SlideShare a Scribd company logo
Project Cost
Management
Project CostManagement
Coincides with PMBOK 7.0
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group
Monitoring and Controlling Process
Group
Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project
Management Plan
4.3 Direct and Manage Project
Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or
Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost
Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project
Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk
Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement
Management
12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders
13.2 Plan Stakeholder
Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
Project Cost Management
Coincides with PMBOK 7.0
The Project Cost Management Processes are:
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
Planning
Monitoring and
Controlling
Executing
Initiating
Closing
Project Cost Management Overview – Planning
Project Cost Management
Coincides with PMBOK 7.0
Plan Cost Management Estimate Costs Determine Budget
1. Project charter
2. Project management plan
3. Enterprise environmental
factors
4. Organizational process assets
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets
1. Project management plan
2. Project documents
3. Business documents
4. Agreements
5. Enterprise environmental factors
6. Organizational process assets
1. Expert judgment
2. Data analysis
3. Meetings
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Bottom-up estimating
5. Three-point estimating
6. Data analysis
7. Project management information system
8. Decision making
1. Expert judgment
2. Cost aggregation
3. Data analysis
4. Historical information review
5. Funding limit reconciliation
6. Financing
1. Cost management plan
1. Cost estimates
2. Basis of estimates
3. Project documents updates
1. Cost baseline
2. Project funding requirements
3. Project documents updates
Inputs
Tools &
Techniques
Outputs
Project Cost Management Overview – Monitoring and Controlling
Project Cost Management
Coincides with PMBOK 7.0
Control Costs
1. Project management plan
2. Project documents
3. Project funding requirements
4. Work performance data
5. Organizational process assets
1. Expert judgment
2. Data analysis
3. To-complete performance index
4. Project management information system
1. Work performance information
2. Cost forecasts
3. Change requests
4. Project management plan updates
5. Project documents updates
InputsTools&
Techniques
Outputs
Key Concepts
Project Cost Management
Coincides with PMBOK 7.0
• Project Cost Management should consider the effect of project decisions on the
subsequent recurring cost of using, maintaining, and supporting the product, service,
or result of the project. Something that reduces the cost of the project might
increase the resulting product’s operating costs.
• The Project Manager must also recognise that different stakeholders measure project
costs in different ways and at different times. For example, the cost of an acquired
item may be measured when the acquisition decision is made or committed, the
order is placed, the item is delivered, or the actual cost is incurred for project
accounting purposes.
Trends and Emerging Practices
Project Cost Management
Coincides with PMBOK 7.0
• The expansion of earned value management (EVM) to include the concept of earned
schedule (ES).
• Uses Earned Schedule (ES) and Actual Time (AT)
• Similar to Earned Value (EV) which uses % of completed work multiplied by Budget at
Completion, Earned Schedule is the % of work completed multiplied by the total
scheduled time.
• An example is we’ve completed 40% of the work, and our estimated schedule was 50
weeks. ES = 0.40 x 50 = 20 weeks.
• Schedule Variance is now ES – AT, and the Schedule Performance Index is now ES /
AT.
Project Cost Management
Coincides with PMBOK 7.0
Knowledge management.
• Does the organization have a formal knowledge management and financial database
repository that a project manager is required to use and that is readily accessible?
Estimating and budgeting.
• Does the organization have existing formal or informal cost estimating and budgeting-
related policies, procedures, and guidelines?
Earned value management.
• Does the organization use earned value management in managing projects?
Use of agile approach.
• Does the organization use agile methodologies in managing projects? How does this
impact cost estimating?
Governance.
• Does the organization have formal or informal audit and governance policies,
procedures, and guidelines
Tailoring Considerations
Considerations for Agile or Adaptive Environments
Project Cost Management
Coincides with PMBOK 7.0
• Projects with high degrees of uncertainty or those where the scope is not yet
fully defined might use lightweight estimation methods.
• These can generate a fast, high-level forecast of project labour costs, which can
then be easily adjusted as changes arise.
• Detailed estimates are reserved for short-term planning horizons in a just-in-
time fashion.

More Related Content

What's hot

PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
Shamil Habet
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
Ashraf Osman, MBA, PMP
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
John Khateeb
 
Project management overview
Project management overviewProject management overview
Project management overview
Jody R Flower
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
DavidMcLachlan1
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
DavidMcLachlan1
 
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
Shamil Habet
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management Framework
Aarti Dahiya PMP
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
DavidMcLachlan1
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
Mohamed Salah Eldien Mohamed Ali
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
Shamil Habet
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
DavidMcLachlan1
 
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Tareq Al-Behairi,PMP,PMI-ACP
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
DavidMcLachlan1
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - Processes
Andrew Mikityuk
 
PMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKPMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOK
skiltful
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
Fida Karim 🇵🇰
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1
reddvise
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
Mohamed Loey
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
Amit Gupta
 

What's hot (20)

PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
 
Project management overview
Project management overviewProject management overview
Project management overview
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
 
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management Framework
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - Processes
 
PMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKPMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOK
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 

Similar to 7.0 Project Cost Management Overview

7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
DavidMcLachlan1
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
DavidMcLachlan1
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
DavidMcLachlan1
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
DavidMcLachlan1
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
DavidMcLachlan1
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
Omer Alsayed PhD,MBA, PMP®
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
Omer Alsayed PhD,MBA, PMP®
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
hatemk
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
HuyNguyen657394
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management Overview
DavidMcLachlan1
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
DavidMcLachlan1
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
Amr Miqdadi
 
Overview of Project Management Knowledge Areas and Processes
Overview of Project Management Knowledge Areas and ProcessesOverview of Project Management Knowledge Areas and Processes
Overview of Project Management Knowledge Areas and Processes
Idris Animasaun, PMP
 
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
Idris Animasaun, PMP
 
Overview of project management knowledge areas 2
Overview of project management knowledge areas 2Overview of project management knowledge areas 2
Overview of project management knowledge areas 2
Idris Animasaun, PMP
 
cost Management V4
cost Management V4cost Management V4
cost Management V4
Qussay Karam
 
9.6 Control Resources
9.6 Control Resources9.6 Control Resources
9.6 Control Resources
DavidMcLachlan1
 
8.1 Plan Quality Management
8.1 Plan Quality Management8.1 Plan Quality Management
8.1 Plan Quality Management
DavidMcLachlan1
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
Omer Alsayed PhD,MBA, PMP®
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
Joshua Render
 

Similar to 7.0 Project Cost Management Overview (20)

7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management Overview
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
 
Overview of Project Management Knowledge Areas and Processes
Overview of Project Management Knowledge Areas and ProcessesOverview of Project Management Knowledge Areas and Processes
Overview of Project Management Knowledge Areas and Processes
 
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
 
Overview of project management knowledge areas 2
Overview of project management knowledge areas 2Overview of project management knowledge areas 2
Overview of project management knowledge areas 2
 
cost Management V4
cost Management V4cost Management V4
cost Management V4
 
9.6 Control Resources
9.6 Control Resources9.6 Control Resources
9.6 Control Resources
 
8.1 Plan Quality Management
8.1 Plan Quality Management8.1 Plan Quality Management
8.1 Plan Quality Management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 

More from DavidMcLachlan1

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
DavidMcLachlan1
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
DavidMcLachlan1
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
DavidMcLachlan1
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
DavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
DavidMcLachlan1
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
DavidMcLachlan1
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
DavidMcLachlan1
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
DavidMcLachlan1
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
DavidMcLachlan1
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
DavidMcLachlan1
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
DavidMcLachlan1
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
DavidMcLachlan1
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
DavidMcLachlan1
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
DavidMcLachlan1
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
DavidMcLachlan1
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
DavidMcLachlan1
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement
DavidMcLachlan1
 

More from DavidMcLachlan1 (17)

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement
 

Recently uploaded

Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
NgcHiNguyn25
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
RitikBhardwaj56
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
Nguyen Thanh Tu Collection
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
Celine George
 
Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
How to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRMHow to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRM
Celine George
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
History of Stoke Newington
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
Bisnar Chase Personal Injury Attorneys
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
Celine George
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
TechSoup
 

Recently uploaded (20)

Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
 
Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
 
How to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRMHow to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRM
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
 

7.0 Project Cost Management Overview

  • 2. Project CostManagement Coincides with PMBOK 7.0 Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement
  • 3. Project Cost Management Coincides with PMBOK 7.0 The Project Cost Management Processes are: 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs Planning Monitoring and Controlling Executing Initiating Closing
  • 4. Project Cost Management Overview – Planning Project Cost Management Coincides with PMBOK 7.0 Plan Cost Management Estimate Costs Determine Budget 1. Project charter 2. Project management plan 3. Enterprise environmental factors 4. Organizational process assets 1. Project management plan 2. Project documents 3. Enterprise environmental factors 4. Organizational process assets 1. Project management plan 2. Project documents 3. Business documents 4. Agreements 5. Enterprise environmental factors 6. Organizational process assets 1. Expert judgment 2. Data analysis 3. Meetings 1. Expert judgment 2. Analogous estimating 3. Parametric estimating 4. Bottom-up estimating 5. Three-point estimating 6. Data analysis 7. Project management information system 8. Decision making 1. Expert judgment 2. Cost aggregation 3. Data analysis 4. Historical information review 5. Funding limit reconciliation 6. Financing 1. Cost management plan 1. Cost estimates 2. Basis of estimates 3. Project documents updates 1. Cost baseline 2. Project funding requirements 3. Project documents updates Inputs Tools & Techniques Outputs
  • 5. Project Cost Management Overview – Monitoring and Controlling Project Cost Management Coincides with PMBOK 7.0 Control Costs 1. Project management plan 2. Project documents 3. Project funding requirements 4. Work performance data 5. Organizational process assets 1. Expert judgment 2. Data analysis 3. To-complete performance index 4. Project management information system 1. Work performance information 2. Cost forecasts 3. Change requests 4. Project management plan updates 5. Project documents updates InputsTools& Techniques Outputs
  • 6. Key Concepts Project Cost Management Coincides with PMBOK 7.0 • Project Cost Management should consider the effect of project decisions on the subsequent recurring cost of using, maintaining, and supporting the product, service, or result of the project. Something that reduces the cost of the project might increase the resulting product’s operating costs. • The Project Manager must also recognise that different stakeholders measure project costs in different ways and at different times. For example, the cost of an acquired item may be measured when the acquisition decision is made or committed, the order is placed, the item is delivered, or the actual cost is incurred for project accounting purposes.
  • 7. Trends and Emerging Practices Project Cost Management Coincides with PMBOK 7.0 • The expansion of earned value management (EVM) to include the concept of earned schedule (ES). • Uses Earned Schedule (ES) and Actual Time (AT) • Similar to Earned Value (EV) which uses % of completed work multiplied by Budget at Completion, Earned Schedule is the % of work completed multiplied by the total scheduled time. • An example is we’ve completed 40% of the work, and our estimated schedule was 50 weeks. ES = 0.40 x 50 = 20 weeks. • Schedule Variance is now ES – AT, and the Schedule Performance Index is now ES / AT.
  • 8. Project Cost Management Coincides with PMBOK 7.0 Knowledge management. • Does the organization have a formal knowledge management and financial database repository that a project manager is required to use and that is readily accessible? Estimating and budgeting. • Does the organization have existing formal or informal cost estimating and budgeting- related policies, procedures, and guidelines? Earned value management. • Does the organization use earned value management in managing projects? Use of agile approach. • Does the organization use agile methodologies in managing projects? How does this impact cost estimating? Governance. • Does the organization have formal or informal audit and governance policies, procedures, and guidelines Tailoring Considerations
  • 9. Considerations for Agile or Adaptive Environments Project Cost Management Coincides with PMBOK 7.0 • Projects with high degrees of uncertainty or those where the scope is not yet fully defined might use lightweight estimation methods. • These can generate a fast, high-level forecast of project labour costs, which can then be easily adjusted as changes arise. • Detailed estimates are reserved for short-term planning horizons in a just-in- time fashion.

Editor's Notes

  1. The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled. The process of developing an approximation of the monetary resources needed to complete project work. The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. The process of monitoring the status of the project to update the project costs and manage changes to the cost baseline.