ISOPE-2010- Lessons Learnt from Recent Deepwater Riser Projects
Jean-François Saint-Marcoux,
Acergy, London, UK
Marin Abelanet
Acergy, Singapore, Singapore
Stéphane Bombino
Acergy, Paris, France
ABSTRACT
Major Risers development Projects have been launched recently (Total
CLOV and Petrobras Pre-salt to name a few). The Business strategy of
major Oil and Gas companies with regards to Subsea Umbilicals
Flowlines and Risers is evolving towards a more segmented approach
requiring optimization of each individual element of the SURF
package. This in turn requires a thorough review of the capabilities of
the concept of each segment to a level that was not considered before.
Acergy has gathered experience in all types of flowlines (rigid,
flexibles, bundles) and risers (SCR’s, Flexibles, single and bundle
Hybrid riser Towers). In particular, Acergy has pioneered the use of
Hybrid Riser Towers and have completed in 2007 the largest bundle
HRT to-date.
The paper will focus on how Risers become industrialized products
with their components being systematically organized through a
technical hierarchy. This in turns allow a detailed FMECA and a
structured detailed engineering package. From the structured
engineering package, result robust interfaces for material sourcing and
Fabrication.
KEY WORDS: Risers, FMECA, Hybrid Riser Towers, Risers,
Ultra-deepwater, Industrial model
NOMENCLATURE
ANSI: American National Standard Institute
API: American Petroleum Institute
BT: Buoyancy Tank
CRA: Corrosion Resistant Alloys
FEED: Front End Engineering Design
FJC: Field Joint Coating
FMECA: Failure Modes, Effects and Criticality Analysis
FPSO: Floating Production Storage and Offloading [unit]
FPU: Floating Production Unit
GOM: Gulf of Mexico
HRT: Hybrid Riser Towers
IMR: Inspection, Maintenance, Repair
ISO: International Standard Organization
LRA: Lower riser assembly
NACE: National Association of Corrosion Engineers
OHTC: Overall Heat Transfer Coefficient
OREDA: Offshore Reliability Data
PIP: Pipe in Pipe
PLET: Pipeline End Termination
SCM: Supply Chain Management
SCR: Steel Catenary Risers
SLOR: Single Line offset Risers
SURF: Subsea Umbilicals Flowlines and Risers
URA: Upper Riser Assembly
INTRODUCTION
As ultra deepwater1
fields are being developed, it becomes more and
more clear that, with the notable exception of the Gulf of Mexico,
FPSO based field architecture with wet Xmas trees is becoming the
norm. Typical examples are Total Angola CLOV development and
Petrobras Brazil Tupi area fields.
Operators, to a large extent, handle themselves directly or through
engineering companies their overall field developments. These field
developments include: Flowlines, Risers, and Floating Production
Units. They expect cost effective solutions and, as they have done for
other areas of petroleum industry, they split their ultra-deepwater scope
of work into segments: Flowlines, Risers and Umbilicals. Therefore it
is for the contractors as they provide any of these segments to adapt
their offer accordingly. As has been well known for centuries,
industrialization is the only solution to achieve a step change in cost-
effectiveness. This paper specifically deals with ultra-deepwater risers
as one of these segments.
STAKES
Industrialization brings cost-effectiveness and reliability through
standardization and repeatable processes. For a basically tailor-made
equipment such as HRT, this implies adapting methods that are of
frequent use in serial manufacturing industries, for instance System
Engineering and Value Analysis concepts.
The main stake is to find relevant tools, among general industrial
engineering methodologies, that can apply to this specific problem, and
that meet operators needs.
The frame to this industrialization / standardization is given by the
following complementary objectives:
1) Structured feedback and lessons learnt through a standardized
description of studied equipment:
- Conceptual description, functional approach;
- Physical description, organized list of equipments and
technologies, maturity approach;
- Organizational description (packages and suppliers tiers
1
Taken as deeper than 1800m per ANSI/API 17A
models).
2) Assess failures:
- Record what went wrong or can go wrong
- Better identify where effort must apply to avoid critical
dysfunctions
- Complete functional knowledge of equipment through
dysfunctional approach
Dysfunctional
modes
Functional
modes
Unknown
Known
Dysfunctional
modes
Functional modes
Standards scope
Unknown
Known
Fig. 1 Failures assessment role in standardization
As described in Fig.1 failure phenomena and scenarios knowledge
improves general knowledge of behavior of equipment, hence allowing
better standardization of products and methods.
AN EXAMPLE OF METHODOLGY
John Milton remarked “Truth and understanding are not such wares as
to be monopolized and traded in by tickets and statutes and standards”.
Yet in spite of this early recognized difficulty, there has been a
continuous push to make available the firmer part of current
understanding into codes and standards and the ANSI-API 17/ISO
13628 series of recommended practices can be seen as the most recent
attempt to do so in the deepwater offshore industry. This effort is
further carried out internally by companies and contractors.
The Fig.2 delineates the simplified workflow process of new concepts
as they are being developed.
The deliverable of the first phase is a functional analysis whereby the
various requirements, from operational to construction (fabrication and
installation) are clearly identified. The major drivers are:
- Flow assurance requirements
- Met ocean conditions
- Site location
- Yard fabrication procedure
- Offshore construction
The second phase consists of the Front End Engineering Design. This
starts with the definition of a concept consistent with the functional
requirements. This is validated with:
- Pre-design analyses
- FMECA
The third and final phase is the delivery of the documents required for
Supply Chain Management (procurement services and their associated
management) and then for construction (fabrication and installation
procedures)
Of course, this straightforward scheme is in reality much more complex
because of overlaps between the phases, different owners of the phases,
not to mention changes along the duration of a particular project.
Fig. 2 Workflow of new riser concept development
To a certain extent it may be said that deepwater risers such as flexible
risers or SCR are single bore units and therefore do not require as much
standardization as HRT’s. By its inherent flexibility in design (selection
of the number of conduits HRT’s in a field and selection of the number
of HRT’s) it lends itself to fit for purpose solution for each field.
Therefore the remaining of the paper will concentrate on HRT’s.
The figures 3 and 4 below respectively describe
- a turret-moored FPSO in ultra deepwater with two HRT’s
(Fig.3)
- an HRT fabrication yard (Fig.4)
Fig. 3 Deepwater FPSO based development with HRT’s
Fig. 4 Deepwater HRT fabrication
HRT FUNCTIONAL ANALYSIS AND
STANDARDIZATION
Industrialization means that pragmatic choices have to be made, and
that those choices must be robust with intended projects and with
regards to potential changes. Functional analysis allows making those
choices judiciously.
Flow Assurance
Pressure containment at design temperature is usually the driver and
requires high strength steel. However because of the potential for
reservoir souring API 5L grade X65 is usually the highest grade used
because of its compliance with NACE MR-01-75. It is therefore
reasonable to standardize on API 5LX65, and to consider CRA as an
option in presence of high CO2. If CRA is justified it will require less
buoyancy and therefore will be even more cost effective compared to
other riser types.
Wet insulation cover a wide range of Overall Heat Transfer Coefficient
and long cool down time. Unlike other riser systems, HRT risers can be
coated with a large thickness of wet insulation without the limitation on
installation squeeze pressure of flexibles, or the limitation of w/D ratio
of dynamic risers. If an OHTC-value of less than 1.5 W/m2
.K is
required, Pipe-in-Pipe solutions are feasible. Therefore Wet insulation
is the selected standard with PIP as an option.
With regards to the number of risers per tower it can be seen that one
riser per tower (SLOR) may lead to layout difficulties whereas large
number of risers may lead to impractical sizes of buoyancy tank.
Standard sizes would be from 4 to 8 main risers2
.
Site location and Met ocean Conditions
The current ultra-deepwater field developments appear to target areas
with a maximum water depth of 3000 to 3500m. This is about the
maximum water depth encountered in the GOM, and in the
Mediterranean Sea. And therefore the concept should be acceptable to
these depths.
This is the case because buoyancy foam which provides buoyancy
along the bundle has been already qualified by drillers.
The in-place dynamics of an HRT is low and therefore a wide range of
met ocean conditions can be accommodated. Met ocean conditions
affect essentially:
- Towing (surface current and waves period and directionality)
- Depth of the buoyancy tank (depth at which the current is still
significant)
Fabrication and Installation
The basic principle is that under usual conditions onshore fabrication is
more cost effective. Additionally quality control techniques are more
easily implemented onshore or even inshore. Still onshore construction
can be adapted to the locally available constructions site:
- Complete onshore construction of the full length of the tower
- Construction segments with inshore jointing (patent pending)
2
This number refers to Production,, Water Injection, and Gas
Injection or export risers. Gas lift risers are smaller and not a
driver of the bundle architecture and therefore not included in
these figures.
The same standard design with minor differences can accommodate
onshore or inshore construction.
Reversible installation operations allow simpler de-commissioning or
re-location. This feature was used as early as in 1995 (Fisher and
Berner 1988; Fisher, Holley, and Brashier 1995).
TECHNICAL HIERARCHY
As HRT’s (both monobore –SLOR- and multibore) are becoming more
and more known a standardization of the HRT has appeared:
- Jumper
- Buoyancy Tank (BT)
- Upper Tower Assembly (URA)
- Bundle
- Lower Tower Assembly (LRA)
- Suction piles
- Spool
The HRT being considered a system, these elements are called “sub-
systems” as shown in Fig. 5
Sub-system
Bundle BUN
Riser base RBA
Buoyancy tank BTA
URA URA
LRA LRA
Jumpers/spools JPS
Others OTH
Fig.5 Identifiers of sub-systems of an HRT.
With the introduction of a technical hierarchy of system, sub-system,
unit, equipment, part, and component it becomes feasible to identify
completely all elements of the “System HRT”. As an example Fig. 6
shows the full decomposition of the production riser down to the
individual weld.
System
Sub-system
Unit
Equipment
Part
Component
Name
2 3 4 5 6 7
x Hybrid riser tower
x Bundle
x Production riser
x Rigid risers
x DJ
x Joint
x Weld
Fig. 6 Use of the Technical Hierarchy levels to describe the HRT down
to its lowest level
The Technical Hierarchy provides the frame to identify each
component of the system down to the individual fabrication operation.
It allows both a top-down and a bottom-up view. As such it allows
answering the following example questions:
- which part, unit or system can be affected by the failure of a
particular weld?
- Which welds would be affected by a change in service
conditions?
The Technical Hierarchy provides a mean of tracking each individual
element from engineering, to procurement, fabrication and installation.
In particular:
- Engineering documents can be referred to a particular level of
the technical hierarchy
- Interfaces are readily identified
- Procurement can be performed at the most cost effective level
with regards to cost and delivery
- Quality Control can be tracked to the same level
Besides the Technical Hierarchy allows proceeding with the FMECA.
HRT FAILURE MODES, EFFECTS AND CRITICALITY
ANALYSIS
The FMECA was conducted by Acergy on its preferred “standard”
architecture.
Principles
The FMECA covers all stages of the life of the HRT:
- Installation of the suction anchor
- Fabrication in the yard, and inshore as applicable
- Installation towing
- Installation upending
- Spools and jumper connections
- Pre-commissioning
- Service life
The following assumptions were made:
- Design is compliant with codes and industry standards
- Design is compliant with specific design analyses developed
by Acergy for similar systems (Total Angola Girassol, BP
Angola Greater Plutonio, ExxonMobil Angola Block 15 Gas
Gathering)
- Extreme and operating conditions as provided by operators
are not exceeded
- Causes originating in Fabrication that may affect service
conditions are included
- Detailed risk analyses will be performed for each specific
project
- Suitable maintenance is provided during service life
- Failures are mutually independent, but common mode
failures are included where necessary
- All parts are manufactured by qualified suppliers with an
approved quality control system
Fabrication
Fabrication risks are related to lifting and handling of parts and sections
of the bundles.
Connections can be monitored through onshore quality control and
hydrotest.
It is easier to consider the fabrication and the sheltered water assembly
as a single phase because the same tools are available there.
The Fig. 7 is a diagram of the fabrication process. To the left is the yard
fabrication of the sub-systems: buoyancy tank, upper riser assembly,
bundle, lower riser assembly and flexibles. To the right is the sheltered
water area where the bundle is assembled to the URA and the LRA.
Fig. 7 Location of Risks at Fabrication phase (low risks omitted for
clarity)
Towing Upending
Main risks are localised at interfaces between the various sub-systems
in particular at URA and LRA where moment and loads are
concentrated.
Unexpected human intervention should be minimized: contingency
plan should detail tasks to a sufficient level, in order to be able to
anticipate contingency risks assessment.
Normally the suction anchor will have been installed long before to
allow settling of the soil.
The Fig. 8 shows both the towing and upending configurations. Those
two operations re performed in a relatively short period of time,
typically a week, by a dedicated fleet of vessels and crew. During tow
care should be exercised to minimize fatigue. This is achieved by a
proper selection of the route and depth of tow. The upending operation
is conducted in a matter of hours.
Fig. 8 Risks at towing and upending phase (low risks omitted for
clarity)
Service
Risks can be grouped as per functions, as follows:
- Loss of containment which can be mitigated by pressure and
temperature monitoring
- Structural integrity: in particular tension provided by the
buoyancy tank;
This is the rationale behind the monitoring of the HRT. Monitoring can
also include the position of the top of the HRT for early assessment of
undesired trend.
The Fig. 9 shows the risks in service. The risks are essentially:
- loss of buoyancy of the buoyancy tank
- tether connection
- erosion in the goosenecks
- loss of permanent buoyancy of the bundle due to water creep
- integrity of the risers weld
- rotolatch connection
- integrity of the spools
All of these risks are well identified and mitigated through engineering
per design codes specialized material qualifications.
Such facilities have been in service for ten years and this contributes
greatly to the assessment of the risks.
Through the OREDA database it is possible to quantitatively assess the
risks of various subsea components and in particular connectors.
Fig. 9 Risks in service (low risks omitted for clarity)
Summary
Risk criticality is assessed from consequence severity and causes
frequency. See Tab.1.
It would be difficult to cascade FMECA into a detailed quantitative
RAM analysis, because it covers a huge variety of concepts, but a few
quantitative parameters could be analyzed:
- frequency provided by OREDA database
- number of failure causes reviewed
- relative proportion of high severity cases
Tab. 1 Table of frequency vs. severity
Frequency
Severity
1
Very
unlikely
2
Unlikely
3
Possible
4
Likely
5
Very
likely
5 Very serious M M H H H
4 Serious L M M H H
3 Moderate L L M M H
2 Slight L L L M M
1 Negligible L L L L M
The results of the FMECA are as follows:
- 2 High severity risks
- 194 Medium severity risks
- 437 Low severity risks
These results are summarized in Fig. 11
Total
0%
31%
69%
H
M
L
Fig. 10 distribution of risks for an HRT
It is interesting to note that the two high risks identified are the
connection at the top and bottom of the HRT, as resulting from the
OREDA (2002) database. These connections are of course inevitable,
and therefore it can be concluded that the proposed design of the HRT
does not provide any additional high risk.
PRACTICAL IMPLICATIONS
First immediate outcome of FMECA is a sorted list of critical failure
scenarios that are mitigated throughout detailed design phase. In other
words, it is a qualitative reliability and availability assessment.
Then, a check-list can be extracted from tables to improve technical
risk management in design:
Tab. 2 : Example of check list of failure modes coverage.
Standard or spec
Part Failure
mode
Cause /
phenomenon,
Ref § Comments
Joint Crack Overpressure ANSI/API…
Another classical outcome of a FMECA is IMR support dossier. It
justifies the preventative inspection and maintenance actions, and
corrective actions. It allows issuing a preliminary list of spare parts, to
be optimized by operating Company from own feedback and policy.
This justified, anticipated approach can simplify spare standardization.
CONCLUSIONS
The recent deepwater projects have fostered an independent review of
HRT concepts. This is opening the door to their industrialization.
It also can be seen that the level of risks of HRT is acceptable as not
significant risk is added by a carefully selected architecture.
Further standardization of engineering will allow shorter delivery and
improved costs.
ACKNOWLEDGMENTS
The authors acknowledge Acergy for allowing them to prepare this
paper. The contribution of Jean Pierre Branchut, Jean-Luc Legras,
Gregoire de Roux, Blaise Seguin and Johann Declerq to several aspects
of the subject of this paper is gratefully acknowledged.
Nevertheless this paper only reflects the opinion of its authors and does
not imply endorsement by the company to which acknowledgements
are made.
REFERENCES
ANSI/API RP 17 A (ISO 13628-1) Design and Operation of Subsea
Production Systems – General Requirements and Recommendations.
January 2006
ANSI/API RP 17 N Recommended Practice for Subsea Production System
Reliability and Technical Risk Management, March 2009
DNV RP-A203 Qualification Procedure for New Technology
Fisher, E., A., Berner, P., C. (1988), “Non-integral Production riser for
Green Canyon Block 29 Development”, OTC 5846, Houston, TX
Fisher, E., A., Holley, P., Brashier, S. (1995), “Development and
Deployment of a Free-standing Production Riser in the Gulf of
Mexico”, OTC 7770, Houston, TX
ISO IEC Guide 73 (2002) Risk Management – Vocabulary Guideline
for use in Standards
ISO 20815 (2008) Petroleum and Natural Gas Industries – Production
Assurance and Reliability Management
OREDA (2002) Offshore Reliability Data Handbook, 4th
edition, DNV

More Related Content

What's hot

Intelligent well completio nm
Intelligent well completio nmIntelligent well completio nm
Intelligent well completio nmbasil_c
 
Subsea Field Development for an ideal Green field.
Subsea Field Development for an ideal Green field.Subsea Field Development for an ideal Green field.
Subsea Field Development for an ideal Green field.Emeka Ngwobia
 
Engineering of Subsea Production Systems
Engineering of Subsea Production SystemsEngineering of Subsea Production Systems
Engineering of Subsea Production SystemspetroEDGE
 
Emergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best PracticeEmergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best PracticeJames Rowley
 
J Ray Firsts
J Ray FirstsJ Ray Firsts
J Ray FirstsMyLast1
 
Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyConference_Presentations
 
Spe yp monthly session hydraulic fracturing technology - april 2021
Spe yp monthly session   hydraulic fracturing technology - april 2021Spe yp monthly session   hydraulic fracturing technology - april 2021
Spe yp monthly session hydraulic fracturing technology - april 2021mohamed atwa
 
Floating LNG/CNG Processing & Storage Offshore Platforms Utilizing a New Tank...
Floating LNG/CNG Processing & Storage Offshore Platforms Utilizing a New Tank...Floating LNG/CNG Processing & Storage Offshore Platforms Utilizing a New Tank...
Floating LNG/CNG Processing & Storage Offshore Platforms Utilizing a New Tank...Altair ProductDesign
 
performance evaluation of desilting devices
performance evaluation of desilting devicesperformance evaluation of desilting devices
performance evaluation of desilting devicesGurdeep singh Johar
 
Spe26043 (fluid entry)
Spe26043 (fluid entry)Spe26043 (fluid entry)
Spe26043 (fluid entry)Gregg Linville
 
Controlling Post-Completion Flow in Steam-Assisted Gravity Drainage Wells
Controlling Post-Completion Flow  in Steam-Assisted Gravity Drainage WellsControlling Post-Completion Flow  in Steam-Assisted Gravity Drainage Wells
Controlling Post-Completion Flow in Steam-Assisted Gravity Drainage WellsBaker Hughes
 
2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_projectSaddam Mussie
 
Hisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsHisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsSarah El Akkad
 
Intelligent well completion
Intelligent well completionIntelligent well completion
Intelligent well completionAkshaya Mishra
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2syed abdul wahab
 

What's hot (19)

Intelligent well completions
Intelligent well completionsIntelligent well completions
Intelligent well completions
 
Subsea Separation presentation
Subsea Separation presentationSubsea Separation presentation
Subsea Separation presentation
 
Intelligent well completio nm
Intelligent well completio nmIntelligent well completio nm
Intelligent well completio nm
 
Subsea Field Development for an ideal Green field.
Subsea Field Development for an ideal Green field.Subsea Field Development for an ideal Green field.
Subsea Field Development for an ideal Green field.
 
Engineering of Subsea Production Systems
Engineering of Subsea Production SystemsEngineering of Subsea Production Systems
Engineering of Subsea Production Systems
 
Emergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best PracticeEmergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best Practice
 
J Ray Firsts
J Ray FirstsJ Ray Firsts
J Ray Firsts
 
Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea Technology
 
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme [IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
 
OGJ Nordstream
OGJ NordstreamOGJ Nordstream
OGJ Nordstream
 
Spe yp monthly session hydraulic fracturing technology - april 2021
Spe yp monthly session   hydraulic fracturing technology - april 2021Spe yp monthly session   hydraulic fracturing technology - april 2021
Spe yp monthly session hydraulic fracturing technology - april 2021
 
Floating LNG/CNG Processing & Storage Offshore Platforms Utilizing a New Tank...
Floating LNG/CNG Processing & Storage Offshore Platforms Utilizing a New Tank...Floating LNG/CNG Processing & Storage Offshore Platforms Utilizing a New Tank...
Floating LNG/CNG Processing & Storage Offshore Platforms Utilizing a New Tank...
 
performance evaluation of desilting devices
performance evaluation of desilting devicesperformance evaluation of desilting devices
performance evaluation of desilting devices
 
Spe26043 (fluid entry)
Spe26043 (fluid entry)Spe26043 (fluid entry)
Spe26043 (fluid entry)
 
Controlling Post-Completion Flow in Steam-Assisted Gravity Drainage Wells
Controlling Post-Completion Flow  in Steam-Assisted Gravity Drainage WellsControlling Post-Completion Flow  in Steam-Assisted Gravity Drainage Wells
Controlling Post-Completion Flow in Steam-Assisted Gravity Drainage Wells
 
2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project
 
Hisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsHisham hajaj, stanley consultants
Hisham hajaj, stanley consultants
 
Intelligent well completion
Intelligent well completionIntelligent well completion
Intelligent well completion
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
 

Viewers also liked

Mes presentation subsea reliability
Mes presentation  subsea reliability  Mes presentation  subsea reliability
Mes presentation subsea reliability Changiz Rezvani
 
Automated FMECA Technology for Tomorrow
Automated FMECA Technology for TomorrowAutomated FMECA Technology for Tomorrow
Automated FMECA Technology for TomorrowMads Grahl-Madsen
 
A Proposal for an Alternative to MTBF/MTTF
A Proposal for an Alternative to MTBF/MTTFA Proposal for an Alternative to MTBF/MTTF
A Proposal for an Alternative to MTBF/MTTFASQ Reliability Division
 
Design and Analysis of Floating Production Systems
Design and Analysis of Floating Production Systems Design and Analysis of Floating Production Systems
Design and Analysis of Floating Production Systems Engineers Australia
 

Viewers also liked (8)

Failure rate not inverse of MTBF always
Failure rate not inverse of MTBF alwaysFailure rate not inverse of MTBF always
Failure rate not inverse of MTBF always
 
Mes presentation subsea reliability
Mes presentation  subsea reliability  Mes presentation  subsea reliability
Mes presentation subsea reliability
 
DOT 2002 Functional Approach to Flow Assurance
DOT 2002 Functional Approach to Flow AssuranceDOT 2002 Functional Approach to Flow Assurance
DOT 2002 Functional Approach to Flow Assurance
 
2015 ars eu_red_s9_schutter
2015 ars eu_red_s9_schutter2015 ars eu_red_s9_schutter
2015 ars eu_red_s9_schutter
 
Automated FMECA Technology for Tomorrow
Automated FMECA Technology for TomorrowAutomated FMECA Technology for Tomorrow
Automated FMECA Technology for Tomorrow
 
overview of reliability engineering
overview of reliability engineeringoverview of reliability engineering
overview of reliability engineering
 
A Proposal for an Alternative to MTBF/MTTF
A Proposal for an Alternative to MTBF/MTTFA Proposal for an Alternative to MTBF/MTTF
A Proposal for an Alternative to MTBF/MTTF
 
Design and Analysis of Floating Production Systems
Design and Analysis of Floating Production Systems Design and Analysis of Floating Production Systems
Design and Analysis of Floating Production Systems
 

Similar to Lessons from Deepwater Riser Projects

Installation challenges
Installation challengesInstallation challenges
Installation challengesAndrea Intieri
 
Technical Prospects of Floating LNG
Technical Prospects of Floating LNGTechnical Prospects of Floating LNG
Technical Prospects of Floating LNGRonak Sani
 
A life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrityA life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrityOkeme Esegine PMP
 
riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15Monica Riccio
 
DNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects ShowcaseDNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects ShowcaseIan Ng
 
iFluids Tank Inspection services
iFluids Tank Inspection servicesiFluids Tank Inspection services
iFluids Tank Inspection servicesJohn Kingsley
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Jerry Brown
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfOmarSAlAbri
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfOmarSAlAbri
 
Embracing Aerial Robotics in the Oil and Gas Sector
Embracing Aerial Robotics in the Oil and Gas SectorEmbracing Aerial Robotics in the Oil and Gas Sector
Embracing Aerial Robotics in the Oil and Gas SectorManaswiMumbarkar
 
Final project report 791417 (1)
Final project report 791417 (1)Final project report 791417 (1)
Final project report 791417 (1)Hernani Neto MIET
 
20120815_155538_49174_TELFONA_ECCOMAS_CFD2006_-_v2-1-2
20120815_155538_49174_TELFONA_ECCOMAS_CFD2006_-_v2-1-220120815_155538_49174_TELFONA_ECCOMAS_CFD2006_-_v2-1-2
20120815_155538_49174_TELFONA_ECCOMAS_CFD2006_-_v2-1-2Julián Maldonado
 
Fabrication of storage buffer vessel
Fabrication of storage buffer vesselFabrication of storage buffer vessel
Fabrication of storage buffer vesselNishant Rao Boddeda
 
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...Forum for the Future
 

Similar to Lessons from Deepwater Riser Projects (20)

Installation challenges
Installation challengesInstallation challenges
Installation challenges
 
Roy Shilling
Roy ShillingRoy Shilling
Roy Shilling
 
Technical Prospects of Floating LNG
Technical Prospects of Floating LNGTechnical Prospects of Floating LNG
Technical Prospects of Floating LNG
 
A life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrityA life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrity
 
WP Offshore Coating Techniques Aug 2015
WP Offshore Coating Techniques Aug 2015WP Offshore Coating Techniques Aug 2015
WP Offshore Coating Techniques Aug 2015
 
riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15
 
DNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects ShowcaseDNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects Showcase
 
iFluids Tank Inspection services
iFluids Tank Inspection servicesiFluids Tank Inspection services
iFluids Tank Inspection services
 
Download
DownloadDownload
Download
 
Pipeline repair techniques
Pipeline repair techniquesPipeline repair techniques
Pipeline repair techniques
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdf
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdf
 
PlatformOptimization
PlatformOptimizationPlatformOptimization
PlatformOptimization
 
Embracing Aerial Robotics in the Oil and Gas Sector
Embracing Aerial Robotics in the Oil and Gas SectorEmbracing Aerial Robotics in the Oil and Gas Sector
Embracing Aerial Robotics in the Oil and Gas Sector
 
Final project report 791417 (1)
Final project report 791417 (1)Final project report 791417 (1)
Final project report 791417 (1)
 
20120815_155538_49174_TELFONA_ECCOMAS_CFD2006_-_v2-1-2
20120815_155538_49174_TELFONA_ECCOMAS_CFD2006_-_v2-1-220120815_155538_49174_TELFONA_ECCOMAS_CFD2006_-_v2-1-2
20120815_155538_49174_TELFONA_ECCOMAS_CFD2006_-_v2-1-2
 
Fabrication of storage buffer vessel
Fabrication of storage buffer vesselFabrication of storage buffer vessel
Fabrication of storage buffer vessel
 
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
 
WP_Extreme_2016 (2)
WP_Extreme_2016 (2)WP_Extreme_2016 (2)
WP_Extreme_2016 (2)
 

Lessons from Deepwater Riser Projects

  • 1. ISOPE-2010- Lessons Learnt from Recent Deepwater Riser Projects Jean-François Saint-Marcoux, Acergy, London, UK Marin Abelanet Acergy, Singapore, Singapore Stéphane Bombino Acergy, Paris, France ABSTRACT Major Risers development Projects have been launched recently (Total CLOV and Petrobras Pre-salt to name a few). The Business strategy of major Oil and Gas companies with regards to Subsea Umbilicals Flowlines and Risers is evolving towards a more segmented approach requiring optimization of each individual element of the SURF package. This in turn requires a thorough review of the capabilities of the concept of each segment to a level that was not considered before. Acergy has gathered experience in all types of flowlines (rigid, flexibles, bundles) and risers (SCR’s, Flexibles, single and bundle Hybrid riser Towers). In particular, Acergy has pioneered the use of Hybrid Riser Towers and have completed in 2007 the largest bundle HRT to-date. The paper will focus on how Risers become industrialized products with their components being systematically organized through a technical hierarchy. This in turns allow a detailed FMECA and a structured detailed engineering package. From the structured engineering package, result robust interfaces for material sourcing and Fabrication. KEY WORDS: Risers, FMECA, Hybrid Riser Towers, Risers, Ultra-deepwater, Industrial model NOMENCLATURE ANSI: American National Standard Institute API: American Petroleum Institute BT: Buoyancy Tank CRA: Corrosion Resistant Alloys FEED: Front End Engineering Design FJC: Field Joint Coating FMECA: Failure Modes, Effects and Criticality Analysis FPSO: Floating Production Storage and Offloading [unit] FPU: Floating Production Unit GOM: Gulf of Mexico HRT: Hybrid Riser Towers IMR: Inspection, Maintenance, Repair ISO: International Standard Organization LRA: Lower riser assembly NACE: National Association of Corrosion Engineers OHTC: Overall Heat Transfer Coefficient OREDA: Offshore Reliability Data PIP: Pipe in Pipe PLET: Pipeline End Termination SCM: Supply Chain Management SCR: Steel Catenary Risers SLOR: Single Line offset Risers SURF: Subsea Umbilicals Flowlines and Risers URA: Upper Riser Assembly INTRODUCTION As ultra deepwater1 fields are being developed, it becomes more and more clear that, with the notable exception of the Gulf of Mexico, FPSO based field architecture with wet Xmas trees is becoming the norm. Typical examples are Total Angola CLOV development and Petrobras Brazil Tupi area fields. Operators, to a large extent, handle themselves directly or through engineering companies their overall field developments. These field developments include: Flowlines, Risers, and Floating Production Units. They expect cost effective solutions and, as they have done for other areas of petroleum industry, they split their ultra-deepwater scope of work into segments: Flowlines, Risers and Umbilicals. Therefore it is for the contractors as they provide any of these segments to adapt their offer accordingly. As has been well known for centuries, industrialization is the only solution to achieve a step change in cost- effectiveness. This paper specifically deals with ultra-deepwater risers as one of these segments. STAKES Industrialization brings cost-effectiveness and reliability through standardization and repeatable processes. For a basically tailor-made equipment such as HRT, this implies adapting methods that are of frequent use in serial manufacturing industries, for instance System Engineering and Value Analysis concepts. The main stake is to find relevant tools, among general industrial engineering methodologies, that can apply to this specific problem, and that meet operators needs. The frame to this industrialization / standardization is given by the following complementary objectives: 1) Structured feedback and lessons learnt through a standardized description of studied equipment: - Conceptual description, functional approach; - Physical description, organized list of equipments and technologies, maturity approach; - Organizational description (packages and suppliers tiers 1 Taken as deeper than 1800m per ANSI/API 17A
  • 2. models). 2) Assess failures: - Record what went wrong or can go wrong - Better identify where effort must apply to avoid critical dysfunctions - Complete functional knowledge of equipment through dysfunctional approach Dysfunctional modes Functional modes Unknown Known Dysfunctional modes Functional modes Standards scope Unknown Known Fig. 1 Failures assessment role in standardization As described in Fig.1 failure phenomena and scenarios knowledge improves general knowledge of behavior of equipment, hence allowing better standardization of products and methods. AN EXAMPLE OF METHODOLGY John Milton remarked “Truth and understanding are not such wares as to be monopolized and traded in by tickets and statutes and standards”. Yet in spite of this early recognized difficulty, there has been a continuous push to make available the firmer part of current understanding into codes and standards and the ANSI-API 17/ISO 13628 series of recommended practices can be seen as the most recent attempt to do so in the deepwater offshore industry. This effort is further carried out internally by companies and contractors. The Fig.2 delineates the simplified workflow process of new concepts as they are being developed. The deliverable of the first phase is a functional analysis whereby the various requirements, from operational to construction (fabrication and installation) are clearly identified. The major drivers are: - Flow assurance requirements - Met ocean conditions - Site location - Yard fabrication procedure - Offshore construction The second phase consists of the Front End Engineering Design. This starts with the definition of a concept consistent with the functional requirements. This is validated with: - Pre-design analyses - FMECA The third and final phase is the delivery of the documents required for Supply Chain Management (procurement services and their associated management) and then for construction (fabrication and installation procedures) Of course, this straightforward scheme is in reality much more complex because of overlaps between the phases, different owners of the phases, not to mention changes along the duration of a particular project. Fig. 2 Workflow of new riser concept development To a certain extent it may be said that deepwater risers such as flexible risers or SCR are single bore units and therefore do not require as much standardization as HRT’s. By its inherent flexibility in design (selection of the number of conduits HRT’s in a field and selection of the number of HRT’s) it lends itself to fit for purpose solution for each field. Therefore the remaining of the paper will concentrate on HRT’s.
  • 3. The figures 3 and 4 below respectively describe - a turret-moored FPSO in ultra deepwater with two HRT’s (Fig.3) - an HRT fabrication yard (Fig.4) Fig. 3 Deepwater FPSO based development with HRT’s Fig. 4 Deepwater HRT fabrication HRT FUNCTIONAL ANALYSIS AND STANDARDIZATION Industrialization means that pragmatic choices have to be made, and that those choices must be robust with intended projects and with regards to potential changes. Functional analysis allows making those choices judiciously. Flow Assurance Pressure containment at design temperature is usually the driver and requires high strength steel. However because of the potential for reservoir souring API 5L grade X65 is usually the highest grade used because of its compliance with NACE MR-01-75. It is therefore reasonable to standardize on API 5LX65, and to consider CRA as an option in presence of high CO2. If CRA is justified it will require less buoyancy and therefore will be even more cost effective compared to other riser types. Wet insulation cover a wide range of Overall Heat Transfer Coefficient and long cool down time. Unlike other riser systems, HRT risers can be coated with a large thickness of wet insulation without the limitation on installation squeeze pressure of flexibles, or the limitation of w/D ratio of dynamic risers. If an OHTC-value of less than 1.5 W/m2 .K is required, Pipe-in-Pipe solutions are feasible. Therefore Wet insulation is the selected standard with PIP as an option. With regards to the number of risers per tower it can be seen that one riser per tower (SLOR) may lead to layout difficulties whereas large number of risers may lead to impractical sizes of buoyancy tank. Standard sizes would be from 4 to 8 main risers2 . Site location and Met ocean Conditions The current ultra-deepwater field developments appear to target areas with a maximum water depth of 3000 to 3500m. This is about the maximum water depth encountered in the GOM, and in the Mediterranean Sea. And therefore the concept should be acceptable to these depths. This is the case because buoyancy foam which provides buoyancy along the bundle has been already qualified by drillers. The in-place dynamics of an HRT is low and therefore a wide range of met ocean conditions can be accommodated. Met ocean conditions affect essentially: - Towing (surface current and waves period and directionality) - Depth of the buoyancy tank (depth at which the current is still significant) Fabrication and Installation The basic principle is that under usual conditions onshore fabrication is more cost effective. Additionally quality control techniques are more easily implemented onshore or even inshore. Still onshore construction can be adapted to the locally available constructions site: - Complete onshore construction of the full length of the tower - Construction segments with inshore jointing (patent pending) 2 This number refers to Production,, Water Injection, and Gas Injection or export risers. Gas lift risers are smaller and not a driver of the bundle architecture and therefore not included in these figures.
  • 4. The same standard design with minor differences can accommodate onshore or inshore construction. Reversible installation operations allow simpler de-commissioning or re-location. This feature was used as early as in 1995 (Fisher and Berner 1988; Fisher, Holley, and Brashier 1995). TECHNICAL HIERARCHY As HRT’s (both monobore –SLOR- and multibore) are becoming more and more known a standardization of the HRT has appeared: - Jumper - Buoyancy Tank (BT) - Upper Tower Assembly (URA) - Bundle - Lower Tower Assembly (LRA) - Suction piles - Spool The HRT being considered a system, these elements are called “sub- systems” as shown in Fig. 5 Sub-system Bundle BUN Riser base RBA Buoyancy tank BTA URA URA LRA LRA Jumpers/spools JPS Others OTH Fig.5 Identifiers of sub-systems of an HRT. With the introduction of a technical hierarchy of system, sub-system, unit, equipment, part, and component it becomes feasible to identify completely all elements of the “System HRT”. As an example Fig. 6 shows the full decomposition of the production riser down to the individual weld. System Sub-system Unit Equipment Part Component Name 2 3 4 5 6 7 x Hybrid riser tower x Bundle x Production riser x Rigid risers x DJ x Joint x Weld Fig. 6 Use of the Technical Hierarchy levels to describe the HRT down to its lowest level The Technical Hierarchy provides the frame to identify each component of the system down to the individual fabrication operation. It allows both a top-down and a bottom-up view. As such it allows answering the following example questions: - which part, unit or system can be affected by the failure of a particular weld? - Which welds would be affected by a change in service conditions? The Technical Hierarchy provides a mean of tracking each individual element from engineering, to procurement, fabrication and installation. In particular: - Engineering documents can be referred to a particular level of the technical hierarchy - Interfaces are readily identified - Procurement can be performed at the most cost effective level with regards to cost and delivery - Quality Control can be tracked to the same level Besides the Technical Hierarchy allows proceeding with the FMECA. HRT FAILURE MODES, EFFECTS AND CRITICALITY ANALYSIS The FMECA was conducted by Acergy on its preferred “standard” architecture. Principles The FMECA covers all stages of the life of the HRT: - Installation of the suction anchor - Fabrication in the yard, and inshore as applicable - Installation towing - Installation upending - Spools and jumper connections - Pre-commissioning - Service life The following assumptions were made: - Design is compliant with codes and industry standards - Design is compliant with specific design analyses developed by Acergy for similar systems (Total Angola Girassol, BP Angola Greater Plutonio, ExxonMobil Angola Block 15 Gas Gathering) - Extreme and operating conditions as provided by operators are not exceeded - Causes originating in Fabrication that may affect service conditions are included - Detailed risk analyses will be performed for each specific project - Suitable maintenance is provided during service life - Failures are mutually independent, but common mode failures are included where necessary - All parts are manufactured by qualified suppliers with an approved quality control system Fabrication Fabrication risks are related to lifting and handling of parts and sections of the bundles.
  • 5. Connections can be monitored through onshore quality control and hydrotest. It is easier to consider the fabrication and the sheltered water assembly as a single phase because the same tools are available there. The Fig. 7 is a diagram of the fabrication process. To the left is the yard fabrication of the sub-systems: buoyancy tank, upper riser assembly, bundle, lower riser assembly and flexibles. To the right is the sheltered water area where the bundle is assembled to the URA and the LRA. Fig. 7 Location of Risks at Fabrication phase (low risks omitted for clarity) Towing Upending Main risks are localised at interfaces between the various sub-systems in particular at URA and LRA where moment and loads are concentrated. Unexpected human intervention should be minimized: contingency plan should detail tasks to a sufficient level, in order to be able to anticipate contingency risks assessment. Normally the suction anchor will have been installed long before to allow settling of the soil. The Fig. 8 shows both the towing and upending configurations. Those two operations re performed in a relatively short period of time, typically a week, by a dedicated fleet of vessels and crew. During tow care should be exercised to minimize fatigue. This is achieved by a proper selection of the route and depth of tow. The upending operation is conducted in a matter of hours. Fig. 8 Risks at towing and upending phase (low risks omitted for clarity) Service Risks can be grouped as per functions, as follows: - Loss of containment which can be mitigated by pressure and temperature monitoring - Structural integrity: in particular tension provided by the buoyancy tank; This is the rationale behind the monitoring of the HRT. Monitoring can also include the position of the top of the HRT for early assessment of undesired trend. The Fig. 9 shows the risks in service. The risks are essentially: - loss of buoyancy of the buoyancy tank - tether connection - erosion in the goosenecks - loss of permanent buoyancy of the bundle due to water creep - integrity of the risers weld - rotolatch connection - integrity of the spools All of these risks are well identified and mitigated through engineering per design codes specialized material qualifications. Such facilities have been in service for ten years and this contributes greatly to the assessment of the risks. Through the OREDA database it is possible to quantitatively assess the risks of various subsea components and in particular connectors.
  • 6. Fig. 9 Risks in service (low risks omitted for clarity) Summary Risk criticality is assessed from consequence severity and causes frequency. See Tab.1. It would be difficult to cascade FMECA into a detailed quantitative RAM analysis, because it covers a huge variety of concepts, but a few quantitative parameters could be analyzed: - frequency provided by OREDA database - number of failure causes reviewed - relative proportion of high severity cases Tab. 1 Table of frequency vs. severity Frequency Severity 1 Very unlikely 2 Unlikely 3 Possible 4 Likely 5 Very likely 5 Very serious M M H H H 4 Serious L M M H H 3 Moderate L L M M H 2 Slight L L L M M 1 Negligible L L L L M The results of the FMECA are as follows: - 2 High severity risks - 194 Medium severity risks - 437 Low severity risks These results are summarized in Fig. 11 Total 0% 31% 69% H M L Fig. 10 distribution of risks for an HRT It is interesting to note that the two high risks identified are the connection at the top and bottom of the HRT, as resulting from the OREDA (2002) database. These connections are of course inevitable, and therefore it can be concluded that the proposed design of the HRT does not provide any additional high risk. PRACTICAL IMPLICATIONS First immediate outcome of FMECA is a sorted list of critical failure scenarios that are mitigated throughout detailed design phase. In other words, it is a qualitative reliability and availability assessment. Then, a check-list can be extracted from tables to improve technical risk management in design: Tab. 2 : Example of check list of failure modes coverage. Standard or spec Part Failure mode Cause / phenomenon, Ref § Comments Joint Crack Overpressure ANSI/API… Another classical outcome of a FMECA is IMR support dossier. It justifies the preventative inspection and maintenance actions, and corrective actions. It allows issuing a preliminary list of spare parts, to be optimized by operating Company from own feedback and policy. This justified, anticipated approach can simplify spare standardization. CONCLUSIONS The recent deepwater projects have fostered an independent review of HRT concepts. This is opening the door to their industrialization. It also can be seen that the level of risks of HRT is acceptable as not significant risk is added by a carefully selected architecture. Further standardization of engineering will allow shorter delivery and improved costs.
  • 7. ACKNOWLEDGMENTS The authors acknowledge Acergy for allowing them to prepare this paper. The contribution of Jean Pierre Branchut, Jean-Luc Legras, Gregoire de Roux, Blaise Seguin and Johann Declerq to several aspects of the subject of this paper is gratefully acknowledged. Nevertheless this paper only reflects the opinion of its authors and does not imply endorsement by the company to which acknowledgements are made. REFERENCES ANSI/API RP 17 A (ISO 13628-1) Design and Operation of Subsea Production Systems – General Requirements and Recommendations. January 2006 ANSI/API RP 17 N Recommended Practice for Subsea Production System Reliability and Technical Risk Management, March 2009 DNV RP-A203 Qualification Procedure for New Technology Fisher, E., A., Berner, P., C. (1988), “Non-integral Production riser for Green Canyon Block 29 Development”, OTC 5846, Houston, TX Fisher, E., A., Holley, P., Brashier, S. (1995), “Development and Deployment of a Free-standing Production Riser in the Gulf of Mexico”, OTC 7770, Houston, TX ISO IEC Guide 73 (2002) Risk Management – Vocabulary Guideline for use in Standards ISO 20815 (2008) Petroleum and Natural Gas Industries – Production Assurance and Reliability Management OREDA (2002) Offshore Reliability Data Handbook, 4th edition, DNV