SlideShare a Scribd company logo
1 of 52
Download to read offline
CE 436 Traffic Engineering
Topic 9: Parking Studies
Prof. Saad AlGadhi
CE 436 –Traffic Engineering
King Saud University
email: salgadhi@ksu.edu.sa
Four Key Parking Issues
1. Parking Generation & Supply Needs
2. Parking Studies & Characteristics
3. Parking Facility Design & Location
4. Parking Programs (not covered)
1. Parking Supply Needs
 How many spaces required? Where?
 Types:
 On-street (curb)
 Off-Street:
 Surface lot
 Garage
 Need for parking depends upon:
 Type and Size of Development Land-Use
 Development general density
 Amount & quality of public transport access available
Parking Generation (PG)
 Relates the maximum observed # of occupied
parking spaces to one underlying variable
 ITE’s Parking Generation Manual (4th, 2010)
 Typical Parking Generation:
 Typical PG Specification Units: Table 12.1
 PG Rates: Table 12.2
Table 12.1 Typical Parking Generation Specification Units
Table 12.2 Typical Parking Generation Rates
Table 12.2 (continued) Typical Parking Generation Rates
PG Rates Example
 Small office park: 25,000 ft2 Find the
peak parking load expected?
Solution:
 Avg. rate = 2.84 per 1000 ft2
 # parking spaces = 2.84 *25=71 space
 From equation, p= 2.51*25+27=90
 Range [71-90]: Do PG localized study
Zoning Regulation
 Specify min. # parking spaces required
for development of specific type & size
 Based upon 85th percentile demand
 Zoning requirements are set 5-10% higher
than the 85th percentile demand
 Recommended values: Table 12.4
Table 12.4 Recommended Parking Space Zoning Requirements in Suburban Settings
Table 12.4 (continued) Recommended Parking Space Zoning Requirements in Suburban Settings
Table 12.4 (continued) Recommended Parking Space Zoning Requirements in Suburban Settings
Zoning Regulation
 Handicapped min. spaces: ITE
2. Parking Studies & Charax.
 Critical to supply needs are:
1. Proximity requirements of parkers
2. Accumulation
3. Duration
 Accumulation and Duration Related by
Capacity (space-hours)
 Inventory study is a pre-requisite.
Proximity: How Far to Walk
 Varies with:
 trip purpose
 Urban area size (Fig. 12.1)
 Walking distance (Table 12.5)
 85 % park within 0.3 mile (500 m)
 75 % park within 0.25 mile (400 m)
 50 %: 500 ft (150 m)
 Over 1 million population: avg. walking distance is
900 ft (275 m)
Figure 12.1 Average Walking Distance by Urbanized Area Population
Table 12.5 CBD Walking Distances to Parking Spaced
Parking Supply Inventory
 Includes observing:
 # of parking spaces
 Their locations
 Time restrictions on use
 Type of parking facility (on-street, off-
street lot, off-street garage)
 Its data collected manually (on foot),
but ITS recently used.
Inventory Methodology
 Study area mapped and precoded (Fig. 12.2)
 Data Field Sheet (Fig. 12.3)
 For unmarked curb parking use:
 7 m (23 ft) for parallel parking
 3.65 m (12 ft) for angle parking
 2.9 m (9.5 ft) for 90-degree parking
Figure 12.2 Illustrative System for Parking Location Coding
Figure 12.3 A Parking Inventory Field Sheet
Inventory Example (p. 258)
 Given:
 11 hr study
 450 spaces available for full 12 hrs.
 280 for 6 hrs
 150 for 7 hrs
 100 for 5 hrs
 Avg. parking duration = 1.4 hr
Inventory Example (p. 258)
 Parking supply? Use Equation 12-2.
Inventory Example (p. 258)
Accumulation & Duration
1. Parking Accumulation: total # of parked
vehicles at any given time.
2. Parking Duration, D: length of time individual
vehicles remain parked.
3. Parking Turnover Rate, TR: # parkers that use
a parking stall over one hour.
4. Occupancy, O = 100 * (max. Accum./Supply)
 Observed by License Plate Survey technique.
Figure 12.4 Parking Accumulation in Urbanized Areas by Population
Figure 12.5 Parking Duration Versus Urbanized Area Population
License Plate Survey
 At regular intervals (10-30 min.)
 observer walks a particular route.
 He records the license plate number of
vehicles occupying each parking space.
 Typical field sheet (Fig. 12.6)
Figure 12.6 A License-Plate Parking Survey Sheet
Table 12.7 Summary and Computations from a Typical Parking Survey Field Sheet
Parking Indicators: Duration
T
x
x
N
IXN
D


)**(
Parking Indicators: Turnover
SS
T
TP
N
TR
*

Table 12.8 Summary Data for an Entire Study Area Parking Survey
Max. Accumulation = 1410 Veh.
Occupancy, O = 1410/1500 * 100 = 94%
Table 12.8 (continued) Summary Data for an Entire Study Area Parking Survey
Areawide total (Sum)= 2119 parkers
Example Analysis Summary
 Tables 12.7 and 12.8
 Avg. Duration, D = 1.12 hr/veh
 Turnover rate, TR = 0.2 veh/stall/hr
 Max. Accumulation = 1410 veh.
 Occupancy, O = 94 %
should be 1
Another
Example
Another
Example
Sum = 67
Off-Street Parking Accumulation
 Counts of entering and departing vehicles
recorder by 15-min interval
 A starting count of occupancy in the facility
 Accumulation = Starting + Entering - Departing
3. Parking Facility Design
 Cost: (lot: Above G: UG)- (1:5:10)
 3 Key design objectives:
1. Convenient and safe
 Proximity to major destinations
 Adequate access/egress facilities (Including
reservoir space)
 Simple and efficient circulation system
 Adequate stall dimensions
 Basic security (veh. theft, personal crime…)
Key design objectives (cont.)
2. Space-efficient & economical to operate
 Maximize parking capacity
 Minimize wasted space
3. Compatible with its environs.:
 Architectural beauty
 No visual or auditory disruption
Parking Dimensions
 Design vehicles: large & small (Fig. 12.7).
 Parking stall width: Table 12.9
 Parking stall length & Depth:
 Length Large: 221 inch (5.62 m)
 Length Small: 181 inch (4.60 m)
 Depth is 90o projection of stall length
 Aisle width = f (angle, aisle directions)
 Parking modules (Fig. 12.8 & Table 12.10)
Figure 12.7 Design Vehicles for Parking Design
Table 12.9 Stall Width Design Criteria for Various Parking Classifications
Parking Modules
 Definition: basic layout of one aisle with a set
of parking stalls on both sides of the aisle.
 For 900 stalls, 2-way aisles used.
 Modules dimensions: Fig. 12.8/Table 12.10
 Four different layouts
 A single set of stalls against a wall (W1)
 Both sets of stall butt up @ walls (W2)
 One set of stalls @ a wall, other interlocked (W3)
 Both sets interlocked with adjacent module (W4)
Figure 12.8 Dimensional Elements of Parking Modules
Table 12.10 Parking Module Layout Dimension Guidelines
Table 12.10 (continued) Parking Module Layout Dimension Guidelines
Figure 12.9 Various Layouts for Integrating Small-Car and Large-Car Stalls in Parking Facilities
Planning Models (Gross Area)
 Parallel Parking 27 sq. m.
 300 Parking 34
 450 Parking 30
 600 Parking 27
 900 Parking 23
Figure 12.10 Parking Garage Circulation Systems
Figure 12.10 (continued) Parking Garage Circulation Systems
HW # 7 problems
 12-1: parking generation rates
 12-6: License plate survey

More Related Content

What's hot

Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodMd. Abdul Kader
 
Traffic volume-study
Traffic volume-studyTraffic volume-study
Traffic volume-studyStone Rayhan
 
Transportation modeling and planning ( The Four-Step Model )
Transportation modeling and planning ( The Four-Step Model )Transportation modeling and planning ( The Four-Step Model )
Transportation modeling and planning ( The Four-Step Model )Ahmad Ali Miftah
 
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)Vijai Krishnan V
 
Chapter 1 traffic characterstics
Chapter 1 traffic charactersticsChapter 1 traffic characterstics
Chapter 1 traffic charactersticsAnkit Patel
 
Measurement of spot speed
Measurement of spot speedMeasurement of spot speed
Measurement of spot speedSagar Vekariya
 
07 Speed, Travel Time & Delay Studies (Traffic Engineering هندسة المرور & Pro...
07 Speed, Travel Time & Delay Studies (Traffic Engineering هندسة المرور & Pro...07 Speed, Travel Time & Delay Studies (Traffic Engineering هندسة المرور & Pro...
07 Speed, Travel Time & Delay Studies (Traffic Engineering هندسة المرور & Pro...Hossam Shafiq I
 
Highway And traffic Engineering
Highway And traffic EngineeringHighway And traffic Engineering
Highway And traffic EngineeringLatif Hyder Wadho
 
Spot speed study, transport planning
Spot speed study, transport planningSpot speed study, transport planning
Spot speed study, transport planningPratyush Kumar
 
Lecture 02 Traffic Flow Characteristics (Traffic Engineering هندسة المرور & D...
Lecture 02 Traffic Flow Characteristics (Traffic Engineering هندسة المرور & D...Lecture 02 Traffic Flow Characteristics (Traffic Engineering هندسة المرور & D...
Lecture 02 Traffic Flow Characteristics (Traffic Engineering هندسة المرور & D...Hossam Shafiq I
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume surveyRashed Alam
 
Traffic studies and importance
Traffic studies and importance Traffic studies and importance
Traffic studies and importance SACHIN NAGAYACH
 
Freeway LOS (Transportation Engineering)
Freeway LOS (Transportation Engineering)Freeway LOS (Transportation Engineering)
Freeway LOS (Transportation Engineering)Hossam Shafiq I
 
Transportation Engineering I
Transportation Engineering  ITransportation Engineering  I
Transportation Engineering IGAURAV. H .TANDON
 
Chapter 2 traffic studies
Chapter 2 traffic studiesChapter 2 traffic studies
Chapter 2 traffic studiesAnkit Patel
 
Spot speed study
Spot speed studySpot speed study
Spot speed studyAmit Raj
 

What's hot (20)

Parking study
Parking studyParking study
Parking study
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation Method
 
Traffic volume-study
Traffic volume-studyTraffic volume-study
Traffic volume-study
 
Transportation modeling and planning ( The Four-Step Model )
Transportation modeling and planning ( The Four-Step Model )Transportation modeling and planning ( The Four-Step Model )
Transportation modeling and planning ( The Four-Step Model )
 
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
 
Chapter 1 traffic characterstics
Chapter 1 traffic charactersticsChapter 1 traffic characterstics
Chapter 1 traffic characterstics
 
Measurement of spot speed
Measurement of spot speedMeasurement of spot speed
Measurement of spot speed
 
07 Speed, Travel Time & Delay Studies (Traffic Engineering هندسة المرور & Pro...
07 Speed, Travel Time & Delay Studies (Traffic Engineering هندسة المرور & Pro...07 Speed, Travel Time & Delay Studies (Traffic Engineering هندسة المرور & Pro...
07 Speed, Travel Time & Delay Studies (Traffic Engineering هندسة المرور & Pro...
 
Highway And traffic Engineering
Highway And traffic EngineeringHighway And traffic Engineering
Highway And traffic Engineering
 
Spot speed study, transport planning
Spot speed study, transport planningSpot speed study, transport planning
Spot speed study, transport planning
 
Lecture 02 Traffic Flow Characteristics (Traffic Engineering هندسة المرور & D...
Lecture 02 Traffic Flow Characteristics (Traffic Engineering هندسة المرور & D...Lecture 02 Traffic Flow Characteristics (Traffic Engineering هندسة المرور & D...
Lecture 02 Traffic Flow Characteristics (Traffic Engineering هندسة المرور & D...
 
Traffic engineering 2
Traffic engineering 2Traffic engineering 2
Traffic engineering 2
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume survey
 
Traffic studies and importance
Traffic studies and importance Traffic studies and importance
Traffic studies and importance
 
Parking study
Parking studyParking study
Parking study
 
Freeway LOS (Transportation Engineering)
Freeway LOS (Transportation Engineering)Freeway LOS (Transportation Engineering)
Freeway LOS (Transportation Engineering)
 
Interchange
InterchangeInterchange
Interchange
 
Transportation Engineering I
Transportation Engineering  ITransportation Engineering  I
Transportation Engineering I
 
Chapter 2 traffic studies
Chapter 2 traffic studiesChapter 2 traffic studies
Chapter 2 traffic studies
 
Spot speed study
Spot speed studySpot speed study
Spot speed study
 

Similar to 09 Parking Studies (Traffic Engineering هندسة المرور & Prof. Saad AlGadhi)

TTE 332 module 3 S2021 Parking Studies
TTE 332 module 3 S2021 Parking StudiesTTE 332 module 3 S2021 Parking Studies
TTE 332 module 3 S2021 Parking StudiesWael ElDessouki
 
Aerodynamic Drag Reduction for A Generic Sport Utility Vehicle Using Rear Suc...
Aerodynamic Drag Reduction for A Generic Sport Utility Vehicle Using Rear Suc...Aerodynamic Drag Reduction for A Generic Sport Utility Vehicle Using Rear Suc...
Aerodynamic Drag Reduction for A Generic Sport Utility Vehicle Using Rear Suc...IJERA Editor
 
,Exit Exam Tutorial -Traffic Engineering.pdf
,Exit Exam Tutorial -Traffic Engineering.pdf,Exit Exam Tutorial -Traffic Engineering.pdf
,Exit Exam Tutorial -Traffic Engineering.pdfsandipanpaul16
 
Analysis for Maximum Utilization of Parking Area
Analysis for Maximum Utilization of Parking AreaAnalysis for Maximum Utilization of Parking Area
Analysis for Maximum Utilization of Parking Areaijsrd.com
 
Car Parking Design in Urban Planning
Car Parking Design in Urban PlanningCar Parking Design in Urban Planning
Car Parking Design in Urban PlanningNzar Braim
 
BDE_SC4_WS3_3_Rodrigo Castineira - Transforming Transport Project
BDE_SC4_WS3_3_Rodrigo Castineira - Transforming Transport ProjectBDE_SC4_WS3_3_Rodrigo Castineira - Transforming Transport Project
BDE_SC4_WS3_3_Rodrigo Castineira - Transforming Transport ProjectBigData_Europe
 
Chapter 3&4
Chapter 3&4Chapter 3&4
Chapter 3&4EWIT
 
Proposed cable car project, Uttarakhnad, India.
Proposed cable car project, Uttarakhnad, India.Proposed cable car project, Uttarakhnad, India.
Proposed cable car project, Uttarakhnad, India.Sameer Mohan
 
Conflict-free dynamic route multi-agv using dijkstra Floyd-warshall hybrid a...
Conflict-free dynamic route multi-agv using dijkstra  Floyd-warshall hybrid a...Conflict-free dynamic route multi-agv using dijkstra  Floyd-warshall hybrid a...
Conflict-free dynamic route multi-agv using dijkstra Floyd-warshall hybrid a...IJECEIAES
 
Report of parking problem
Report of parking problemReport of parking problem
Report of parking problemMukesh909081
 
Analysis of Different Parking Space and its Comparison
Analysis of Different Parking Space and its ComparisonAnalysis of Different Parking Space and its Comparison
Analysis of Different Parking Space and its Comparisonijsrd.com
 
A Computer Model for Selecting Equipment for Earthmoving Operations Using Sim...
A Computer Model for Selecting Equipment for Earthmoving Operations Using Sim...A Computer Model for Selecting Equipment for Earthmoving Operations Using Sim...
A Computer Model for Selecting Equipment for Earthmoving Operations Using Sim...Hassan Eliwa
 
Parking design in front of CE building BUET by Pronob ghosh 1204011
Parking design in front of CE building BUET by Pronob ghosh 1204011Parking design in front of CE building BUET by Pronob ghosh 1204011
Parking design in front of CE building BUET by Pronob ghosh 1204011Pronob Ghosh
 
Presentation-11th ACUUS International Conference
Presentation-11th ACUUS International ConferencePresentation-11th ACUUS International Conference
Presentation-11th ACUUS International ConferenceMeliti Pappa
 
Conceptualization of IoT Powered Parking System
Conceptualization of IoT Powered Parking SystemConceptualization of IoT Powered Parking System
Conceptualization of IoT Powered Parking SystemIJERA Editor
 
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...Hossam Shafiq I
 
Development of Routing for Car Navigation Systems
Development of Routing for Car Navigation SystemsDevelopment of Routing for Car Navigation Systems
Development of Routing for Car Navigation SystemsAtsushi Koike
 

Similar to 09 Parking Studies (Traffic Engineering هندسة المرور & Prof. Saad AlGadhi) (20)

Smart parking
Smart parkingSmart parking
Smart parking
 
TTE 332 module 3 S2021 Parking Studies
TTE 332 module 3 S2021 Parking StudiesTTE 332 module 3 S2021 Parking Studies
TTE 332 module 3 S2021 Parking Studies
 
Aerodynamic Drag Reduction for A Generic Sport Utility Vehicle Using Rear Suc...
Aerodynamic Drag Reduction for A Generic Sport Utility Vehicle Using Rear Suc...Aerodynamic Drag Reduction for A Generic Sport Utility Vehicle Using Rear Suc...
Aerodynamic Drag Reduction for A Generic Sport Utility Vehicle Using Rear Suc...
 
,Exit Exam Tutorial -Traffic Engineering.pdf
,Exit Exam Tutorial -Traffic Engineering.pdf,Exit Exam Tutorial -Traffic Engineering.pdf
,Exit Exam Tutorial -Traffic Engineering.pdf
 
Analysis for Maximum Utilization of Parking Area
Analysis for Maximum Utilization of Parking AreaAnalysis for Maximum Utilization of Parking Area
Analysis for Maximum Utilization of Parking Area
 
Car Parking Design in Urban Planning
Car Parking Design in Urban PlanningCar Parking Design in Urban Planning
Car Parking Design in Urban Planning
 
Unit 3 ii ppt
Unit 3 ii pptUnit 3 ii ppt
Unit 3 ii ppt
 
BDE_SC4_WS3_3_Rodrigo Castineira - Transforming Transport Project
BDE_SC4_WS3_3_Rodrigo Castineira - Transforming Transport ProjectBDE_SC4_WS3_3_Rodrigo Castineira - Transforming Transport Project
BDE_SC4_WS3_3_Rodrigo Castineira - Transforming Transport Project
 
Private hospitals’ parking health care’s debated contribution in traffic cong...
Private hospitals’ parking health care’s debated contribution in traffic cong...Private hospitals’ parking health care’s debated contribution in traffic cong...
Private hospitals’ parking health care’s debated contribution in traffic cong...
 
Chapter 3&4
Chapter 3&4Chapter 3&4
Chapter 3&4
 
Proposed cable car project, Uttarakhnad, India.
Proposed cable car project, Uttarakhnad, India.Proposed cable car project, Uttarakhnad, India.
Proposed cable car project, Uttarakhnad, India.
 
Conflict-free dynamic route multi-agv using dijkstra Floyd-warshall hybrid a...
Conflict-free dynamic route multi-agv using dijkstra  Floyd-warshall hybrid a...Conflict-free dynamic route multi-agv using dijkstra  Floyd-warshall hybrid a...
Conflict-free dynamic route multi-agv using dijkstra Floyd-warshall hybrid a...
 
Report of parking problem
Report of parking problemReport of parking problem
Report of parking problem
 
Analysis of Different Parking Space and its Comparison
Analysis of Different Parking Space and its ComparisonAnalysis of Different Parking Space and its Comparison
Analysis of Different Parking Space and its Comparison
 
A Computer Model for Selecting Equipment for Earthmoving Operations Using Sim...
A Computer Model for Selecting Equipment for Earthmoving Operations Using Sim...A Computer Model for Selecting Equipment for Earthmoving Operations Using Sim...
A Computer Model for Selecting Equipment for Earthmoving Operations Using Sim...
 
Parking design in front of CE building BUET by Pronob ghosh 1204011
Parking design in front of CE building BUET by Pronob ghosh 1204011Parking design in front of CE building BUET by Pronob ghosh 1204011
Parking design in front of CE building BUET by Pronob ghosh 1204011
 
Presentation-11th ACUUS International Conference
Presentation-11th ACUUS International ConferencePresentation-11th ACUUS International Conference
Presentation-11th ACUUS International Conference
 
Conceptualization of IoT Powered Parking System
Conceptualization of IoT Powered Parking SystemConceptualization of IoT Powered Parking System
Conceptualization of IoT Powered Parking System
 
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
 
Development of Routing for Car Navigation Systems
Development of Routing for Car Navigation SystemsDevelopment of Routing for Car Navigation Systems
Development of Routing for Car Navigation Systems
 

More from Hossam Shafiq I

14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...Hossam Shafiq I
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...Hossam Shafiq I
 
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...Hossam Shafiq I
 
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...Hossam Shafiq I
 
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...Hossam Shafiq I
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...Hossam Shafiq I
 
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...Hossam Shafiq I
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...Hossam Shafiq I
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...Hossam Shafiq I
 
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...Hossam Shafiq I
 
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...Hossam Shafiq I
 
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...Hossam Shafiq I
 
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...Hossam Shafiq I
 
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....Hossam Shafiq I
 
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...Hossam Shafiq I
 
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...Hossam Shafiq I
 
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...Hossam Shafiq I
 
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...Hossam Shafiq I
 
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...Hossam Shafiq I
 
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...Hossam Shafiq I
 

More from Hossam Shafiq I (20)

14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
 
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
 
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
 
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
 
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
 
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
 
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
 
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
 
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
 
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
 
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
 
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
 
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
 
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
 
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
 
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
 

Recently uploaded

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 

09 Parking Studies (Traffic Engineering هندسة المرور & Prof. Saad AlGadhi)

  • 1. CE 436 Traffic Engineering Topic 9: Parking Studies Prof. Saad AlGadhi CE 436 –Traffic Engineering King Saud University email: salgadhi@ksu.edu.sa
  • 2. Four Key Parking Issues 1. Parking Generation & Supply Needs 2. Parking Studies & Characteristics 3. Parking Facility Design & Location 4. Parking Programs (not covered)
  • 3. 1. Parking Supply Needs  How many spaces required? Where?  Types:  On-street (curb)  Off-Street:  Surface lot  Garage  Need for parking depends upon:  Type and Size of Development Land-Use  Development general density  Amount & quality of public transport access available
  • 4. Parking Generation (PG)  Relates the maximum observed # of occupied parking spaces to one underlying variable  ITE’s Parking Generation Manual (4th, 2010)  Typical Parking Generation:  Typical PG Specification Units: Table 12.1  PG Rates: Table 12.2
  • 5. Table 12.1 Typical Parking Generation Specification Units
  • 6. Table 12.2 Typical Parking Generation Rates
  • 7. Table 12.2 (continued) Typical Parking Generation Rates
  • 8. PG Rates Example  Small office park: 25,000 ft2 Find the peak parking load expected? Solution:  Avg. rate = 2.84 per 1000 ft2  # parking spaces = 2.84 *25=71 space  From equation, p= 2.51*25+27=90  Range [71-90]: Do PG localized study
  • 9. Zoning Regulation  Specify min. # parking spaces required for development of specific type & size  Based upon 85th percentile demand  Zoning requirements are set 5-10% higher than the 85th percentile demand  Recommended values: Table 12.4
  • 10. Table 12.4 Recommended Parking Space Zoning Requirements in Suburban Settings
  • 11. Table 12.4 (continued) Recommended Parking Space Zoning Requirements in Suburban Settings
  • 12. Table 12.4 (continued) Recommended Parking Space Zoning Requirements in Suburban Settings
  • 14. 2. Parking Studies & Charax.  Critical to supply needs are: 1. Proximity requirements of parkers 2. Accumulation 3. Duration  Accumulation and Duration Related by Capacity (space-hours)  Inventory study is a pre-requisite.
  • 15. Proximity: How Far to Walk  Varies with:  trip purpose  Urban area size (Fig. 12.1)  Walking distance (Table 12.5)  85 % park within 0.3 mile (500 m)  75 % park within 0.25 mile (400 m)  50 %: 500 ft (150 m)  Over 1 million population: avg. walking distance is 900 ft (275 m)
  • 16. Figure 12.1 Average Walking Distance by Urbanized Area Population
  • 17. Table 12.5 CBD Walking Distances to Parking Spaced
  • 18. Parking Supply Inventory  Includes observing:  # of parking spaces  Their locations  Time restrictions on use  Type of parking facility (on-street, off- street lot, off-street garage)  Its data collected manually (on foot), but ITS recently used.
  • 19. Inventory Methodology  Study area mapped and precoded (Fig. 12.2)  Data Field Sheet (Fig. 12.3)  For unmarked curb parking use:  7 m (23 ft) for parallel parking  3.65 m (12 ft) for angle parking  2.9 m (9.5 ft) for 90-degree parking
  • 20. Figure 12.2 Illustrative System for Parking Location Coding
  • 21. Figure 12.3 A Parking Inventory Field Sheet
  • 22. Inventory Example (p. 258)  Given:  11 hr study  450 spaces available for full 12 hrs.  280 for 6 hrs  150 for 7 hrs  100 for 5 hrs  Avg. parking duration = 1.4 hr
  • 23. Inventory Example (p. 258)  Parking supply? Use Equation 12-2.
  • 25. Accumulation & Duration 1. Parking Accumulation: total # of parked vehicles at any given time. 2. Parking Duration, D: length of time individual vehicles remain parked. 3. Parking Turnover Rate, TR: # parkers that use a parking stall over one hour. 4. Occupancy, O = 100 * (max. Accum./Supply)  Observed by License Plate Survey technique.
  • 26. Figure 12.4 Parking Accumulation in Urbanized Areas by Population
  • 27. Figure 12.5 Parking Duration Versus Urbanized Area Population
  • 28. License Plate Survey  At regular intervals (10-30 min.)  observer walks a particular route.  He records the license plate number of vehicles occupying each parking space.  Typical field sheet (Fig. 12.6)
  • 29. Figure 12.6 A License-Plate Parking Survey Sheet
  • 30. Table 12.7 Summary and Computations from a Typical Parking Survey Field Sheet
  • 33. Table 12.8 Summary Data for an Entire Study Area Parking Survey Max. Accumulation = 1410 Veh. Occupancy, O = 1410/1500 * 100 = 94%
  • 34. Table 12.8 (continued) Summary Data for an Entire Study Area Parking Survey Areawide total (Sum)= 2119 parkers
  • 35. Example Analysis Summary  Tables 12.7 and 12.8  Avg. Duration, D = 1.12 hr/veh  Turnover rate, TR = 0.2 veh/stall/hr  Max. Accumulation = 1410 veh.  Occupancy, O = 94 %
  • 38. Off-Street Parking Accumulation  Counts of entering and departing vehicles recorder by 15-min interval  A starting count of occupancy in the facility  Accumulation = Starting + Entering - Departing
  • 39. 3. Parking Facility Design  Cost: (lot: Above G: UG)- (1:5:10)  3 Key design objectives: 1. Convenient and safe  Proximity to major destinations  Adequate access/egress facilities (Including reservoir space)  Simple and efficient circulation system  Adequate stall dimensions  Basic security (veh. theft, personal crime…)
  • 40. Key design objectives (cont.) 2. Space-efficient & economical to operate  Maximize parking capacity  Minimize wasted space 3. Compatible with its environs.:  Architectural beauty  No visual or auditory disruption
  • 41. Parking Dimensions  Design vehicles: large & small (Fig. 12.7).  Parking stall width: Table 12.9  Parking stall length & Depth:  Length Large: 221 inch (5.62 m)  Length Small: 181 inch (4.60 m)  Depth is 90o projection of stall length  Aisle width = f (angle, aisle directions)  Parking modules (Fig. 12.8 & Table 12.10)
  • 42. Figure 12.7 Design Vehicles for Parking Design
  • 43. Table 12.9 Stall Width Design Criteria for Various Parking Classifications
  • 44. Parking Modules  Definition: basic layout of one aisle with a set of parking stalls on both sides of the aisle.  For 900 stalls, 2-way aisles used.  Modules dimensions: Fig. 12.8/Table 12.10  Four different layouts  A single set of stalls against a wall (W1)  Both sets of stall butt up @ walls (W2)  One set of stalls @ a wall, other interlocked (W3)  Both sets interlocked with adjacent module (W4)
  • 45. Figure 12.8 Dimensional Elements of Parking Modules
  • 46. Table 12.10 Parking Module Layout Dimension Guidelines
  • 47. Table 12.10 (continued) Parking Module Layout Dimension Guidelines
  • 48. Figure 12.9 Various Layouts for Integrating Small-Car and Large-Car Stalls in Parking Facilities
  • 49. Planning Models (Gross Area)  Parallel Parking 27 sq. m.  300 Parking 34  450 Parking 30  600 Parking 27  900 Parking 23
  • 50. Figure 12.10 Parking Garage Circulation Systems
  • 51. Figure 12.10 (continued) Parking Garage Circulation Systems
  • 52. HW # 7 problems  12-1: parking generation rates  12-6: License plate survey