SlideShare a Scribd company logo
1 of 6
Download to read offline
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 943
Comparative Study of Flatslab and Beam-slab System for a Multi-
storied RC building
Bhavani Shankar1, Suchetan Mokashi2, Ashithkrishna Upadhyaya3, Nazih Riyaz4, Ameer Suhail5,
Jeevan N S6
1Assistant Professor, Srinivas School of Engineering, Mangaluru, Karnataka, India
2,3,4,5,6 B.E Students, Srinivas School of Engineering, Mukka, Mangaluru, Karnataka, India.
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - In this new era of construction flat slab is playing
one of the most important role, nowdaysflatslabconstruction
is widely adopted due to its main advantages like accessibility
of more space, easier frame work and speedy construction
compared to other slab systems. In this particular work
comparison is done between flat slab system and beam-slab
system for varied spans between columns and their rate
analysis is done. For this work multi storied RC building (G+5)
is considered, the modeling of both flat slab and beam-slab
system is done using well known software ETABS for different
spans between the columns i.e. 5m, 7m and 9m. The flat slab
design is also done for all three spans. The quantity of steel
and concrete is calculated for both flat slab and beam slab
building and rate analysis is done.
1. INTRODUCTION
Flat slab is RC slab with no beams, the slab is directlykept on
the columns of the building, and the loads coming from the
slab is directly transferred to the columns.
There are many types of the flat slab depending on the load
distributed on it. If the loads are minimum or common on
the slab then slab is directly kept on the columns which are
known as flat plate. If the load carried by the slab is more or
dynamic then drop panels are provided which is commonly
known as flat slab with drops. As shown in the fig. Since
there are no beams and the slab is placed on the columnsthe
under the application of the loads the columns try to punch
through the slab. Therefore to avoid this column heads are
provided. That type of slab is known as flat slab with column
head. The flat slab is mainly used where zigzag column
alignments are there, now a day flat slab is often adopted
due its advantages over the beam-slab systems. The flat slab
is easy in construction since there are no beams in it and it
makes the frame work during the construction also easy.
Benefit of using flat slabs are manifold not only in terms of
prospective design and layout efficacy but is also helpful for
total construction process especially for easing off
installation procedures and saving on construction time.
1.1 FLATSLAB SYSTEM
Flat slab is a slab with no beams where the load coming
from the slab is directly transferred to the columns. In this
work the flat slab with the drop panel is considered. The flat
slab consists of different componentslikedrop,columnhead,
panel, middle strip and column.
Drop- This is the primary part of the flat slab to oppose
the punching which is originating at the contact section of
slab and column support.
Column head- When the loads at the column slab
connection is more than the punching action will laso be
more hence its necessary to provide column head.
Column- Column is a vertical member which can resist
uni-axial and biaxial stresses developed due to loads. It can
undergo buckling with respective its length. The minimum
percentage of steel 0.8% and maximum is 4%.
1.2 ADVANTAGES OF FLATSLAB
Its been observed that the flat slab without the drop panels
construction can be achieved in very less time and also flat
slab with the drop panels can be constructed in very less
time as compared to conventional slab system.
The form work for the flat slab construction is easy and can
be done in a very less time.
Since there are no beams the accessibility of the spaceinside
the building is greatly increased.
The floor height can be reduced to great extent due to the
absence of beams and no extra cost for false ceilings.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 944
Since more space is available more versatile plans can be
accommodated in the building to meet the client needs.
2. BEAM-SLAB SYSTEM
Beam-slab system is also called as the conventional slab
system. This is a old and traditional method of construction
used in the multi-storied structures. In this system the slab
are kept on the beams, the loads coming from the slab is
taken by the beam and the beams are connected to the
column where further load is transferred.
This construction of this system involves complex frame
work and the reinforcement. The depth of the beam mainly
depends on the load and its span.
ADVANTAGES:
• It’s a traditional method of construction.
• Long spans can be accommodated.
• The structure is very rigid.
• Availability of more floor height.
DISAVANTAGES:
 The frame work for this system is very complex
due to the presence of the beams.
 Floor height should be more.
 Less accessibility of the space due to the presence
of beam.
 Construction is not fast.
3. SOFTWARES USED
The work is mainly based on the software since the design
and modeling is required. Following are the some software
used in this project,
a) CSI ETABS
b) MICROSOFT EXCEL
ETABS- This software mainly provides a great interface
for modeling the structure with all advanced configurations.
In this work EATBS is mainly used to model the both flat slab
and beam-slab buildings.
MICROSOFT EXCEL- The software is mainly used for the
design calculationsoftheflatslabandquantitycalculationsof
steel and concrete for both slab systems, the rate analysis is
also done using this software.
The main aim of using this software is to reduce manual
calculations and values are exact and error free.
4. MODELING
The modeling of the flat slab structure and beam-slab
structure is done using well known software ETABS. The
modeling of flat slaband beamslabisdonefordifferentspans
that are 5m, 7m and 9m between the columns.
5.1 MODELLING OF FLAT SLAB SYSTEM
Concrete and Steel details
Flatslab with 5m span between the columns,
Concrete grade of normal slab & drop M20
Concrete grade of column M20
Density of concrete 25 KN/m3
Grade of steel Fe415
Plan dimension 21m X 21 m
Total height of building 16.125 m
Building considered (G+5)
Story height 3 m
Base consideration Fixed
Depth of slab 225 mm
Depth of drop 375 mm
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 945
Figure 1 FLAT SLAB MODEL (5m)
MODEL OF FLATSLAB WITH 7m SPAN BETWEENT THE
COLUMNS
Figure 2 FLATSLAB MODEL (7m)
MODEL OF FLAT SLAB WITH 9m SPAN BETWEEN THE
COLUMNS
Fig 3 Flatslab model 9m span
5.2 MODELING OF BEAM-SLAB SYSTEM
Beam-slab for 5m span between the columns
Plan dimension 15 m X 15m
Spacing between the columns 5 m
Total height of building 15.875 m
Building considered (G+5)
Story height 3 m
Base consideration Fixed
Size of the column 600*600 mm
Size of the beam 300*750 mm
Depth of the slab 175 mm
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 946
Figure 04 BEAM SLAB (5m)
Beam-slab for 7m span between columns
Fig. 05 Model of beam-slab 7m span
Beam-slab for 9m span between columns
Plan dimension 27 m X 27m
Spacing between the columns 9 m
Total height of building 15.875 m
Building considered (G+5)
Story height 3 m
Base consideration Fixed
Size of the column 600*600 mm
Size of the beam 300*750 mm
Depth of the slab 175 mm
Fig 06 BEAM-SLAB (9m)
6. DESIGN OF FLATSLAB
The design of flat slab was carried out for three different
spans i.e. 5m, 7m and 9m, as per Indian standards code
IS456:2000. The details of reinforcement are given below,
For 5m span
Middle strip Column strip
Top in
"mm C/C"
Bottom in
"mm C/C"
Top in "mm
C/C"
Bottom in
"mm C/C"
300 300 160 300
For 7m span
Middle strip Column strip
Top in
"mm C/C"
Bottom in
"mm C/C"
Top in "mm
C/C"
Bottom in
"mm C/C"
300 300 85 260
For 9m span
Middle strip Column strip
Top in
"mm C/C"
Bottom in
"mm C/C"
Top in "mm
C/C"
Bottom in
"mm C/C"
300 300 140 270
Plan dimension 21 m X 21 m
Spacing between the columns 7 m
Total height of building 15.875 m
Building considered (G+5)
Story height 3 m
Base consideration Fixed
Size of the column 600*600 mm
Size of the beam 300*750 mm
Depth of the slab 175 mm
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 947
7. QUANTITIES
The quantities for steel and concrete for both flat slab and
the beam-slab were calculated using the design details,
quantities are given below,
For flat slab:
FLATSLAB (FOR ONE FLOOR)
Span in m -> 5 7 9
MATERIAL QUANTITES
Steel in 'kg' 3120 8104 11309
Concrete in 'm3' 50.7 117.7 242
For Beam-slab :
BEAM-SLAB(FOR ONE FLOOR)
Span in m -> 5 7 9
MATERIAL QUANTITES
Steel in 'kg' 4721 10747.4 25908
Concrete in 'm3' 44.1 106.15 194.4
8. RATE ANALYSIS
From the quantity analysis which is done above we have got
the total quantities for the steel and the concrete, by
considering present day cost for concrete and steel we have
calculated the cost for both flat slab and beam-slab systems
for all the three spans and analysis was done between them.
The present costs for concrete and steel
For mixing and laying concrete :
Slab : Rs. 520/- per cft
Beams : Rs. 580/- per cft
For steel bending and placing : Rs. 60/kg
RATE ANALYSIS
COST IN RS.
SPAN in m CONVENTIONAL FLATSLAB
RATE
DIFFERENCE
5 1090620 1117207 26587
7 2599631 2646113 46482
9 5224566 5130073 94493
Graph of rate analysis:
9. CONCLUSIONS
This project represents the comparative study between
Flatslab and beam-slab systems for a multi-storied RC
building (G+5) for varied span between the columns, on the
basis of above results we can conclude that
1. By observing the above results and graph we can
say that for shorter spans the flatslab is costlier
than the conventional slab systems.
2. But we can see that as span between column
increases the quantities forbeamslabincreasesand
hence the cost of the beam slab also increases.
3. For 9m span between the columns the rateof beam-
slab is more than the cost of flat slab, so we can
conclude that as the span between columns
increases the beam slab gets colstlier than the
flatslab.
4. Hence by this project we can say that by adopting
the flat slab systems in larger spanconstructionwill
save lot of money and since flat slab is more
advantageous than the beam slab, construction will
be easier, fast, economic and affordable.
10. REFERENCES
1. Amrut manav (2016), “Comparative study of linear
and non-linear seismic response of rc structure
situated in different seismic zones of India”,
International Research Journal of Engineering and
Technology,
2. Vinod goud (2016) “Analysis design of flatslabwith
and without shear wall of multi storied buildings
frame.” ,IOSR journals of engineering, volume 06,
sep 2016
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 948
3. Vinkuj k.tilva (2017), “Parametric study on flat slab
building with and without column drop”, vol -03,
feb2017
4. M.K. Devtale (2016), “Comparison of Seismic
Response between Flat Slab Building and Regular
Frame Building”, International journal of
advancement in engineering technology,
management and applied science, volume 03, June
2016
5. Mohana H S (2015) “Comparative Study of Flat Slab
and Conventional Slab Structure Using ETABS for
Different Earthquake Zones of India” International
Research Journal of Engineering and Technology,
volume-2, June 2015.

More Related Content

What's hot

1.6 _Important element required to complete a building
1.6  _Important element required to complete a building1.6  _Important element required to complete a building
1.6 _Important element required to complete a building
Teow Beng Hur
 

What's hot (20)

IRJET- Effect of Pile Cap Thickness Variation on Load Carrying Capacity o...
IRJET-  	  Effect of Pile Cap Thickness Variation on Load Carrying Capacity o...IRJET-  	  Effect of Pile Cap Thickness Variation on Load Carrying Capacity o...
IRJET- Effect of Pile Cap Thickness Variation on Load Carrying Capacity o...
 
Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...
Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...
Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...
 
IRJET- Seismic Analysis of Shear Wall Optimization for Multi-Storey Building
IRJET- Seismic Analysis of Shear Wall Optimization for Multi-Storey BuildingIRJET- Seismic Analysis of Shear Wall Optimization for Multi-Storey Building
IRJET- Seismic Analysis of Shear Wall Optimization for Multi-Storey Building
 
Mivan tech
Mivan techMivan tech
Mivan tech
 
IRJET- Comparative Study of different Position of Shear Wall using Software
IRJET- Comparative Study of different Position of Shear Wall using SoftwareIRJET- Comparative Study of different Position of Shear Wall using Software
IRJET- Comparative Study of different Position of Shear Wall using Software
 
IRJET- Comparative Study on Seismic Analysis of Multistorey Buildings wit...
IRJET-  	  Comparative Study on Seismic Analysis of Multistorey Buildings wit...IRJET-  	  Comparative Study on Seismic Analysis of Multistorey Buildings wit...
IRJET- Comparative Study on Seismic Analysis of Multistorey Buildings wit...
 
1.6 _Important element required to complete a building
1.6  _Important element required to complete a building1.6  _Important element required to complete a building
1.6 _Important element required to complete a building
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
 
Effect of wind load on tall buildings in different terrain category
Effect of wind load on tall buildings in different terrain categoryEffect of wind load on tall buildings in different terrain category
Effect of wind load on tall buildings in different terrain category
 
IRJET-Analysis of RC Structure with and without Shear Wall and Optimum Locati...
IRJET-Analysis of RC Structure with and without Shear Wall and Optimum Locati...IRJET-Analysis of RC Structure with and without Shear Wall and Optimum Locati...
IRJET-Analysis of RC Structure with and without Shear Wall and Optimum Locati...
 
IRJET- Cost Comparison of different Grid Patterns of Floor Slab of Same Span
IRJET- Cost Comparison of different Grid Patterns of Floor Slab of Same SpanIRJET- Cost Comparison of different Grid Patterns of Floor Slab of Same Span
IRJET- Cost Comparison of different Grid Patterns of Floor Slab of Same Span
 
Group Project Presentation - 2 (Final)
Group Project Presentation - 2 (Final)Group Project Presentation - 2 (Final)
Group Project Presentation - 2 (Final)
 
IRJET- Analysis of Steel Braced Symmetrical RCC Building with Designed I-Sect...
IRJET- Analysis of Steel Braced Symmetrical RCC Building with Designed I-Sect...IRJET- Analysis of Steel Braced Symmetrical RCC Building with Designed I-Sect...
IRJET- Analysis of Steel Braced Symmetrical RCC Building with Designed I-Sect...
 
Major projects aluminium of formwork civil engineering
Major  projects aluminium of formwork civil engineeringMajor  projects aluminium of formwork civil engineering
Major projects aluminium of formwork civil engineering
 
Taming The Wind with Engineered Tall Walls
Taming The Wind with Engineered Tall WallsTaming The Wind with Engineered Tall Walls
Taming The Wind with Engineered Tall Walls
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
 
Comparative Studies of Construction Techniques (Conventional VS MIVAN)
Comparative Studies of Construction Techniques (Conventional VS MIVAN)Comparative Studies of Construction Techniques (Conventional VS MIVAN)
Comparative Studies of Construction Techniques (Conventional VS MIVAN)
 
IRJET- Design of Earthquake Resistant Structure of Multi-Story RCC Building
IRJET- Design of Earthquake Resistant Structure of Multi-Story RCC BuildingIRJET- Design of Earthquake Resistant Structure of Multi-Story RCC Building
IRJET- Design of Earthquake Resistant Structure of Multi-Story RCC Building
 
IRJET- Techno – Economic Study of Different Type of Slab
IRJET-  	  Techno – Economic Study of Different Type of SlabIRJET-  	  Techno – Economic Study of Different Type of Slab
IRJET- Techno – Economic Study of Different Type of Slab
 
Seismic Performance of Symmetrical Building with & without Isolators
Seismic Performance of Symmetrical Building with & without IsolatorsSeismic Performance of Symmetrical Building with & without Isolators
Seismic Performance of Symmetrical Building with & without Isolators
 

Similar to IRJET- Comparative Study of Flat slab and Beam-Slab System for a Multi-Storied RC Building

Similar to IRJET- Comparative Study of Flat slab and Beam-Slab System for a Multi-Storied RC Building (20)

IRJET- Wind Analysis for RC Building using Belt Truss
IRJET- Wind Analysis for RC Building using Belt TrussIRJET- Wind Analysis for RC Building using Belt Truss
IRJET- Wind Analysis for RC Building using Belt Truss
 
Effect of Oblique Column and Viscous Damper on Podium Structure Using Etabs
Effect of Oblique Column and Viscous Damper on Podium Structure Using EtabsEffect of Oblique Column and Viscous Damper on Podium Structure Using Etabs
Effect of Oblique Column and Viscous Damper on Podium Structure Using Etabs
 
STUDY OF PUSHOVER ANALYSIS OF G+10 RCC BUILDING WITH SHEAR WALL
STUDY OF PUSHOVER ANALYSIS OF G+10 RCC BUILDING WITH SHEAR WALLSTUDY OF PUSHOVER ANALYSIS OF G+10 RCC BUILDING WITH SHEAR WALL
STUDY OF PUSHOVER ANALYSIS OF G+10 RCC BUILDING WITH SHEAR WALL
 
IRJET- A Study on Performance of High-Rise Building with different Struct...
IRJET-  	  A Study on Performance of High-Rise Building with different Struct...IRJET-  	  A Study on Performance of High-Rise Building with different Struct...
IRJET- A Study on Performance of High-Rise Building with different Struct...
 
IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...
IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...
IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...
 
IRJET- Methodology of 3S Construction Method “Prefabrication Technology”
IRJET-  	  Methodology of 3S Construction Method “Prefabrication Technology”IRJET-  	  Methodology of 3S Construction Method “Prefabrication Technology”
IRJET- Methodology of 3S Construction Method “Prefabrication Technology”
 
IRJET- Non Linear Static Seismic Analysis of Vertically Irregular Building Fr...
IRJET- Non Linear Static Seismic Analysis of Vertically Irregular Building Fr...IRJET- Non Linear Static Seismic Analysis of Vertically Irregular Building Fr...
IRJET- Non Linear Static Seismic Analysis of Vertically Irregular Building Fr...
 
Analysis and Design of G+3 Residential Building using STRUDS
Analysis and Design of G+3 Residential Building using STRUDSAnalysis and Design of G+3 Residential Building using STRUDS
Analysis and Design of G+3 Residential Building using STRUDS
 
Comparative Study of Different Web Openings in Castellated Beam by Using Ansy...
Comparative Study of Different Web Openings in Castellated Beam by Using Ansy...Comparative Study of Different Web Openings in Castellated Beam by Using Ansy...
Comparative Study of Different Web Openings in Castellated Beam by Using Ansy...
 
IRJET- A Technical Approach to Flat Slab Multistorey Building under Wind Spee...
IRJET- A Technical Approach to Flat Slab Multistorey Building under Wind Spee...IRJET- A Technical Approach to Flat Slab Multistorey Building under Wind Spee...
IRJET- A Technical Approach to Flat Slab Multistorey Building under Wind Spee...
 
Study on Behavior of Tubular Diagrid Structures During Seismic Excitation
Study on Behavior of Tubular Diagrid Structures During Seismic ExcitationStudy on Behavior of Tubular Diagrid Structures During Seismic Excitation
Study on Behavior of Tubular Diagrid Structures During Seismic Excitation
 
IRJET- Elastic-Plastic Analysis of Plane Portal Frame by STAAD
IRJET- Elastic-Plastic Analysis of Plane Portal Frame by STAADIRJET- Elastic-Plastic Analysis of Plane Portal Frame by STAAD
IRJET- Elastic-Plastic Analysis of Plane Portal Frame by STAAD
 
COMPARATIVE STUDY ON SEISMIC ANALYSIS OF CONVENTIONAL SLAB AND FLAT SLAB STRU...
COMPARATIVE STUDY ON SEISMIC ANALYSIS OF CONVENTIONAL SLAB AND FLAT SLAB STRU...COMPARATIVE STUDY ON SEISMIC ANALYSIS OF CONVENTIONAL SLAB AND FLAT SLAB STRU...
COMPARATIVE STUDY ON SEISMIC ANALYSIS OF CONVENTIONAL SLAB AND FLAT SLAB STRU...
 
IRJET- A Parametric Study on the Siesmic Performance of Flat Slab Multi-S...
IRJET-  	  A Parametric Study on the Siesmic Performance of Flat Slab Multi-S...IRJET-  	  A Parametric Study on the Siesmic Performance of Flat Slab Multi-S...
IRJET- A Parametric Study on the Siesmic Performance of Flat Slab Multi-S...
 
Performance Study of High Rise Building with Diagrid System Under Dynamic Loa...
Performance Study of High Rise Building with Diagrid System Under Dynamic Loa...Performance Study of High Rise Building with Diagrid System Under Dynamic Loa...
Performance Study of High Rise Building with Diagrid System Under Dynamic Loa...
 
Performance Based Analysis of Concealed Beam in Reinforced Concrete Structure
Performance Based Analysis of Concealed Beam in Reinforced Concrete StructurePerformance Based Analysis of Concealed Beam in Reinforced Concrete Structure
Performance Based Analysis of Concealed Beam in Reinforced Concrete Structure
 
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
 
“Comparative Study of G+16 Building Regular and Irregular buildings Design wi...
“Comparative Study of G+16 Building Regular and Irregular buildings Design wi...“Comparative Study of G+16 Building Regular and Irregular buildings Design wi...
“Comparative Study of G+16 Building Regular and Irregular buildings Design wi...
 
IRJET- Comparative Study and Buckling Analysis of Hollow Castellated Colu...
IRJET-  	  Comparative Study and Buckling Analysis of Hollow Castellated Colu...IRJET-  	  Comparative Study and Buckling Analysis of Hollow Castellated Colu...
IRJET- Comparative Study and Buckling Analysis of Hollow Castellated Colu...
 
Elastic and Inelastic Responses of Multi-Storey Buildings Symmetric and Asymm...
Elastic and Inelastic Responses of Multi-Storey Buildings Symmetric and Asymm...Elastic and Inelastic Responses of Multi-Storey Buildings Symmetric and Asymm...
Elastic and Inelastic Responses of Multi-Storey Buildings Symmetric and Asymm...
 

More from IRJET Journal

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 

Recently uploaded (20)

AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 

IRJET- Comparative Study of Flat slab and Beam-Slab System for a Multi-Storied RC Building

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 943 Comparative Study of Flatslab and Beam-slab System for a Multi- storied RC building Bhavani Shankar1, Suchetan Mokashi2, Ashithkrishna Upadhyaya3, Nazih Riyaz4, Ameer Suhail5, Jeevan N S6 1Assistant Professor, Srinivas School of Engineering, Mangaluru, Karnataka, India 2,3,4,5,6 B.E Students, Srinivas School of Engineering, Mukka, Mangaluru, Karnataka, India. ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - In this new era of construction flat slab is playing one of the most important role, nowdaysflatslabconstruction is widely adopted due to its main advantages like accessibility of more space, easier frame work and speedy construction compared to other slab systems. In this particular work comparison is done between flat slab system and beam-slab system for varied spans between columns and their rate analysis is done. For this work multi storied RC building (G+5) is considered, the modeling of both flat slab and beam-slab system is done using well known software ETABS for different spans between the columns i.e. 5m, 7m and 9m. The flat slab design is also done for all three spans. The quantity of steel and concrete is calculated for both flat slab and beam slab building and rate analysis is done. 1. INTRODUCTION Flat slab is RC slab with no beams, the slab is directlykept on the columns of the building, and the loads coming from the slab is directly transferred to the columns. There are many types of the flat slab depending on the load distributed on it. If the loads are minimum or common on the slab then slab is directly kept on the columns which are known as flat plate. If the load carried by the slab is more or dynamic then drop panels are provided which is commonly known as flat slab with drops. As shown in the fig. Since there are no beams and the slab is placed on the columnsthe under the application of the loads the columns try to punch through the slab. Therefore to avoid this column heads are provided. That type of slab is known as flat slab with column head. The flat slab is mainly used where zigzag column alignments are there, now a day flat slab is often adopted due its advantages over the beam-slab systems. The flat slab is easy in construction since there are no beams in it and it makes the frame work during the construction also easy. Benefit of using flat slabs are manifold not only in terms of prospective design and layout efficacy but is also helpful for total construction process especially for easing off installation procedures and saving on construction time. 1.1 FLATSLAB SYSTEM Flat slab is a slab with no beams where the load coming from the slab is directly transferred to the columns. In this work the flat slab with the drop panel is considered. The flat slab consists of different componentslikedrop,columnhead, panel, middle strip and column. Drop- This is the primary part of the flat slab to oppose the punching which is originating at the contact section of slab and column support. Column head- When the loads at the column slab connection is more than the punching action will laso be more hence its necessary to provide column head. Column- Column is a vertical member which can resist uni-axial and biaxial stresses developed due to loads. It can undergo buckling with respective its length. The minimum percentage of steel 0.8% and maximum is 4%. 1.2 ADVANTAGES OF FLATSLAB Its been observed that the flat slab without the drop panels construction can be achieved in very less time and also flat slab with the drop panels can be constructed in very less time as compared to conventional slab system. The form work for the flat slab construction is easy and can be done in a very less time. Since there are no beams the accessibility of the spaceinside the building is greatly increased. The floor height can be reduced to great extent due to the absence of beams and no extra cost for false ceilings.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 944 Since more space is available more versatile plans can be accommodated in the building to meet the client needs. 2. BEAM-SLAB SYSTEM Beam-slab system is also called as the conventional slab system. This is a old and traditional method of construction used in the multi-storied structures. In this system the slab are kept on the beams, the loads coming from the slab is taken by the beam and the beams are connected to the column where further load is transferred. This construction of this system involves complex frame work and the reinforcement. The depth of the beam mainly depends on the load and its span. ADVANTAGES: • It’s a traditional method of construction. • Long spans can be accommodated. • The structure is very rigid. • Availability of more floor height. DISAVANTAGES:  The frame work for this system is very complex due to the presence of the beams.  Floor height should be more.  Less accessibility of the space due to the presence of beam.  Construction is not fast. 3. SOFTWARES USED The work is mainly based on the software since the design and modeling is required. Following are the some software used in this project, a) CSI ETABS b) MICROSOFT EXCEL ETABS- This software mainly provides a great interface for modeling the structure with all advanced configurations. In this work EATBS is mainly used to model the both flat slab and beam-slab buildings. MICROSOFT EXCEL- The software is mainly used for the design calculationsoftheflatslabandquantitycalculationsof steel and concrete for both slab systems, the rate analysis is also done using this software. The main aim of using this software is to reduce manual calculations and values are exact and error free. 4. MODELING The modeling of the flat slab structure and beam-slab structure is done using well known software ETABS. The modeling of flat slaband beamslabisdonefordifferentspans that are 5m, 7m and 9m between the columns. 5.1 MODELLING OF FLAT SLAB SYSTEM Concrete and Steel details Flatslab with 5m span between the columns, Concrete grade of normal slab & drop M20 Concrete grade of column M20 Density of concrete 25 KN/m3 Grade of steel Fe415 Plan dimension 21m X 21 m Total height of building 16.125 m Building considered (G+5) Story height 3 m Base consideration Fixed Depth of slab 225 mm Depth of drop 375 mm
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 945 Figure 1 FLAT SLAB MODEL (5m) MODEL OF FLATSLAB WITH 7m SPAN BETWEENT THE COLUMNS Figure 2 FLATSLAB MODEL (7m) MODEL OF FLAT SLAB WITH 9m SPAN BETWEEN THE COLUMNS Fig 3 Flatslab model 9m span 5.2 MODELING OF BEAM-SLAB SYSTEM Beam-slab for 5m span between the columns Plan dimension 15 m X 15m Spacing between the columns 5 m Total height of building 15.875 m Building considered (G+5) Story height 3 m Base consideration Fixed Size of the column 600*600 mm Size of the beam 300*750 mm Depth of the slab 175 mm
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 946 Figure 04 BEAM SLAB (5m) Beam-slab for 7m span between columns Fig. 05 Model of beam-slab 7m span Beam-slab for 9m span between columns Plan dimension 27 m X 27m Spacing between the columns 9 m Total height of building 15.875 m Building considered (G+5) Story height 3 m Base consideration Fixed Size of the column 600*600 mm Size of the beam 300*750 mm Depth of the slab 175 mm Fig 06 BEAM-SLAB (9m) 6. DESIGN OF FLATSLAB The design of flat slab was carried out for three different spans i.e. 5m, 7m and 9m, as per Indian standards code IS456:2000. The details of reinforcement are given below, For 5m span Middle strip Column strip Top in "mm C/C" Bottom in "mm C/C" Top in "mm C/C" Bottom in "mm C/C" 300 300 160 300 For 7m span Middle strip Column strip Top in "mm C/C" Bottom in "mm C/C" Top in "mm C/C" Bottom in "mm C/C" 300 300 85 260 For 9m span Middle strip Column strip Top in "mm C/C" Bottom in "mm C/C" Top in "mm C/C" Bottom in "mm C/C" 300 300 140 270 Plan dimension 21 m X 21 m Spacing between the columns 7 m Total height of building 15.875 m Building considered (G+5) Story height 3 m Base consideration Fixed Size of the column 600*600 mm Size of the beam 300*750 mm Depth of the slab 175 mm
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 947 7. QUANTITIES The quantities for steel and concrete for both flat slab and the beam-slab were calculated using the design details, quantities are given below, For flat slab: FLATSLAB (FOR ONE FLOOR) Span in m -> 5 7 9 MATERIAL QUANTITES Steel in 'kg' 3120 8104 11309 Concrete in 'm3' 50.7 117.7 242 For Beam-slab : BEAM-SLAB(FOR ONE FLOOR) Span in m -> 5 7 9 MATERIAL QUANTITES Steel in 'kg' 4721 10747.4 25908 Concrete in 'm3' 44.1 106.15 194.4 8. RATE ANALYSIS From the quantity analysis which is done above we have got the total quantities for the steel and the concrete, by considering present day cost for concrete and steel we have calculated the cost for both flat slab and beam-slab systems for all the three spans and analysis was done between them. The present costs for concrete and steel For mixing and laying concrete : Slab : Rs. 520/- per cft Beams : Rs. 580/- per cft For steel bending and placing : Rs. 60/kg RATE ANALYSIS COST IN RS. SPAN in m CONVENTIONAL FLATSLAB RATE DIFFERENCE 5 1090620 1117207 26587 7 2599631 2646113 46482 9 5224566 5130073 94493 Graph of rate analysis: 9. CONCLUSIONS This project represents the comparative study between Flatslab and beam-slab systems for a multi-storied RC building (G+5) for varied span between the columns, on the basis of above results we can conclude that 1. By observing the above results and graph we can say that for shorter spans the flatslab is costlier than the conventional slab systems. 2. But we can see that as span between column increases the quantities forbeamslabincreasesand hence the cost of the beam slab also increases. 3. For 9m span between the columns the rateof beam- slab is more than the cost of flat slab, so we can conclude that as the span between columns increases the beam slab gets colstlier than the flatslab. 4. Hence by this project we can say that by adopting the flat slab systems in larger spanconstructionwill save lot of money and since flat slab is more advantageous than the beam slab, construction will be easier, fast, economic and affordable. 10. REFERENCES 1. Amrut manav (2016), “Comparative study of linear and non-linear seismic response of rc structure situated in different seismic zones of India”, International Research Journal of Engineering and Technology, 2. Vinod goud (2016) “Analysis design of flatslabwith and without shear wall of multi storied buildings frame.” ,IOSR journals of engineering, volume 06, sep 2016
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 948 3. Vinkuj k.tilva (2017), “Parametric study on flat slab building with and without column drop”, vol -03, feb2017 4. M.K. Devtale (2016), “Comparison of Seismic Response between Flat Slab Building and Regular Frame Building”, International journal of advancement in engineering technology, management and applied science, volume 03, June 2016 5. Mohana H S (2015) “Comparative Study of Flat Slab and Conventional Slab Structure Using ETABS for Different Earthquake Zones of India” International Research Journal of Engineering and Technology, volume-2, June 2015.