SlideShare a Scribd company logo
1 of 32
Download to read offline
INDIAN STRUCTURAL INTEGRITY SOCIETY
WORKSHOP
Structural Integrity Assessment of Nuclear Energy Assets
9th – 10th May 2018
AERB Auditorium,Niyamak Bhavan-B Mumbai .
An Overview of Technology
Development
(Posers & Challenges for Structural
Analysis Community)
SF Vhora,ED(TD),NPCIL
9 May 2018
R&D Facilities
R&D activities related to following promote
structural integrity of NPP Structures, Systems
& Components.
• Passive Decay Heat Removal System
• Containment Spray System
• Passive Catalytic Recombiners
• Containment Filtered Vent System
• Pressure Tube burst test studies
Remote Tooling
• Remote Tooling activities such as following
promote structural integrity of critical
components and equipment:
• BARCIS Inspection
• Steam generator inspection and debris removal
• Heat exchanger in-service inspection
• Installation, Repair & Refurbishment of reactor
component
• Use of automated welding
Indigenization
• Indigenisation promotes structural integrity as
critical raw materials such as steam generator,
pressurizer forgings, end shield tube sheet
plates get manufactured within the country
under regime of strict NPCIL QA coverage.
Construction Time Minimization
Certain type of modular construction has
tendency to create conditions which enhance
quality of construction and therefore
structural integrity.
• Preformed Ring Liner, Structural steel floor &
Integral dome modules have proven this
• ESCIA is one prime example of this
• New approach to Speedy fabrication is arrived
Posers & Challenges
Nuclear Industry Biggest Challenge
• Economic viability of Operating Units & New
Projects in the face of disruptive Renewables
technological & economical advances
• Operating Units – Major Issues
- In service health of critical components
- Plant Life Extension
New Projects :
- Issues coming up during construction which
can significantly delay
Regulatory review of Issues during
Project Construction
• Experience world over seems to indicate that the delay
caused by incidents which ultimately impact structural
integrity e.g. Concrete quality, weld quality, Cal vault
• Examples of EPRs at OL3 & FM3 , AP1000 at VC Summer
show huge financial implications & bankruptcies
• Average Construction time of India (9.0y) is about 3-4 years
greater than Korea (5.3y)& China(6.0y)
• For 700 PHWR certain proposed modifications are
worrisome as to further erode economic viability
• Therefore ready analysis capabilities in place with full
models could be a great investment as a time saver
• This Workshop can promote such an approach
Operating Units
KAPS-1,2 Pressure Tube issue
• Possibility of Combination of factors has not
been explored
• In-situ Pressure test after defueling – should it
have been considered?
• Why did we not think to pressure test taken
out PTs earlier?
Operating Units – World Over
• Wide variation in approach to life extension
• USA NRC appears to have consistent approach
• Most US plants life extended up to 60 y & thinking of
80 y
• CANDUs in Canada – mostly extending channel life has
given a breather – NPCIL needs to learn from this
approach – collaborate on channel issues
• Elsewhere picture is confused
• Armenia – shutdown after earthquake – decision
revoked when power crisis
R&D/TD Perspective based Proposal
• Since NPCIL is going to construct 12 units need to anticipate
likely issues which may crop up impacting structural
integrity aspects
• If two full independent models of RB can be made ready for
taking up analysis & providing results within days could
have a huge commercial benefit
• Some physical model of RB & Internals can be thought of &
tested on shake table
• Impact analysis for assumed RB internal structure & ICW
may show there may not be much of concern
• This workshop may consider proposing such an approach
• R&D/TD funds could be made available
Engineering Thinking & Trends which impact
safety & economic viability of 700 PHWRs
These pertain to structural integrity issues in general
Potential for erosion:
• RB diameter increase & spacing increase
• Replacement of structural steel floor with concrete
floor
• PDHRS removal
Potential for helping:
- Adoption of PRL, SSF&HA, ESCIA & Dome with rebars
also preinstalled
- Built-in shuttering cum EP in some parts of RB
- longer term – revert to structural steel option ?
Some 700 PHWR New Design Concepts As implemented
MODULAR CONSTRUCTION
Presentation focus on Major Modular Construction
techniques & New approaches to speed up
fabrication of critical path activities.
A Nuclear project has Nuclear Island, Conventional
Island & Balance of Plant.
Critical path goes through Reactor building.
Benchmarking has established that project completion
can happen from FPC to Commercial in about 50 to
60 months.
Adoption of New Technologies & Excellence in Project
Execution can achieve this.
(Implementation of Modular Construction Ideas were
preceded by Structural Analysis by DTD,NPCIL)
PRE-FORMED RING LINER (PRL)
Preformed Ring Liner (PRL) Concept Adoption
Backing
Truss Crane hook location
Wire Ropes
Spider
Slings
PRL
 Lesser congestion in IC wall resulting in simplified
construction due to elimination of the Out of plane
portion of backing truss from liner.
 Majority of fabrication can be done at ground,
resulting in good quality weld leading to better leak
tightness in liner.
 Availability of tower crane for other works improves.
 More parallelization in construction work can be
realized leading to substantial construction time
minimization.
Recent Major Modular Construction Step at KAPP-3&4
STRUCTURAL STEEL FLOOR & HEADER
ASSEMBLIES MODULE (SSF&HA)
TECHNICAL FEASIBILITY OF
INTEGRATED
ERECTION of HA &
SSFM(Cont)
ERECTION SEQUENCE
TECHNICAL FEASIBILITY OF INTEGRATED ERECTION
of HA & SSFM(Cont)
FEM
analysis
STRUCTURAL STEEL FLOOR
MODULES
END SHIELD CALANDRIA
INTEGRATED ASSEMBLY (ESCIA)
ESCIA
• This idea has the potential to radically change the way NPCIL
Builds new project.
• Concept arrived can eliminate 12 to 16 months from 700
Project schedule
• Is symbolic of addressing the only weakness of NPCIL – timely
execution of projects.
• Adopting this would also call for different approach to Supply
Chain & Project Execution.
Technical feasibility of ESCIA
• Feasibility established through detailed study of options
Scheme considers following steps
• Makes use of heavy duty crane to bring the assembly direct to FM vault
• Subsequently uses the current method of sliding the assembly in place
• Does not call for stoppage of civil construction on North side
• Calls for minor change in design of End Shield Calandria side flanges to be made
similar to FM side Flanges.
Why Confident? Successful Implementation of Major Modules PRL & SSFA has been
carried out, Dome in planning stage
TECHNICAL FEASIBILITY OF END SHIELD & CALANDRIA INTEGRATED ASSEMBLY (ESCIA)
SEQUENCE OF
ERECTION
TECHNICAL FEASIBILITY OF END SHIELD & CALANDRIA INTEGRATED ASSEMBLY (ESCIA)
PROVISION FOR
FULL
REHEARSAL
These are preliminary conceptualization views subject to further
detailing & refinement .
ESCIA Preliminary Design of Workshop
Vision for future construction
of 700 MWe PHWR
Summary
Technology Development Activities of NPCIL are:
• Contributing to Safe & Reliable Operation of NPPs.
• Addressing Supply Chain constraints
• Evolving Methodologies for Quick Construction
• These will provide Robust, Economical & therefore
Export worthy PHWR Technologies for the future
sustainability of the planet.
ProSIM R and D Pvt Ltd
Website : www.pro-sim.com
Contact us: enquiry@pro-sim.com
INDIAN STRUCTURAL INTEGREITY SOCIETY
(InSIS)
Website: www.instint.in
Contact us: insisblr@gmail.com

More Related Content

What's hot

CV_Electrical and Instrumentation Engineer
CV_Electrical and Instrumentation EngineerCV_Electrical and Instrumentation Engineer
CV_Electrical and Instrumentation EngineerDeva Narayanan
 
Seismic qualification using ASME/PNAE codes santhosh
Seismic qualification using ASME/PNAE codes santhoshSeismic qualification using ASME/PNAE codes santhosh
Seismic qualification using ASME/PNAE codes santhoshProSIM R & D Pvt. Ltd.
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)Vijayakumar Kumar
 
LF Lanza Resume 2016
LF Lanza Resume 2016LF Lanza Resume 2016
LF Lanza Resume 2016Lou Lanza
 
EME 185 Poster
EME 185 PosterEME 185 Poster
EME 185 Postertonygom
 
Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Nicholas Naing
 
Tct ccs master 180917 rev b
Tct ccs master 180917 rev bTct ccs master 180917 rev b
Tct ccs master 180917 rev bDamian Connelly
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...AMI GE International
 

What's hot (20)

CV_Talgat Turekulov_eng
CV_Talgat Turekulov_engCV_Talgat Turekulov_eng
CV_Talgat Turekulov_eng
 
CV_Electrical and Instrumentation Engineer
CV_Electrical and Instrumentation EngineerCV_Electrical and Instrumentation Engineer
CV_Electrical and Instrumentation Engineer
 
Resume
ResumeResume
Resume
 
Seismic qualification using ASME/PNAE codes santhosh
Seismic qualification using ASME/PNAE codes santhoshSeismic qualification using ASME/PNAE codes santhosh
Seismic qualification using ASME/PNAE codes santhosh
 
Derek Berry - IACMI/Wind Technology Area
Derek Berry - IACMI/Wind Technology AreaDerek Berry - IACMI/Wind Technology Area
Derek Berry - IACMI/Wind Technology Area
 
Mohamed Abou mesalem updated CV
Mohamed Abou mesalem  updated CVMohamed Abou mesalem  updated CV
Mohamed Abou mesalem updated CV
 
Sandia 2014 Wind Turbine Blade Workshop- Standish
Sandia 2014 Wind Turbine Blade Workshop- StandishSandia 2014 Wind Turbine Blade Workshop- Standish
Sandia 2014 Wind Turbine Blade Workshop- Standish
 
Sandia 2014 Wind Turbine Blade Workshop- Grife
Sandia 2014 Wind Turbine Blade Workshop- GrifeSandia 2014 Wind Turbine Blade Workshop- Grife
Sandia 2014 Wind Turbine Blade Workshop- Grife
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)
 
MOHAMED SALEM C.V
MOHAMED  SALEM  C.VMOHAMED  SALEM  C.V
MOHAMED SALEM C.V
 
Additively Manufactured Blade Mold Demonstration Project
Additively Manufactured Blade Mold Demonstration ProjectAdditively Manufactured Blade Mold Demonstration Project
Additively Manufactured Blade Mold Demonstration Project
 
LF Lanza Resume 2016
LF Lanza Resume 2016LF Lanza Resume 2016
LF Lanza Resume 2016
 
Jarred Hellon - CV
Jarred Hellon - CVJarred Hellon - CV
Jarred Hellon - CV
 
Senior Project_JPL
Senior Project_JPLSenior Project_JPL
Senior Project_JPL
 
EME 185 Poster
EME 185 PosterEME 185 Poster
EME 185 Poster
 
Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3
 
2014 Wind Turbine Blade Workshop- Johansen
2014 Wind Turbine Blade Workshop- Johansen2014 Wind Turbine Blade Workshop- Johansen
2014 Wind Turbine Blade Workshop- Johansen
 
2014 Sandia Wind Turbine Blade Workshop- Maniaci
2014 Sandia Wind Turbine Blade Workshop- Maniaci2014 Sandia Wind Turbine Blade Workshop- Maniaci
2014 Sandia Wind Turbine Blade Workshop- Maniaci
 
Tct ccs master 180917 rev b
Tct ccs master 180917 rev bTct ccs master 180917 rev b
Tct ccs master 180917 rev b
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
 

Similar to Overview of Technology Development _ S_ F _Vhora

UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdfUHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdfSriRam101316
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Muhammad Umar
 
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...IRJET Journal
 
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptxAbdalmoedAlaiashy2
 
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...Mark Mitchell
 
Reactor Building Integration_ Final Presentation_ Spring 2014 pfp
Reactor Building Integration_ Final Presentation_ Spring 2014 pfpReactor Building Integration_ Final Presentation_ Spring 2014 pfp
Reactor Building Integration_ Final Presentation_ Spring 2014 pfpHuu Duy Nguyen
 
INTRODUCTION TO PRE ENGINEERED BUILDINGS.pptx
INTRODUCTION TO PRE ENGINEERED BUILDINGS.pptxINTRODUCTION TO PRE ENGINEERED BUILDINGS.pptx
INTRODUCTION TO PRE ENGINEERED BUILDINGS.pptxsatish sajja
 
Isb engineering specialist
Isb engineering specialistIsb engineering specialist
Isb engineering specialistisbengineering
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsJean-Francois Saint-Marcoux
 
How Advanced Simulation will Impact the Offshore Industry both Now and in the...
How Advanced Simulation will Impact the Offshore Industry both Now and in the...How Advanced Simulation will Impact the Offshore Industry both Now and in the...
How Advanced Simulation will Impact the Offshore Industry both Now and in the...Altair
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
Parabolic trough collectors comparison
Parabolic trough collectors comparisonParabolic trough collectors comparison
Parabolic trough collectors comparisonSolarReference
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerTarun Sharna
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerTarun Sharna
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...IRJET Journal
 
2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind 2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind MEC Intelligence
 
A Review on PEB Regarding Cost and Time
A Review on PEB Regarding Cost and TimeA Review on PEB Regarding Cost and Time
A Review on PEB Regarding Cost and TimeIRJET Journal
 

Similar to Overview of Technology Development _ S_ F _Vhora (20)

CV_AKSHAY RAJPUT
CV_AKSHAY RAJPUTCV_AKSHAY RAJPUT
CV_AKSHAY RAJPUT
 
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdfUHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
 
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
 
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
 
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
 
Reactor Building Integration_ Final Presentation_ Spring 2014 pfp
Reactor Building Integration_ Final Presentation_ Spring 2014 pfpReactor Building Integration_ Final Presentation_ Spring 2014 pfp
Reactor Building Integration_ Final Presentation_ Spring 2014 pfp
 
INTRODUCTION TO PRE ENGINEERED BUILDINGS.pptx
INTRODUCTION TO PRE ENGINEERED BUILDINGS.pptxINTRODUCTION TO PRE ENGINEERED BUILDINGS.pptx
INTRODUCTION TO PRE ENGINEERED BUILDINGS.pptx
 
Isb engineering specialist
Isb engineering specialistIsb engineering specialist
Isb engineering specialist
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
 
How Advanced Simulation will Impact the Offshore Industry both Now and in the...
How Advanced Simulation will Impact the Offshore Industry both Now and in the...How Advanced Simulation will Impact the Offshore Industry both Now and in the...
How Advanced Simulation will Impact the Offshore Industry both Now and in the...
 
Enrico S. Simon
Enrico S. SimonEnrico S. Simon
Enrico S. Simon
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Parabolic trough collectors comparison
Parabolic trough collectors comparisonParabolic trough collectors comparison
Parabolic trough collectors comparison
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineer
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineer
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
 
E&C Profilep123
E&C Profilep123E&C Profilep123
E&C Profilep123
 
2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind 2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind
 
A Review on PEB Regarding Cost and Time
A Review on PEB Regarding Cost and TimeA Review on PEB Regarding Cost and Time
A Review on PEB Regarding Cost and Time
 

More from ProSIM R & D Pvt. Ltd.

Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...ProSIM R & D Pvt. Ltd.
 
Flow Induced Vibration of tubes and tube tanks- Kanwar Prateek
Flow Induced Vibration of tubes and tube tanks- Kanwar PrateekFlow Induced Vibration of tubes and tube tanks- Kanwar Prateek
Flow Induced Vibration of tubes and tube tanks- Kanwar PrateekProSIM R & D Pvt. Ltd.
 
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...ProSIM R & D Pvt. Ltd.
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalProSIM R & D Pvt. Ltd.
 
Business opportunities in PHWR and technical preparedness from vendors Philip...
Business opportunities in PHWR and technical preparedness from vendors Philip...Business opportunities in PHWR and technical preparedness from vendors Philip...
Business opportunities in PHWR and technical preparedness from vendors Philip...ProSIM R & D Pvt. Ltd.
 
Seismic analysis as per PNAE- Mohammad salman
Seismic analysis as per PNAE- Mohammad salman Seismic analysis as per PNAE- Mohammad salman
Seismic analysis as per PNAE- Mohammad salman ProSIM R & D Pvt. Ltd.
 
Role of Materials and Corrosion -Vivekanand Kain
Role of Materials and Corrosion -Vivekanand Kain Role of Materials and Corrosion -Vivekanand Kain
Role of Materials and Corrosion -Vivekanand Kain ProSIM R & D Pvt. Ltd.
 
Business Opportunity in LWR program and technical preparedness for Indian Ven...
Business Opportunity in LWR program and technical preparedness for Indian Ven...Business Opportunity in LWR program and technical preparedness for Indian Ven...
Business Opportunity in LWR program and technical preparedness for Indian Ven...ProSIM R & D Pvt. Ltd.
 
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj ProSIM R & D Pvt. Ltd.
 
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...ProSIM R & D Pvt. Ltd.
 
Earthquake resistant design of nuclear power plant- S.m.ingole
Earthquake resistant design of nuclear power plant- S.m.ingole Earthquake resistant design of nuclear power plant- S.m.ingole
Earthquake resistant design of nuclear power plant- S.m.ingole ProSIM R & D Pvt. Ltd.
 
Frequency Response Analysis by Prof Satish IISc
Frequency Response Analysis  by Prof Satish IIScFrequency Response Analysis  by Prof Satish IISc
Frequency Response Analysis by Prof Satish IIScProSIM R & D Pvt. Ltd.
 
Increasing Transformer Reliability by Smart Bushing
Increasing Transformer Reliability by Smart BushingIncreasing Transformer Reliability by Smart Bushing
Increasing Transformer Reliability by Smart BushingProSIM R & D Pvt. Ltd.
 
Seimic Qualification of Transformers - Pradeep ProSIM
Seimic Qualification of Transformers - Pradeep ProSIMSeimic Qualification of Transformers - Pradeep ProSIM
Seimic Qualification of Transformers - Pradeep ProSIMProSIM R & D Pvt. Ltd.
 
Modelling of Transformer for Surges by Udaya Kumar (IISc)
Modelling of Transformer for Surges by Udaya Kumar (IISc)Modelling of Transformer for Surges by Udaya Kumar (IISc)
Modelling of Transformer for Surges by Udaya Kumar (IISc)ProSIM R & D Pvt. Ltd.
 
Challenges in Transformer Technology -by Mr. Krishnaiah (Kryfs)
Challenges in Transformer Technology -by Mr. Krishnaiah (Kryfs)Challenges in Transformer Technology -by Mr. Krishnaiah (Kryfs)
Challenges in Transformer Technology -by Mr. Krishnaiah (Kryfs)ProSIM R & D Pvt. Ltd.
 

More from ProSIM R & D Pvt. Ltd. (20)

Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
 
Fracture mechanics&amp_Sundar R
Fracture mechanics&amp_Sundar RFracture mechanics&amp_Sundar R
Fracture mechanics&amp_Sundar R
 
Flow Induced Vibration of tubes and tube tanks- Kanwar Prateek
Flow Induced Vibration of tubes and tube tanks- Kanwar PrateekFlow Induced Vibration of tubes and tube tanks- Kanwar Prateek
Flow Induced Vibration of tubes and tube tanks- Kanwar Prateek
 
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R Pal
 
Business opportunities in PHWR and technical preparedness from vendors Philip...
Business opportunities in PHWR and technical preparedness from vendors Philip...Business opportunities in PHWR and technical preparedness from vendors Philip...
Business opportunities in PHWR and technical preparedness from vendors Philip...
 
Seismic analysis as per PNAE- Mohammad salman
Seismic analysis as per PNAE- Mohammad salman Seismic analysis as per PNAE- Mohammad salman
Seismic analysis as per PNAE- Mohammad salman
 
Role of Materials and Corrosion -Vivekanand Kain
Role of Materials and Corrosion -Vivekanand Kain Role of Materials and Corrosion -Vivekanand Kain
Role of Materials and Corrosion -Vivekanand Kain
 
Business Opportunity in LWR program and technical preparedness for Indian Ven...
Business Opportunity in LWR program and technical preparedness for Indian Ven...Business Opportunity in LWR program and technical preparedness for Indian Ven...
Business Opportunity in LWR program and technical preparedness for Indian Ven...
 
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
 
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
 
Earthquake resistant design of nuclear power plant- S.m.ingole
Earthquake resistant design of nuclear power plant- S.m.ingole Earthquake resistant design of nuclear power plant- S.m.ingole
Earthquake resistant design of nuclear power plant- S.m.ingole
 
Z-set introduction presentation
Z-set introduction presentationZ-set introduction presentation
Z-set introduction presentation
 
Transformer Failures and Case Studies
Transformer Failures and Case StudiesTransformer Failures and Case Studies
Transformer Failures and Case Studies
 
Frequency Response Analysis by Prof Satish IISc
Frequency Response Analysis  by Prof Satish IIScFrequency Response Analysis  by Prof Satish IISc
Frequency Response Analysis by Prof Satish IISc
 
Design Automation by Sara
Design Automation by SaraDesign Automation by Sara
Design Automation by Sara
 
Increasing Transformer Reliability by Smart Bushing
Increasing Transformer Reliability by Smart BushingIncreasing Transformer Reliability by Smart Bushing
Increasing Transformer Reliability by Smart Bushing
 
Seimic Qualification of Transformers - Pradeep ProSIM
Seimic Qualification of Transformers - Pradeep ProSIMSeimic Qualification of Transformers - Pradeep ProSIM
Seimic Qualification of Transformers - Pradeep ProSIM
 
Modelling of Transformer for Surges by Udaya Kumar (IISc)
Modelling of Transformer for Surges by Udaya Kumar (IISc)Modelling of Transformer for Surges by Udaya Kumar (IISc)
Modelling of Transformer for Surges by Udaya Kumar (IISc)
 
Challenges in Transformer Technology -by Mr. Krishnaiah (Kryfs)
Challenges in Transformer Technology -by Mr. Krishnaiah (Kryfs)Challenges in Transformer Technology -by Mr. Krishnaiah (Kryfs)
Challenges in Transformer Technology -by Mr. Krishnaiah (Kryfs)
 

Recently uploaded

Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 

Recently uploaded (20)

young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 

Overview of Technology Development _ S_ F _Vhora

  • 1. INDIAN STRUCTURAL INTEGRITY SOCIETY WORKSHOP Structural Integrity Assessment of Nuclear Energy Assets 9th – 10th May 2018 AERB Auditorium,Niyamak Bhavan-B Mumbai .
  • 2. An Overview of Technology Development (Posers & Challenges for Structural Analysis Community) SF Vhora,ED(TD),NPCIL 9 May 2018
  • 3. R&D Facilities R&D activities related to following promote structural integrity of NPP Structures, Systems & Components. • Passive Decay Heat Removal System • Containment Spray System • Passive Catalytic Recombiners • Containment Filtered Vent System • Pressure Tube burst test studies
  • 4. Remote Tooling • Remote Tooling activities such as following promote structural integrity of critical components and equipment: • BARCIS Inspection • Steam generator inspection and debris removal • Heat exchanger in-service inspection • Installation, Repair & Refurbishment of reactor component • Use of automated welding
  • 5. Indigenization • Indigenisation promotes structural integrity as critical raw materials such as steam generator, pressurizer forgings, end shield tube sheet plates get manufactured within the country under regime of strict NPCIL QA coverage.
  • 6. Construction Time Minimization Certain type of modular construction has tendency to create conditions which enhance quality of construction and therefore structural integrity. • Preformed Ring Liner, Structural steel floor & Integral dome modules have proven this • ESCIA is one prime example of this • New approach to Speedy fabrication is arrived
  • 8. Nuclear Industry Biggest Challenge • Economic viability of Operating Units & New Projects in the face of disruptive Renewables technological & economical advances • Operating Units – Major Issues - In service health of critical components - Plant Life Extension New Projects : - Issues coming up during construction which can significantly delay
  • 9. Regulatory review of Issues during Project Construction • Experience world over seems to indicate that the delay caused by incidents which ultimately impact structural integrity e.g. Concrete quality, weld quality, Cal vault • Examples of EPRs at OL3 & FM3 , AP1000 at VC Summer show huge financial implications & bankruptcies • Average Construction time of India (9.0y) is about 3-4 years greater than Korea (5.3y)& China(6.0y) • For 700 PHWR certain proposed modifications are worrisome as to further erode economic viability • Therefore ready analysis capabilities in place with full models could be a great investment as a time saver • This Workshop can promote such an approach
  • 10. Operating Units KAPS-1,2 Pressure Tube issue • Possibility of Combination of factors has not been explored • In-situ Pressure test after defueling – should it have been considered? • Why did we not think to pressure test taken out PTs earlier?
  • 11. Operating Units – World Over • Wide variation in approach to life extension • USA NRC appears to have consistent approach • Most US plants life extended up to 60 y & thinking of 80 y • CANDUs in Canada – mostly extending channel life has given a breather – NPCIL needs to learn from this approach – collaborate on channel issues • Elsewhere picture is confused • Armenia – shutdown after earthquake – decision revoked when power crisis
  • 12. R&D/TD Perspective based Proposal • Since NPCIL is going to construct 12 units need to anticipate likely issues which may crop up impacting structural integrity aspects • If two full independent models of RB can be made ready for taking up analysis & providing results within days could have a huge commercial benefit • Some physical model of RB & Internals can be thought of & tested on shake table • Impact analysis for assumed RB internal structure & ICW may show there may not be much of concern • This workshop may consider proposing such an approach • R&D/TD funds could be made available
  • 13. Engineering Thinking & Trends which impact safety & economic viability of 700 PHWRs These pertain to structural integrity issues in general Potential for erosion: • RB diameter increase & spacing increase • Replacement of structural steel floor with concrete floor • PDHRS removal Potential for helping: - Adoption of PRL, SSF&HA, ESCIA & Dome with rebars also preinstalled - Built-in shuttering cum EP in some parts of RB - longer term – revert to structural steel option ?
  • 14. Some 700 PHWR New Design Concepts As implemented
  • 16. Presentation focus on Major Modular Construction techniques & New approaches to speed up fabrication of critical path activities. A Nuclear project has Nuclear Island, Conventional Island & Balance of Plant. Critical path goes through Reactor building. Benchmarking has established that project completion can happen from FPC to Commercial in about 50 to 60 months. Adoption of New Technologies & Excellence in Project Execution can achieve this. (Implementation of Modular Construction Ideas were preceded by Structural Analysis by DTD,NPCIL)
  • 18. Preformed Ring Liner (PRL) Concept Adoption Backing Truss Crane hook location Wire Ropes Spider Slings PRL  Lesser congestion in IC wall resulting in simplified construction due to elimination of the Out of plane portion of backing truss from liner.  Majority of fabrication can be done at ground, resulting in good quality weld leading to better leak tightness in liner.  Availability of tower crane for other works improves.  More parallelization in construction work can be realized leading to substantial construction time minimization.
  • 19. Recent Major Modular Construction Step at KAPP-3&4
  • 20. STRUCTURAL STEEL FLOOR & HEADER ASSEMBLIES MODULE (SSF&HA)
  • 21. TECHNICAL FEASIBILITY OF INTEGRATED ERECTION of HA & SSFM(Cont) ERECTION SEQUENCE
  • 22. TECHNICAL FEASIBILITY OF INTEGRATED ERECTION of HA & SSFM(Cont) FEM analysis
  • 25. ESCIA • This idea has the potential to radically change the way NPCIL Builds new project. • Concept arrived can eliminate 12 to 16 months from 700 Project schedule • Is symbolic of addressing the only weakness of NPCIL – timely execution of projects. • Adopting this would also call for different approach to Supply Chain & Project Execution.
  • 26. Technical feasibility of ESCIA • Feasibility established through detailed study of options Scheme considers following steps • Makes use of heavy duty crane to bring the assembly direct to FM vault • Subsequently uses the current method of sliding the assembly in place • Does not call for stoppage of civil construction on North side • Calls for minor change in design of End Shield Calandria side flanges to be made similar to FM side Flanges. Why Confident? Successful Implementation of Major Modules PRL & SSFA has been carried out, Dome in planning stage
  • 27. TECHNICAL FEASIBILITY OF END SHIELD & CALANDRIA INTEGRATED ASSEMBLY (ESCIA) SEQUENCE OF ERECTION
  • 28. TECHNICAL FEASIBILITY OF END SHIELD & CALANDRIA INTEGRATED ASSEMBLY (ESCIA) PROVISION FOR FULL REHEARSAL
  • 29. These are preliminary conceptualization views subject to further detailing & refinement . ESCIA Preliminary Design of Workshop
  • 30. Vision for future construction of 700 MWe PHWR
  • 31. Summary Technology Development Activities of NPCIL are: • Contributing to Safe & Reliable Operation of NPPs. • Addressing Supply Chain constraints • Evolving Methodologies for Quick Construction • These will provide Robust, Economical & therefore Export worthy PHWR Technologies for the future sustainability of the planet.
  • 32. ProSIM R and D Pvt Ltd Website : www.pro-sim.com Contact us: enquiry@pro-sim.com INDIAN STRUCTURAL INTEGREITY SOCIETY (InSIS) Website: www.instint.in Contact us: insisblr@gmail.com