SlideShare a Scribd company logo
1 of 222
NUE 505A Electrical systems safety Assessment preparation
Protection devices
10 -1 1 10 10 2 10 3 4.5 Time (sec) Current (x I RATED ) B Magnetic Section Thermal Section Circuit Breaker Types
10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) 7.5 C Thermal Section New Magnetic operation Circuit Breaker Types
10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) 12 D Thermal Section New Magnetic operation Circuit Breaker Types
RCD,s
Residual Current Device  RCD Safety Switch LOAD N A/s Supply When the circuit is in good condition. (No Earth Faults) (I  active =  I  neutral) = No Flux = No Induced EMF Supply to the Load is Maintained I A I N
RCD with Earth Fault LOAD N A/s Supply  When an Earth Faults occurs. (I  active     I  neutral) = Flux in Core = Induced EMF The fault is Isolated
Safety Switch N A/s Supply Not Earthed A person can receive a shock with a “Safety Switch” installed Another point to consider: An RCD rated at 40Amps will not trip (like a C/B) if say 52Amps will to flow through the device.
3   RCD  3   LOAD  N L1 Supply LOAD L2 L3
3   RCD  1   LOAD  N Supply LOAD A
 
 
 
 
Max Demand Calculations Domestic Lighting
 
 
 
 
Max Demand Calculations Domestic Power
 
 
 
 
Max Demand Calculations Domestic Appliances
 
 
Max Demand Calculations Domestic Multi-phase
 
 
 
Max Demand Calculations Non-Domestic Lighting
A Small motel installation contains the following
 
 
 
Max Demand Calculations Non-Domestic Power
A factory has the following loading, calculate the maximum demand consideration.
 
 
Max Demand Calculations Non-Domestic Appliances
A factory has the following three-phase loads,what would be the loading for a maximum demand calculation.
 
 
Cable selection
 
 
 
 
 
Cable selection based on voltage drop
 
 
 
 
 
 
Voltage drop Single-phase
 
 
 
 
 
Voltage drop Multi-phase
 
 
 
Conductor size based on voltage drop
 
 
 
 
 
 
 
Overall multi-phase voltage drop calculation
 
 
 
Fault loop impedance
AS/NZ 3000:2000 - 1.7.4.3.3 ,[object Object],[object Object],[object Object],[object Object],6.3.3.2.1 6.3.3.2.2 Amendment AS/NZS 3000:2000
The Fault Loop  1. The impedance needs to be low enough, to allow a high enough fault current, to operate the protective device, within a given time period. (6.3.3.2.2)  2. The Earth Loop Impedance is matched to the Protective Device Tripping Characteristics. 3 Phase Supply N/L
Earth System ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Earth System 1 Measure the Fault Loop Impedance… ,[object Object],[object Object]
Earth System ♦  Z LOOP  =  Z ACTIVE  + Z EARTH  + Z  NEUTRAL  + Z  TX ♦  All these will limit current and dictate the fault current that will flow. Load N/L 16A MEN Link must be left intact
Earth System AS3000: Wiring Rules
Earth System
10 -1 1 10 10 2 10 3 4 Time (sec) Current (x I RATED ) B Circuit Breaker Types 1x Magnetic Section Thermal Section
10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) Circuit Breaker Types 1x 7.5 C Thermal Section New Magnetic operation
10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) Circuit Breaker Types 1x 12.5 D Thermal Section New Magnetic operation
Earth System Load 16A N/L MEN Link must be left intact
Earth System Load 16A N/L Active Earth MEN Link must be left intact
 
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Earth System 1 Measure the Fault Loop Impedance… ,[object Object],[object Object],2. Calculate the maximum length allowable  for the Final Sub Circuit and come in under that.
Earth System Load 16A N/L With 80% of voltage drop here in a fault,  the FSC must have 80% of the total Fault Loop Impedance. Where the length and CSA of the mains is  not known, we may assume that 80% of the voltage drop under fault conditions will occur in the final sub-circuit (B5.2.1b).
0.8 x V NOM  x CSA ACTIVE  x CSA  EARTH L MAX  =  I TRIP  x    x (CSA ACTIVE  + CSA  EARTH )    = 22.5 x 10 -3   ohm-mm 2 /metre for Copper = 36 x 10 -3  ohm-mm 2 /metre   for Aluminium ,[object Object],[object Object],[object Object],[object Object],(Page 237 AS3000)
 
Earth System 1 Measure the Fault Loop Impedance… ,[object Object],[object Object],2. Calculate the maximum length allowable  for the Final Sub Circuit and come in under that. 3.  Measure the A/A-E impedance. (Compare it to Table 3.2 AS3017)
AS3017: Testing and Inspection Guidlines ,[object Object],[object Object],[object Object],[object Object]
MAIN SWITCHBOARD Load
But what if the cable/CB size is not there on that table?
Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away.  C/B is 400A type “C”.  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…  7.  Measure the actual loop impedance. MAIN SWITCHBOARD Load Z = V/I A V I    5A
[object Object],[object Object],[object Object],Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…  Note that including X L  of the cable only  comes into play above 120mm 2 Z R X L
[object Object],[object Object],[object Object],Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…  ,[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…
[object Object],[object Object],[object Object],[object Object],Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…  R A  + R E  =  0.0298  X A  + X E  = 0.02065  Z =  0.0362  R ACTIVE R EARTH X ACTIVE X EARTH
4.  Is Loop Z < Maximum Allowable Z? Last Step…: ,[object Object],[object Object],Z =  0.0362  Z = 0.0512 
Remember the last question? Q:  Why do we want a low resistance earth wire?  To CREATE a high enough fault current to trip the protective device. To ensure that we do create a high enough fault current, fault loop impedance must be low enough.
AS3017: Testing and Inspection Guidlines
A Simplified  Circuit We need to look at a complete loop (circuit) 3 Phase Supply The current path includes the: Supply Transformer, Distribution System, Mains, Protection Device, Final Sub-Circuit including the Load N/L
B5.1 Maximum Circuit Length ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
3 Phase Supply There will always be more than 80% of the Nominal Voltage AS/NZ3000:2000  B5.2.1 b Zext Zint Zint =  0.8 Uo I a B5.2.1
Isolation, disconnection and reconnection procedures
Safe Isolation   ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
 
MEN Connection
MEN SYSTEM
Recent studies have shown that 95% of electricians do not fully understand the MEN system.  This figure comes from the Electrical Contractors Association of Queensland who were conducting training sessions throughout Queensland during 1998.  They asked electricians to draw a MEN system and explain it. Only 5% could!!! MEN System
MEN Connection Consumer Mains MAIN SWITCHBOARD Circuit Protective Devices Earth Link Neutral Link Main Switch
MEN Connection Circuit Protective Devices Consumer Mains MAIN SWITCHBOARD Neutral Link Main Switch So why do we earth the  neutral at the board?
Load Direct Earthing System 16A Q: Will the  fuse blow? FAULT R TOTAL = 23.5  I FAULT  = V/R = 240/23.5    10A 0.3  0.2  23 
Load MEN Earthing System 0.3  0.2  16A R TOTAL = 1  Q: Will the  fuse blow? 0.5  I FAULT  = V/R = 240/1 = 240A N/L FAULT R RETURN  = 0.5//23      0.5  23 
Q:  Why do we want a low resistance earth wire?  To CREATE a high enough fault current to trip the protective device.
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Earth Link Neutral Link NORMAL LOAD CURRENT Typical  Earth stake to Earth resistance  = 30   - 2k  Main Switch Load Low R Consumer Mains
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Earth Link Neutral Link FAULT CURRENT Main Switch Load A Low Resistance earth  CREATES A high fault current. Low R
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link What are the values given by AS3000 on earth resistance? Main Switch Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link 2   maximum 2   maximum Main Switch Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link Main Switch < 0.5  (6.3.3.2.2) Load “ The resistance of the protective  earthing conductors shall be  low enough to permit the  passage of current  necessary to operate the  overcurrent protective device” (6.3.3.2.2)
Why Test
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Earth Link Neutral Link Load OPEN  CIRCUIT MEN Connection
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Earth Link Neutral Link NORMAL LOAD CURRENT Everything operates  OK!!! Load
THEREFORE FAULT  CURRENT WILL BE VERY LOW MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT But RESISTANCE TO EARTH IS  USUALLY HIGH. Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT AND PROTECTION WILL NOT TRIP. Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT NOTE  THAT IF ACTIVE IS SHORTED TO EARTH, ALL EARTHS ARE LIVE!!! Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT NOTE  ALSO THAT UNDER NORMAL CONDITIONS EVERYTHING ELSE WILL STILL WORK OK!!! Load
Open Circuit MEN Connection MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains Neutral Link DISTRIBUTION BOARD 3 Circuit Protective  Devices Earthing Bar DISTRIBUTION BOARD  2 Circuit Protective Devices Neutral Link Earthing Bar Main  Earthing  Conductor Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD  1 Main Switch What happens on  Distribution Boards  when the MSB MEN link open-circuits ? AS3000 5.6.6b(iv)
[object Object]
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link A N LIVEN UP:  -Earth stake -Water pipes -Taps -Sink -Cases of appliances Load
MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains ` Neutral Link DISTRIBUTION BOARD 3 Circuit Protective  Devices Earthing Bar DISTRIBUTION BOARD  2 Circuit Protective Devices Neutral Link Earthing Bar Main  Earthing  Conductor Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD  1 Main Switch What happens on  Distribution Boards  when Main Active  and Main Neutral are swapped? N A
[object Object],[object Object]
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link OPEN  CIRCUIT Neutral Load
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link LOAD CURRENT Load
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link LOAD CURRENT Load
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Lo load Resistance Hi stake - earth Resistance: 30   - 2k  Load Voltages... High Voltage Low Voltage High Voltage  on  Earth System
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Lo load Resistance Hi stake - earth Resistance: 30   - 2k  High Voltage Low Voltage Livens: -Taps, -Sinks -Water pipes -Metal cases of appliances Load Voltages... High Voltage  on  Earth System
Q: What causes “tingles” on taps? MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads
Q: What causes “tingles” on taps? VD N =4V MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads
Q: What causes “tingles” on taps? MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads 4V 0V
Testing
TEST  EQUIPMENT  REQUIRED  (AS3017 1.6.2) ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
TEST  EQUIPMENT  REQUIRED  (AS3017 1.6.2) ,[object Object],[object Object],[object Object],[object Object],[object Object]
TESTS ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Step 1: Visual Examination
General Requirements Clause No. What to look for 2.9.6  No exposed live parts.  E.g. no excessive removal of insulation at terminations, terminal covers in place etc. Double insulation maintained where required.  E.g. no single insulation in ceiling above light fittings, no more than 100mm single insulation in wall behind accessories, insulating shrouds installed where required. 1.9 All equipment is approved/compliant with Australian Standards and in good condition.  E.g. no unsafe/damaged or non-compliant equipment installed.
Consumer Mains Clause No. What to look for 3.4.1 Consumers Mains should be able to carry the maximum demand current of the installation with some capacity to spare.  As a guide: 16mm2 (or parallel 6mm2) for overhead mains, 10mm2 for underground mains.
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Initial Procedures ,[object Object],[object Object],[object Object]
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light
[object Object],[object Object],[object Object],[object Object],STEP 2: Earth Continuity
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light Known resistance
STEP 3: Insulation Resistance ,[object Object],[object Object],[object Object],[object Object],1. Consumer Mains: Disconnect any service bonding conductor:
STEP 3: Insulation Resistance ,[object Object],[object Object],[object Object],2. Final Subcircuits: With all C/B’s ON or fuse wedges IN, and all switches in the installation ON:
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light Switched Active
STEP 3: Insulation Resistance ,[object Object]
[object Object],[object Object],[object Object],[object Object],STEP 4: Polarity Tests
STEP 5: Correct Circuit Connections ,[object Object],[object Object]
MEN Connection MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains ` Neutral Link DISTRIBUTION BOARD 3 Circuit Protective  Devices Earthing Bar DISTRIBUTION BOARD  2 Circuit Protective Devices Neutral  Link Earthing Bar Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD  1 Main Switch A N Thank You The End
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety

More Related Content

What's hot

Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsPower System Operation
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protectionsrini09
 
Transformer maintenance
Transformer maintenance Transformer maintenance
Transformer maintenance Molla Morshad
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
 
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSimple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSARAVANAN A
 
ETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardHimmelstern
 
ETAP - Iec 60364 - cable sizing (dimensionamiento de cables)
ETAP - Iec 60364 - cable sizing (dimensionamiento de cables)ETAP - Iec 60364 - cable sizing (dimensionamiento de cables)
ETAP - Iec 60364 - cable sizing (dimensionamiento de cables)Himmelstern
 
7SA522 Distance Protection Relay For Transmission Lines
7SA522 Distance Protection Relay For Transmission Lines7SA522 Distance Protection Relay For Transmission Lines
7SA522 Distance Protection Relay For Transmission Linesashwini reliserv
 
Substation Maintenance
Substation MaintenanceSubstation Maintenance
Substation Maintenancekarikalan123
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
 
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docxELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docxDwarika Bhushan Sharma
 
cable ampacity calculations- IEC
cable ampacity calculations- IECcable ampacity calculations- IEC
cable ampacity calculations- IECJoe Khan
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guideSlides Hub
 
3 phase transformer protection
3 phase transformer protection3 phase transformer protection
3 phase transformer protectionHimanshu Paghdal
 

What's hot (20)

Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protection
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 
Transformer maintenance
Transformer maintenance Transformer maintenance
Transformer maintenance
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSimple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
 
ETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardETAP - Short circuit ansi standard
ETAP - Short circuit ansi standard
 
ETAP - Iec 60364 - cable sizing (dimensionamiento de cables)
ETAP - Iec 60364 - cable sizing (dimensionamiento de cables)ETAP - Iec 60364 - cable sizing (dimensionamiento de cables)
ETAP - Iec 60364 - cable sizing (dimensionamiento de cables)
 
7SA522 Distance Protection Relay For Transmission Lines
7SA522 Distance Protection Relay For Transmission Lines7SA522 Distance Protection Relay For Transmission Lines
7SA522 Distance Protection Relay For Transmission Lines
 
Substation Maintenance
Substation MaintenanceSubstation Maintenance
Substation Maintenance
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
Arc Flash Solutions
Arc Flash SolutionsArc Flash Solutions
Arc Flash Solutions
 
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
BUS BAR  PROTECTION PPT BY:-R.K.PANDITBUS BAR  PROTECTION PPT BY:-R.K.PANDIT
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
 
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docxELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
 
cable ampacity calculations- IEC
cable ampacity calculations- IECcable ampacity calculations- IEC
cable ampacity calculations- IEC
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guide
 
3 phase transformer protection
3 phase transformer protection3 phase transformer protection
3 phase transformer protection
 

Similar to Electrical Systems Safety

Fire Pump Short Circuit and WIC Considerations
Fire Pump Short Circuit and WIC ConsiderationsFire Pump Short Circuit and WIC Considerations
Fire Pump Short Circuit and WIC ConsiderationsJames S Nasby
 
1. Determine the voltage drop at the motor frame for an earth .docx
1. Determine the voltage drop at the motor frame for an earth .docx1. Determine the voltage drop at the motor frame for an earth .docx
1. Determine the voltage drop at the motor frame for an earth .docxjackiewalcutt
 
3_Overcurrent Protection.pdf
3_Overcurrent Protection.pdf3_Overcurrent Protection.pdf
3_Overcurrent Protection.pdfLiewChiaPing
 
Bsf earthing system calculation-1
Bsf earthing system calculation-1Bsf earthing system calculation-1
Bsf earthing system calculation-1Raymund Cortez
 
Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.Mustafa Ismail
 
Si Intro(100413)
Si Intro(100413)Si Intro(100413)
Si Intro(100413)imsong
 
Introduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptIntroduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptAhmed Ramadan
 
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptxCHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptxLiewChiaPing
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersThorne & Derrick International
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)saurabhVEC
 
Panasonic SA-AK450P SA-AK450PC - Manual de servicio
Panasonic SA-AK450P SA-AK450PC - Manual de servicioPanasonic SA-AK450P SA-AK450PC - Manual de servicio
Panasonic SA-AK450P SA-AK450PC - Manual de servicioAnonimo Goncen
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)ingcortez
 
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...Jobin Abraham
 

Similar to Electrical Systems Safety (20)

Fire Pump Short Circuit and WIC Considerations
Fire Pump Short Circuit and WIC ConsiderationsFire Pump Short Circuit and WIC Considerations
Fire Pump Short Circuit and WIC Considerations
 
CT and VT.pptx
CT and VT.pptxCT and VT.pptx
CT and VT.pptx
 
Lecture 18
Lecture 18Lecture 18
Lecture 18
 
1. Determine the voltage drop at the motor frame for an earth .docx
1. Determine the voltage drop at the motor frame for an earth .docx1. Determine the voltage drop at the motor frame for an earth .docx
1. Determine the voltage drop at the motor frame for an earth .docx
 
DC Component of Fault Current
DC Component of Fault CurrentDC Component of Fault Current
DC Component of Fault Current
 
3_Overcurrent Protection.pdf
3_Overcurrent Protection.pdf3_Overcurrent Protection.pdf
3_Overcurrent Protection.pdf
 
Bsf earthing system calculation-1
Bsf earthing system calculation-1Bsf earthing system calculation-1
Bsf earthing system calculation-1
 
Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.
 
Si Intro(100413)
Si Intro(100413)Si Intro(100413)
Si Intro(100413)
 
Introduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptIntroduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.ppt
 
Ehv line design
Ehv line designEhv line design
Ehv line design
 
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptxCHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
 
Lecture_18.ppt
Lecture_18.pptLecture_18.ppt
Lecture_18.ppt
 
ECNG 6503 #2
ECNG 6503  #2ECNG 6503  #2
ECNG 6503 #2
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
Panasonic SA-AK450P SA-AK450PC - Manual de servicio
Panasonic SA-AK450P SA-AK450PC - Manual de servicioPanasonic SA-AK450P SA-AK450PC - Manual de servicio
Panasonic SA-AK450P SA-AK450PC - Manual de servicio
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)
 
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
 
Sub station design
Sub station designSub station design
Sub station design
 

More from Talia Carbis

4.1.13 Light Demand 3
4.1.13 Light Demand 34.1.13 Light Demand 3
4.1.13 Light Demand 3Talia Carbis
 
4.1.12 Light Demand 2 Table Part2
4.1.12 Light Demand 2 Table Part24.1.12 Light Demand 2 Table Part2
4.1.12 Light Demand 2 Table Part2Talia Carbis
 
4.1.11 Light Demand 2 Table
4.1.11 Light Demand 2 Table4.1.11 Light Demand 2 Table
4.1.11 Light Demand 2 TableTalia Carbis
 
4.1.10 Light Demand 2
4.1.10 Light Demand 24.1.10 Light Demand 2
4.1.10 Light Demand 2Talia Carbis
 
4.1.9 Light Demand 1
4.1.9 Light Demand 14.1.9 Light Demand 1
4.1.9 Light Demand 1Talia Carbis
 
4.1.8 Light Demand
4.1.8 Light Demand4.1.8 Light Demand
4.1.8 Light DemandTalia Carbis
 
4.1.7 Example Domestic 3
4.1.7 Example Domestic 34.1.7 Example Domestic 3
4.1.7 Example Domestic 3Talia Carbis
 
4.1.6 Example Domestic 2
4.1.6 Example Domestic 24.1.6 Example Domestic 2
4.1.6 Example Domestic 2Talia Carbis
 
4.1.5 Example Domestic 1
4.1.5 Example Domestic 14.1.5 Example Domestic 1
4.1.5 Example Domestic 1Talia Carbis
 
4.1.3 Example Solution Three
4.1.3 Example Solution Three4.1.3 Example Solution Three
4.1.3 Example Solution ThreeTalia Carbis
 
4.1.2 Example Three
4.1.2 Example Three4.1.2 Example Three
4.1.2 Example ThreeTalia Carbis
 
4.1.1 Example Single
4.1.1 Example Single4.1.1 Example Single
4.1.1 Example SingleTalia Carbis
 
14.5.4 Example 1 Part 1
14.5.4 Example 1 Part 114.5.4 Example 1 Part 1
14.5.4 Example 1 Part 1Talia Carbis
 
14.5.8 Example 1 Part 5
14.5.8 Example 1 Part 514.5.8 Example 1 Part 5
14.5.8 Example 1 Part 5Talia Carbis
 

More from Talia Carbis (20)

7.4.6 slip
7.4.6 slip7.4.6 slip
7.4.6 slip
 
4.2.1 Better Load
4.2.1 Better Load4.2.1 Better Load
4.2.1 Better Load
 
4.1.13 Light Demand 3
4.1.13 Light Demand 34.1.13 Light Demand 3
4.1.13 Light Demand 3
 
4.1.12 Light Demand 2 Table Part2
4.1.12 Light Demand 2 Table Part24.1.12 Light Demand 2 Table Part2
4.1.12 Light Demand 2 Table Part2
 
4.1.11 Light Demand 2 Table
4.1.11 Light Demand 2 Table4.1.11 Light Demand 2 Table
4.1.11 Light Demand 2 Table
 
4.1.10 Light Demand 2
4.1.10 Light Demand 24.1.10 Light Demand 2
4.1.10 Light Demand 2
 
4.1.9 Light Demand 1
4.1.9 Light Demand 14.1.9 Light Demand 1
4.1.9 Light Demand 1
 
4.1.8 Light Demand
4.1.8 Light Demand4.1.8 Light Demand
4.1.8 Light Demand
 
4.1.7 Example Domestic 3
4.1.7 Example Domestic 34.1.7 Example Domestic 3
4.1.7 Example Domestic 3
 
4.1.6 Example Domestic 2
4.1.6 Example Domestic 24.1.6 Example Domestic 2
4.1.6 Example Domestic 2
 
4.1.5 Example Domestic 1
4.1.5 Example Domestic 14.1.5 Example Domestic 1
4.1.5 Example Domestic 1
 
4.1.4 Step 2
4.1.4 Step 24.1.4 Step 2
4.1.4 Step 2
 
4.1.3 Example Solution Three
4.1.3 Example Solution Three4.1.3 Example Solution Three
4.1.3 Example Solution Three
 
4.1.2 Example Three
4.1.2 Example Three4.1.2 Example Three
4.1.2 Example Three
 
4.1.1 Example Single
4.1.1 Example Single4.1.1 Example Single
4.1.1 Example Single
 
5.4.4 LR Circuits
5.4.4 LR Circuits5.4.4 LR Circuits
5.4.4 LR Circuits
 
14.5.4 Example 1 Part 1
14.5.4 Example 1 Part 114.5.4 Example 1 Part 1
14.5.4 Example 1 Part 1
 
14.5.3 Improve
14.5.3 Improve14.5.3 Improve
14.5.3 Improve
 
14.1.2 TRA Power
14.1.2 TRA Power14.1.2 TRA Power
14.1.2 TRA Power
 
14.5.8 Example 1 Part 5
14.5.8 Example 1 Part 514.5.8 Example 1 Part 5
14.5.8 Example 1 Part 5
 

Recently uploaded

Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Angeliki Cooney
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...apidays
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...apidays
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...apidays
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamUiPathCommunity
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Bhuvaneswari Subramani
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxRustici Software
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsNanddeep Nachan
 

Recently uploaded (20)

Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 

Electrical Systems Safety

  • 1. NUE 505A Electrical systems safety Assessment preparation
  • 2.
  • 4. 10 -1 1 10 10 2 10 3 4.5 Time (sec) Current (x I RATED ) B Magnetic Section Thermal Section Circuit Breaker Types
  • 5. 10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) 7.5 C Thermal Section New Magnetic operation Circuit Breaker Types
  • 6. 10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) 12 D Thermal Section New Magnetic operation Circuit Breaker Types
  • 8. Residual Current Device RCD Safety Switch LOAD N A/s Supply When the circuit is in good condition. (No Earth Faults) (I active = I neutral) = No Flux = No Induced EMF Supply to the Load is Maintained I A I N
  • 9. RCD with Earth Fault LOAD N A/s Supply  When an Earth Faults occurs. (I active  I neutral) = Flux in Core = Induced EMF The fault is Isolated
  • 10. Safety Switch N A/s Supply Not Earthed A person can receive a shock with a “Safety Switch” installed Another point to consider: An RCD rated at 40Amps will not trip (like a C/B) if say 52Amps will to flow through the device.
  • 11. 3  RCD 3  LOAD N L1 Supply LOAD L2 L3
  • 12. 3  RCD 1  LOAD N Supply LOAD A
  • 13.  
  • 14.  
  • 15.  
  • 16.  
  • 17. Max Demand Calculations Domestic Lighting
  • 18.  
  • 19.  
  • 20.  
  • 21.  
  • 22. Max Demand Calculations Domestic Power
  • 23.  
  • 24.  
  • 25.  
  • 26.  
  • 27. Max Demand Calculations Domestic Appliances
  • 28.  
  • 29.  
  • 30. Max Demand Calculations Domestic Multi-phase
  • 31.  
  • 32.  
  • 33.  
  • 34. Max Demand Calculations Non-Domestic Lighting
  • 35. A Small motel installation contains the following
  • 36.  
  • 37.  
  • 38.  
  • 39. Max Demand Calculations Non-Domestic Power
  • 40. A factory has the following loading, calculate the maximum demand consideration.
  • 41.  
  • 42.  
  • 43. Max Demand Calculations Non-Domestic Appliances
  • 44. A factory has the following three-phase loads,what would be the loading for a maximum demand calculation.
  • 45.  
  • 46.  
  • 48.  
  • 49.  
  • 50.  
  • 51.  
  • 52.  
  • 53. Cable selection based on voltage drop
  • 54.  
  • 55.  
  • 56.  
  • 57.  
  • 58.  
  • 59.  
  • 61.  
  • 62.  
  • 63.  
  • 64.  
  • 65.  
  • 67.  
  • 68.  
  • 69.  
  • 70. Conductor size based on voltage drop
  • 71.  
  • 72.  
  • 73.  
  • 74.  
  • 75.  
  • 76.  
  • 77.  
  • 78. Overall multi-phase voltage drop calculation
  • 79.  
  • 80.  
  • 81.  
  • 83.
  • 84. The Fault Loop 1. The impedance needs to be low enough, to allow a high enough fault current, to operate the protective device, within a given time period. (6.3.3.2.2) 2. The Earth Loop Impedance is matched to the Protective Device Tripping Characteristics. 3 Phase Supply N/L
  • 85.
  • 86.
  • 87. Earth System ♦ Z LOOP = Z ACTIVE + Z EARTH + Z NEUTRAL + Z TX ♦ All these will limit current and dictate the fault current that will flow. Load N/L 16A MEN Link must be left intact
  • 88. Earth System AS3000: Wiring Rules
  • 90. 10 -1 1 10 10 2 10 3 4 Time (sec) Current (x I RATED ) B Circuit Breaker Types 1x Magnetic Section Thermal Section
  • 91. 10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) Circuit Breaker Types 1x 7.5 C Thermal Section New Magnetic operation
  • 92. 10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) Circuit Breaker Types 1x 12.5 D Thermal Section New Magnetic operation
  • 93. Earth System Load 16A N/L MEN Link must be left intact
  • 94. Earth System Load 16A N/L Active Earth MEN Link must be left intact
  • 95.  
  • 96.
  • 97.
  • 98. Earth System Load 16A N/L With 80% of voltage drop here in a fault, the FSC must have 80% of the total Fault Loop Impedance. Where the length and CSA of the mains is not known, we may assume that 80% of the voltage drop under fault conditions will occur in the final sub-circuit (B5.2.1b).
  • 99.
  • 100.  
  • 101.
  • 102.
  • 104. But what if the cable/CB size is not there on that table?
  • 105.
  • 106. Say, 300mm 2 orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away… 7. Measure the actual loop impedance. MAIN SWITCHBOARD Load Z = V/I A V I  5A
  • 107.
  • 108.
  • 109.
  • 110.
  • 111.
  • 112. Remember the last question? Q: Why do we want a low resistance earth wire?  To CREATE a high enough fault current to trip the protective device. To ensure that we do create a high enough fault current, fault loop impedance must be low enough.
  • 113. AS3017: Testing and Inspection Guidlines
  • 114. A Simplified Circuit We need to look at a complete loop (circuit) 3 Phase Supply The current path includes the: Supply Transformer, Distribution System, Mains, Protection Device, Final Sub-Circuit including the Load N/L
  • 115.
  • 116. 3 Phase Supply There will always be more than 80% of the Nominal Voltage AS/NZ3000:2000 B5.2.1 b Zext Zint Zint = 0.8 Uo I a B5.2.1
  • 117. Isolation, disconnection and reconnection procedures
  • 118.
  • 119.  
  • 122. Recent studies have shown that 95% of electricians do not fully understand the MEN system. This figure comes from the Electrical Contractors Association of Queensland who were conducting training sessions throughout Queensland during 1998. They asked electricians to draw a MEN system and explain it. Only 5% could!!! MEN System
  • 123. MEN Connection Consumer Mains MAIN SWITCHBOARD Circuit Protective Devices Earth Link Neutral Link Main Switch
  • 124. MEN Connection Circuit Protective Devices Consumer Mains MAIN SWITCHBOARD Neutral Link Main Switch So why do we earth the neutral at the board?
  • 125. Load Direct Earthing System 16A Q: Will the fuse blow? FAULT R TOTAL = 23.5  I FAULT = V/R = 240/23.5  10A 0.3  0.2  23 
  • 126. Load MEN Earthing System 0.3  0.2  16A R TOTAL = 1  Q: Will the fuse blow? 0.5  I FAULT = V/R = 240/1 = 240A N/L FAULT R RETURN = 0.5//23  0.5  23 
  • 127. Q: Why do we want a low resistance earth wire?  To CREATE a high enough fault current to trip the protective device.
  • 128. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Earth Link Neutral Link NORMAL LOAD CURRENT Typical Earth stake to Earth resistance = 30  - 2k  Main Switch Load Low R Consumer Mains
  • 129. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Earth Link Neutral Link FAULT CURRENT Main Switch Load A Low Resistance earth CREATES A high fault current. Low R
  • 130. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link What are the values given by AS3000 on earth resistance? Main Switch Load
  • 131. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link 2  maximum 2  maximum Main Switch Load
  • 132. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link Main Switch < 0.5  (6.3.3.2.2) Load “ The resistance of the protective earthing conductors shall be low enough to permit the passage of current necessary to operate the overcurrent protective device” (6.3.3.2.2)
  • 134. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Earth Link Neutral Link Load OPEN CIRCUIT MEN Connection
  • 135. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Earth Link Neutral Link NORMAL LOAD CURRENT Everything operates OK!!! Load
  • 136. THEREFORE FAULT CURRENT WILL BE VERY LOW MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT But RESISTANCE TO EARTH IS USUALLY HIGH. Load
  • 137. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT AND PROTECTION WILL NOT TRIP. Load
  • 138. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT NOTE THAT IF ACTIVE IS SHORTED TO EARTH, ALL EARTHS ARE LIVE!!! Load
  • 139. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT NOTE ALSO THAT UNDER NORMAL CONDITIONS EVERYTHING ELSE WILL STILL WORK OK!!! Load
  • 140. Open Circuit MEN Connection MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains Neutral Link DISTRIBUTION BOARD 3 Circuit Protective Devices Earthing Bar DISTRIBUTION BOARD 2 Circuit Protective Devices Neutral Link Earthing Bar Main Earthing Conductor Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD 1 Main Switch What happens on Distribution Boards when the MSB MEN link open-circuits ? AS3000 5.6.6b(iv)
  • 141.
  • 142. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link A N LIVEN UP: -Earth stake -Water pipes -Taps -Sink -Cases of appliances Load
  • 143. MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains ` Neutral Link DISTRIBUTION BOARD 3 Circuit Protective Devices Earthing Bar DISTRIBUTION BOARD 2 Circuit Protective Devices Neutral Link Earthing Bar Main Earthing Conductor Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD 1 Main Switch What happens on Distribution Boards when Main Active and Main Neutral are swapped? N A
  • 144.
  • 145. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link OPEN CIRCUIT Neutral Load
  • 146. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link LOAD CURRENT Load
  • 147. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link LOAD CURRENT Load
  • 148. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Lo load Resistance Hi stake - earth Resistance: 30  - 2k  Load Voltages... High Voltage Low Voltage High Voltage on Earth System
  • 149. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Lo load Resistance Hi stake - earth Resistance: 30  - 2k  High Voltage Low Voltage Livens: -Taps, -Sinks -Water pipes -Metal cases of appliances Load Voltages... High Voltage on Earth System
  • 150. Q: What causes “tingles” on taps? MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads
  • 151. Q: What causes “tingles” on taps? VD N =4V MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads
  • 152. Q: What causes “tingles” on taps? MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads 4V 0V
  • 154.
  • 155.
  • 156.
  • 157.
  • 158. General Requirements Clause No. What to look for 2.9.6 No exposed live parts. E.g. no excessive removal of insulation at terminations, terminal covers in place etc. Double insulation maintained where required. E.g. no single insulation in ceiling above light fittings, no more than 100mm single insulation in wall behind accessories, insulating shrouds installed where required. 1.9 All equipment is approved/compliant with Australian Standards and in good condition. E.g. no unsafe/damaged or non-compliant equipment installed.
  • 159. Consumer Mains Clause No. What to look for 3.4.1 Consumers Mains should be able to carry the maximum demand current of the installation with some capacity to spare. As a guide: 16mm2 (or parallel 6mm2) for overhead mains, 10mm2 for underground mains.
  • 160.
  • 161.
  • 162.
  • 163.
  • 164.
  • 165.
  • 166. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light
  • 167.
  • 168. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light Known resistance
  • 169.
  • 170.
  • 171. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light
  • 172. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light Switched Active
  • 173.
  • 174.
  • 175.
  • 176. MEN Connection MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains ` Neutral Link DISTRIBUTION BOARD 3 Circuit Protective Devices Earthing Bar DISTRIBUTION BOARD 2 Circuit Protective Devices Neutral Link Earthing Bar Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD 1 Main Switch A N Thank You The End