start of each iteration as well as during its execution?