SlideShare a Scribd company logo
1 of 32
Download to read offline
INDIAN STRUCTURAL INTEGRITY SOCIETY
Workshop on Structural Integrity
Assessment of Nuclear Energy Assets
9th – 10th May 2018
AERB Auditorium, Niyamak Bhavan-B,
Mumbai
Business opportunities opening
up in NPCIL PHWR programs and
technical Preparedness expected
from vendors…….
P V Philipkutty
Associate Director
(Nuclear & Mechanical Systems),
Procurement Directorate
Nuclear Power Corporation of India
Limited
Present Nuclear power scenario in India
• 22 Reactors operating under NPCIL- an
installed capacity of 6780 MWe (TAPS 1-4, RAPS 2-6,
MAPS 1&2, NAPS 1&2, KAPS 1&2, KGS 1-4 & KKNPP 1&2)
• 8 Reactors are under construction
• 2X700 MWe at KAPP 3&4 Gujarat
• 2X700 MWe at RAPP 7&8 Rajasthan 6700 MWe
• 2X700 MWe at GHAVP 1&2 at Haryana
• 2X 1000 MWe at KK NPP 3&4 Tamilnadu
Performance-Electrical generation …
Rapid growth- Expectation of GOI-People…
• Government of India has sanctioned plants to be built
in fleet mode - pressing speed button
• Government of India has also sanctioned large size
additional LWRs
• Government of India has also laid down expectations
in the form of 24 LWRs through import route
Fleet mode construction of plants
• 10 PHWR type Reactors 700 MWe each –
7000 MWe
• 2 LWR type reactors at Kudankulam NPP of
1000 MWe each – 2000 MWe
Total of 9000 MW nuclear capacity sanctioned
Future Nuclear capacity addition planned
• 24 Reactors of LWR technology as
additionality through import route –
• 6X 1650 MWe at Jaitapur, Maharashtra
• 6X 1208 MWe at Kovada, Andhra Pradesh 29.000 MWe
• 6X 1000 MWe at Mithivirdhi, Gujarat
• 6X 1000 MWe at Haripur West Bengal
Total of 29,000 MW nuclear capacity
Nuclear Power Plant Sites in India
Procurement Strategy for GHAVP-1&2
• GHAVP-1&2 will be similar to KAPP-3&4/
RAPP-7&8
• All major Nuclear Components will be directly
procured by NPCIL
• There will be approx. 25 nos. of Supply Packages
• EPC Packages will be approx. 10 nos.
• Major Site Contracts will be 03 nos.
Procurement Strategy for GHAVP-1&2
• 25 nos. of Supply Packages.
□ End Shield Package
□ Calandria Assembly
□ End Fittings and Associated Components
□ C.V Top Hatch Beams & Deck Plate Assembly
□ Air Lock Doors (MAL & AAL)
□ Zircoloy Package
□ Crane Package
□ Hoist Package
□ Drive Mechanism (AR, CR & SR)
□ Stand Pipe Thimble Package
Procurement Strategy for GHAVP-1&2
□ Bellow Package
□ Lifting Table
□ D2O Heat Exchanger Package, PDHRS-CD & ECCS
□ Pressuriser and Bleed Condenser
□ Reactor Header Assemblies
□ Steam Generator
□ Phosphor Bronze Wire-mesh supply
□ Primary Pump, Blowers & Compressors Package
□ Primary Coolant Pump Package
□ Distillation Column for D2O Upgrading Plant
□ Fuel Handling System Items
Procurement Strategy for GHAVP-1&2
 10 nos. of EPC Packages.
 Primary Package
 Common Services Package
□ Plant Water Package
□ Transformer Package
□ Diesel Generator Package
□ Nuclear Instrumentation Package
□ Turbine Island Package
□ Control Centre Instrumentation Package
□ Field Instrumentation Package
□ Main Plant Electrical Package
Procurement Strategy for GHAVP-1&2
 03 Nos Major Site Contracts.
□ Main Plant Civil Works
□ NDCT & CCW Package
□ IDCT Package
• Primary Piping Package (PPP)
Scope of major packages
SN. Description Unit Quantity
1 Feeder Pipes Kms. 27
2 CS Pipes Kms. 31.5
3 SS Pipes Kms. 83
4 SS Tubes Kms. 66
5 Custom bends Mtrs. 387
6 Feeder fittings Nos. 4700
7 CS/SS fittings Nos. 75000
8 Tanks/Vessels/Misc. Equipment Nos. 300
9 Lead Shielded Vessels Nos. 182
10 Strainers Nos. 170
11 Snubbers Nos. 80
12 Heat Exchangers (PHE + Shell & Tube) Nos. 76
13 Metallic Bellows Nos. 386
14 Filter vessels Nos. 74
15 Vee wire screen Nos. 207
16 Heaters Nos. 56
17 Sub-micron filters Nos. 22
18 Lead shots MT 95
19 Lead Bricks Nos. 38000
20 Instruments LG/FG/LMD Nos 150
• Main Plant Air Conditioning & Ventilation Package (To be part of PPP from GHAVP-
1&2 onwards)
Scope of major packages
SN Description Unit Quantity KAPP-3&4
1 Centrifugal Fans, Axial Fans & Propeller Fans Nos. 417
2 Coolers & Air Handling Unit (AHU) Nos. 204
3 Dryer Systems 12
4 Isolation Dampers Nos. 236
5 GSS Ducting Sqm. 55000
6 Grills, diffusers,dampers,louvers etc Sqm. 785
7 HDPE Filter,Felt Fabric Filter,HEPA Filter & combined HEPA and Charcoal
Filter,Filter Frames
Nos. 2000
8 Fire Dampers Nos. 917
9 Air Washer Plant Nos. 7
10 Containment pentration Bellow Nos. 64
11 Passive Catalytic Recombiner (PCRD) Nos. 180
12 Containment Filtered Venting System (CFVS) Nos. 2
• Common Services Package (CSP)
Scope of major packages
Sl. Description Unit Quantity
1 CS Pipes Kms. 75
2 SS Pipes Kms. 53
3 CS Pipe fittings Nos. 66000
4 SS Pipe fittings Nos. 56000
5 Structural material MT 2000
6 Hilti Bolts Nos. 5000
7 CM Chiller (210 TR) Nos. 04
8 VAL Chiller (930 TR) Nos. 03
9 Compressors (20 NM3/min at 8.5 kg/cm2) Nos. 03
10 Air Drying plants Nos. 04
11 Tanks & Vessels Nos 150
12 Heat Exchangers Nos. 30
13 Valves Nos. 8000
14 Diaphragm Valves Nos. 1400
15 Pumps Nos. 200
16 Ultrasonic flow meter Nos. 32
17 Strainers/steam traps Nos. 500
18 Decontamination equipment Nos. 06
19 Laundry equipment Nos. 16
SL. Description Unit Quantity
(for 2 x 700MWe)
1 285 MVA Generator Transformer (Single phase) Nos. 6
2 70 MVA Startup Transformer Nos. 4
3 70 MVA Transformer Nos. 4
4 6.6 KV Switchgear (Class-IV & III) Nos. 8 + 8
5 415 V Switchgear (Class-IV, III & II) Nos. 14 +12+4
6 415 V Motor Control Centers (Class-IV, III & II) Nos. 12+24 +4
7 4200 KW DG sets Nos. 8
8 500 KVA Uninterrupted Power Supply (UPS) Nos. 4
9 HV Power Cables Kms. 54
10 LV Power Cables Kms. 560
11 Control cables Kms. 450
12 Control Power Supplies (ACVRs) Nos. 12
13 Cable Trays and accessories Nos. 1,10,000
14 360 V DC Power batteries Bank 4
15 220 V DC Control batteries Bank 8
16 Electrical Penetration Assemblies (Power) Nos. 52
17 Electrical Penetration Assemblies (C&I) Nos. 50
18 Structural steel for Cable tray supports MT 1000
19 Main Output System Protection panels Nos. 8
Major Electrical items in 2 x 700 MWe PHWR Nuclear Power Plant (Excluding
220 KV and 400 KV Switchyard)
MAJOR SCOPE OF C&I PACKAGES
Field Instrumentation Package
SN Description Unit Quantity
1 Instruments and Accessories (Transmitters, Gauges, RTDs, Thermocouples, Sensors, Level,
Pressure, DP Switches)
Nos. 9000+
2 Cables KM 2000+
3 SS Tubing KM 100+
4Industrial System like Physical Protection System, Access Control System, Fire Alarm System,
Communication System and CCTV System
Lot Lot
5 Local Control Panels Nos. 500+
6 Junction Boxes Nos. 5000+
7 Flow Elements, Flow Meters, Gauges and PLC based systems. Lot Lot
CONTROL CENTRE INSTRUMENTATION PACKAGE
400 plus Computer based and Relay based systems, Control Room Panels and
Computer Accessories.
NUCLEAR INSTRUMENTATION PACKAGE:
40 systems related to Nuclear Instrumentation, Radiation Monitoring and SPNDs.
Setting up of Reactors in Fleet mode
 Sanction from Government of India for setting up of
7000MWe (PHWR)+ 4000MWe (LWR) in one go.
 Financial sanction is in place as on today for 8400 MWe
(PHWRs) + 4000 MWe (LWRs).
 It is first time in the history of power sector that financial
sanction is issued by Government of India for 16
reactors.
 Total cost involved is ₹2,00,000 Cr. (₹1,20,000 Cr. for
PHWRs and ₹80,000 Cr. for LWRs).
Setting up of Reactors in Fleet mode
 70% of the above cost will be for the manufacturing
sector and about 25% for the construction sector
(Leaving only IDC, salary & perks for NPCIL)
 The above job is to be completed in next 10-12 years i.e.
about ₹20,000 Cr. per year, which is more than ₹50 Cr.
per day.
 Entire nuclear industry shall take up this challenge and
get themselves organised for making it happen.
• End shields (2 nos. per Reactor unit): 20 Nos
• Calandria (1 No. per Reactor unit) : 10 Nos
• Reactor Header (8 Nos. per Reactor unit): 80 Nos
• Pressuriser (1 No. per Reactor Unit): 10 Nos
• Steam Generator (4 Nos. per Reactor unit): 40 Nos
• Primary Coolant Pumps (4 Nos. per Reactor Unit): 40 Nos
Tendering actions already initiated for all these components……
Requirement of Major Equipment for Fleet Mode
Reactors:
Fleet Mode Reactors - Schedule for First Pour of
Concrete (FPC)
• Five Years (60 Months) Construction Schedule is considered from First Pour
of Concrete (FPC) to Criticality
Fleet mode Challenges
• Siting and pre-project activities
• Enhanced industrial support in
manufacturing and project execution
• Planning for human resource- for
realizing the rapid growth plan
• Renewed approach in safety review and
regulatory clearance
For the success of this program
 Engineering input shall be frozen
 Supply chain shall be well organised
 Construction, Erection and Commissioning shall be on
time (both Civil and EPC)
Engineering Input
• Standardisation is the key; both detailed plant
engineering and equipment engineering shall remain
the same.
• GHAVP-1&2 layout, design & engineering will be
followed for all future 700 MWe type PHWRs except
for site specific changes.
• Keeping GHAVP-1&2 as the standard model, two
enveloping designs; one for soil strata and other for
rock strata have been envisaged for Seismic
Qualification process.
Supply Chain
• Nuclear Suppliers have the pivotal role to play
• We will have full transparency in ordering
• Strategy for procurement has already been
approved by NPCIL Board
• For some of the long delivery items we are
already into tendering mode
Challenges in supply chain….
• Quality issues in the recent past is an area of
concern. It is a challenge definitely Industry
need to address.
• We expect Industry to learn from experience of
KAPP-3&4 and RAPP-7&8.
• Industry shall build robust internal QA system
and Focus on First time correct approach.
• Quality shall be ensured by fool proof systems in
the shop floor / Construction sites by the
Industry – not by NPCIL QA
Challenges in supply chain….
• Simultaneous construction activities will be needed at
number of sites. Support of industry for construction
activity at such large scale is a challenge.
• Weak financials of the contractors affecting the site
progress is a major area of concern in the recent past.
Industry need to address this.
• Industry also need to address their HR issues. We
need quality manpower & expertise with the
Industries.
• NPCIL is already addressing HR issues. Major
recruitment is planned; thrust being given on NPCIL
QA manpower.
• We are also working on the feedback received from
Industry. Changes suggested in GCC and Contract
conditions are being addressed. Will be implemented
for future contracts.
Challenges in supply chain….
• Nuclear power shall be cost competitive. It is
important for all stakeholders.
• Environmentalists also identify Nuclear as a green
power today.
• If we ensure cost competitive & safe power, many
such fleet mode we can expect in near future.
Challenges in supply chain….
ProSIM R and D Pvt Ltd
Website : www.pro-sim.com
Contact us: enquiry@pro-sim.com
Indian Structural Integrity Society (InSIS)
Website: www.instint.in
Contact us: insisblr@gmail.com

More Related Content

What's hot

References NAOY 04_2014
References NAOY 04_2014References NAOY 04_2014
References NAOY 04_2014Billy Norstrom
 
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...KBC (A Yokogawa Company)
 
LFG Strategic Plan v9 - Final
LFG Strategic Plan v9 - FinalLFG Strategic Plan v9 - Final
LFG Strategic Plan v9 - FinalWill Dickinson
 
The Gas Recovery Systems - Sphere Decontamination Presentation
The Gas Recovery Systems - Sphere Decontamination PresentationThe Gas Recovery Systems - Sphere Decontamination Presentation
The Gas Recovery Systems - Sphere Decontamination PresentationGulfCoastConsulting
 
2011 deep research report on china wind turbine pitch systems industry
2011 deep research report on china wind turbine pitch systems industry2011 deep research report on china wind turbine pitch systems industry
2011 deep research report on china wind turbine pitch systems industrysmarter2011
 
Pegaso Is1 R S1 C2 Transition Project Plan Link
Pegaso Is1 R S1 C2 Transition Project Plan LinkPegaso Is1 R S1 C2 Transition Project Plan Link
Pegaso Is1 R S1 C2 Transition Project Plan Linkjacyn1
 
Capstone turbine corporation e-finity distributed generation
Capstone turbine corporation  e-finity distributed generation Capstone turbine corporation  e-finity distributed generation
Capstone turbine corporation e-finity distributed generation TNenergy
 
Europe User Conference: Albemarle FCC-SIM calibration best practices
Europe User Conference: Albemarle FCC-SIM calibration best practicesEurope User Conference: Albemarle FCC-SIM calibration best practices
Europe User Conference: Albemarle FCC-SIM calibration best practicesKBC (A Yokogawa Company)
 
Piotr Blaut Student Placement
Piotr Blaut Student PlacementPiotr Blaut Student Placement
Piotr Blaut Student PlacementPiotr Blaut
 
Europe User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationEurope User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationKBC (A Yokogawa Company)
 
Aggreko Corporate Overview 2012
Aggreko Corporate Overview 2012Aggreko Corporate Overview 2012
Aggreko Corporate Overview 2012Lewis_Scremin
 
Europe User Conference: MOL multi unit optimization of FCC and VGOHTR reactor...
Europe User Conference: MOL multi unit optimization of FCC and VGOHTR reactor...Europe User Conference: MOL multi unit optimization of FCC and VGOHTR reactor...
Europe User Conference: MOL multi unit optimization of FCC and VGOHTR reactor...KBC (A Yokogawa Company)
 
Indian Gas Scenario
Indian Gas ScenarioIndian Gas Scenario
Indian Gas ScenarioJayanta Bora
 
Sui Northern Gas Pipelines Limited
Sui Northern Gas Pipelines LimitedSui Northern Gas Pipelines Limited
Sui Northern Gas Pipelines LimitedMark Peterson
 
Preliminary Test Results: High Performance Optically Pumped Cesium Beam Clock
Preliminary Test Results: High Performance Optically Pumped Cesium Beam ClockPreliminary Test Results: High Performance Optically Pumped Cesium Beam Clock
Preliminary Test Results: High Performance Optically Pumped Cesium Beam ClockADVA
 
2012 deep research report on china wind turbine control systems industry
2012 deep research report on china wind turbine control systems industry2012 deep research report on china wind turbine control systems industry
2012 deep research report on china wind turbine control systems industrysmarter2011
 
GE ADGT Application - Virtual Pipeline
GE ADGT Application - Virtual PipelineGE ADGT Application - Virtual Pipeline
GE ADGT Application - Virtual PipelineGE코리아
 

What's hot (20)

References NAOY 04_2014
References NAOY 04_2014References NAOY 04_2014
References NAOY 04_2014
 
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
 
LFG Strategic Plan v9 - Final
LFG Strategic Plan v9 - FinalLFG Strategic Plan v9 - Final
LFG Strategic Plan v9 - Final
 
The Gas Recovery Systems - Sphere Decontamination Presentation
The Gas Recovery Systems - Sphere Decontamination PresentationThe Gas Recovery Systems - Sphere Decontamination Presentation
The Gas Recovery Systems - Sphere Decontamination Presentation
 
2011 deep research report on china wind turbine pitch systems industry
2011 deep research report on china wind turbine pitch systems industry2011 deep research report on china wind turbine pitch systems industry
2011 deep research report on china wind turbine pitch systems industry
 
Throttle Energy Business PPT
Throttle Energy Business PPTThrottle Energy Business PPT
Throttle Energy Business PPT
 
Pegaso Is1 R S1 C2 Transition Project Plan Link
Pegaso Is1 R S1 C2 Transition Project Plan LinkPegaso Is1 R S1 C2 Transition Project Plan Link
Pegaso Is1 R S1 C2 Transition Project Plan Link
 
Capstone turbine corporation e-finity distributed generation
Capstone turbine corporation  e-finity distributed generation Capstone turbine corporation  e-finity distributed generation
Capstone turbine corporation e-finity distributed generation
 
Europe User Conference: Albemarle FCC-SIM calibration best practices
Europe User Conference: Albemarle FCC-SIM calibration best practicesEurope User Conference: Albemarle FCC-SIM calibration best practices
Europe User Conference: Albemarle FCC-SIM calibration best practices
 
Piotr Blaut Student Placement
Piotr Blaut Student PlacementPiotr Blaut Student Placement
Piotr Blaut Student Placement
 
Europe User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationEurope User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluation
 
GTC
GTCGTC
GTC
 
Aggreko Corporate Overview 2012
Aggreko Corporate Overview 2012Aggreko Corporate Overview 2012
Aggreko Corporate Overview 2012
 
Europe User Conference: MOL multi unit optimization of FCC and VGOHTR reactor...
Europe User Conference: MOL multi unit optimization of FCC and VGOHTR reactor...Europe User Conference: MOL multi unit optimization of FCC and VGOHTR reactor...
Europe User Conference: MOL multi unit optimization of FCC and VGOHTR reactor...
 
Indian Gas Scenario
Indian Gas ScenarioIndian Gas Scenario
Indian Gas Scenario
 
Sui Northern Gas Pipelines Limited
Sui Northern Gas Pipelines LimitedSui Northern Gas Pipelines Limited
Sui Northern Gas Pipelines Limited
 
Tier 4 Generators
Tier 4 GeneratorsTier 4 Generators
Tier 4 Generators
 
Preliminary Test Results: High Performance Optically Pumped Cesium Beam Clock
Preliminary Test Results: High Performance Optically Pumped Cesium Beam ClockPreliminary Test Results: High Performance Optically Pumped Cesium Beam Clock
Preliminary Test Results: High Performance Optically Pumped Cesium Beam Clock
 
2012 deep research report on china wind turbine control systems industry
2012 deep research report on china wind turbine control systems industry2012 deep research report on china wind turbine control systems industry
2012 deep research report on china wind turbine control systems industry
 
GE ADGT Application - Virtual Pipeline
GE ADGT Application - Virtual PipelineGE ADGT Application - Virtual Pipeline
GE ADGT Application - Virtual Pipeline
 

Similar to Indian nuclear structural integrity society workshop

India presentation 2
India presentation 2India presentation 2
India presentation 2UKTI2014
 
Standard design bop_sep10
Standard design bop_sep10Standard design bop_sep10
Standard design bop_sep10PRABIR DATTA
 
Indian scenario of super critical power plants issues and challenges by ntpc...
Indian scenario of super critical power plants  issues and challenges by ntpc...Indian scenario of super critical power plants  issues and challenges by ntpc...
Indian scenario of super critical power plants issues and challenges by ntpc...Ajay Singhal
 
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptxCASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptxanand735393
 
Epc proposal 3x660 mw with cost analysis
Epc proposal 3x660 mw with cost analysisEpc proposal 3x660 mw with cost analysis
Epc proposal 3x660 mw with cost analysisNikhil Kumar Rai
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptsomnathmahapatra6
 
Advanced Designs of VVER Reactor Plant
Advanced Designs of VVER Reactor PlantAdvanced Designs of VVER Reactor Plant
Advanced Designs of VVER Reactor Plantmyatom
 
Project management in thermal power plants
Project management in thermal power plantsProject management in thermal power plants
Project management in thermal power plantsPrashant Alekar
 
Rejith complete cv
Rejith complete cvRejith complete cv
Rejith complete cvrejith raman
 
CV_Electrical and Instrumentation Engineer
CV_Electrical and Instrumentation EngineerCV_Electrical and Instrumentation Engineer
CV_Electrical and Instrumentation EngineerDeva Narayanan
 
Power plants in bangladesh
Power plants in bangladeshPower plants in bangladesh
Power plants in bangladeshImran Hossain
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanIBRAR AHMAD
 
2012 deep research report on global and china pv inverter industry
2012 deep research report on global and china pv inverter industry2012 deep research report on global and china pv inverter industry
2012 deep research report on global and china pv inverter industrysmarter2011
 
PDB-presentation(1).pptx
PDB-presentation(1).pptxPDB-presentation(1).pptx
PDB-presentation(1).pptxSajibDas40
 

Similar to Indian nuclear structural integrity society workshop (20)

India presentation 2
India presentation 2India presentation 2
India presentation 2
 
Standard design bop_sep10
Standard design bop_sep10Standard design bop_sep10
Standard design bop_sep10
 
Indian scenario of super critical power plants issues and challenges by ntpc...
Indian scenario of super critical power plants  issues and challenges by ntpc...Indian scenario of super critical power plants  issues and challenges by ntpc...
Indian scenario of super critical power plants issues and challenges by ntpc...
 
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptxCASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
 
Epc proposal 3x660 mw with cost analysis
Epc proposal 3x660 mw with cost analysisEpc proposal 3x660 mw with cost analysis
Epc proposal 3x660 mw with cost analysis
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
 
Advanced Designs of VVER Reactor Plant
Advanced Designs of VVER Reactor PlantAdvanced Designs of VVER Reactor Plant
Advanced Designs of VVER Reactor Plant
 
Project management in thermal power plants
Project management in thermal power plantsProject management in thermal power plants
Project management in thermal power plants
 
Rejith complete cv
Rejith complete cvRejith complete cv
Rejith complete cv
 
Morales_PES_GM_2015.pdf
Morales_PES_GM_2015.pdfMorales_PES_GM_2015.pdf
Morales_PES_GM_2015.pdf
 
CV_Electrical and Instrumentation Engineer
CV_Electrical and Instrumentation EngineerCV_Electrical and Instrumentation Engineer
CV_Electrical and Instrumentation Engineer
 
Encotec -Company Presentation_Apr 2016
Encotec -Company Presentation_Apr 2016Encotec -Company Presentation_Apr 2016
Encotec -Company Presentation_Apr 2016
 
Introduction of CO2 Reduction Technologies in Steelworks
Introduction of  CO2 Reduction Technologies in SteelworksIntroduction of  CO2 Reduction Technologies in Steelworks
Introduction of CO2 Reduction Technologies in Steelworks
 
Power plants in bangladesh
Power plants in bangladeshPower plants in bangladesh
Power plants in bangladesh
 
presentation vsv.ppt
presentation vsv.pptpresentation vsv.ppt
presentation vsv.ppt
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistan
 
2012 deep research report on global and china pv inverter industry
2012 deep research report on global and china pv inverter industry2012 deep research report on global and china pv inverter industry
2012 deep research report on global and china pv inverter industry
 
PDB-presentation(1).pptx
PDB-presentation(1).pptxPDB-presentation(1).pptx
PDB-presentation(1).pptx
 
CESC-TGS REPORT
CESC-TGS REPORTCESC-TGS REPORT
CESC-TGS REPORT
 
Bhel report block 4
Bhel report block 4Bhel report block 4
Bhel report block 4
 

More from ProSIM R & D Pvt. Ltd.

Pro sim nuclear offerings engineering design-siesmic-qualification
Pro sim nuclear offerings engineering design-siesmic-qualificationPro sim nuclear offerings engineering design-siesmic-qualification
Pro sim nuclear offerings engineering design-siesmic-qualificationProSIM R & D Pvt. Ltd.
 
ProSIM engineering consultancy offerings to nuclear power sector
ProSIM engineering consultancy offerings to nuclear power sectorProSIM engineering consultancy offerings to nuclear power sector
ProSIM engineering consultancy offerings to nuclear power sectorProSIM R & D Pvt. Ltd.
 
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...ProSIM R & D Pvt. Ltd.
 
Siesmic Evaluation for Structural Integrity Assessment of Nuclear Power Plants
Siesmic Evaluation for Structural Integrity Assessment of Nuclear Power PlantsSiesmic Evaluation for Structural Integrity Assessment of Nuclear Power Plants
Siesmic Evaluation for Structural Integrity Assessment of Nuclear Power PlantsProSIM R & D Pvt. Ltd.
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraProSIM R & D Pvt. Ltd.
 
Flow Induced Vibration of tubes and tube tanks- Kanwar Prateek
Flow Induced Vibration of tubes and tube tanks- Kanwar PrateekFlow Induced Vibration of tubes and tube tanks- Kanwar Prateek
Flow Induced Vibration of tubes and tube tanks- Kanwar PrateekProSIM R & D Pvt. Ltd.
 
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...ProSIM R & D Pvt. Ltd.
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalProSIM R & D Pvt. Ltd.
 
Simulation and Analysis of Nuclear Power plant Equipments sandhya
Simulation and Analysis of Nuclear Power plant Equipments sandhyaSimulation and Analysis of Nuclear Power plant Equipments sandhya
Simulation and Analysis of Nuclear Power plant Equipments sandhyaProSIM R & D Pvt. Ltd.
 
Seismic qualification using ASME/PNAE codes santhosh
Seismic qualification using ASME/PNAE codes santhoshSeismic qualification using ASME/PNAE codes santhosh
Seismic qualification using ASME/PNAE codes santhoshProSIM R & D Pvt. Ltd.
 
Seismic analysis as per PNAE- Mohammad salman
Seismic analysis as per PNAE- Mohammad salman Seismic analysis as per PNAE- Mohammad salman
Seismic analysis as per PNAE- Mohammad salman ProSIM R & D Pvt. Ltd.
 
Role of Materials and Corrosion -Vivekanand Kain
Role of Materials and Corrosion -Vivekanand Kain Role of Materials and Corrosion -Vivekanand Kain
Role of Materials and Corrosion -Vivekanand Kain ProSIM R & D Pvt. Ltd.
 
Seismic qualification of equipment by testing-Bhavsar
Seismic qualification of equipment by testing-Bhavsar Seismic qualification of equipment by testing-Bhavsar
Seismic qualification of equipment by testing-Bhavsar ProSIM R & D Pvt. Ltd.
 
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj ProSIM R & D Pvt. Ltd.
 
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...ProSIM R & D Pvt. Ltd.
 
Earthquake resistant design of nuclear power plant- S.m.ingole
Earthquake resistant design of nuclear power plant- S.m.ingole Earthquake resistant design of nuclear power plant- S.m.ingole
Earthquake resistant design of nuclear power plant- S.m.ingole ProSIM R & D Pvt. Ltd.
 
Frequency Response Analysis by Prof Satish IISc
Frequency Response Analysis  by Prof Satish IIScFrequency Response Analysis  by Prof Satish IISc
Frequency Response Analysis by Prof Satish IIScProSIM R & D Pvt. Ltd.
 

More from ProSIM R & D Pvt. Ltd. (20)

Pro sim nuclear offerings engineering design-siesmic-qualification
Pro sim nuclear offerings engineering design-siesmic-qualificationPro sim nuclear offerings engineering design-siesmic-qualification
Pro sim nuclear offerings engineering design-siesmic-qualification
 
ProSIM engineering consultancy offerings to nuclear power sector
ProSIM engineering consultancy offerings to nuclear power sectorProSIM engineering consultancy offerings to nuclear power sector
ProSIM engineering consultancy offerings to nuclear power sector
 
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
Seismic evaluation of nuclear power plants - ICNPG - 2018 - Invited lecture b...
 
Siesmic Evaluation for Structural Integrity Assessment of Nuclear Power Plants
Siesmic Evaluation for Structural Integrity Assessment of Nuclear Power PlantsSiesmic Evaluation for Structural Integrity Assessment of Nuclear Power Plants
Siesmic Evaluation for Structural Integrity Assessment of Nuclear Power Plants
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
 
Fracture mechanics&amp_Sundar R
Fracture mechanics&amp_Sundar RFracture mechanics&amp_Sundar R
Fracture mechanics&amp_Sundar R
 
Flow Induced Vibration of tubes and tube tanks- Kanwar Prateek
Flow Induced Vibration of tubes and tube tanks- Kanwar PrateekFlow Induced Vibration of tubes and tube tanks- Kanwar Prateek
Flow Induced Vibration of tubes and tube tanks- Kanwar Prateek
 
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
INTEGRITY REQUIREMENTS OF SHIELDING FLASK FOR TRANSPORTATION THROUGH PUBLIC D...
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R Pal
 
Simulation and Analysis of Nuclear Power plant Equipments sandhya
Simulation and Analysis of Nuclear Power plant Equipments sandhyaSimulation and Analysis of Nuclear Power plant Equipments sandhya
Simulation and Analysis of Nuclear Power plant Equipments sandhya
 
Seismic qualification using ASME/PNAE codes santhosh
Seismic qualification using ASME/PNAE codes santhoshSeismic qualification using ASME/PNAE codes santhosh
Seismic qualification using ASME/PNAE codes santhosh
 
Seismic analysis as per PNAE- Mohammad salman
Seismic analysis as per PNAE- Mohammad salman Seismic analysis as per PNAE- Mohammad salman
Seismic analysis as per PNAE- Mohammad salman
 
Role of Materials and Corrosion -Vivekanand Kain
Role of Materials and Corrosion -Vivekanand Kain Role of Materials and Corrosion -Vivekanand Kain
Role of Materials and Corrosion -Vivekanand Kain
 
Seismic qualification of equipment by testing-Bhavsar
Seismic qualification of equipment by testing-Bhavsar Seismic qualification of equipment by testing-Bhavsar
Seismic qualification of equipment by testing-Bhavsar
 
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
Safety and Criticality of Nuclear Systems-Regulatory perspectives-Bhardwaj
 
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
Overview of structural Integrity Requirements for SSCs of Nuclear Power plant...
 
Earthquake resistant design of nuclear power plant- S.m.ingole
Earthquake resistant design of nuclear power plant- S.m.ingole Earthquake resistant design of nuclear power plant- S.m.ingole
Earthquake resistant design of nuclear power plant- S.m.ingole
 
Z-set introduction presentation
Z-set introduction presentationZ-set introduction presentation
Z-set introduction presentation
 
Transformer Failures and Case Studies
Transformer Failures and Case StudiesTransformer Failures and Case Studies
Transformer Failures and Case Studies
 
Frequency Response Analysis by Prof Satish IISc
Frequency Response Analysis  by Prof Satish IIScFrequency Response Analysis  by Prof Satish IISc
Frequency Response Analysis by Prof Satish IISc
 

Recently uploaded

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

Indian nuclear structural integrity society workshop

  • 1. INDIAN STRUCTURAL INTEGRITY SOCIETY Workshop on Structural Integrity Assessment of Nuclear Energy Assets 9th – 10th May 2018 AERB Auditorium, Niyamak Bhavan-B, Mumbai
  • 2. Business opportunities opening up in NPCIL PHWR programs and technical Preparedness expected from vendors……. P V Philipkutty Associate Director (Nuclear & Mechanical Systems), Procurement Directorate Nuclear Power Corporation of India Limited
  • 3. Present Nuclear power scenario in India • 22 Reactors operating under NPCIL- an installed capacity of 6780 MWe (TAPS 1-4, RAPS 2-6, MAPS 1&2, NAPS 1&2, KAPS 1&2, KGS 1-4 & KKNPP 1&2) • 8 Reactors are under construction • 2X700 MWe at KAPP 3&4 Gujarat • 2X700 MWe at RAPP 7&8 Rajasthan 6700 MWe • 2X700 MWe at GHAVP 1&2 at Haryana • 2X 1000 MWe at KK NPP 3&4 Tamilnadu
  • 4.
  • 6. Rapid growth- Expectation of GOI-People… • Government of India has sanctioned plants to be built in fleet mode - pressing speed button • Government of India has also sanctioned large size additional LWRs • Government of India has also laid down expectations in the form of 24 LWRs through import route
  • 7. Fleet mode construction of plants • 10 PHWR type Reactors 700 MWe each – 7000 MWe • 2 LWR type reactors at Kudankulam NPP of 1000 MWe each – 2000 MWe Total of 9000 MW nuclear capacity sanctioned
  • 8. Future Nuclear capacity addition planned • 24 Reactors of LWR technology as additionality through import route – • 6X 1650 MWe at Jaitapur, Maharashtra • 6X 1208 MWe at Kovada, Andhra Pradesh 29.000 MWe • 6X 1000 MWe at Mithivirdhi, Gujarat • 6X 1000 MWe at Haripur West Bengal Total of 29,000 MW nuclear capacity
  • 9. Nuclear Power Plant Sites in India
  • 10. Procurement Strategy for GHAVP-1&2 • GHAVP-1&2 will be similar to KAPP-3&4/ RAPP-7&8 • All major Nuclear Components will be directly procured by NPCIL • There will be approx. 25 nos. of Supply Packages • EPC Packages will be approx. 10 nos. • Major Site Contracts will be 03 nos.
  • 11. Procurement Strategy for GHAVP-1&2 • 25 nos. of Supply Packages. □ End Shield Package □ Calandria Assembly □ End Fittings and Associated Components □ C.V Top Hatch Beams & Deck Plate Assembly □ Air Lock Doors (MAL & AAL) □ Zircoloy Package □ Crane Package □ Hoist Package □ Drive Mechanism (AR, CR & SR) □ Stand Pipe Thimble Package
  • 12. Procurement Strategy for GHAVP-1&2 □ Bellow Package □ Lifting Table □ D2O Heat Exchanger Package, PDHRS-CD & ECCS □ Pressuriser and Bleed Condenser □ Reactor Header Assemblies □ Steam Generator □ Phosphor Bronze Wire-mesh supply □ Primary Pump, Blowers & Compressors Package □ Primary Coolant Pump Package □ Distillation Column for D2O Upgrading Plant □ Fuel Handling System Items
  • 13. Procurement Strategy for GHAVP-1&2  10 nos. of EPC Packages.  Primary Package  Common Services Package □ Plant Water Package □ Transformer Package □ Diesel Generator Package □ Nuclear Instrumentation Package □ Turbine Island Package □ Control Centre Instrumentation Package □ Field Instrumentation Package □ Main Plant Electrical Package
  • 14. Procurement Strategy for GHAVP-1&2  03 Nos Major Site Contracts. □ Main Plant Civil Works □ NDCT & CCW Package □ IDCT Package
  • 15. • Primary Piping Package (PPP) Scope of major packages SN. Description Unit Quantity 1 Feeder Pipes Kms. 27 2 CS Pipes Kms. 31.5 3 SS Pipes Kms. 83 4 SS Tubes Kms. 66 5 Custom bends Mtrs. 387 6 Feeder fittings Nos. 4700 7 CS/SS fittings Nos. 75000 8 Tanks/Vessels/Misc. Equipment Nos. 300 9 Lead Shielded Vessels Nos. 182 10 Strainers Nos. 170 11 Snubbers Nos. 80 12 Heat Exchangers (PHE + Shell & Tube) Nos. 76 13 Metallic Bellows Nos. 386 14 Filter vessels Nos. 74 15 Vee wire screen Nos. 207 16 Heaters Nos. 56 17 Sub-micron filters Nos. 22 18 Lead shots MT 95 19 Lead Bricks Nos. 38000 20 Instruments LG/FG/LMD Nos 150
  • 16. • Main Plant Air Conditioning & Ventilation Package (To be part of PPP from GHAVP- 1&2 onwards) Scope of major packages SN Description Unit Quantity KAPP-3&4 1 Centrifugal Fans, Axial Fans & Propeller Fans Nos. 417 2 Coolers & Air Handling Unit (AHU) Nos. 204 3 Dryer Systems 12 4 Isolation Dampers Nos. 236 5 GSS Ducting Sqm. 55000 6 Grills, diffusers,dampers,louvers etc Sqm. 785 7 HDPE Filter,Felt Fabric Filter,HEPA Filter & combined HEPA and Charcoal Filter,Filter Frames Nos. 2000 8 Fire Dampers Nos. 917 9 Air Washer Plant Nos. 7 10 Containment pentration Bellow Nos. 64 11 Passive Catalytic Recombiner (PCRD) Nos. 180 12 Containment Filtered Venting System (CFVS) Nos. 2
  • 17. • Common Services Package (CSP) Scope of major packages Sl. Description Unit Quantity 1 CS Pipes Kms. 75 2 SS Pipes Kms. 53 3 CS Pipe fittings Nos. 66000 4 SS Pipe fittings Nos. 56000 5 Structural material MT 2000 6 Hilti Bolts Nos. 5000 7 CM Chiller (210 TR) Nos. 04 8 VAL Chiller (930 TR) Nos. 03 9 Compressors (20 NM3/min at 8.5 kg/cm2) Nos. 03 10 Air Drying plants Nos. 04 11 Tanks & Vessels Nos 150 12 Heat Exchangers Nos. 30 13 Valves Nos. 8000 14 Diaphragm Valves Nos. 1400 15 Pumps Nos. 200 16 Ultrasonic flow meter Nos. 32 17 Strainers/steam traps Nos. 500 18 Decontamination equipment Nos. 06 19 Laundry equipment Nos. 16
  • 18. SL. Description Unit Quantity (for 2 x 700MWe) 1 285 MVA Generator Transformer (Single phase) Nos. 6 2 70 MVA Startup Transformer Nos. 4 3 70 MVA Transformer Nos. 4 4 6.6 KV Switchgear (Class-IV & III) Nos. 8 + 8 5 415 V Switchgear (Class-IV, III & II) Nos. 14 +12+4 6 415 V Motor Control Centers (Class-IV, III & II) Nos. 12+24 +4 7 4200 KW DG sets Nos. 8 8 500 KVA Uninterrupted Power Supply (UPS) Nos. 4 9 HV Power Cables Kms. 54 10 LV Power Cables Kms. 560 11 Control cables Kms. 450 12 Control Power Supplies (ACVRs) Nos. 12 13 Cable Trays and accessories Nos. 1,10,000 14 360 V DC Power batteries Bank 4 15 220 V DC Control batteries Bank 8 16 Electrical Penetration Assemblies (Power) Nos. 52 17 Electrical Penetration Assemblies (C&I) Nos. 50 18 Structural steel for Cable tray supports MT 1000 19 Main Output System Protection panels Nos. 8 Major Electrical items in 2 x 700 MWe PHWR Nuclear Power Plant (Excluding 220 KV and 400 KV Switchyard)
  • 19. MAJOR SCOPE OF C&I PACKAGES Field Instrumentation Package SN Description Unit Quantity 1 Instruments and Accessories (Transmitters, Gauges, RTDs, Thermocouples, Sensors, Level, Pressure, DP Switches) Nos. 9000+ 2 Cables KM 2000+ 3 SS Tubing KM 100+ 4Industrial System like Physical Protection System, Access Control System, Fire Alarm System, Communication System and CCTV System Lot Lot 5 Local Control Panels Nos. 500+ 6 Junction Boxes Nos. 5000+ 7 Flow Elements, Flow Meters, Gauges and PLC based systems. Lot Lot CONTROL CENTRE INSTRUMENTATION PACKAGE 400 plus Computer based and Relay based systems, Control Room Panels and Computer Accessories. NUCLEAR INSTRUMENTATION PACKAGE: 40 systems related to Nuclear Instrumentation, Radiation Monitoring and SPNDs.
  • 20. Setting up of Reactors in Fleet mode  Sanction from Government of India for setting up of 7000MWe (PHWR)+ 4000MWe (LWR) in one go.  Financial sanction is in place as on today for 8400 MWe (PHWRs) + 4000 MWe (LWRs).  It is first time in the history of power sector that financial sanction is issued by Government of India for 16 reactors.  Total cost involved is ₹2,00,000 Cr. (₹1,20,000 Cr. for PHWRs and ₹80,000 Cr. for LWRs).
  • 21. Setting up of Reactors in Fleet mode  70% of the above cost will be for the manufacturing sector and about 25% for the construction sector (Leaving only IDC, salary & perks for NPCIL)  The above job is to be completed in next 10-12 years i.e. about ₹20,000 Cr. per year, which is more than ₹50 Cr. per day.  Entire nuclear industry shall take up this challenge and get themselves organised for making it happen.
  • 22. • End shields (2 nos. per Reactor unit): 20 Nos • Calandria (1 No. per Reactor unit) : 10 Nos • Reactor Header (8 Nos. per Reactor unit): 80 Nos • Pressuriser (1 No. per Reactor Unit): 10 Nos • Steam Generator (4 Nos. per Reactor unit): 40 Nos • Primary Coolant Pumps (4 Nos. per Reactor Unit): 40 Nos Tendering actions already initiated for all these components…… Requirement of Major Equipment for Fleet Mode Reactors:
  • 23. Fleet Mode Reactors - Schedule for First Pour of Concrete (FPC) • Five Years (60 Months) Construction Schedule is considered from First Pour of Concrete (FPC) to Criticality
  • 24. Fleet mode Challenges • Siting and pre-project activities • Enhanced industrial support in manufacturing and project execution • Planning for human resource- for realizing the rapid growth plan • Renewed approach in safety review and regulatory clearance
  • 25. For the success of this program  Engineering input shall be frozen  Supply chain shall be well organised  Construction, Erection and Commissioning shall be on time (both Civil and EPC)
  • 26. Engineering Input • Standardisation is the key; both detailed plant engineering and equipment engineering shall remain the same. • GHAVP-1&2 layout, design & engineering will be followed for all future 700 MWe type PHWRs except for site specific changes. • Keeping GHAVP-1&2 as the standard model, two enveloping designs; one for soil strata and other for rock strata have been envisaged for Seismic Qualification process.
  • 27. Supply Chain • Nuclear Suppliers have the pivotal role to play • We will have full transparency in ordering • Strategy for procurement has already been approved by NPCIL Board • For some of the long delivery items we are already into tendering mode
  • 28. Challenges in supply chain…. • Quality issues in the recent past is an area of concern. It is a challenge definitely Industry need to address. • We expect Industry to learn from experience of KAPP-3&4 and RAPP-7&8. • Industry shall build robust internal QA system and Focus on First time correct approach. • Quality shall be ensured by fool proof systems in the shop floor / Construction sites by the Industry – not by NPCIL QA
  • 29. Challenges in supply chain…. • Simultaneous construction activities will be needed at number of sites. Support of industry for construction activity at such large scale is a challenge. • Weak financials of the contractors affecting the site progress is a major area of concern in the recent past. Industry need to address this. • Industry also need to address their HR issues. We need quality manpower & expertise with the Industries.
  • 30. • NPCIL is already addressing HR issues. Major recruitment is planned; thrust being given on NPCIL QA manpower. • We are also working on the feedback received from Industry. Changes suggested in GCC and Contract conditions are being addressed. Will be implemented for future contracts. Challenges in supply chain….
  • 31. • Nuclear power shall be cost competitive. It is important for all stakeholders. • Environmentalists also identify Nuclear as a green power today. • If we ensure cost competitive & safe power, many such fleet mode we can expect in near future. Challenges in supply chain….
  • 32. ProSIM R and D Pvt Ltd Website : www.pro-sim.com Contact us: enquiry@pro-sim.com Indian Structural Integrity Society (InSIS) Website: www.instint.in Contact us: insisblr@gmail.com