SlideShare a Scribd company logo
1 of 19
Perform Quantitative Risk
Analysis
Perform Quantitative Risk Analysis
Coincides with PMBOK 11.4
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project Management
Plan
4.3 Direct and Manage Project Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
What is it?
Perform Quantitative Risk Analysis is the process of numerically
analysing the combined effect of identified individual project risks and
other sources of uncertainty on overall project objectives.
Why?
The key benefit of this process is that it quantifies overall project risk
exposure, and it can also provide additional quantitative risk
information to support risk response planning.
Perform Quantitative Risk Analysis
Coincides with PMBOK 11.4
Overview
• Quantitative risk analysis requires specialized risk software and expertise in the
development and interpretation of risk models.
• The use of quantitative risk analysis for a project will be specified in the project’s
risk management plan
• Outputs from Perform Quantitative Risk Analysis are used as inputs to the Plan Risk
Responses process, particularly in recommending responses to the level of overall
project risk and key individual risks.
Coincides with PMBOK 11.4
Perform Quantitative Risk Analysis
Perform Quantitative Risk Analysis
Coincides with PMBOK 11.4
Inputs Tools & Techniques Outputs
1. Project management plan
• Risk management plan
• Scope baseline
• Schedule baseline
• Cost baseline
2. Project documents
• Assumption log
• Basis of estimates
• Cost estimates
• Cost forecasts
• Duration estimates
• Milestone list
• Resource requirements
• Risk register
• Risk report
• Schedule forecasts
3. Enterprise environmental factors
4. Organizational process assets
1. Expert judgment
2. Data gathering
• Interviews
3. Interpersonal and team skills
• Facilitation
4. Representations of uncertainty
5. Data analysis
• Simulations
• Sensitivity analysis
• Decision tree analysis
• Influence diagrams
1. Project documents updates
• Risk report
Inputs, Tools & Techniques, Outputs
Perform Quantitative Risk Analysis
Coincides with PMBOK 11.4
11.4 Perform
Quantitative Risk
Analysis
Project
Management
Plan
Enterprise/Orga
nization
• Assumption log
• Basis of estimates
• Cost estimates
• Cost forecasts
• Duration estimates
• Milestone list
• Resource requirements
• Risk register
• Risk report
• Schedule forecasts
• Enterprise environmental factors
• Organizational process assets
Project
Documents
Project
Documents• Risk report
• Risk management plan
• Scope baseline
• Schedule baseline
• Cost baseline
Perform Quantitative Risk Analysis - Inputs
Coincides with PMBOK 11.4
Project Management Plan
Project management plan components include:
• Risk management plan
• Scope baseline
• Schedule baseline
• Cost baseline
Perform Quantitative Risk Analysis - Inputs
Coincides with PMBOK 11.4
Project Documents
Project documents that can be considered as inputs for this process include:
• Assumption log
• Basis of estimates
• Cost estimates
• Cost forecasts
• Duration estimates
• Milestone list
• Resource requirements
• Risk register
• Risk report
• Schedule forecasts
Coincides with PMBOK 11.4
Enterprise Environmental Factors
The enterprise environmental factors that can influence Perform Quantitative
Risk Analysis include but are not limited to:
• Industry studies of similar projects
• Published material, including commercial risk databases or checklists.
Perform Quantitative Risk Analysis - Inputs
Coincides with PMBOK 11.4
Organisational Process Assets
The organizational process assets that can influence the Perform
Quantitative Risk Analysis process include information from similar
completed projects.
Perform Quantitative Risk Analysis - Inputs
Perform Quantitative Risk Analysis – Tools & Techniques
Coincides with PMBOK 11.4
Expert Judgment
Expertise should be considered from individuals or groups with specialized knowledge
or training in the following topics:
• Translating information on individual project risks and other sources of uncertainty
into numeric inputs for the quantitative risk analysis model
• Selecting the most appropriate representation of uncertainty to model particular
risks or other sources of uncertainty
• Modelling techniques that are appropriate in the context of the project
• Identifying which tools would be most suitable for the selected modelling
techniques
• Interpreting the outputs of quantitative risk analysis.
Perform Quantitative Risk Analysis – Tools & Techniques
Coincides with PMBOK 11.4
Data Gathering
Interviews may be used to generate inputs for the quantitative risk analysis, drawing
on inputs that include individual project risks and other sources of uncertainty. This is
particularly useful where information is required from experts. The interviewer
should promote an environment of trust and confidentiality during the interview to
encourage honest and unbiased contributions.
Coincides with PMBOK 11.4
Interpersonal Team and Skills
Perform Quantitative Risk Analysis – Tools & Techniques
Interpersonal and team skills that can be used for this process include but are not
limited to facilitation. A skilled facilitator is useful for gathering input data during a
dedicated risk workshop involving project team members and other stakeholders.
Facilitated workshops can improve effectiveness by:
• Establishing a clear understanding of the purpose of the workshop
• Building consensus among participants
• Ensuring continued focus on the task
• Using creative approaches to deal with interpersonal conflict or sources of bias
Coincides with PMBOK 11.4
Representations of Uncertainty
Perform Quantitative Risk Analysis – Tools & Techniques
• Quantitative risk analysis requires inputs to a quantitative risk analysis model that
reflect individual project risks and other sources of uncertainty.
• Where the duration, cost, or resource requirement for a planned activity is
uncertain, the range of possible values can be represented in the model as a
probability distribution. This may take several forms, the most commonly used are
triangular, normal, lognormal, beta, uniform, or discrete distributions.
Coincides with PMBOK 11.4
Data Analysis - Simulation
Perform Quantitative Risk Analysis – Tools & Techniques
• Quantitative risk analysis uses a
model that simulates the combined
effects of individual project risks
and other sources of uncertainty to
evaluate their potential impact on
achieving project objectives.
• Monte Carlo Analysis is typically
used for simulation.
S-curve from a Monte Carlo cost risk analysis
Coincides with PMBOK 11.4
Data Analysis – Sensitivity Analysis
Perform Quantitative Risk Analysis – Tools & Techniques
• Sensitivity analysis helps to determine
which individual project risks or other
sources of uncertainty have the most
potential impact on project outcomes.
• It correlates variations in project
outcomes with variations in elements of
the quantitative risk analysis model.
Tornado Diagram
Coincides with PMBOK 11.4
Data Analysis – Decision Tree Analysis
Perform Quantitative Risk Analysis – Tools & Techniques
• Decision trees are used to support
selection of the best of several
alternative courses of action.
• Alternative paths through the project
are shown in the decision tree using
branches representing different
decisions or events, each of which can
have associated costs and related
individual project risks (including both
threats and opportunities).
Decision Tree
Coincides with PMBOK 11.4
Data Analysis – Influence Diagrams
Perform Quantitative Risk Analysis – Tools & Techniques
• Influence diagrams are graphical aids to decision making under uncertainty. An
influence diagram represents a project or situation within the project as a set of
entities, outcomes, and influences, together with the relationships and effects
between them.
• Where an element in the influence diagram is uncertain as a result of the existence
of individual project risks or other sources of uncertainty, this can be represented
in the influence diagram using ranges or probability distributions.
Perform Quantitative Risk Analysis – Outputs
Coincides with PMBOK 11.4
Project Document Updates
Project documents that can be considered as outputs for this process include but are
not limited to the risk report. The risk report will be updated to reflect the results of
the quantitative risk analysis. This will typically include:
• Assessment of overall project risk exposure
• Detailed probabilistic analysis of the project
• Prioritized list of individual project risks.
• Trends in quantitative risk analysis results
• Recommended risk responses.

More Related Content

What's hot

Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learningVanita Ahuja
 
Project risk management - Methodology and application
Project risk management - Methodology and applicationProject risk management - Methodology and application
Project risk management - Methodology and applicationMarco De Santis, PMP, CFPP
 
Project risk management
Project risk managementProject risk management
Project risk managementEr Swati Nagal
 
Risk-management
 Risk-management Risk-management
Risk-managementUmesh Gupta
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best PracticesPMILebanonChapter
 
Project risk management
Project risk managementProject risk management
Project risk managementDewang Agrawal
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementKaustubh Gupta
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
Risk Assessment: Creating a Risk Matrix
Risk Assessment: Creating a Risk MatrixRisk Assessment: Creating a Risk Matrix
Risk Assessment: Creating a Risk MatrixEtQ, Inc.
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk managementPMC Mentor
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementSaket Bansal
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk AnalysisDavidMcLachlan1
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk ManagementHayat Denzi
 
11.5 Plan Risk Responses
11.5 Plan Risk Responses11.5 Plan Risk Responses
11.5 Plan Risk ResponsesDavidMcLachlan1
 

What's hot (20)

Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 
Project risk management - Methodology and application
Project risk management - Methodology and applicationProject risk management - Methodology and application
Project risk management - Methodology and application
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk-management
 Risk-management Risk-management
Risk-management
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Risk Management Framework
Risk Management FrameworkRisk Management Framework
Risk Management Framework
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Risk Assessment: Creating a Risk Matrix
Risk Assessment: Creating a Risk MatrixRisk Assessment: Creating a Risk Matrix
Risk Assessment: Creating a Risk Matrix
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk Management
 
Risk management
Risk managementRisk management
Risk management
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
 
Risk management
Risk managementRisk management
Risk management
 
11.5 Plan Risk Responses
11.5 Plan Risk Responses11.5 Plan Risk Responses
11.5 Plan Risk Responses
 

Similar to 11.4 Perform Quantitative Risk Analysis

11.1 Plan Risk Management
11.1 Plan Risk Management11.1 Plan Risk Management
11.1 Plan Risk ManagementDavidMcLachlan1
 
11.6 Implement Risk Responses
11.6 Implement Risk Responses11.6 Implement Risk Responses
11.6 Implement Risk ResponsesDavidMcLachlan1
 
11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management OverviewDavidMcLachlan1
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis Shereef Sabri
 
Organizational project maturity model (opm3)
Organizational project maturity model (opm3)Organizational project maturity model (opm3)
Organizational project maturity model (opm3)Daniele Pinto
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost ManagementDavidMcLachlan1
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management reqGlen Alleman
 
Perform qualitative risk analysis
Perform qualitative risk analysis Perform qualitative risk analysis
Perform qualitative risk analysis Shereef Sabri
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project KnowledgeDavidMcLachlan1
 
Project management part 3
Project management part 3Project management part 3
Project management part 3hkbhadraa
 
13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder EngagementDavidMcLachlan1
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Managementhatemk
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 

Similar to 11.4 Perform Quantitative Risk Analysis (20)

11.1 Plan Risk Management
11.1 Plan Risk Management11.1 Plan Risk Management
11.1 Plan Risk Management
 
11.6 Implement Risk Responses
11.6 Implement Risk Responses11.6 Implement Risk Responses
11.6 Implement Risk Responses
 
11.2 Identify Risks
11.2 Identify Risks11.2 Identify Risks
11.2 Identify Risks
 
11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management Overview
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis
 
11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
 
Project managment 10
Project managment  10Project managment  10
Project managment 10
 
Organizational project maturity model (opm3)
Organizational project maturity model (opm3)Organizational project maturity model (opm3)
Organizational project maturity model (opm3)
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management req
 
Perform qualitative risk analysis
Perform qualitative risk analysis Perform qualitative risk analysis
Perform qualitative risk analysis
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
Project management part 3
Project management part 3Project management part 3
Project management part 3
 
13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 

More from DavidMcLachlan1

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement ContractsDavidMcLachlan1
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct ProcurementsDavidMcLachlan1
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control ProcurementsDavidMcLachlan1
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope ManagementDavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIDavidMcLachlan1
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2DavidMcLachlan1
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2DavidMcLachlan1
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management EnvironmentDavidMcLachlan1
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentDavidMcLachlan1
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core PracticesDavidMcLachlan1
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningDavidMcLachlan1
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean FrameworksDavidMcLachlan1
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean FrameworksDavidMcLachlan1
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile EnvironmentDavidMcLachlan1
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core PracticesDavidMcLachlan1
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principlesDavidMcLachlan1
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...DavidMcLachlan1
 

More from DavidMcLachlan1 (20)

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 

Recently uploaded

History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Recently uploaded (20)

History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 

11.4 Perform Quantitative Risk Analysis

  • 2. Perform Quantitative Risk Analysis Coincides with PMBOK 11.4 Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement
  • 3. What is it? Perform Quantitative Risk Analysis is the process of numerically analysing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives. Why? The key benefit of this process is that it quantifies overall project risk exposure, and it can also provide additional quantitative risk information to support risk response planning. Perform Quantitative Risk Analysis Coincides with PMBOK 11.4
  • 4. Overview • Quantitative risk analysis requires specialized risk software and expertise in the development and interpretation of risk models. • The use of quantitative risk analysis for a project will be specified in the project’s risk management plan • Outputs from Perform Quantitative Risk Analysis are used as inputs to the Plan Risk Responses process, particularly in recommending responses to the level of overall project risk and key individual risks. Coincides with PMBOK 11.4 Perform Quantitative Risk Analysis
  • 5. Perform Quantitative Risk Analysis Coincides with PMBOK 11.4 Inputs Tools & Techniques Outputs 1. Project management plan • Risk management plan • Scope baseline • Schedule baseline • Cost baseline 2. Project documents • Assumption log • Basis of estimates • Cost estimates • Cost forecasts • Duration estimates • Milestone list • Resource requirements • Risk register • Risk report • Schedule forecasts 3. Enterprise environmental factors 4. Organizational process assets 1. Expert judgment 2. Data gathering • Interviews 3. Interpersonal and team skills • Facilitation 4. Representations of uncertainty 5. Data analysis • Simulations • Sensitivity analysis • Decision tree analysis • Influence diagrams 1. Project documents updates • Risk report Inputs, Tools & Techniques, Outputs
  • 6. Perform Quantitative Risk Analysis Coincides with PMBOK 11.4 11.4 Perform Quantitative Risk Analysis Project Management Plan Enterprise/Orga nization • Assumption log • Basis of estimates • Cost estimates • Cost forecasts • Duration estimates • Milestone list • Resource requirements • Risk register • Risk report • Schedule forecasts • Enterprise environmental factors • Organizational process assets Project Documents Project Documents• Risk report • Risk management plan • Scope baseline • Schedule baseline • Cost baseline
  • 7. Perform Quantitative Risk Analysis - Inputs Coincides with PMBOK 11.4 Project Management Plan Project management plan components include: • Risk management plan • Scope baseline • Schedule baseline • Cost baseline
  • 8. Perform Quantitative Risk Analysis - Inputs Coincides with PMBOK 11.4 Project Documents Project documents that can be considered as inputs for this process include: • Assumption log • Basis of estimates • Cost estimates • Cost forecasts • Duration estimates • Milestone list • Resource requirements • Risk register • Risk report • Schedule forecasts
  • 9. Coincides with PMBOK 11.4 Enterprise Environmental Factors The enterprise environmental factors that can influence Perform Quantitative Risk Analysis include but are not limited to: • Industry studies of similar projects • Published material, including commercial risk databases or checklists. Perform Quantitative Risk Analysis - Inputs
  • 10. Coincides with PMBOK 11.4 Organisational Process Assets The organizational process assets that can influence the Perform Quantitative Risk Analysis process include information from similar completed projects. Perform Quantitative Risk Analysis - Inputs
  • 11. Perform Quantitative Risk Analysis – Tools & Techniques Coincides with PMBOK 11.4 Expert Judgment Expertise should be considered from individuals or groups with specialized knowledge or training in the following topics: • Translating information on individual project risks and other sources of uncertainty into numeric inputs for the quantitative risk analysis model • Selecting the most appropriate representation of uncertainty to model particular risks or other sources of uncertainty • Modelling techniques that are appropriate in the context of the project • Identifying which tools would be most suitable for the selected modelling techniques • Interpreting the outputs of quantitative risk analysis.
  • 12. Perform Quantitative Risk Analysis – Tools & Techniques Coincides with PMBOK 11.4 Data Gathering Interviews may be used to generate inputs for the quantitative risk analysis, drawing on inputs that include individual project risks and other sources of uncertainty. This is particularly useful where information is required from experts. The interviewer should promote an environment of trust and confidentiality during the interview to encourage honest and unbiased contributions.
  • 13. Coincides with PMBOK 11.4 Interpersonal Team and Skills Perform Quantitative Risk Analysis – Tools & Techniques Interpersonal and team skills that can be used for this process include but are not limited to facilitation. A skilled facilitator is useful for gathering input data during a dedicated risk workshop involving project team members and other stakeholders. Facilitated workshops can improve effectiveness by: • Establishing a clear understanding of the purpose of the workshop • Building consensus among participants • Ensuring continued focus on the task • Using creative approaches to deal with interpersonal conflict or sources of bias
  • 14. Coincides with PMBOK 11.4 Representations of Uncertainty Perform Quantitative Risk Analysis – Tools & Techniques • Quantitative risk analysis requires inputs to a quantitative risk analysis model that reflect individual project risks and other sources of uncertainty. • Where the duration, cost, or resource requirement for a planned activity is uncertain, the range of possible values can be represented in the model as a probability distribution. This may take several forms, the most commonly used are triangular, normal, lognormal, beta, uniform, or discrete distributions.
  • 15. Coincides with PMBOK 11.4 Data Analysis - Simulation Perform Quantitative Risk Analysis – Tools & Techniques • Quantitative risk analysis uses a model that simulates the combined effects of individual project risks and other sources of uncertainty to evaluate their potential impact on achieving project objectives. • Monte Carlo Analysis is typically used for simulation. S-curve from a Monte Carlo cost risk analysis
  • 16. Coincides with PMBOK 11.4 Data Analysis – Sensitivity Analysis Perform Quantitative Risk Analysis – Tools & Techniques • Sensitivity analysis helps to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes. • It correlates variations in project outcomes with variations in elements of the quantitative risk analysis model. Tornado Diagram
  • 17. Coincides with PMBOK 11.4 Data Analysis – Decision Tree Analysis Perform Quantitative Risk Analysis – Tools & Techniques • Decision trees are used to support selection of the best of several alternative courses of action. • Alternative paths through the project are shown in the decision tree using branches representing different decisions or events, each of which can have associated costs and related individual project risks (including both threats and opportunities). Decision Tree
  • 18. Coincides with PMBOK 11.4 Data Analysis – Influence Diagrams Perform Quantitative Risk Analysis – Tools & Techniques • Influence diagrams are graphical aids to decision making under uncertainty. An influence diagram represents a project or situation within the project as a set of entities, outcomes, and influences, together with the relationships and effects between them. • Where an element in the influence diagram is uncertain as a result of the existence of individual project risks or other sources of uncertainty, this can be represented in the influence diagram using ranges or probability distributions.
  • 19. Perform Quantitative Risk Analysis – Outputs Coincides with PMBOK 11.4 Project Document Updates Project documents that can be considered as outputs for this process include but are not limited to the risk report. The risk report will be updated to reflect the results of the quantitative risk analysis. This will typically include: • Assessment of overall project risk exposure • Detailed probabilistic analysis of the project • Prioritized list of individual project risks. • Trends in quantitative risk analysis results • Recommended risk responses.

Editor's Notes

  1. This process is not required for every project, but where it is used, it is performed throughout the project.
  2. Perform Quantitative Risk Analysis is not required for all projects. Undertaking a robust analysis depends on the availability of high-quality data about individual project risks and other sources of uncertainty, as well as a sound underlying project baseline for scope, schedule, and cost. It also consumes additional time and cost. Quantitative risk analysis is the only reliable method to assess overall project risk through evaluating the aggregated effect on project outcomes of all individual project risks and other sources of uncertainty. Perform Quantitative Risk Analysis uses information on individual project risks that have been assessed by the Perform Qualitative Risk Analysis process as having a significant potential to affect the project’s objectives.
  3. Risk management plan - The risk management plan specifies whether quantitative risk analysis is required for the project. It also details the resources available for the analysis and the expected frequency of analyses. Scope baseline - The scope baseline describes the starting point from which the effect of individual project risks and other sources of uncertainty are evaluated. Schedule baseline - The schedule baseline describes the starting point from which the effect of individual project risks and other sources of uncertainty can be evaluated. Cost baseline - The cost baseline describes the starting point from which the effect of individual project risks and other sources of uncertainty can be evaluated.
  4. Assumption log - Assumptions may form inputs to the quantitative risk analysis if they are assessed as posing a risk to project objectives. The effect of constraints may also be modeled during a quantitative risk analysis. Basis of estimates - The basis of estimates used in the planning of the project may be reflected in variability modeled during a quantitative risk analysis process. This may include information on the estimate’s purpose, classification, assumed accuracy, methodology, and source. Cost estimates - Cost estimates provide the starting point from which cost variability is evaluated. Cost forecasts - Forecasts such as the project’s estimate to complete (ETC), estimate at completion (EAC), budget at completion (BAC), and to-complete performance index (TCPI) may be compared to the results of a quantitative cost risk analysis to determine the confidence level associated with achieving these targets. Duration estimates - Duration estimates provide the starting point from which schedule variability is evaluated. Milestone list - Significant events in the project define the schedule targets against which the results of a quantitative schedule risk analysis are compared, in order to determine the confidence level associated with achieving these targets. Resource requirements - Resource requirements provide the starting point from which variability is evaluated. Risk register - The risk register contains details of individual project risks to be used as input for quantitative risk analysis. Risk report - The risk report describes sources of overall project risk and the current overall project risk status. Schedule forecasts - Forecasts may be compared to the results of a quantitative schedule risk analysis to determine the confidence level associated with achieving these targets.
  5. Care should be taken when selecting an appropriate probability distribution to reflect the range of possible values for the planned activity. Individual project risks may be covered by probability distributions. Alternatively, risks may be included in the model as probabilistic branches, where optional activities are added to the model to represent the time and/or cost impact of the risk should it occur, and the chance that these activities actually occur in a particular simulation run matches the risk’s probability. Branches are most useful for risks that might occur independently of any planned activity. Where risks are related, for example, with a common cause or a logical dependency, correlation is used in the model to indicate this relationship. Other sources of uncertainty may also be represented using branches to describe alternative paths through the project.
  6. Simulations are typically performed using a Monte Carlo analysis. When running a Monte Carlo analysis for cost risk, the simulation uses the project cost estimates. When running a Monte Carlo analysis for schedule risk, the schedule network diagram and duration estimates are used. An integrated quantitative cost-schedule risk analysis uses both inputs. The output is a quantitative risk analysis model. Computer software is used to iterate the quantitative risk analysis model several thousand times. The input values (e.g., cost estimates, duration estimates, or occurrence of probabilistic branches) are chosen at random for each iteration. Outputs represent the range of possible outcomes for the project (e.g., project end date, project cost at completion). Typical outputs include a histogram presenting the number of iterations where a particular outcome resulted from the simulation, or a cumulative probability distribution (S-curve) representing the probability of achieving any particular outcome or less. An example S-curve from a Monte Carlo cost risk analysis is shown in Figure 11-13.
  7. An example tornado diagram is shown in Figure One typical display of sensitivity analysis is the tornado diagram, which presents the calculated correlation coefficient for each element of the quantitative risk analysis model that can influence the project outcome. This can include individual project risks, project activities with high degrees of variability, or specific sources of ambiguity. Items are ordered by descending strength of correlation, giving the typical tornado appearance.
  8. The end-points of branches in the decision tree represent the outcome from following that particular path, which can be negative or positive. The decision tree is evaluated by calculating the expected monetary value of each branch, allowing the optimal path to be selected. An example decision tree is shown in Figure Figure: The decision tree shows how to make a decision between alternative capital strategies (represented as “decision nodes”) when the environment contains uncertain elements (represented as “chance nodes”). Here, a decision is being made whether to invest $120M US to build a new plant or to instead invest only $50M US to upgrade the existing plant. For each decision, the demand (which is uncertain, and therefore represents a “chance node”) must be accounted for. For example, strong demand leads to $200M revenue with the new plant but only $120M US for the upgraded plant, perhaps due to capacity limitations of the upgraded plant. The end of each branch shows the net effect of the payoffs minus costs. For each decision branch, all effects are added (see shaded areas) to determine the overall Expected Monetary Value (EMV) of the decision. Remember to account for the investment costs. From the calculations in the shaded areas, the upgraded plant has a higher EMV of $46M – also the EMV of the overall decision. (This choice also represents the lowest risk, avoiding the worst case possible outcome of a loss of $30M).
  9. The influence diagram is then evaluated using a simulation technique, such as Monte Carlo analysis, to indicate which elements have the greatest influence on key outcomes. Outputs from an influence diagram are similar to other quantitative risk analysis methods, including S-curves and tornado diagrams.
  10. Assessment of overall project risk exposure. Overall project risk is reflected in two key measures: Chances of project success, indicated by the probability that the project will achieve its key objectives (e.g., required end date or interim milestones, required cost target, etc.) given the identified individual project risks and other sources of uncertainty; and Degree of inherent variability remaining within the project at the time the analysis was conducted, indicated by the range of possible project outcomes. Detailed probabilistic analysis of the project. Key outputs from the quantitative risk analysis are presented, such as S-curves, tornado diagrams, and criticality analysis, together with a narrative interpretation of the results. Possible detailed results of a quantitative risk analysis may include: Amount of contingency reserve needed to provide a specified level of confidence; Identification of individual project risks or other sources of uncertainty that have the greatest effect on the project critical path; and Major drivers of overall project risk, with the greatest influence on uncertainty in project outcomes. Prioritized list of individual project risks. This list includes those individual project risks that pose the greatest threat or present the greatest opportunity to the project, as indicated by sensitivity analysis. Trends in quantitative risk analysis results. As the analysis is repeated at different times during the project life cycle, trends may become apparent that inform the planning of risk responses. Recommended risk responses. The risk report may present suggested responses to the level of overall project risk exposure or key individual project risks, based on the results of the quantitative risk analysis. These recommendations will form inputs to the Plan Risk Responses process.