Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. You are performing Earned Value Management on your project. The Cost Baseline in Earned Value
Management is also a part of:
A. Cost Estimating Baseline
B. Performance Baseline
C. Cost Measurement Baseline
D. Budget Baseline
HINT: The keyword to look here is 'performance'.
Question
3. The correct answer is B.
A Cost Baseline is a part of the Performance Baseline. The Performance Baseline is an approved
plan for the project work to which the project execution is compared, and deviations are
measured for management control. The Performance Baseline typically integrates the scope,
schedule and cost parameters of a project.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.