SlideShare a Scribd company logo
1 of 11
Download to read offline
1
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
Part 5: Snubber Performance Measurements
David D. Shipp, PE
Fellow, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
Thomas J. Dionise, PE
Senior Member, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
2
2
Snubber Performance Measurements
• Data Center
• Purpose of Measurements
• Test procedures
• Medium voltage measurements
• Selecting a meter
• Using voltage dividers
• Safety concerns
• Data Center challenges
2
3
3
Purpose of Performance Measurements
• Ensure the proper operation of the snubbers
• Measure the transient overvoltage waveforms at the transformer
primary
• produced during switching of the primary vacuum circuit breakers
• verify they do not exhibit high frequency transients (magnitude, rate-
of-rise and frequency).
• Specify the meters and voltage dividers needed for the transient
measurement
• guide electrical contractor with their installation
• electrical contractor to operate all equipment following the test
procedure
• After completion of the site monitoring during the snubber tests,
analyze the measurement data and document the test results in
an engineering report.
4
4
Data Center
Highlights
• Tier III
• LEEDS Certified
• 12.5MVA Capacity
• 13.2KV Ring Bus
3
5
5
Data Center – Measurement Locations
Vacuum
Breaker
Short
Cable
Cast-Coil
Transformer
6
6
Data Center – Electrical Highlights
• 2 x 24.9 kV lines from Factory Shoals and Buzzard
Roast
• 2 x 12.5 MVA transformers
• 13.2 kV “ring-bus” configuration
• MSA and MSB and generator bus GPS
• Vacuum circuit breakers – 600A mains & ties, 200A feeders
• 3 x 2250 KW generators
• 6 x 3750KVA cast coil transformers, 90kV BIL
• 3 x DE Subs CSA, CSB and CSC
• 3 x SE Subs MDSA, MDSB and MLB
• Feeder cable lengths vary from 109 to 249 Feet
4
7
7
RC Snubber at MVS - Typical
200 A
Disconnect to
transformerRC Snubber
13.8 kV
0.25 microFarad
30 ohm
Cast Coil
3750KVA
Transformer
8
8
RC Snubber at MVS - Typical
Snubber Specs
13.8 kV
0.25 microFarad
30 ohm
5
9
9
Test Procedure
• Test Procedure required by contractor
• Prepared 2 weeks in advance of testing
• developed the instructions
• Included safety briefing each day
• Site specifics supplied by the contractor
• LO/TO instructions
• Breaker operations
• All meter connections made de-energized & LO/TO
• No one in transformer room during tests
• Signature of “Responsible Engineer” before test began
• detailed test procedure form
10
10
Measurement Equipment
• Measurement equipment included voltage
dividers and a transient recording device
• Voltage Dividers
• Capacitive and resistive elements
• 10MHz frequency response
• Three-Phase Power Quality Recorder
• transient voltage waveshape sampling
• 200 nsec sample resolution
• 5 Mhz sampling
6
11
11
Test Measurement Setup (Typical)
12
12
Voltage Divider Connections
• Highly stranded No. 8, 15 kV insulated hookup wire
• Insulated wire was a precaution – could have used
bare conductor
• maintained 8inch minimum separation for 15kV
between phases and ground
• Routed wires with gradual curve – no 90 degree
bends
• Connection at surge arrester at bus to transformer
primary windings
7
13
13
Voltage Divider Connections
14
14
Voltage Divider Connections
• Base of each divider grounded
• Grounded to ground bus in primary disconnect
• Used same highly stranded no. 8, 15kV insulated
hookup wire
• Connection to PQ Meter
• Cables to match input impedance of meter to that
of voltage divider
• Voltage divider was calibrated prior to shipping to
site
8
15
15
CT Connections
• Primary interest was voltage at transformer
• Secondary interest was snubber current
• Connected CTs at ground side of snubbers
16
16
Initial view of events
Energize
(see zoom)
De-energize
(see zoom)
• RMS trend of voltage
• VCB energized and de-energized transformer
9
17
17
Zoom View of Energize
• Slight overshoot above normal crest
• Ring well damped
18
18
Zoom View of De-Energize
• No transient on opening
• Well damped
10
19
19
Other Tests – transformer natural frequencies
• Sweep Frequency Response Analysis (SFRA)
ImpedancePhaseAngle
Frequency
20
20
Data Center Challenges
• Contractor requested measurements
• Advised contractor
• First hookup/measurement – 1 day
• Remaining 5 transformers – 2nd day
• Prepare two voltage divider carts in advance
• Contractor agreed to schedule but…
• This was a construction site
• Project manager had other objectives
• Snubber testing viewed as an “inconvenience”
• Voltage divider carts were not prepared
• Be prepared to negotiate
11
21
21
Summary
• Prepare test procedure – 2 weeks in advance
• Request onelines and site photos to plan hookups
• Ship all equipment in advance
• For safety, two engineers perform measurements
• Follow test procedure
• Make all connections de-energized, LO/TO
• No one in transformer room during test
• Radio contact with contractor performing switching
• Download data after each test
• Analyze results before proceeding to next test
• Begin building test report while on-site

More Related Content

What's hot

A2.34+transformer+maintenance+tutorial
A2.34+transformer+maintenance+tutorialA2.34+transformer+maintenance+tutorial
A2.34+transformer+maintenance+tutorialJack Duff
 
ECE 469 Final Project Presentation.PPTX
ECE 469 Final Project Presentation.PPTXECE 469 Final Project Presentation.PPTX
ECE 469 Final Project Presentation.PPTXMarat Amanzholov
 
891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgearmichaeljmack
 
Gas insulated auto sectionalizer
Gas insulated auto sectionalizerGas insulated auto sectionalizer
Gas insulated auto sectionalizerJoeChueng
 
LV 124 & LV 148 Solutions - WKS Informatik
LV 124 & LV 148 Solutions - WKS InformatikLV 124 & LV 148 Solutions - WKS Informatik
LV 124 & LV 148 Solutions - WKS InformatikAndreea Solomon
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...Ali Sepehri
 
Appraisal ppt ankur
Appraisal ppt ankurAppraisal ppt ankur
Appraisal ppt ankurAnkur Mishra
 
Dynamic Sectoring of Torremolinos' Water Distribution Network
Dynamic Sectoring of Torremolinos' Water Distribution NetworkDynamic Sectoring of Torremolinos' Water Distribution Network
Dynamic Sectoring of Torremolinos' Water Distribution NetworkSimón José Pulido Leboeuf
 
Critical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignCritical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignConsultingSpecifyingEngineer
 
Paralleling Switchgear
Paralleling SwitchgearParalleling Switchgear
Paralleling Switchgearmichaeljmack
 
RTStand LV 124 - fully-automated testing system for LV 124
RTStand LV 124 - fully-automated testing system for LV 124RTStand LV 124 - fully-automated testing system for LV 124
RTStand LV 124 - fully-automated testing system for LV 124Andreea Solomon
 
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsystDesign and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsystIRJET Journal
 

What's hot (20)

Fundamentals of Field Testing Meters
Fundamentals of Field Testing MetersFundamentals of Field Testing Meters
Fundamentals of Field Testing Meters
 
A2.34+transformer+maintenance+tutorial
A2.34+transformer+maintenance+tutorialA2.34+transformer+maintenance+tutorial
A2.34+transformer+maintenance+tutorial
 
ECE 469 Final Project Presentation.PPTX
ECE 469 Final Project Presentation.PPTXECE 469 Final Project Presentation.PPTX
ECE 469 Final Project Presentation.PPTX
 
BR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-BrochureBR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-Brochure
 
891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear
 
RPS-SF6LBS-PKE
RPS-SF6LBS-PKERPS-SF6LBS-PKE
RPS-SF6LBS-PKE
 
Gas insulated auto sectionalizer
Gas insulated auto sectionalizerGas insulated auto sectionalizer
Gas insulated auto sectionalizer
 
LV 124 & LV 148 Solutions - WKS Informatik
LV 124 & LV 148 Solutions - WKS InformatikLV 124 & LV 148 Solutions - WKS Informatik
LV 124 & LV 148 Solutions - WKS Informatik
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
 
Appraisal ppt ankur
Appraisal ppt ankurAppraisal ppt ankur
Appraisal ppt ankur
 
FAZIL PASHA CV 3.6.2015
FAZIL PASHA CV 3.6.2015FAZIL PASHA CV 3.6.2015
FAZIL PASHA CV 3.6.2015
 
16950
1695016950
16950
 
Dynamic Sectoring of Torremolinos' Water Distribution Network
Dynamic Sectoring of Torremolinos' Water Distribution NetworkDynamic Sectoring of Torremolinos' Water Distribution Network
Dynamic Sectoring of Torremolinos' Water Distribution Network
 
RLS type indoor SF6 load break switch(Disconnector)
RLS type indoor SF6 load break switch(Disconnector)RLS type indoor SF6 load break switch(Disconnector)
RLS type indoor SF6 load break switch(Disconnector)
 
RLW type pole mounted vacuum load break switch
RLW type pole mounted vacuum load break switchRLW type pole mounted vacuum load break switch
RLW type pole mounted vacuum load break switch
 
Critical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignCritical Power: Generators and Generator System Design
Critical Power: Generators and Generator System Design
 
Paralleling Switchgear
Paralleling SwitchgearParalleling Switchgear
Paralleling Switchgear
 
RTStand LV 124 - fully-automated testing system for LV 124
RTStand LV 124 - fully-automated testing system for LV 124RTStand LV 124 - fully-automated testing system for LV 124
RTStand LV 124 - fully-automated testing system for LV 124
 
Ppt pe
Ppt pePpt pe
Ppt pe
 
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsystDesign and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
 

Similar to Transformer Snubber Performance Testing at Data Center

Testing of Circuit Breakers.pptx
Testing of Circuit Breakers.pptxTesting of Circuit Breakers.pptx
Testing of Circuit Breakers.pptxTafhim Bin Nasir
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptxTalhaAbdulRehman2
 
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.nikhilhiware
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTranscat
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHShankar Singh
 
GRADED UNIT POWERPOINT FINISHED!!!!!
GRADED UNIT POWERPOINT FINISHED!!!!!GRADED UNIT POWERPOINT FINISHED!!!!!
GRADED UNIT POWERPOINT FINISHED!!!!!Patrick O'Donnell
 
Transformer protection using microcontroller and gsm technology
Transformer protection using microcontroller and gsm technologyTransformer protection using microcontroller and gsm technology
Transformer protection using microcontroller and gsm technologyKartik Patel
 
Decoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike TachickDecoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike Tachicknacetwincities
 
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurTraining from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurR-One Power
 

Similar to Transformer Snubber Performance Testing at Data Center (20)

Testing of Circuit Breakers.pptx
Testing of Circuit Breakers.pptxTesting of Circuit Breakers.pptx
Testing of Circuit Breakers.pptx
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptx
 
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV Systems
 
Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories
 
Testing of cb
Testing of cbTesting of cb
Testing of cb
 
Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17
 
GRADED UNIT POWERPOINT FINISHED!!!!!
GRADED UNIT POWERPOINT FINISHED!!!!!GRADED UNIT POWERPOINT FINISHED!!!!!
GRADED UNIT POWERPOINT FINISHED!!!!!
 
Transformer protection using microcontroller and gsm technology
Transformer protection using microcontroller and gsm technologyTransformer protection using microcontroller and gsm technology
Transformer protection using microcontroller and gsm technology
 
Test Switch Operation, Specification & Accessories
Test Switch Operation, Specification & AccessoriesTest Switch Operation, Specification & Accessories
Test Switch Operation, Specification & Accessories
 
various types of transformers.
various types of transformers.various types of transformers.
various types of transformers.
 
Field Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best PracticesField Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best Practices
 
Decoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike TachickDecoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike Tachick
 
Hands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter TestingHands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter Testing
 
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurTraining from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
 

More from michaeljmack

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993michaeljmack
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbookmichaeljmack
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbookmichaeljmack
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systemsmichaeljmack
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgearmichaeljmack
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrushmichaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modelingmichaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protectionmichaeljmack
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systemsmichaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spacesmichaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distributionmichaeljmack
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performancemichaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulatormichaeljmack
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plantsmichaeljmack
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Storiesmichaeljmack
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Sheddingmichaeljmack
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentalsmichaeljmack
 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

Transformer Snubber Performance Testing at Data Center

  • 1. 1 Transformer Failure Due to Circuit Breaker Induced Switching Transients Part 5: Snubber Performance Measurements David D. Shipp, PE Fellow, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 Thomas J. Dionise, PE Senior Member, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 2 2 Snubber Performance Measurements • Data Center • Purpose of Measurements • Test procedures • Medium voltage measurements • Selecting a meter • Using voltage dividers • Safety concerns • Data Center challenges
  • 2. 2 3 3 Purpose of Performance Measurements • Ensure the proper operation of the snubbers • Measure the transient overvoltage waveforms at the transformer primary • produced during switching of the primary vacuum circuit breakers • verify they do not exhibit high frequency transients (magnitude, rate- of-rise and frequency). • Specify the meters and voltage dividers needed for the transient measurement • guide electrical contractor with their installation • electrical contractor to operate all equipment following the test procedure • After completion of the site monitoring during the snubber tests, analyze the measurement data and document the test results in an engineering report. 4 4 Data Center Highlights • Tier III • LEEDS Certified • 12.5MVA Capacity • 13.2KV Ring Bus
  • 3. 3 5 5 Data Center – Measurement Locations Vacuum Breaker Short Cable Cast-Coil Transformer 6 6 Data Center – Electrical Highlights • 2 x 24.9 kV lines from Factory Shoals and Buzzard Roast • 2 x 12.5 MVA transformers • 13.2 kV “ring-bus” configuration • MSA and MSB and generator bus GPS • Vacuum circuit breakers – 600A mains & ties, 200A feeders • 3 x 2250 KW generators • 6 x 3750KVA cast coil transformers, 90kV BIL • 3 x DE Subs CSA, CSB and CSC • 3 x SE Subs MDSA, MDSB and MLB • Feeder cable lengths vary from 109 to 249 Feet
  • 4. 4 7 7 RC Snubber at MVS - Typical 200 A Disconnect to transformerRC Snubber 13.8 kV 0.25 microFarad 30 ohm Cast Coil 3750KVA Transformer 8 8 RC Snubber at MVS - Typical Snubber Specs 13.8 kV 0.25 microFarad 30 ohm
  • 5. 5 9 9 Test Procedure • Test Procedure required by contractor • Prepared 2 weeks in advance of testing • developed the instructions • Included safety briefing each day • Site specifics supplied by the contractor • LO/TO instructions • Breaker operations • All meter connections made de-energized & LO/TO • No one in transformer room during tests • Signature of “Responsible Engineer” before test began • detailed test procedure form 10 10 Measurement Equipment • Measurement equipment included voltage dividers and a transient recording device • Voltage Dividers • Capacitive and resistive elements • 10MHz frequency response • Three-Phase Power Quality Recorder • transient voltage waveshape sampling • 200 nsec sample resolution • 5 Mhz sampling
  • 6. 6 11 11 Test Measurement Setup (Typical) 12 12 Voltage Divider Connections • Highly stranded No. 8, 15 kV insulated hookup wire • Insulated wire was a precaution – could have used bare conductor • maintained 8inch minimum separation for 15kV between phases and ground • Routed wires with gradual curve – no 90 degree bends • Connection at surge arrester at bus to transformer primary windings
  • 7. 7 13 13 Voltage Divider Connections 14 14 Voltage Divider Connections • Base of each divider grounded • Grounded to ground bus in primary disconnect • Used same highly stranded no. 8, 15kV insulated hookup wire • Connection to PQ Meter • Cables to match input impedance of meter to that of voltage divider • Voltage divider was calibrated prior to shipping to site
  • 8. 8 15 15 CT Connections • Primary interest was voltage at transformer • Secondary interest was snubber current • Connected CTs at ground side of snubbers 16 16 Initial view of events Energize (see zoom) De-energize (see zoom) • RMS trend of voltage • VCB energized and de-energized transformer
  • 9. 9 17 17 Zoom View of Energize • Slight overshoot above normal crest • Ring well damped 18 18 Zoom View of De-Energize • No transient on opening • Well damped
  • 10. 10 19 19 Other Tests – transformer natural frequencies • Sweep Frequency Response Analysis (SFRA) ImpedancePhaseAngle Frequency 20 20 Data Center Challenges • Contractor requested measurements • Advised contractor • First hookup/measurement – 1 day • Remaining 5 transformers – 2nd day • Prepare two voltage divider carts in advance • Contractor agreed to schedule but… • This was a construction site • Project manager had other objectives • Snubber testing viewed as an “inconvenience” • Voltage divider carts were not prepared • Be prepared to negotiate
  • 11. 11 21 21 Summary • Prepare test procedure – 2 weeks in advance • Request onelines and site photos to plan hookups • Ship all equipment in advance • For safety, two engineers perform measurements • Follow test procedure • Make all connections de-energized, LO/TO • No one in transformer room during test • Radio contact with contractor performing switching • Download data after each test • Analyze results before proceeding to next test • Begin building test report while on-site