SlideShare a Scribd company logo
1 of 1
Download to read offline
ENGINEERING PROJECTS
Constellation Energy/Exelon – Nine Mile Point /Calvert Cliffs Nuclear Power Station Units 1 and 2
• Currently leading design efforts for implementation of open phase detection scheme at the primary side of
115kV reserve station transformers utilizing SEL multifunction relays (SEL-487 and SEL-421). Responsible for
presenting project scope and challenges during formal meetings with client throughout the project.
• Prepared scoping study, technical specification, and lead team of approximately 10 multi-discipline
engineers/designers to design for the replacement of the main generator voltage regulator with a digital
automatic voltage regulator. Design included updating/creating station drawings (i.e. schematics, single lines,
wiring diagrams, physical layout, cable routing, etc.). Frequently interfaced with client and vendor for schedule
and status updates, and to discuss technical challenges throughout the project. Provided onsite installation
support. Project was successfully installed in 2015 on schedule and received praise from the client.
• Performed design and for installation of 13.2kV outdoor padmounted reclosers in order to provide ground and
phase fault protection for site power transformers. Design included routing 750MCM direct buried cable in
addition to installation of underground cable splices. Analytical work included coordination/setpoint analysis
between recloser controller and upstream SEL-551 relay using ETAP.
• Frequently performs technical reviews of coordination, load flow, short circuit, and motor starting power system
studies prepared by junior engineers to evaluate engineering changes made to the station.
• Prepared modification package and lead design team to replace feeder cables for 16,500HP feedwater pump
motor.
• Calculated current and voltage transformer accuracy for 345KV relaying and revenue metering equipment.
• Designed dual 480V sump pump motor control circuits and control panels with multiple alarms and
manual/off/auto capabilities.
Entergy – Pilgrim Nuclear Power Station
• Replaced Ni-Cad backup battery for outdoor switchgear breaker control to facilitate transfer of power from
onsite source to emergency diesel generators. Scope included battery sizing study, development of minimum cell
temperatures and correction factors, development of battery testing requirements, as well as special
consideration for min/max temperatures and their effect on battery capacity and aging.
Entergy – James A. Fitzpatrick Nuclear Power Station
• Modeled entire medium and low voltage AC auxiliary system and performed load flow and short circuit
calculations using ETAP. Study included a full report of inputs, assumptions, methodology, results, acceptance
criteria, and conclusions. Where input was not available, plant walkdowns were performed.
• Developed modification package to replace station reserve auxiliary transformers to enhance acceptable offsite
power operating voltage range using automatic load tap changers. Scope of work included electrical analysis,
development of wiring drawings, schematics, one-line diagrams, outline drawings, power system studies, and
post-modification test plan. Developed optimal transformer tap settings as well as alarm setpoints by performing
ETAP simulations.
• Supported the resolution of multiple emergent unplanned plant events onsite on short notice (i.e. transformer
explosion, high voltage CCVT fire due to ferroresonance). Received praise from the client on each occasion. As
a result, client selected our company as their engineer of choice for projects moving forward.
Dominion Energy – Kewaunee Nuclear Power Station
• Performed 125VDC safety related and non-safety related battery sizing, battery charger sizing, and DC short
circuit analysis for plant emergency systems using ETAP. Developed battery load profile for postulated plant
emergencies based on review of elementary drawings and station operating procedures. Plant walkdowns were
conducted for data gathering. This was a first of its kind calculation utilizing ETAP at the time and as a result,
became a DC system analysis subject matter expert.
• Prepared study to develop settings for main generator protection and coordination. Protection scheme included
transformer and generator differential (87), backup distance (21), negative phase sequence (46), over excitation
protection, etc.
References available upon request Page 1 of 1

More Related Content

What's hot

Uhde Shedden Project Undertaken
Uhde Shedden Project UndertakenUhde Shedden Project Undertaken
Uhde Shedden Project UndertakenMichael Macek
 
Power Distribution HVAC Responsibilities
Power Distribution HVAC ResponsibilitiesPower Distribution HVAC Responsibilities
Power Distribution HVAC ResponsibilitiesLevingston George
 
BeeExperienceandCommissioningPhilosophy
BeeExperienceandCommissioningPhilosophyBeeExperienceandCommissioningPhilosophy
BeeExperienceandCommissioningPhilosophyFrank Richards
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid ResilienceAdvisian
 
RESUME - RAKESH PATEL
RESUME - RAKESH PATELRESUME - RAKESH PATEL
RESUME - RAKESH PATELRakesh patel
 
Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019Advisian
 
Kobe Galloway2 _10-2014
Kobe Galloway2 _10-2014Kobe Galloway2 _10-2014
Kobe Galloway2 _10-2014Kobe Galloway
 
Virtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing PerformanceVirtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing PerformanceGSE Systems, Inc.
 
Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1Nicholas Naing
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Nicholas Naing
 
Belgium_Electrabel__Sarich_NPP_Maintenance_Optimization
Belgium_Electrabel__Sarich_NPP_Maintenance_OptimizationBelgium_Electrabel__Sarich_NPP_Maintenance_Optimization
Belgium_Electrabel__Sarich_NPP_Maintenance_OptimizationVictorien Chatelain
 
Jonathan Wong Resume
Jonathan Wong ResumeJonathan Wong Resume
Jonathan Wong ResumeJonathan Wong
 
Case studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response programCase studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response programZondits
 
Wind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningWind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningAdvisian
 

What's hot (20)

Uhde Shedden Project Undertaken
Uhde Shedden Project UndertakenUhde Shedden Project Undertaken
Uhde Shedden Project Undertaken
 
11 reno sandia_dgi_reno_sand2016-4701 pe
11 reno sandia_dgi_reno_sand2016-4701 pe11 reno sandia_dgi_reno_sand2016-4701 pe
11 reno sandia_dgi_reno_sand2016-4701 pe
 
Power Distribution HVAC Responsibilities
Power Distribution HVAC ResponsibilitiesPower Distribution HVAC Responsibilities
Power Distribution HVAC Responsibilities
 
BeeExperienceandCommissioningPhilosophy
BeeExperienceandCommissioningPhilosophyBeeExperienceandCommissioningPhilosophy
BeeExperienceandCommissioningPhilosophy
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid Resilience
 
RESUME - RAKESH PATEL
RESUME - RAKESH PATELRESUME - RAKESH PATEL
RESUME - RAKESH PATEL
 
Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019
 
Kobe Galloway2 _10-2014
Kobe Galloway2 _10-2014Kobe Galloway2 _10-2014
Kobe Galloway2 _10-2014
 
Virtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing PerformanceVirtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing Performance
 
Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1
 
2016 Resume
2016  Resume2016  Resume
2016 Resume
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2
 
Belgium_Electrabel__Sarich_NPP_Maintenance_Optimization
Belgium_Electrabel__Sarich_NPP_Maintenance_OptimizationBelgium_Electrabel__Sarich_NPP_Maintenance_Optimization
Belgium_Electrabel__Sarich_NPP_Maintenance_Optimization
 
Resume (cv)
Resume (cv)Resume (cv)
Resume (cv)
 
Project Day Tank
Project Day TankProject Day Tank
Project Day Tank
 
17 mohit epri-sandia symposium_v1
17 mohit epri-sandia symposium_v117 mohit epri-sandia symposium_v1
17 mohit epri-sandia symposium_v1
 
Jonathan Wong Resume
Jonathan Wong ResumeJonathan Wong Resume
Jonathan Wong Resume
 
Case studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response programCase studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response program
 
Wind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningWind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioning
 
Cliff Resume 2016
Cliff Resume 2016Cliff Resume 2016
Cliff Resume 2016
 

Viewers also liked

Tra diem thi dai hoc su pham tpHCM 2014 - diemthisieutoc.vn
Tra diem thi dai hoc su pham tpHCM 2014 - diemthisieutoc.vnTra diem thi dai hoc su pham tpHCM 2014 - diemthisieutoc.vn
Tra diem thi dai hoc su pham tpHCM 2014 - diemthisieutoc.vnDiem Thi Sieu Toc
 
Efficacity presentation linked_in_en
Efficacity presentation linked_in_enEfficacity presentation linked_in_en
Efficacity presentation linked_in_enJoël Danard
 
DESOL CAPABILITY PROFILE - PROJECTS
DESOL CAPABILITY PROFILE - PROJECTSDESOL CAPABILITY PROFILE - PROJECTS
DESOL CAPABILITY PROFILE - PROJECTSDESOL INDIA
 
Tra diem thi hoc vien cong nghe buu chinh vien thong phia nam 2014 - diemthis...
Tra diem thi hoc vien cong nghe buu chinh vien thong phia nam 2014 - diemthis...Tra diem thi hoc vien cong nghe buu chinh vien thong phia nam 2014 - diemthis...
Tra diem thi hoc vien cong nghe buu chinh vien thong phia nam 2014 - diemthis...Diem Thi Sieu Toc
 
Cover Letter_2015 (Send)
Cover Letter_2015 (Send)Cover Letter_2015 (Send)
Cover Letter_2015 (Send)Caley Hayes
 
Prueba única de informática del periodo
Prueba  única  de  informática del periodoPrueba  única  de  informática del periodo
Prueba única de informática del periodobalacera
 
English 6 Unit 1: Greetings Lesson B1 – 3 - Good morning
English 6 Unit 1: Greetings Lesson B1 – 3 - Good morningEnglish 6 Unit 1: Greetings Lesson B1 – 3 - Good morning
English 6 Unit 1: Greetings Lesson B1 – 3 - Good morningDân Phạm Việt
 
Cómoobtenertuspropias semillas Manualpara agricultoresecológicos
Cómoobtenertuspropias semillas Manualpara agricultoresecológicosCómoobtenertuspropias semillas Manualpara agricultoresecológicos
Cómoobtenertuspropias semillas Manualpara agricultoresecológicosAlfonso Cinta
 
Ficha de-trabalho-saga
Ficha de-trabalho-sagaFicha de-trabalho-saga
Ficha de-trabalho-sagasandramarques8
 
Como Ser um Líder Inspirador
Como Ser um Líder InspiradorComo Ser um Líder Inspirador
Como Ser um Líder InspiradorDiego Mangabeira
 

Viewers also liked (16)

Tra diem thi dai hoc su pham tpHCM 2014 - diemthisieutoc.vn
Tra diem thi dai hoc su pham tpHCM 2014 - diemthisieutoc.vnTra diem thi dai hoc su pham tpHCM 2014 - diemthisieutoc.vn
Tra diem thi dai hoc su pham tpHCM 2014 - diemthisieutoc.vn
 
RHA Rave
RHA RaveRHA Rave
RHA Rave
 
Autismo
Autismo Autismo
Autismo
 
Rough Draft_3
Rough Draft_3Rough Draft_3
Rough Draft_3
 
Certificate_1
Certificate_1Certificate_1
Certificate_1
 
Efficacity presentation linked_in_en
Efficacity presentation linked_in_enEfficacity presentation linked_in_en
Efficacity presentation linked_in_en
 
DESOL CAPABILITY PROFILE - PROJECTS
DESOL CAPABILITY PROFILE - PROJECTSDESOL CAPABILITY PROFILE - PROJECTS
DESOL CAPABILITY PROFILE - PROJECTS
 
шалфей
шалфейшалфей
шалфей
 
Tra diem thi hoc vien cong nghe buu chinh vien thong phia nam 2014 - diemthis...
Tra diem thi hoc vien cong nghe buu chinh vien thong phia nam 2014 - diemthis...Tra diem thi hoc vien cong nghe buu chinh vien thong phia nam 2014 - diemthis...
Tra diem thi hoc vien cong nghe buu chinh vien thong phia nam 2014 - diemthis...
 
Cover Letter_2015 (Send)
Cover Letter_2015 (Send)Cover Letter_2015 (Send)
Cover Letter_2015 (Send)
 
Prueba única de informática del periodo
Prueba  única  de  informática del periodoPrueba  única  de  informática del periodo
Prueba única de informática del periodo
 
English 6 Unit 1: Greetings Lesson B1 – 3 - Good morning
English 6 Unit 1: Greetings Lesson B1 – 3 - Good morningEnglish 6 Unit 1: Greetings Lesson B1 – 3 - Good morning
English 6 Unit 1: Greetings Lesson B1 – 3 - Good morning
 
Cómoobtenertuspropias semillas Manualpara agricultoresecológicos
Cómoobtenertuspropias semillas Manualpara agricultoresecológicosCómoobtenertuspropias semillas Manualpara agricultoresecológicos
Cómoobtenertuspropias semillas Manualpara agricultoresecológicos
 
El buen trato
El buen tratoEl buen trato
El buen trato
 
Ficha de-trabalho-saga
Ficha de-trabalho-sagaFicha de-trabalho-saga
Ficha de-trabalho-saga
 
Como Ser um Líder Inspirador
Como Ser um Líder InspiradorComo Ser um Líder Inspirador
Como Ser um Líder Inspirador
 

Similar to Nuclear Power Station Engineering Projects

Larry Hebert Resume
Larry Hebert ResumeLarry Hebert Resume
Larry Hebert ResumeLarry Hebert
 
Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Dennis Kehoe
 
Western Power Graduate Roles & breakdown of primary work tasks
Western Power Graduate Roles & breakdown of primary work tasksWestern Power Graduate Roles & breakdown of primary work tasks
Western Power Graduate Roles & breakdown of primary work tasksMichael Macek
 
Senior Electrical Engineer resume Jan 2016
Senior Electrical Engineer resume  Jan  2016Senior Electrical Engineer resume  Jan  2016
Senior Electrical Engineer resume Jan 2016Khadar Ali Shaik, P.Eng
 
Sam res (houston) oil and gas
Sam res (houston) oil and gasSam res (houston) oil and gas
Sam res (houston) oil and gasSam Mehta
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017Dex Bugariu
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017Dex Bugariu
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017Dex Bugariu
 
Bidhan R DEY-Resume
Bidhan R DEY-ResumeBidhan R DEY-Resume
Bidhan R DEY-ResumeBidhan Dey
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016Sher Chuhan
 
Sam res (houston) O &G
Sam res (houston) O &GSam res (houston) O &G
Sam res (houston) O &GSam Mehta
 
ahmed mohamed diaa_original
ahmed mohamed diaa_originalahmed mohamed diaa_original
ahmed mohamed diaa_originalAHMED DIAA
 

Similar to Nuclear Power Station Engineering Projects (20)

Larry Hebert Resume
Larry Hebert ResumeLarry Hebert Resume
Larry Hebert Resume
 
wathiq alanbaki
wathiq alanbakiwathiq alanbaki
wathiq alanbaki
 
Rex Scott 2016-11-03 resume
Rex Scott 2016-11-03 resumeRex Scott 2016-11-03 resume
Rex Scott 2016-11-03 resume
 
Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015
 
Western Power Graduate Roles & breakdown of primary work tasks
Western Power Graduate Roles & breakdown of primary work tasksWestern Power Graduate Roles & breakdown of primary work tasks
Western Power Graduate Roles & breakdown of primary work tasks
 
Electrical engineer 5 Years Exp
Electrical engineer 5 Years ExpElectrical engineer 5 Years Exp
Electrical engineer 5 Years Exp
 
Senior Electrical Engineer resume Jan 2016
Senior Electrical Engineer resume  Jan  2016Senior Electrical Engineer resume  Jan  2016
Senior Electrical Engineer resume Jan 2016
 
DESIGN
DESIGNDESIGN
DESIGN
 
Sam res (houston) oil and gas
Sam res (houston) oil and gasSam res (houston) oil and gas
Sam res (houston) oil and gas
 
venkatCV
venkatCVvenkatCV
venkatCV
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017
 
Bidhan R DEY-Resume
Bidhan R DEY-ResumeBidhan R DEY-Resume
Bidhan R DEY-Resume
 
resume
resumeresume
resume
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016
 
Sam res (houston) O &G
Sam res (houston) O &GSam res (houston) O &G
Sam res (houston) O &G
 
ahmed mohamed diaa_original
ahmed mohamed diaa_originalahmed mohamed diaa_original
ahmed mohamed diaa_original
 
Jaydeep_Resume
Jaydeep_ResumeJaydeep_Resume
Jaydeep_Resume
 
Sathish Kumar-Resume.
Sathish Kumar-Resume.Sathish Kumar-Resume.
Sathish Kumar-Resume.
 

Nuclear Power Station Engineering Projects

  • 1. ENGINEERING PROJECTS Constellation Energy/Exelon – Nine Mile Point /Calvert Cliffs Nuclear Power Station Units 1 and 2 • Currently leading design efforts for implementation of open phase detection scheme at the primary side of 115kV reserve station transformers utilizing SEL multifunction relays (SEL-487 and SEL-421). Responsible for presenting project scope and challenges during formal meetings with client throughout the project. • Prepared scoping study, technical specification, and lead team of approximately 10 multi-discipline engineers/designers to design for the replacement of the main generator voltage regulator with a digital automatic voltage regulator. Design included updating/creating station drawings (i.e. schematics, single lines, wiring diagrams, physical layout, cable routing, etc.). Frequently interfaced with client and vendor for schedule and status updates, and to discuss technical challenges throughout the project. Provided onsite installation support. Project was successfully installed in 2015 on schedule and received praise from the client. • Performed design and for installation of 13.2kV outdoor padmounted reclosers in order to provide ground and phase fault protection for site power transformers. Design included routing 750MCM direct buried cable in addition to installation of underground cable splices. Analytical work included coordination/setpoint analysis between recloser controller and upstream SEL-551 relay using ETAP. • Frequently performs technical reviews of coordination, load flow, short circuit, and motor starting power system studies prepared by junior engineers to evaluate engineering changes made to the station. • Prepared modification package and lead design team to replace feeder cables for 16,500HP feedwater pump motor. • Calculated current and voltage transformer accuracy for 345KV relaying and revenue metering equipment. • Designed dual 480V sump pump motor control circuits and control panels with multiple alarms and manual/off/auto capabilities. Entergy – Pilgrim Nuclear Power Station • Replaced Ni-Cad backup battery for outdoor switchgear breaker control to facilitate transfer of power from onsite source to emergency diesel generators. Scope included battery sizing study, development of minimum cell temperatures and correction factors, development of battery testing requirements, as well as special consideration for min/max temperatures and their effect on battery capacity and aging. Entergy – James A. Fitzpatrick Nuclear Power Station • Modeled entire medium and low voltage AC auxiliary system and performed load flow and short circuit calculations using ETAP. Study included a full report of inputs, assumptions, methodology, results, acceptance criteria, and conclusions. Where input was not available, plant walkdowns were performed. • Developed modification package to replace station reserve auxiliary transformers to enhance acceptable offsite power operating voltage range using automatic load tap changers. Scope of work included electrical analysis, development of wiring drawings, schematics, one-line diagrams, outline drawings, power system studies, and post-modification test plan. Developed optimal transformer tap settings as well as alarm setpoints by performing ETAP simulations. • Supported the resolution of multiple emergent unplanned plant events onsite on short notice (i.e. transformer explosion, high voltage CCVT fire due to ferroresonance). Received praise from the client on each occasion. As a result, client selected our company as their engineer of choice for projects moving forward. Dominion Energy – Kewaunee Nuclear Power Station • Performed 125VDC safety related and non-safety related battery sizing, battery charger sizing, and DC short circuit analysis for plant emergency systems using ETAP. Developed battery load profile for postulated plant emergencies based on review of elementary drawings and station operating procedures. Plant walkdowns were conducted for data gathering. This was a first of its kind calculation utilizing ETAP at the time and as a result, became a DC system analysis subject matter expert. • Prepared study to develop settings for main generator protection and coordination. Protection scheme included transformer and generator differential (87), backup distance (21), negative phase sequence (46), over excitation protection, etc. References available upon request Page 1 of 1